Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Sub6 Soakaway-System PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

The Livestock Waste Control Scheme :

Guidelines for Soakaway System

THE SOAKAWAY SYSTEM

A soakaway system normally includes screens, a catch pit, a septic tank, soakaway pit and
trenches, and the associated dung channels. Farms which can achieve very high levels of dry removal
of solid waste, and low levels of water use (ie. chicken and small duck farms), will not normally require
septic tanks. Septic tanks will invariably be required for pig farms where any effluent is generated.
Figure 1 below is a schematic diagram showing the general arrangement of the components of a
soakaway system.

Covered Vent Pipe Covered Covered Covered Vent Pipe


Access Access Access Access
Opening Opening Opening Opening
Detachable
Screen

Dung
Channel
Catchpit

Sludge
Sludge

Septic Tank
(for pig farms)

Soakaway Pit Soakaway


Trench

Fig ure 1 The General Arrang ement of Components of a Soakaway S ys

The general components of a soakaway system are described below:

i) Dung Channel

Purpose : To collect and convey wastewater to the inlet of the catch-pit.

RECYCLE D PAPER
Design Considerations:

(a) Sufficiently wide to facilitate periodic maintenance.


(b) Sufficient gradient to enable self cleansing.
(c) Prevention of rainwater ingress and overflow.
(d) Fitted with screening gear to enable the removal of solids.

Maintenance Requirement: Settled / screened solids and fallen leaves in the dung channels
should be removed after every washing of livestock structures,
and be properly disposed of in accordance with the Code of
Practice for Livestock Waste Management.

ii) Screen

Purpose : To remove suspended solids and coarse matter in the wastewater.

Design Considerations:

(a) Openings should be sufficiently small to retain the solids but large enough to allow
the wastewater to pass through.
(b) Screenings can be easily removed on a regular basis.

Maintenance Requirement: Periodic removal of screenings and cleaning.

iii) Catch-pit

Purpose : To collect wastewater from dung channels and to facilitate removal of solid matters.

Design Considerations:

(a) Sufficiently large to prevent overflows.


(b) Enable screening of solids and grits.
(c) Provision for emptying solids and grits.
(d) Covered to prevent ingress of rainwater.

Maintenance Requirement: Removal of trapped solids and grits after every washing or
hosing down operation.

iv) Septic Tank

Purpose: To facilitate sedimentation and decomposition of small solid particles. (Septic


tanks are normally not required for poultry farms because dry muck-out at
poultry farms can achieve very high levels of solids removal. Soakaway pits/
trenches are however necessary.)

Design Considerations:

(a) Sufficiently large to provide a minimum capacity for 3 days storage of wastewater,
and to hold all the sludge likely to accumulate between desludging. The required size
is therefore determined by the amount of water used during washing, the solids content
of the wastewater entering the tank (and therefore the amount of solids remaining after
dry muck-out) and the frequency of desludging. Table 1 illustrates how the required
capacity for a pig farm can be affected by different operational practices. For example,
if the amount of water used in a pig farm is 15L/pig/day, with 80% of solids removed
during dry muck-out, and the tank is desludged once every 3 months, the required
capacity is about 0.15m3 per pig. Nevertheless, a septic tank should not be smaller
than 2.5m3 to enable ease of maintenance.

(b) Well vented with a vent pipe to avoid accumulation of methane or other obnoxious gases.

(c) Leak-proof.

(d) Covered to prevent external deposition of solids or ingress of rain.

(e) Access for mechanical desludging.

Table 1 Size of Septic Tank for Pig Farms with Different Operational Practices

S eptic tan k size (m3 / pi g)


Quantity of
Desludging for di fferent percentage
washwater
interval removal of solids during dry mu ck-out
used
(month)
(L/pig/day) 70% 80% 90%

15 3 0.20 0.15 0.10

6 0.35 0.25 0.15

10 3 0.18 0.13 0.08

6 0.32 0.23 0.13

5 3 0.16 0.11 0.07

6 0.30 0.21 0.11

Maintenance Requirement: Periodic sludge removal, at least once every 6 months but
once every 3 months is normally expected.

v) The Soakaway Pit/Trench

Purpose : Percolation of wastewater to surrounding subsoil.

Design Considerations:

(a) Soakaway pit should be sufficiently large to avoid flooding and overflow. The minimum
capacity of the pit should accommodate all the wastewater produced during one washing
or in one day, whichever figure is the greater.
(b) Permeability of Soil. If the percolation rate is too high, the wastewater might drain into
the nearby watercourses before any effective treatment. If it is too low, the pit/trenches
might soon clog up and wastewater would overflow. A site percolation test should be
conducted to determine the soil permeability. Table 2 illustrates the maximum allowable
loadings of soakaway pits and trenches. The common simplified procedures of percolation
test for determining the absorption capacity of soil are given below:

Excavate a hole 300mm square to the proposed depth of the pit and trench.

Fill the hole with approximately 150mm of water and allow it to seep away
completely; no need to measure the time.

Refill the hole with water to a depthof 150mm and observe the time, in minutes,
for water to seep completely away.

Table 2 Soakaway Area Requirements at Different Soil Percolation Rates

Time for water Required trench Required pit


to fall 150mm bottom area (m2 ) percolation are a (m2 )
in test pit per 1,000L/day per 1,000L/day
(minutes) of wastewater of wastewater

6 or less 31 23

12 38 29

30 51 38

60 72 53

180 152 111

Note
1. T his table is only applicable to small inland duck farms or those poultry or pig farms intending to carry out dry muck-
out of livestock waste.
2. A septic tank is required for pig farms.

(c) Sufficient Soakaway Area. A reasonable percolation rate which is neither too high
nor too low is about 60 minutes for water to fall 150mm. With such a percolation
rate, a pig farm using 15L/pig/day of washwater and removing 80% of solids during
dry muck-out requires a minimum soakaway trench area of 0.9m2 for every pig (ie.
0.75m of trench if it is 1.2m wide). Table 3 illustrates how this requirement can be
affected by differing operational practices. For a chicken farm using 0.4L/chicken/
week of washwater and achieving 97% removal of solids, a minimum of about 0.4m2
of trench is required for every 100 chickens (ie. 0.33m of trench if it is 1.2m wide).
Table 4 illustrates how this requirement can be affected by different operational
practices. Similarly, a duck farm generating 1,000L/day of wastewater requires 72m2
of trench (ie. 60m of trench if it is 1.2m wide). Table 2 illustrates how this requirement
can be affected by different soil percolation rates.
Table 3 Soakaway Trench Area Requirement for Pig Farms with Different Operat ional Practices

Percentage removal of solids


durin g dry muck-out 70% 80% 90%

Minimu m soakaway trench


area requirement
(m2 /pig) 1.1 0.9 0.7

Note
T he above is based on
1. a soil pe rcolation t ime (ra te) of 60 min utes fo r wa ter to fall 15 0mm (NB. t he t ren ch area re quir eme nt m ay
be reduce d if th e p erc olat ion ra te is incr ease d, pro rat a t o t he r equire ment s shown in Ta ble 2; on the oth er
hand, the tre nch are a would ne ed t o be in cre ased if the pe rcolation r ate is slo wer. );
2. a septic tank is provided; and
3. a wash wat er usage ra te o f 1 5L/p ig/day. (NB. the tre nch are a re quireme nt c an be r educed slightly by re ducing
th e am ount of washwa ter used.)

Table 4 Soakaway Trench Area Requirement for Chicken Farms w ith Different Operat ional Practices

Minimum soakaway tren ch area


Quantity of (m2 /100 chicken)
washwater Wash for di fferent percentage
used Interval removal of solids
pe r wash durin g dry muck-out
(L/chicken) (day)
95% 97% 99%

3 0.70 0.46 0.22

0.4 7 0.64 0.40 0.16

28 0.61 0.37 0.13

Note
T he above is based on a soil percolation time (rate) of 60 minutes for water to fall 150mm. (NB. the trench area requirement may
be reduced if the percolation rate is increased, pro rata to the requirements shown in Table 2; on the other hand, the trench area requirement
would need to be increased if the percolation rate is slower.)

(d) A soakaway pit or trench should be located sufficiently far away from building
foundations, watercourses and wells, in order to safeguard public health and maintain
the structural integrity of nearby buildings. A safe distance is generally 30m from
watercourses and wells, and 3m from structures.

Maintenance Requirement : Periodic removal of any sludge accumulated.

You might also like