Presentation-3 Chapter Two-1 PDF
Presentation-3 Chapter Two-1 PDF
Presentation-3 Chapter Two-1 PDF
.
Consent Legal capacity Legality of the object
Consideration Formalities
Contract
1. Consent
Capability of parties
Capacity means competence to enter in to a legally
binding agreement.
Legal capacity is of two types: Personal (Own)capacity;
and Representative(Agent)capacity;
The agreeing parties should be capable of contracting
and give their consents sustainable at law
According to this provision, no agreement is deemed an
enforceable contract if any of the parties is incapable of
contracting. Capability of persons is defined in the
introductory part of this course as stated in Article
1678(a) of the civil Code. Just as an example, an
agreement with a minor (under the age of 18.) is not
deemed as an enforceable contract. As is agreements
with those considered mentally in competent, mentally
ill, under the influence of alcohol and other drugs
Capability…continued
The following may not have (legal) capacity to enter
in to contract & bind themselves. These are:-
Minors (under the age of 18);
Companies adjudged or declared bankrupt;
Judicially interdicted persons;
Legally interdicted persons;
Persons, whose civil rights are suspended by the judgment
of the court;
Non-nationals, unless permitted by law or special
prerogative;
Non-authorized Agents;
Agents, whose Power of Attorney has been revoked;
Agents , the Scope of their Power of Attorney does not
cover the intended transaction(ex. Tendering or
Negotiation or Contract Signing, .); and
Others;
3. Consideration
Consideration is 'the price for the promise'. I.e it is what
one party can get from the other party in return for performing
contract obligations.
Consideration involves a benefit moving from the offeree to the
offeror in exchange for the promise. Usually it is money or a
promise to pay money but it can also be some other benefit.
Consideration must be:
Of some value, but not necessarily adequate
Additional to the duty in the law
Additional to previous contract agreements
For a future act
• If one party makes a promise and the other party offers nothing
in return for that promise, the promise is unenforceable due to
lack of consideration. This can best be exemplified by a charity
organization withdrawing its promise to do something without
expecting anything in exchange. The decision to keep the
promise is at the discretion of the charity organization.
In case of a construction contract, if a contractor
4. Legality of the object
The objects of the contract is sufficiently defined and is possible
and lawful
The object of the contract is the obligation to perform
something. The lack of an object or an effective (defined,
possible, lawful, and freely determined by the parties) object
prevents the formation of contract, makes it non-existent, of no
effect, null and void. Impossible object can be objects that
couldn’t be fulfilled by an average person of the contracting
party’s capability (for example to sale a house which you don’t
have) while illegal objects are those which are not permitted or
are immoral to perform. Such activities may be like agreements
to commit crimes or civil wrongs, agreements which may injure
the state, drug lording/trafficking, promotion of corruption,
agreements which limit a person's ability to carry out trade, etc.
Please, see Article 1678 (b) cum Article 1711, Article 1718 of the
Civil Code)
5. Formalities
Form may mean types of contract.
Form may also mean the making of the contract orally or in
writing.
In this case, form is related with the validity & proof of the
contract itself.
Should the contract is to be made in certain prescribed form, it
means that contract should be made in writing. See Art. 1719
The contract is presented in the form provided by law, if any
If there is no special form provided by law, the parties can agree
the contract to be in the form that suites them. However, the law
usually stipulates special form for some trades. For example, a
contract involving an immovable object should be in a written
form and needs to be registered by the authorities. Similarly, any
contract involving public organizations should be in writing. As do
contracts of long time such as of guarantee, insurance contracts.
See Article 1727 of Civil code
Formalities…continued
Formal Informal
Interpretation Interpretation
By the By the
By the contract By the
By arbitral Conditio
ing Engineer
the tribunal ns of (FIDIC
Contract parties Clause20.1)
court (FIDIC cl. (Civil Code By the
20.6) (FIDICClaus
Art. 3307-
e1.2)
3324 )
Adjudicato
r
(Article 25-26
Effects of Contract…Continued
Frustration
(contract was executable at the time of
agreement but subsequent events (out of
control of both parties) made it impossible
(not harder or more expensive))
• Force majeure (war, earth quake, natural hazard)
Breach
(failure to carry fundamental obligations
under the contract)
– Leads to compensation and/or termination
– Famous in construction as liquidated
damage
Types of Contract
Local Construction
Public Condition of Contract
• The Standard Conditions of Contracts
in use in Ethiopia i.e. the Conditions
of Contract:
» Of the MoWUD( Ministry of Works & Urban
Development); and
» PPA (Public Procurement Agency) under
the Ministry of Finance & Economic
Development).
• The PPA Conditions of Contract is
issued in January 2006 and 2011.
• it is applicable to all possible sorts of
public procurement.
• The 2006 PPA GCC is composed of 62
46
Clauses
Public Condition of Contract
– It contains the following five parts.
– General; (Clause 1-Clause 26)
– Time Control; (Clause 27-Clause 32)
– Quality Control; (Clause 33-Clause
36)
– Cost Control; (Clause 37-Clause 54)
– Finishing the Contract; (Clause 55-
Clause 62)
47
Public Condition of
Contract
General
(Clause 1-Clause 26)
48
Priority / Precedence
• All efforts should be made for the documents to be
supportive of each other.
– If discrepancy [most GCCs –PPA-also usually clearly
stipulated in the PCC] provide provisions for overruling:
– Agreement
– Letter of acceptance
– Contractor’s bid
– Special Conditions of Contract
– General Conditions of Contract
– Specifications
– Drawings
– Bill of Quantities or Activity Schedule
• .ContractProferentum
• Ruling law - the law of the country the work in
executed.(FDRE)
– International contractors prefer international laws and chamber of
arbitrations.
49
Communication
50
Employer
• Has responsibilities to:
• Pay the due payments for the contractor;
• Provide the site and right of access to it in
due time;
• Look into the statutory aspects of the
construction such as permission to
construct, custom clearance etc;
• Employer’s personnel and other contractors
to cooperate with contractor;
51
Power of Engineer
52
• Issuing variation, which exceeds XXX
amount
• Issuing variation, if the sum of all
variations issued has exceeded X% of the
Contract Price;
• Certifying payment if the contract price
will be exceeded;
• Issuing any taking-over certificate;
• Authorising the use of provisional sums in
excess of the monetary limit for variations;
• Certifying additional payment
• Issuing Defect Liability Certificate
– Risky (emergency) situations are
always exempted 53
Engineer’s approval
• In most cases the Engineer’s approval
doesn’t relieve the contractor of his
duties.
• Even the engineer’s approval of as built
drawings may not relieve the contractor
of his duties if work wasn’t executed
accordingly
54
Sub contract
• Subletting
• Usually not allowed to sublet the whole work
• Is to be held responsible for the performance of his
subcontractors;
• Require Engineers approval and without the
approval of the Employer in writing.
• Some countries specify trade contracting in the first
place (to encourage SMMEs)
• Subletting doesn’t include provision of labor, supply
of material according to spec, subcontracting to a
pre-declared contractor
55
Risks
• Employer's (Excepted) force majuere risks
• War, hostilities, rebellion, revolution
etc
• entitle the contractor for Excusable
delays or Excusable compensable
delays
• Contractor is not normally required
to insure for such risks
• However, some of these risks are
insurable (eg defaults from designer),
• Employer can insure for such risks but
can also provide the premium to
contractor to insure together with 56
contractor’s risks
Insurance of work
• Under PPA, Contractor need to insure
– Loss of or damage to the Works, Plant, and
Materials;
– Loss of or damage to Equipment;
– Loss of or damage to property (except the
Works, Plant, Materials, and Equipment) in
connection with the Contract; and
– Personal injury or death.
57
Further Requirements
• Evidence requirment.
• Adequacy ( notification of changes)
58
Cost of Insurance
• Premium is an amount to be paid for a
contract of insurance
• Contractor’s should include cost of
insurance in their tender
• they should be provided details of
information , excess levels etc
59
Excess / Deductibles
• Purpose of specifying excess levels in
tender documents
• Excess level affect the premium
• Common bases for pricing
• Excess levels requires the insured to
suffer the first part of any claim . Makes
him take care and exclude trivial claims
which incur insurers administration costs
greater than value of claim
60
others
• Remedy on contractor’s failure to insure
• Insurance in the joint names
• Cross liability clauses
• Indemnity
61
Site inspection & Tender
sufficiency
• Contractor encourage to inspect site before
tender and satisfy himself:
– necessary information, so far as is practicable, having
regard to considerations of cost and time, as to risks,
contingencies and all other circumstances which may
influence or affect his Tender
• form and nature thereof, including the sub-surface
conditions,
• the hydrological and climatic conditions,
• the extent and nature of work and materials necessary for
the execution of the Works
• the means of access to the Site and the accommodation he
may require,
• Availability of resource and skill
• No enough resource and time to carry out thorough
investigation
– Employer is asked to make available information
• Usually collected for design purpose (design (review)
report) 62
• The omens on interpretation lies on the contractor
Site inspection & Tender
sufficiency
• Tender submitted is assumed to
made with due consent and
satisfaction of contractor
– If an unusually adverse conditions occur
(which couldn’t have been foreseen by a
knowledgeable contractor), contractor
can be compensated for time or/and
cost.
– Interpreting ‘unusually adverse
condition’ is a major matter of dispute
63
Time
Time Control
(Clause 27-Clause 32)
64
Program
• Often submitted before signing
Agreement Form and needs to be
approved by Engineer
• Mobilization (if applicable) and detailed
work programme.
• The details and time for submission to be
stated in the special condition of contract.
• The Engineer’s approval of the Program
shall not alter the Contractor’s obligations
65
Extention of Time
Disruption Claims
Prolongation Claims
Acceleration
Concurrent Delays
Successive Delays
Critical and Non Critical Activities
Time at Large
66
Extention of
Time...Continued
• Usually incorporate possibilities of
extension of the intended completion time
• Otherwise, given the possibility of
change clauses, time may be put at
large
• Under time at large condition,
Contractor expected to complete
work in a reasonable time
67
Quality Control
(Clause 33-Clause 36)
68
Execution of the work
• Contractor is obliged to perform the work, with
due diligence, with strict conformity of the
contract (provided that it is legally and physically
possible) and to the satisfaction of the Engineer
• Work to be in accordance to the drawings and
specifications
• If specs and drawing are generic, work and material to be
of the highest quality-that approved by the Engineer
• Contractor should care for the work executed
and keep it safe
• The contractor controls the resources and runs
the execution of the work;
• The site operations, construction methods and programms
of execution should be left for him;
– However, Engineer can disapprove programs and
construction methods if feels doesn’t conform with contract or
safety;
69
Key Resource Deployment
• Contractor is expected to comply
with:
– Key personnel requirements
– Key equipment requirements
– Make workmanship to the quality
specified
– Use the appropriately specified
materials
– keep the operations safe, etc
• The Engineer is at liberty to
disapprove: 70
Workmanship and Material
• Contractor is expected to execute
the work
– Using quality material and
workmanship specified for
– If, upon inspection, work is not to
quality specified contractor will be
asked to rectify
• Cost of inspection could be covered by
contractor if work was faulty
71
Cost Control
(Clause 37-Clause 54)
72
Contract Type
• An Admeasurements Contract with a Bill
of Quantities
• A Lump Sum Contract with an Activity
Schedule
73
Change in BOQ
• Rate will be adjusted if the
increment or decreament of quantity
exceeds:
– in the Bill of Quantities for the
particular item by more than 25%
– the change exceeds 5% of the Initial
Contract Price.
– Both condition have to be satisfied
• The rationale for this is that the basis of the
tender is no longer be valid if the quantities
either increase or decrease substantially. 74
Change in
BOQ...Continued
• Clients prior approval is required if thereby the
Initial Contract Price is exceeded by more than
15 %, .
• The Contractor will submit detail costbreak down
if requested by the Engineer.
75
Variation
• Increase or decrease the quantity of any
work (other than by re-measurement).
• Omit any such work.
• Change the character or quality of any such
work.
• Change lines, levels, dimensions.
• Execute (necessary) additional work.
• Change the sequence or timing of
construction.
76
Variation...Continued
• Variation should be within the scope of
the work
• Provide provision for procedures and
conditions to fix rates of altered items
• In most cases, Engineer given the
authority to give change orders and
fix rates
• Note: A contractor is not required to
sign, approve or even agree to a variation
order. It is an order to do certain works.
77
Variation...Continued
• the Contractor shall provide a
quotation for carrying out the
Variation
• If the Contractor’s quotation is
unreasonable, the Engineer may
order the Variation and make a
change to the Contract Price
• Provisions for contractor to
disagree but still execute
78
Payment
• Contractor shall submit to the Engineer
monthly statements .
• The Employer shall pay the Contractor
within 30 days.
• Interest(at prevailing bank interest rate)
for delayed payment by the client
• Minimum interim amount shuld be
specified
79
Payment Form
• Work Done
plus Variations
plus Dayworks
plus Contract Price Adjustment (CPA)
less Retention
plus Materials on Site (MoS)
less Advance Payment repayment
plus Any other amount
80
Compensation Events
Failure to give possession of site
Delay in issuing drawing
Adverse physical, political or economical
conditions
• Delay in Advance payment .
The effects on the Contractor of any of the
Employer’s Risks.
• Contractar to uncover or to carry out
additional tests upon work, which is then
found to have no Defects.
81
DayWork
Variations where it is necessary or
desirable to instruct work on a daywork
basis e.g emergency work, or other works
where BoQ rates do not apply or cannot
be extrapolated.
• Daily records.
• Monthly statement.
82
Contract Price Adjustment
Sub-Clause 47.1.
Increases or decreases to be determined
in accordance with Part II (Particular
Conditions).
83
Methods of Calculating CPA
• The most common methods are
– Proven Cost Method
– Formula Method
84
Cost Control
• contractor is required, at tender stage, to
detail those elements of his costs which
he requires to be subject to CPA.
• These details include the actual cost and
supplier of the various elements upon
which the tender was based.
• The contractor is then reimbursed the
difference between these “Basic Costs”
and the "Actual" invoiced cost of those
same items when they are purchased.
85
Proven Cost Method
Description Unit Qty Basic Price Current Price
Difference CPA
Cement qt 200 300.00 400.00
100.00 20,000.00
Diesel l 1000 10 15 5.00
5,000.00
Total CPA for this Month (Birr)
25,000.00
86
Formula Method
87
Formula
Method...Continued
• Base date = 28 days prior to the deadline
for bid submission
• The sources of indices shall be those
listed in the Contractor’s Bid, as approved
by the Engineer.
88
Retention
5% limit.
Withhold 10% of IPC until 5% limit
reached.
50% released at Taking Over.
50% released at Defects Liability
Certificate.
The contractor can replace it with
Retention Money Guarantee.
89
Advance Payment
• Interest free Up to 30% to the Contractor
for mobilization and front end expenses
for that specific project
• Repaid by deductions from IPC’s.
• Exact terms and conditions of this loan
contained in Particular Conditions and the
Appendix to Tender.
• The retention on each IPC is calculated as
a % of the total value of work done
(including variations, dayworks and CPA) .
90
Advance
Payment...Continued
• Unconditional Bank Guarantee in a
form and by a bank acceptable to the
Employer, denominated in Ethiopian Birr in
the amount of the advance payment.
• The Guarantee shall remain effective until
the advance payment has been repaid
• The Contractor is to use the advance
payment only to pay for Equipment, Plant,
Materials, and mobilization expenses
required specifically for execution of the
contract(supported by invoice)
91
Any Other Sum
• Interest on late payments.
• Claims. Clause
• Bonus Payments (if applicable).
92
Liquidated Damages
• Sub-Clause 49.1.
• Pre agreed amount stated in the Appendix
to Bid
• Types of damages by the client
– The additional cost of supervision consultants.
– Benefit obtained from completion of the
project
93
Finishing the Contract
(Clause 55-Clause 62)
94
Completion
• Contractor shall request the Engineer to
issue a certificate of Completion of the
Works.
• The Employer shall take over the Site and
the Works within seven days of the
Engineer’s issuing a Certificate of
Completion
95
Hand over
• Upon substantial completion, contractor can ask
for taking over certificate
– Work need to pass inspection and contractor
promises to rectify defects and complete
outstanding works during defect liability period
• Taking over can be partial
• Final certificate is issued after defect liability
period
– Contractor is supposed to hand in as built
drawings and maintenance manual the work
96
Final Payment
• Final payment
• Payments after certification of
acceptance-after defect liability
period
• Net balance including retention
money
• Due within reasonable days of
submission of final statement
97
Termination
• Contracts can be terminated if one side
defaults to annul/nulify the contract.
– PPA
• Not planned or unauthorised stopage by
contractor (for 28 days)
• Instruction by engineer to delay the work that
stood long (more than 28 days)
• Liquidation (other than reconstruction or
amalgamation) or bankruptcy by Employer or
Contractor;
• Certified payments not made for a long time (more
than 90 days after certification)
98
Termination
• PPA’s provisions
– The Engineer gives Notice that failure to
correct a particular Defect is a fundamental
breach of Contract and the Contractor fails to
correct it within a reasonable period of time
determined by the Engineer;
– Failure to maintain a required Security
– Delay more than by the number of days for
which the maximum amount of liquidated
damages can be paid.
– If the Contractor, in the judgment of the
Employer has engaged in corrupt, fraudulent,
collusive or coercive practices in competing for
or in executing the Contract.
99
Termination payments
• Termination payments
• If a project is terminated due the
Employer’s defaults
• Payments are to be made as if
contract is discharged
• Compensations for the losses
(including losses in benefits) are also
paid
100
Adjudication
• Procedures in PPA
– Adjudicator to be proposed by the Procuring
entity in the BDS
– If bidder doesn’t agree can reject, then can be
assigned by a specified Appointing body
– Contractor should forward issue to
adjudicators within 14 days
– Adjudicators should give opinion within 28
days
– If no party refers the case to arbitration within
28 days, decision by the adjudicators to be
binding and final
– Irrespective of decision, cost of adjudicator to
be shared 101
Contract
International Construction
Contract
Introduction
This part of the Course deals about international
construction contract based on the FIDIC
international Conditions of Contract.
The specific FIDIC conditions of contract to be
referred shall be that of the MDB Harmonized
Edition, 2006.
The delivery method adopted by the said
conditions of contract is that of design, bid &
build (DBB).
This condition of contract has been approved by
all major international financial and
development institutions.
Structure of the MDB Harmonized Edition
The said condition of contract is divided in to 20
major clauses & 177 sub-clauses;
Introduction
The Legal Part
The Contract Agreement;
The (latest) Minutes of Meeting, if any;
Others, if any;
Introduction
The Commercial Part
The Performance Security Form;
Others, if any
Introduction
The Technical Part
The Technical Specifications;
The Drawing;
The Bill of Quantities;
Others, if any;
The Contract Agreement shall also
declare the priority of the Contract
Documents i.e. which Contract Document
shall have precedence or priority over
the other in case of ambiguity or
discrepancy between or among the
relevant Contract Documents.
MDB FIDIC Harmonized (Edition 2006)
The major clauses are the following:
Clause 1: General Provisions
Clause 2: The Employer
Clause 3: The Engineer
Clause 4: The Contractor
Clause 5: Nominated Subcontractors
Clause 6: Staff & Labour
Clause 7: Plant, Materials &Workmanship
Clause 8: Commencement, Delays & Suspension
Clause 9: Tests on Completion
Clause 10: Employer’s Taking Over
Clause 11: Defects Liability
Clause 12: Measurement and Evaluation
Information
Clause 4.1 (a) & (b) design information, in case where the
Contractor is required under the Contract to design part of the
permanent Works;
Clause 4.24 geological or archeological finds(Fossils);
Clause 5.4 submitting evidence in relation to payments made to
the nominated sub-contractors, as the Engineer requests;
Clause 6.10 details of Labour & Equipment;
Clause 8.3 programme & revised programme;
Clause 12.1 particulars as requested by the Engineer information
pertaining to measurement of Works;
Clause 13.5 in relation to provisional sums submission of
quotations, receipts , vouchers & accounts or receipts for
substantiation of the use of the said sums;
Clause 13.6 on use of Day Work items, on daily basis;
Clause 14.3 submitting monthly statements to the Engineer for
payment purposes;
Clause 20.1 contemporary records as per the request of the
Engineer;
Obligation to supply Information & Notice
Notices
Clause 1.9 giving notices in relation to delayed drawings or instructions by
the Engineer;
Clause 1.13 giving of all notices in relation to the execution & completion of
the Works & remedying any defects therein;
Clause 2.1 giving notice to the Employer in case of failure of the Employer in
providing possession of Site;
Clause 4.2 in case of submission of the Performance Security copy to the
Employer;
Clause 4.12 in case of encountering unforeseeable physical conditions: to the
Employer;
Clause 4.16 notice to be given to the Engineer in relation to transport of
Goods & Plant to be delivered to the Site;
Clause 7.3 giving notice to the Engineer in case of any work is ready & before
it is covered up, put out of sight, or packaged for storage or transport or
inspection;
Clause 8.4 giving notice to the Engineer in case of request for extension of
time (EOT) for completion;
Clause 8.9 giving notice to the Engineer in case of suspension of work
instructed by the Engineer;
Clause 8.11 giving notice to the Engineer in case of prolonged suspension of
the Works;
Clause 10.1 giving notice to the Engineer in case of requesting the Taking
Over of the Works & Sections, if any;
6. Administrative Obligation
Clause 1.6 entering into a Contract Agreement;
Clause 1.7 (a) securing prior consent for assignment
from the Employer;
Clause 3.5 duty to consult with the Engineer;
Clause 4.4 (b) securing prior consent from the Engineer
for Subcontracting;
Clause 4.6 providing appropriate opportunities for the
Employer’s Personnel and any other contractors
employed by the Employer & for personnel of public
authorities;
Clause 6.1-making arrangement for the engagement of
staff & labour;
Clause 6.1 Affording opportunity of access to the Site to
the Engineer, other personnel & for the public
authorities;
Clause 7.8 payment of royalties;
Clause 20.5 attempting amicable settlement;
7. Obligation upon or after
Completion
Clause 11.1 remedying defects & completion of
outstanding works, if any;
Clause 11.11 clearance of Site upon completion;
Clause 14.10 submission of Statement at
Completion to the Engineer;
Clause 14.11 submission of draft Final
Statement to the Engineer;
Clause 14.11 submission of further information
relative to the finalization of the draft Final
Statement;
Clause 14.12 submitting written discharge to
the Employer confirming that the total of the
Final Statement represents full & final
settlement of all monies due to the Contractor;
Any point of discussion