Cost Estimation: 5.1 Costs Associated With Constructed Facilities
Cost Estimation: 5.1 Costs Associated With Constructed Facilities
Cost Estimation: 5.1 Costs Associated With Constructed Facilities
The capital cost for a construction project includes the expenses related to the inital
establishment of the facility:
The operation and maintenance cost in subsequent years over the project life cycle
includes the following expenses:
The magnitude of each of these cost components depends on the nature, size and
location of the project as well as the management organization, among many
considerations. The owner is interested in achieving the lowest possible overall
project cost that is consistent with its investment objectives.
Contingent amounts not spent for construction can be released near the end of
construction to the owner or to add additional project elements.
In this chapter, we shall focus on the estimation of construction cost, with only
occasional reference to other cost components. In Chapter 6, we shall deal with the
economic evaluation of a constructed facility on the basis of both the capital cost
and the operation and maintenance cost in the life cycle of the facility. It is at this
stage that tradeoffs between operating and capital costs can be analyzed.
Unit costs for bill of quantities. A unit cost is assigned to each of the facility
components or tasks as represented by the bill of quantities. The total cost is the
summation of the products of the quantities multiplied by the corresponding unit
costs. The unit cost method is straightforward in principle but quite laborious in
application. The initial step is to break down or disaggregate a process into a
number of tasks. Collectively, these tasks must be completed for the construction
of a facility. Once these tasks are defined and quantities representing these tasks
are assessed, a unit cost is assigned to each and then the total cost is determined by
summing the costs incurred in each task. The level of detail in decomposing into
tasks will vary considerably from one estimate to another.
Allocation of joint costs. Allocations of cost from existing accounts may be used
to develop a cost function of an operation. The basic idea in this method is that
each expenditure item can be assigned to particular characteristics of the operation.
Ideally, the allocation of joint costs should be causally related to the category of
basic costs in an allocation process. In many instances, however, a causal
relationship between the allocation factor and the cost item cannot be identified or
may not exist. For example, in construction projects, the accounts for basic costs
may be classified according to (1) labor, (2) material, (3) construction equipment,
(4) construction supervision, and (5) general office overhead. These basic costs
may then be allocated proportionally to various tasks which are subdivisions of a
project.
Back to top
5.3 Types of Construction Cost Estimates
Construction cost constitutes only a fraction, though a substantial fraction, of the
total project cost. However, it is the part of the cost under the control of the
construction project manager. The required levels of accuracy of construction cost
estimates vary at different stages of project development, ranging from ball park
figures in the early stage to fairly reliable figures for budget control prior to
construction. Since design decisions made at the beginning stage of a project life
cycle are more tentative than those made at a later stage, the cost estimates made at
the earlier stage are expected to be less accurate. Generally, the accuracy of a cost
estimate will reflect the information available at the time of estimation.
1. Design Estimates. For the owner or its designated design professionals, the
types of cost estimates encountered run parallel with the planning and
design as follows:
o Screening estimates (or order of magnitude estimates)
o Preliminary estimates (or conceptual estimates)
o Detailed estimates (or definitive estimates)
o Engineer's estimates based on plans and specifications
2. Bid Estimates. For the contractor, a bid estimate submitted to the owner
either for competitive bidding or negotiation consists of direct construction
cost including field supervision, plus a markup to cover general overhead
and profits. The direct cost of construction for bid estimates is usually
derived from a combination of the following approaches.
o Subcontractor quotations
o Quantity takeoffs
o Construction procedures.
3. 3. Control Estimates. For monitoring the project during construction, a
control estimate is derived from available information to establish:
o Budget estimate for financing
o Budgeted cost after contracting but prior to construction
o Estimated cost to completion during the progress of construction.
Design Estimates
In the planning and design stages of a project, various design estimates reflect the
progress of the design. At the very early stage, the screening estimate or order of
magnitude estimate is usually made before the facility is designed, and must
therefore rely on the cost data of similar facilities built in the past. A preliminary
estimate or conceptual estimate is based on the conceptual design of the facility at
the state when the basic technologies for the design are known. The detailed
estimate or definitive estimate is made when the scope of work is clearly defined
and the detailed design is in progress so that the essential features of the facility are
identifiable. Theengineer's estimate is based on the completed plans and
specifications when they are ready for the owner to solicit bids from construction
contractors. In preparing these estimates, the design professional will include
expected amounts for contractors' overhead and profits.
The costs associated with a facility may be decomposed into a hierarchy of levels
that are appropriate for the purpose of cost estimation. The level of detail in
decomposing the facility into tasks depends on the type of cost estimate to be
prepared. For conceptual estimates, for example, the level of detail in defining
tasks is quite coarse; for detailed estimates, the level of detail can be quite fine.
As an example, consider the cost estimates for a proposed bridge across a river. A
screening estimate is made for each of the potential alternatives, such as a tied arch
bridge or a cantilever truss bridge. As the bridge type is selected, e.g. the
technology is chosen to be a tied arch bridge instead of some new bridge form, a
preliminary estimate is made on the basis of the layout of the selected bridge form
on the basis of the preliminary or conceptual design. When the detailed design has
progressed to a point when the essential details are known, a detailed estimate is
made on the basis of the well defined scope of the project. When the detailed plans
and specifications are completed, an engineer's estimate can be made on the basis
of items and quantities of work.
Bid Estimates
The contractor's bid estimates often reflect the desire of the contractor to secure the
job as well as the estimating tools at its disposal. Some contractors have well
established cost estimating procedures while others do not. Since only the lowest
bidder will be the winner of the contract in most bidding contests, any effort
devoted to cost estimating is a loss to the contractor who is not a successful bidder.
Consequently, the contractor may put in the least amount of possible effort for
making a cost estimate if it believes that its chance of success is not high.
Control Estimates
Both the owner and the contractor must adopt some base line for cost control
during the construction. For the owner, a budget estimate must be adopted early
enough for planning long term financing of the facility. Consequently, the detailed
estimate is often used as the budget estimate since it is sufficient definitive to
reflect the project scope and is available long before the engineer's estimate. As the
work progresses, the budgeted cost must be revised periodically to reflect the
estimated cost to completion. A revised estimated cost is necessary either because
of change orders initiated by the owner or due to unexpected cost overruns or
savings.
For the contractor, the bid estimate is usually regarded as the budget estimate,
which will be used for control purposes as well as for planning construction
financing. The budgeted cost should also be updated periodically to reflect the
estimated cost to completion as well as to insure adequate cash flows for the
completion of the project.