G+5 Building... Report Date 18-Oct-17 12:48 Project Start 02-Oct-17 Project Finish 10-Jul-18
G+5 Building... Report Date 18-Oct-17 12:48 Project Start 02-Oct-17 Project Finish 10-Jul-18
G+5 Building... Report Date 18-Oct-17 12:48 Project Start 02-Oct-17 Project Finish 10-Jul-18
WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete
BES11.GG5.GG5 SubStructure
A1980 Levelling 1 1 0% 25-Oct-17 25-Oct-17 SS.Site Supervisor
A1990 Shuttering foundation 1 1 0% 26-Oct-17 26-Oct-17 MZ.Mazdoor
A2000 Reinforcement for foundation and 1 1 0% 26-Oct-17 26-Oct-17 SS.Site Supervisor
column
A2010 Concreting 1 1 0% 27-Oct-17 27-Oct-17 MS.Mason
A2030 De-shuttering 1 1 0% 03-Nov-17 03-Nov-17 MZ.Mazdoor
A2040 Fill around foundation 1 1 0% 03-Nov-17 03-Nov-17 SS.Site Supervisor
A2020 Curing 4 4 0% 30-Oct-17 02-Nov-17 MZ.Mazdoor
BES11.GG5.GG5 SuperStructure
BES11.GG5.GGround Floor
BES11.GGSkeletal Works
A2060 Plinth beam concreting 1 1 0% 08-Nov-17 08-Nov-17 MS.Mason
A2070 Plinth beam deshuttering 1 1 0% 09-Nov-17 09-Nov-17 MS.Mason
A2100 Column concreting 1 1 0% 20-Nov-17 20-Nov-17 MS.Mason
A2130 Beam concreting and deshuttering 1 1 0% 29-Nov-17 29-Nov-17 MS.Mason
BES11.GG5.GFirst Floor
BES11.GGSkeletal Works
A2210 Concreting of column 1 1 0% 22-Dec-17 22-Dec-17 MS.Mason
A2240 Concreting of beam 1 1 0% 03-Jan-18 03-Jan-18 MS.Mason
A2270 Concreting of slab 1 1 0% 15-Jan-18 15-Jan-18 MS.Mason
Page 1 of 4
G+5 Building... Project Start 02-Oct-17
Report Date 18-Oct-17 12:48 Project Finish 10-Jul-18
WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete
BES11.GG5.GSecond Floor
BES11.GGSkeletal Works
A2320 Concreting of column 1 1 0% 25-Jan-18 25-Jan-18 MS.Mason
A2350 Concreting of beam 1 1 0% 06-Feb-18 06-Feb-18 MS.Mason
A2380 Concreting of slab 1 1 0% 16-Feb-18 16-Feb-18 MS.Mason
A2310 Reinforcement and shutering of 2 2 0% 23-Jan-18 24-Jan-18 SS.Site Supervisor
column
A2340 Reinforcement and shuttering of 2 2 0% 02-Feb-18 05-Feb-18 SS.Site Supervisor
beam
A2370 Reinforcement and shuttering of 2 2 0% 14-Feb-18 15-Feb-18 SS.Site Supervisor
slab
A2330 Deshuttering and curing of column 5 5 0% 26-Jan-18 01-Feb-18 MZ.Mazdoor
BES11.GG5.GThird Floor
BES11.GGSkeletal Works
A2430 Concreting of column 1 1 0% 01-Mar-18 01-Mar-18 MS.Mason
A2460 Concreting of beam 1 1 0% 13-Mar-18 13-Mar-18 MS.Mason
A2490 Concreting of slab 1 1 0% 23-Mar-18 23-Mar-18 MS.Mason
A2420 Reinforcement and shutering of 2 2 0% 27-Feb-18 28-Feb-18 SS.Site Supervisor
column
A2450 Reinforcement and shuttering of 2 2 0% 09-Mar-18 12-Mar-18 SS.Site Supervisor
beam
A2480 Reinforcement and shuttering of 2 2 0% 21-Mar-18 22-Mar-18 SS.Site Supervisor
slab
A2440 Deshuttering and curing of column 5 5 0% 02-Mar-18 08-Mar-18 MZ.Mazdoor
Page 2 of 4
G+5 Building... Project Start 02-Oct-17
Report Date 18-Oct-17 12:48 Project Finish 10-Jul-18
WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete
BES11.GG5.GFourth Floor
BES11.GGSkeletal Works
A2560 Concreting of column 1 1 0% 04-Apr-18 04-Apr-18 MS.Mason
A2590 Concreting of beam 1 1 0% 16-Apr-18 16-Apr-18 MS.Mason
A2620 Concreting of slab 1 1 0% 26-Apr-18 26-Apr-18 MS.Mason
A2550 Reinforcement and shutering of 2 2 0% 02-Apr-18 03-Apr-18 SS.Site Supervisor
column
A2580 Reinforcement and shuttering of 2 2 0% 12-Apr-18 13-Apr-18 SS.Site Supervisor
beam
A2610 Reinforcement and shuttering of 2 2 0% 24-Apr-18 25-Apr-18 SS.Site Supervisor
slab
A2570 Deshuttering and curing of column 5 5 0% 05-Apr-18 11-Apr-18 MZ.Mazdoor
BES11.GG5.GFifth Floor
BES11.GGSkeletal Works
A2670 Concreting of column 1 1 0% 08-May-18 08-May-18 MS.Mason
A2700 Concreting of beam 1 1 0% 18-May-18 18-May-18 MS.Mason
A2660 Reinforcement and shutering of 2 2 0% 04-May-18 07-May-18 SS.Site Supervisor
column
A2690 Reinforcement and shuttering of 2 2 0% 16-May-18 17-May-18 SS.Site Supervisor
beam
A2680 Deshuttering and curing of column 5 5 0% 09-May-18 15-May-18 MZ.Mazdoor
BES11.GG5.GRoof
A2730 Insulation and testing 4 4 0% 05-Jun-18 08-Jun-18 MS.Mason
A2740 Tile roof 4 4 0% 11-Jun-18 14-Jun-18 MS.Mason
A2770 Install gutters 4 4 0% 15-Jun-18 20-Jun-18 MS.Mason
A2760 Install wood member 5 5 0% 15-Jun-18 21-Jun-18 MS.Mason
A2720 Cast concrete 6 6 0% 28-May-18 04-Jun-18 SS.Site Supervisor
Page 3 of 4
G+5 Building... Project Start 02-Oct-17
Report Date 18-Oct-17 12:48 Project Finish 10-Jul-18
WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete
BES11.GG5.GG5 Finishing
A2790 Carpentry works 5 5 0% 08-Jun-18 14-Jun-18 C.Carpenter
A2800 Insulation and plastering 5 5 0% 15-Jun-18 21-Jun-18 MS.Mason
A2780 Electrical wirings 6 6 0% 31-May-18 07-Jun-18 E.Electrician
A2810 Inner wall painting 6 6 0% 22-Jun-18 29-Jun-18 MZ.Mazdoor
A2820 External painting and coating 7 7 0% 02-Jul-18 10-Jul-18 MZ.Mazdoor
Page 4 of 4