PSOC Sample Questions
PSOC Sample Questions
com
UNIT I: INTRODUCTION
PART A:
PART B:
1. i) Define the following: (1) Hot reserve (2) Cold reserve (3) diversity factor
ii)A generating station has the following daily load cycle:
Time in (hrs) 0-6 6-10 10-12 12-16 16-20 20-24
Load(MW) 20 25 30 25 35 20
Draw the load curve and calculate maximum demand, units generated per day, average
load, load factor.
2. Explain the following: (i) Load forecasting (ii) Economic dispatch control.
3. (i) Explain the following terms: Installed reserve, spinning reserve, cold reserve, hot
reserve.
(ii)A power station has to meet the following demand:
Group A:200KW between 8 A.M and 6 P.M
Group B:100KW between 6 A.M and 10 A.M
Group C:50KW between 6 A.M and 10 A.M
Group D:100KW between 10 A.M and 6 P.M and then between 6 P.M and 6 A.M. Plot
the daily load curve and determine diversity factor, units generated per day and load
factor.
www.vidyarthiplus.com
www.vidyarthiplus.com
4. (i)Discuss about the recent trends in real time control of power systems.
(ii) Write short notes on load forecasting.
5. i)What is meant by chronological load curve? Give the information obtained from load
curves.
ii)Explain the advantages and different types of computer control system.
6. Describe briefly about plant level and system level control.
7. i) what are the information obtained from load curve and load duration curve?
ii) Briefly describe the importance of load forecasting and explain the method of least
square fit forecasting the base load.
8. What are objectives of modern trend in real time control of power system? Explain the
significant features of computer control in power system.
9. i) with neat sketch describe the p-f and Q-V control structure.
ii) Explain the following terms
i. Maximum Demand
ii. Plant use factor
iii. Plant capacity factor
iv. Reserve capacity
10. (i) Explain the need for voltage and frequency regulation in power system
(ii) A generating station has maximum demand of 400 MW. The annual load factor is
65% and capacity factor is 50% find the reserve capacity of the plant.
11. Draw load curve and load duration curve. Explain the importance of these curves in
connection with economic operation of power system
12. A generating station has maximum demand of 20 MW, load factor is 60% and capacity
factor is 50% find the reserve capacity of the plant, daily energy produced, maximum
energy that could be produced daily if the plant were running all the time and maximum
energy that could be produced if the plant when running(acc. To operating schedule)
were fully loaded.
13. A generating station has a maximum demand of 50,000 KW.calculate the cost per unit
generated from the following data.
Capital Cost = Rs95 x 106
Annual load factor = 40%
Annual cost of fuel and oil = Rs9 x 106
Taxes, wages and salaries etc.= Rs7.5 x 106
Interest and depreciation = 12%
www.vidyarthiplus.com
www.vidyarthiplus.com
PART A:
PART B:
1. Two synchronous generators operating in parallel. Their capacities are 300MW and
400MW. The droop characteristics of their governors are 4% and 5% from no load to full
load. Assuming that the generators are operating at 50HZ at no load , how would be a
load of 600MW shared between them. What will be the system frequency at this load?
Assume free governor action.
2. Develop the state variable model of a two area system and state the advantages of the
model.
3. Draw the block diagram of uncontrolled two area load frequency control system and
explain the salient features under static condition.
4. How is speed governor mechanism modeled? Explain its operations with the speed load
characteristics.
5. Derive the transfer function model and draw the block diagram for single control area
provided with governor system. From the transfer function derive the expression for
steady state frequency error for a step load change.
6. What are the components of speed governor system of an alternator? Derive its transfer
function with an aid of a block diagram.
www.vidyarthiplus.com
www.vidyarthiplus.com
www.vidyarthiplus.com
www.vidyarthiplus.com
Unit-3
Part-B
1.a) Explain the short term Hydro-thermal scheduling problem with necessary
expressions.
b) Discuss the optimal power flow with inequality constraints. [16]
2. (a) Explain input - output characteristics of thermal power stations.
(b) Define in detail cost curve of thermal stations. [8+8]
3. Discuss the combined hydro- electric and steam station operation. [16]
4. In a two plant operation system, the Hydro plant is operate for 12 hrs. during
www.vidyarthiplus.com
www.vidyarthiplus.com
each day and the hydro plant is operate all over the day. The characteristics of the
steam and hydro plants are
CT = 0.3 PGT 2 +20 PGT + 5 Rs/hr
WH =0.4PGH 2 +20 PGH m3 / sec
When both plants are running, the power flow from steam plant to load is 300 MW
and the total quantity of water is used for the hydro plant operation during 12 hrs is
180106 m3 . Determine the generation of hydro plant and cost of water used.
[16]
5. Describe different methods for solving hydro thermal scheduling. [16]
200 MW<=PS<=1200 MW
0<=PH<=200 MW
Load for first and second time period are 600 and 1000.
Use DP.
www.vidyarthiplus.com
www.vidyarthiplus.com
10. Explain pumped storage hydro scheduling with a lemta gamma iteration method.
Unit-4
UNIT COMMITMENT AND ECONOMIC DISPATCH
Part-A
1. What is meant by FLAC?
2. Write the condition for the optimal power dispatch in a lossless system.
3. Draw the incremental fuel cost curve.
4. What is meant by spinning reserve?
5. Write the significance of Unit Commitment.
6. Draw the incremental cost curve of a thermal power plant.
7. Write the equality and inequality constraints considered in the economic dispatch
problem.
8. Define spinning reserve constraint in unit commitment problem.
9. What is minimum up and minimum down time in unit commitment problem?
10. Define participation factor.
11. What is participation factor with respect to economic load dispatch
12. Write the co-ordination equation taking losses into account.
13. What is meant by incremental cost curve?
14. Compare with unit commitment and Economic load dispatch
15. List the few constraints that are accounted in unit commitment problem
16. What is meant by priority list method
17. Mention the assumption made in the formation of loss formula matrix B.
18. What are the advantages of using forward dynamic programming method
19. State unit commitment problem.
20. What is difference between load frequency controller and economic dispatch controller
Part-B
1. State the unit commitment problem. With the help of a flow chart, explain
forward dynamic programming solution method of unit commitment problem.
2. The fuel inputs per hour of plants 1 and 2 are given as
F 1 = 0.2P 1 2+40P 1 +120Rs/hr
F 2 =0.25P 2 2+30P 2 +150Rs/hr
Determine the economic operating schedule and the corresponding cost of
generation. The maximum and the minimum loading on each unit are 100MW
and 25MW. Assume the transmission losses are ignored and the total demand is
www.vidyarthiplus.com
www.vidyarthiplus.com
180MW. Also determine the saving obtained if the load is equally shared by both
the units.
3. (i) With the help of Flow chart explain Economic dispatch by Iteration method
without loss.
(ii) The fuel cost of two units are given by
F 1 =F 1 (P G1 ) = 1.5+20P G1 +0.1P G1 2 Rs\hr
F 2 =F 2 (P G2 ) = 1.9+30P G2 +0.1P G2 2Rs\hr
If the total demand on the generator is 200 MW. Find the economic load
scheduling of the two units.
(iii) What is the significance of equality and inequality constraints in the
formulation of optimum dispatch problem?
4. (i) What is unit commitment problem? Discuss the constraints that are to be
accounted in unit commitment problem.
(ii) Obtain the priority list of unit commitment using full load average production
cost for the given data:
Heat rate of unit1 H 1 = 510+7.2P G1 +0.00142 P G1 2MW\hr
Heat rate of unit2 H 2 = 310+7.85P G2 +0.00194P G2 2MW\hr
Heat rate of unit3 H 3 = 78+7.97P G3 +0.00482P G3 2MW\hr. P D =500MW
Unit Mm(MW) Max(MW) Fuel Cost (K)
1 150 600 1.1
2 100 400 1.0
3 50 200 1.2
5. (i) Explain the unit commitment problem using priority ordering load dispatch.
(ii) Explain the term Incremental Operating Cost of power system related with
economic dispatch.
6. The fuel inputs per hour of plants 1 and 2 are given as
F 1 = 0.2P 1 2+40P 1 +120 Rs/hr
F 2 =0.25P 2 2+30P 2 +150Rs/hr
Determine the economic operating schedule and the corresponding cost of
generation if the maximum and minimum loading on each unit is 100MW and
25MW.Assume the transmission losses are ignored and the total demand is 180
MW. Also determine the saving obtained if the load is equally shared by both the
units.
7. Explain various constraints in UC and indicate the steps involved in solving UC
by DP method.
8. Formulate the coordination equations with losses neglected and also explain the
algorithmic steps of iterative method to find the solution of coordination
equations.
9. (i)Explain the priority list method of solving unit commitment Problem. State
merits and limitations of this method.
10. The fuel cost functions for three thermal plants in $/h are given
www.vidyarthiplus.com
www.vidyarthiplus.com
by
F 1 =0.004P g1 2+5.3P g1 +500
F 2 =0.006P g2 2+5.5P g2 +400
F 3 =0.009P g3 2+5.8P g3 +200 where P g1 ,P g2 ,P g3 are in MW.
Find the optimal dispatch and the total cost when the total load is
925 MW with the following generator limits.
100MWP g1 450MW,
100MWP g2 350MW,
100MWP g3 225MW
11. (i)Explain the forward dynamic programming method of solving unit commitment
problem.
(ii)Develop an iterative algorithm for solving the optimum dispatch equation of an
'n' bus power system taking into account the effects of system losses.
12. (i)Construct the priority list for the units given below.
H 1 =510+7.20P 1 +0.00142P 1 2 .P min =150MW.P max =600MW.
Fuel cost=1.1Rs/MBtu.
H 2 =310+7.85P 2 +0.00194P 2 2 .P min =100MW.P max =400MW.
Fuel cost=1.0Rs/MBtu
H 3 =78+7.97P 3 +0.00482P 3 2 .P min =50MW.P max =200MW.
Fuel cost=1.2Rs/MBtu
ii)Derive the co ordination equation with losses neglected.
14. With a neat flow chart explain the iterative algorithm for solving the economic
dispatch equation of N bus power system taking into account the effects of
system losses.
15. The fuel-cost functions for three thermal plants are given by
F 1 =0.004P g1 2+5.3P g1 +500 $/hr
F 2 =0.006P g2 2+5.5P g2 +400 $/hr
www.vidyarthiplus.com
www.vidyarthiplus.com
16. In power system having two units, the loss co-efficient are
B 11 =0.0015MW-1, B 12 =-0.0006MW-1
B 21 =0.0006MW-1,B 22 =0.0024MW-1
The incremental production costs of the units are
=0.08P G1 +20 Rs/MWhr
=0.09P G2 +16Rs/MWhr
Find the generation schedule for =20 and 25. Find also change in
transmission loss between two schedules.
17. Explain the Forward Dynamic Programming method of solving unit commitment problem
with neat flow chart.
F 1 =940+5.46PG1+0.0016PG12
F 2 =820+5.35PG2+0.0019PG22
www.vidyarthiplus.com
www.vidyarthiplus.com
Unit-5
COMPUTER CONTROL OF POWER SYSTEMS
Part-A
1. What are the functions of SCADA?
2. Define state estimation.
3. What is SCADA?
4. Write any two functions of Load Dispatch Center.
5. Define network topology in power system.
6. What are the different operating states in power system.
7. Distinguish between reliability and security of power system.
8. What are the EMS functions?
9. List out the conditions for normal operations of a power system.
10. What do you understand by security constraints?
11. What is contingency analysis program
12. List the factors that affects the power system security
13. What are the typical sensors used in power system application
14. When is power system considered to be secured?
15. What are the tasks of energy control center?
16. What are the important types of relay used for protection,
17. Denote the hierarchical levels used in EMS.
18. Write the importance of state estimation in power system.
19. List out the conditions for normal operation of power system.
20. What are the functions of load control centre?
Part-B
1. Briefly explain various functions of SCADA with neat diagram. Also list some of the
common features of all SCADA systems
2. Discuss the various functions, system monitoring and control of load dispatch center.
3. (i) What is EMS? What are its major functions in power system operation and control?
(ii) Draw the block diagram to show the hardware configuration of a SCADA system for
a power system and explain the application of SCADA in monitoring and control of
power system
4. Explain the security monitoring using state estimation with necessary diagrams.
5. (i)Explain need of computer control of power system.
(ii) Explain the major functions of system security control.
6. Explain various state transitions and control strategies using state transition diagram.
www.vidyarthiplus.com
www.vidyarthiplus.com
www.vidyarthiplus.com