Permanent Fence Method Statement Rev 1 2

Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

SA FENCE AND GATE Eskom Enterprise Doc No.

SAFG Eskom Kusile Date: 2012/10/16


Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

METHOD STATEMENT
INSTALLATION OF 2.4 WELDED MESH SECURITY FENCE

Documents Attached

1 Method Statement

2 QCP/ITP

3 Risk Assessment

Signature Date
Approved by: Project
Manager
SA Fence & Gate
Approved by: Project
Manager
Kusile Power Station

1
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

INTRODUCTION

THE PURPOSE OF THIS DOCUMENT IS TO OUT LINE ALL THE WORK THAT SA
FENCE AND GATE WILL BE DOING DURING THE KUSILE PROJECT. THIS WILL
INCUDE ALL THE WORK PROCEDURES AND INSTRUCTION THAT ARE MADE BY
THE SHE AND KUSILE SPECIFICATIONS

SCOPE

THIS METHOD STATEMENT WILL APPLY TO THE INSTALATION OF THE 2.4 HIGH
WELDING MESH SERCURITY FENCE AS PER DRAWING SUPPLIED BY ESKOM
KUSILE.
1. SITE ESTABLISHMENT
2. MATERIAL DELIVERY
3. DEFINITIONS
4. REFERENCES
5. RESPONSIBILITIES, AUTHORITY, ACCOUNTABILITY
6. STRIPPING AND STOCKPILLING AREAS
7. EARTHWORKS
7.1 EXCAVATIONS
7.2 PLANT AND TOOLS REQUIRED
8. PREPERATION OF INSTALLING FENCE
9. CASTING CONCRETE - READY MIX
10. QUALITY CONTROL AND ASSURANCE
11. POLES INSTALLATION
12. FENCE INSTALLATION
13. EARTHING
14. GATE INSTALLATION
15. STRAINING OF WIRES
16. CUTTING OF STEEL MESH WIRES
17. HEALTH AND SAFETY
17.1 TERMS, DEFINITIONS AND ABBREVIATIONS
17.2 RESPONSIBILITIES, AUTHORITY AND ACCOUNTABILITIES
17.3 USING OF A LADDER
17.4 PERSONAL PROTECTIVE EQUIPMENT
17.5 FIRST AID, EMERGENCY EQUIPMENT AND PROCEDURE
17.6 HOUSEKEEPING (ON A DAILY BASIS)
17.7 RISK ASSESMENT (ATTACHED)

2
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

18. ENVIRONMENTAL
18.1 VEGETATION CLEARING AND TOPSOIL REMOVAL
18.2 NOISE
18.3 DUST
18.4 EMERGENCY PREPAREDNESS
18.5 ACCIDENTAL LEAKS & SPILLAGES
18.6 FLORA & FAUNA
18.7 ABLUTION FACILITIES
18.8 SOLID WASTE MANAGEMENT
18.9 ACCOMODATION OF TRAFFIC
18.10 LANDSCAPPING & REHABILITATION
18.11 PREVENTION OF FIRE
18.12 INSTALLATION
18.13 WORKING NEAR A WETLAND

1 Site Establishment
Site Establishment was executed as per approved method statement.

2 Material Delivery
All material delivered to Kusile site will be delivered to SA Fence and Gate site lay down area. All
material will be inspected and approved by client before installation as per quality control
procedures.

3 DEFINITIONS, TERMS, ABBREVIATIONS

• “QA/QC” MEANS QUALITY ASSURANCE /QUALITY CONTROL OFFICER


• “PPE” MEANS PERSONAL PROTECTIVE EQUIPMENT
• “ECO” MEANS ENVIROMENTAL CONTROL OFFICER
• “CR” MEANS CONSTRUCTION REGULATION
• “EMP” MEANS ENVIROMENTAL MANAGEMENT PLAN
• “OHSA” MEANS OCCUPATIONAL HEALTH AND SAFETY ACT

3
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

4 REFERENCES

• PROJECT KUSILE POWER STATION STANDARDS ENVIROMENTAL


SPECIFICATION
• ENVIROMENTAL MANAGEMENT PLAN
• CONSTRUCTION REGULATION 2003
• OCCUPATIONAL HEALTH AND SAFETY ACT, ACT NO 85 OF 1993

5 RESPONSIBILITIES, AUTHORITY, ACCOUNTABILITY

The preparation, review and approval of this procedure are the


responsibility of:

• Preparation : Site Manager


• Review : Contracts Manager
• Approval : Project Manager (Eskom Kusile Power Station)
• The requirements of this Method Statement is binding on all SA FENCE
AND GATE employees and contracting bodies.
• Site Agent and Foreman are responsible for ensuring this activity is
carried out in accordance with this Method Statement.
• QA/QC officers are also responsible for ensuring that this activity is
carried out in accordance with this Method Statement and that
necessary inspection will be done.

6 STRIPPING AND STOCKPILE AREA

Stripping shall be done for the following reasons:

• Where construction vehicles will be moving


• Where temporary facilities will be placed such as toilets
• Where the fence will be erected

The contractor shall strip the topsoil which includes the top 150mm of soil (or
to the depth of the bedrock where the soil is shallower than 150mm) and root

4
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

material of cleared vegetation, for subsequent use during rehabilitation.


Topsoil shall be stripped from all areas of the working area where topsoil will
be impacted by construction activities including areas for temporary facilities,
as directed by the Engineer.

Stockpile area shall be identified by Eskom power stations EO (environmental


officer) for SA Fence and Gate to comply to. Topsoil and subsoil stockpiles shall
not exceed 2m in height and shall be so placed as to occupy the minimum
width compatible with the natural angle of repose of the material, and shall be
taken to prevent the material from spreading over too wide a surface.

7. Earthworks

Clearing areas of all grass, weeds, shrubs, debris, including grubbing up all
roots and cart away all vegetation and debris to indicated spoil areas.

Once the clearing is completed the setting out will be carried out by the
qualified Surveyor, according to the coordinates on the drawings prior to any
excavation commences.

All excavations work will be performed in accordance with method and


specification under 1200D.

The excavation material will be stockpiled at the designed areas approved by


Eskom Kusile power station.

Tipper trucks will be used to transport the top soil to the area of the stock pile.

Compaction and backfill to be carried out to the specifics according to the


inspection test method.

Compaction of 90 Mod AASHTO will be applicable on the backfill around fence


mesh trench, fence post and G5 material and will be randomly tested by an
independent laboratory.

5
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

7.1 Excavation

• All excavations shall be done by the following methods:


o Hand excavation
o TLB with small bucket
o K9 Digger
o Trencher
• All excavations shall be carried out under supervision and the excavator
operator shall be trained, assessed and deemed competent to operate the
excavator, by the supervisor
• The excavator shall be used according to its design and functionality
• Excavation required is for 300mm deep wire mesh installation, post
foundation as per drawing (146838-OUYX-S3916A) and for earthing on
outer fence as per drawing (Ref 0.54/393)
• All excavated trenches shall be barricaded to prevent any person/any
excavator and other construction vehicles on site from falling into the
trench or the excavation
• The site plan from the client shall be used to avoid digging and damaging
underground services thereby endangering the safety and health of any
personnel. Testing to be done by contractor prior to commencement of
worked to locate any underground services in planned work area.
• An approval excavation permit shall be obtained from Eskom prior to
any excavation activity.
• The depth of the service must be known or determined to prevent
damages on services
• If any service is damaged Eskom will be notified immediately
• A pre-ignition start inspection shall be conducted prior to assume
excavation

6
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

7.2 PLANT & TOOLS REQUIRED FOR THE ACTIVITY

• Tipper truck
• Roller
• Grader
• Excavator
• TLB
• Generator
• Front End Loader
• Water Tank
• Shovels, Picks, jackhammer, Gwala , Grinder and Drill Machine

8. Preparation of installing the fence

Once the earthwork is completed, inspected and approved the preparation of


the fence will commence.

A 2.7 Welded Mesh (for the installation of 2.4m high fence) will be inspected
at the lay down area then transported to site by a LDV with a trailer.

All employees will be doing the preparation by hand and full PPE will be worn
at all times

9. Casting of concrete - Ready mix

• Before concrete is cast inspections will take place by a competent


person.
• 25Mpa ready mix will be delivered on site with a POD that will be used
by the employees.
• The casting of the concrete will be done direct from the ready mix truck
by the use of the shoot; in case a wheelbarrow is needed it will be
available on site. It will be inspected on a daily basis.

7
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

• Poles will be stabilized until the concrete has cured for the fence to be
installed.
• A slump tests will be done on each truck and when cubes are being
taken (the slump must be 90mm). Cube samples (6 cubes) will be taken
at least one per day or per 50m3 of concrete.
• Test cubes will be tested by an independent laboratory. 3 at 7 days and 3
at 28 days. Results will be forwarded to Eskom for verification.

10. QUALITY CONTROL AND ASSURANCE

All quality control will be executed by SA Fence and Gate in conjunction with
prescribed specifications of Eskom.

A Quality control officer of SA Fence and Gate will liaise with Eskom’s quality
department to ensure that all requirements are met.

11. Poles installation:

The poles will be installed as per drawing 146838-OUYX-S3916A-F and


client’s specification. Post installation will comprise of the following:

• Corner posts to be installed at fence corners with Two metal stays


• Straining Posts will be installed at a maximum of 40m intervals with two
metal stays.
• Intermediates will be installed between all corner and straining posts at
a maximum of four meter intervals.

12. Fence installation

The fence will be installed as per drawing 146838-OUYX-S3916A-F and


client’s specification. Fencing shall be 2.4 m in height and will comprise of
the following:

• A minimum of Five equally spaced strands of high tensile wire, with the
lowest strand being at ground level and the highest being at 2.4m

8
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

• The bottom 400mm of the welded mesh will be bitumen coated and
buried 300mm below the ground.
• Welded mesh fencing of 2.4m in height, secured to the wire strands and
posts, with binding wire.
• Topped with overhangs secured to each post and intermediate with two
bolts.
• Barbed wire to be attached to overhangs.
• Trench will be backfilled and compacted after installation of welded
mesh fence, using the TLB or by hand and a walk behind roller.

13. Earthing:

All earthing will be installed / executed in compliance with client specification


and drawings. Earthing will be done with 10mm solid copper rod connected to
3m long 16mm earth spikes at intervals of maximum 20m. Earthing at gates
and removable panels will be done at each end.

Earth rod of 10mm solid copper to be connected to earth spike with CADWELD.
Earth rod of 10mm solid copper to be buried in ground as per details and
connected to fence poles with 50mm x 50mm earth clamp. Earth clamp to be
fixed to poles with a 16mm bolt.

• Setting out and determining earth spikes positions.


• If any earth spike positions have an impact on the environment the input
of the Environmental Officer will be required and work executed to their
prescribed method.
• Approval by client for earth spike positions.
• Excavations to be done by hand (shovel and pick) and / or machine
(TLB).
• Excavate 1.5m x 1.5m x 1m deep hole to create workspace.
• Excavate .4m x .6m x 1m deep trench for 10mm solid copper rod.
• Earth from excavations to be reused for backfill, thus no carting away of
earth.
• Excavations to be barricaded and make safe.

9
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

• Insert 16mm - 1.5m solid copper rod into ground 1m below ground level
in excavated hole.
• Fit 16mm coupler and insert second 16mm - 1.5m solid copper rod into
ground.
• CADWELD 10m solid copper rod to top of earth spike.
• Lay 10mm solid copper rod into trench and connect to fence pole.
• Drill 17mm diameter hole into fence pole for earth clamp 100m from
ground level.
• Connect 10mm solid copper rod to fence pole with 50 x 50mm earth
clamp and fix clamp to pole with 16mm diameter bolt and nut.
• Ensure that good connection is achieved at CADWELD and Earth Clamp.
• Client to inspect connections and 10mm solid copper earth rod before
closing excavations.
• Excavated material to be used as backfill. Backfill to excavations in layers
of 150mm and compacted every layer.

14. Gate installation

The gates will be installed as per drawing 146838-OUYX-S3916 and client’s


specification. Gates shall be 2.4 m in height and will comprise of the following:

• Gates to suite the width of access as required


• Gate posts to be installed in the same manner as mentioned above, used
for corner and straining posts.
• Gates to be attached to gate posts as per client specifications.(drawing
146838-OUYX-S3916)

15.Straining of wires

Lines will be strained between two poles as required by specification. Straining


wire will be done by hand using a fence puller to tension the straining wire. It
will then be tied to the bolt that is attached to the post, tightened by a nut.

10
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

16. Cutting of steel/Mesh wire

• Steels will be cut using a portable grinder or pliers used by somebody with
experience and have been inducted
• All waste generated from grinding of Mesh wire shall be disposed of at
demarcated areas as indicated by client.
• All cutting equipment compiled with OHS act in terms of safe guarding.
• Safety goggles shall be used at all times to protect employees’ eyes from
sparks or hazardous material entering eyes.

17. Health and Safety

This method statement will apply to the clearing, excavating, compacting and
loading of material, 2.4 welded mesh fence, waste management, casting
concrete, plant equipment and PPE to be worn on site when carrying out this
tasks/works by SA FENCE AND GATE.

17.1 TERMS, DEFINITIONS, ABBRIVIATIONS

“QA/QC” Means Quality Assurance / Quality control Officer


“PPE” Means Personal Protective Equipment
“SO” Means Safety Officer
“OHSA” Means Occupational Health and Safety Act
“EO” Means Environmental Officer
“Excavation works” Means the making of any man made cavity, trench,
pit or depression formed by cutting, digging, or scooping.

17.2 Responsibilities, Authority and Accountability SHEQ will ensure :

• All employees and contractors involved in this activity are competent to


do so

11
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

• All employees and contractors are required to conduct this work


undergo a SHEQ induction.
• All employees and contractors involved in this activity are trained with
regards to the content of this Method Statement

17.3 Using of a ladder

• Training will be provided


• Daily toolbox talks will remind employees on how to use a ladder
• Not more than one person on a ladder
• When a person is on the ladder one person must always hold or support
the ladder
• Ladder instructions must be read and practiced daily
• Don’t use the top 3 rungs on the ladders.
• When you have tools that you want to use on the top of the ladder use a
bucket
• Three point contact is very important
• Eyes on path at all times

17.4 Personal Protective Equipment

We shall wear the Personal protective equipment clothing listed at all


times when on site. No workers shall be permitted on site without the
full PPE as specified
• Hard hat
• Goggles
• Overalls with high visibility reflector vest
• Steel toe boots / gumboots in wet areas
• Dust mask
• Ear plugs (when working in a noisy area)
• All employees will be equipped with their PPE and no one shall be
on site without the above required PPE
• The PPE clothing is applicable to everyone coming on site

12
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

17.5 First Aid, emergency equipment and procedure

• We will ensure that persons at work receive prompt first aid treatment
in case of injuries or emergency
• We will provide first aid box or boxes at or near the work place which
shall be available and accessible
• No persons is allowed to carry on with their task in case an emergency
siren or alarm sound
• Report any incident/accident immediately to supervisor or safety
representative on site
• Every minor injury shall be treated on site by the competent first aider
as OHS act
• All person working on site will undergo induction, safety awareness
training and environmental training with regarding emergency
procedures, fire, or electrical shut down

17.6 Housekeeping (on daily basis)

• We shall continuously maintain and implement housekeeping on our


construction site to avoid injuries to persons on site, client, visitors
and or sub-contractors
• Everything in its place. No materials or hand tools will be lying on the
ground when not in use.
• We shall store them safely in the toolbox on site
• All waste scrap produced on site shall be removed at appropriate
intervals to enhance a healthy and safe environment for persons
working on site
• No smoking or dumping on site shall be permitted unless it is a
demarcated smoking area to avoid cigarette butt on the ground.

13
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

18. ENVIROMENTAL

18.1 VEGETATION CLEARING AND TOPSOIL REMOVAL

SA Fence and Gate shall ensure that the clearance of vegetation is strictly
restricted to the area required for the work (such as the fence will be erected,
toilets will be placed and access roads where vehicles and workers will walk).

• All cleared vegetation will either be mulched and mixed into a topsoil or
disposed at an approved disposal site
• All disposal of vegetation by burying or burning is prohibited
• Topsoil will be stripped which will include the top 150mm of the soil, for
subsequent use during rehabilitation and re-vegetation.

18.2 Noise

The contractor does envisaged that the project will generate excessive noise
(more than 85 dB), but instances whereby the equipment such drilling machine
will be used, the workers will be advised to wear ear plugs.

18.3 Dust

It will be suppressed according to the client’s standard environmental


specification. Eskom’s Environmental officer will issue a permit to SA Fence
and Gate for extraction of water to be used for dust suppression. A water
tanker shall be permanently available on site for the control of dust
generation, and SA Fence and Gate shall ensure that the sprays do not
generate excess run off. During high wind conditions, SA Fence and Gate shall
comply with the Engineer’s instructions regarding dust dumping measures.

An appropriate number of water tankers shall be permanently available for the


control of dust generation, and the Contractor shall ensure that the sprays do
not generate excess run off. There shall be sufficient water tankers of

14
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

adequate capacity to enable the dampening of all working areas and access/
haul roads. During high wind conditions, the Contractor shall comply with the
Engineer’s instructions regarding additional dust-damping measures.

18.4 Emergency preparedness

Telephone numbers of emergency services, including local fire fighting


services are pasted in all offices of SA Fence and Gate, and all employees
are made aware on the evacuation routes, from all their workplace, in case
there is an emergency of fire for them to relocate their workplace.
Assemble points are noted for such cases.

18.5 Accidental leaks and spillages

In the event of a spill, the source of the spillage shall be isolated, the
spillage will be contained. The area where the pillage incident has occurred
shall be cordoned off and secured. SA Fence and Gate shall maintain spill
kits on the site at all times and shall ensure that there is always adequate
supply of absorbent material available in the spill kit.

18.6 Flora and Fauna

Poaching of animals will not be allowed on site, should animals be seen on


site, the will be reported to the Environmental Officer competent to rescue
such animals.

18.7 Ablution facilities

SA Fence and Gate shall provide adequate ablution facilities for workers in
the construction camp. Acts of excretion and urination shall be strictly
prohibited other than at the facilities provided

15
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

I. Toilets shall be located within 100 m from any points of work


but not closer than 50 meters to any watercourse or water
body,

II. Mobile toilets will be provided so that it will be moved as the


process of fence erection goes on.

III. Toilets shall be secured to the ground to prevent them from


toppling due to wind or any other cause;

IV. No spillage shall occur when the toilets are cleaned or emptied
and the contents shall be properly removed from site by
Sanitech,

V. Discharge of waste from toilets into the environment and burial


of waste is strictly prohibited,

VI. Toilets shall be provided with external closing mechanism to


prevent toilet paper from being blown out, and

VII. Toilets will be emptied before long weekends and builder’s


holidays and shall be locked after working hours.

18.8 Solid waste management

The management of solid waste at the working area shall be strictly controlled
and monitored; the quantities of waste generated shall be minimized as
wheelie bins will be provided by Roshcon. Littering will be avoided, there will
be no burying, dumping and burning of waste material shall occur. Bins shall
never be allowed to overflow and shall be emptied twice in a week. All solid
waste will be collected by Roshcon and be disposed off-site at an approved
landfill site.

16
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

18.9 Accommodation of traffic

SA Fence and Gate shall ensure vehicle traffic safety at all times and shall
implement safety measures. Fence and Gate shall control the movement of
all the vehicles and equipment including of the suppliers so that they
remain on designated routes. On gravel road on the site and within 500 m
of the site, the vehicles of Fence and Gate and the suppliers shall not
exceed a speed of 40 km/h.

18.10 Landscaping and Rehabilitation

Rehabilitation will be done during the process of erecting (on-going process


e.g. before erecting fence on point B, the top soil that was removed from point
A, will be backfilled to where it was removed.)

18.11 Prevention of fire

SA Fence and Gate shall take adequate precautions to ensure that the fire
hazard on and near the site is reduced to a minimum. Smoking shall not be
permitted on site, it will only be allowed in areas designated as smoking area.

18.12 Installation

Installation of all material will be done as per the client’s standard


environmental specification, together with the addendum from DEA.

18.13 Working near a wetland

• Before construction activity begins, silt fence shall be installed upslope


of the wetland or adjacent to any drainage ways that lead to the
wetland. Any damaged silt fence will immediately be repaired or
replaced adjacent to a wetland and sediments collected down slope of
17
SA FENCE AND GATE Eskom Enterprise Doc No. SAFG Eskom Kusile Date: 2012/10/16
Investment Holdings (Pty) Ltd Kusile Power station 002/2012 Rev 1 Pages: 18

fence shall be removed. In addition of controlling sediment, the silt


fence will serve as a construction limit to prevent damage to existing
vegetation.
• Stockpiling of materials adjacent to a wetland will be avoided.
Construction materials or debris will not be allowed to spread or be
blown into the wetland. Vehicles and equipment will not be parked near
a wetland because they will damage vegetation and increase erosion.
• Upland vegetation adjacent to the wetland serves as a buffer that slows
water and filters sediment. The existing buffers of vegetation will be
protected in order to preserve wetlands. If it is necessary to disturb the
soil adjacent to a wetland, vegetation will be restored as quickly as
possible.
• Where earthwork is being undertaken in close proximity to any
watercourse, slopes shall be stabilised using sandbags or geotextile
fabric to prevent sand and rock from entering the water channel.
• Appropriate rehabilitation and revegetation measures for the wetland
banks shall be implemented timeously, including stabilizing the banks
after construction. The various soil layers shall be removed and
stockpiled separately. Following the completion of the construction
activities, the soil layers shall be returned in the reverse order to which
they were removed.

18