Basement
Basement
Basement
DCQ3043 CONSTRUCTION
TECHNOLOGY 3
TOPIC: BASEMENT
1. Semi-basement
Single storey with only one, two or three
wall fully or partially below ground
level.
2. Residential basement
A shallow or semi-basement providing
space for storage and/or accommodation,
associated with housing.
3. Shallow basement
Not more than one storey wholly below
ground level.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 5
BASEMENT
Types of Basement (cont’d):
4. Deep basement
More than one storey wholly
below ground level.
5. Cellar basement
Used for storage, heating plant
and for purpose other than
habitation.
1. Structural stability
2. Durability
3. Moisture exclusion
4. Buildability
Sheet Pile
Horizontal Bracing
Support
This method need to construct a R.C. retaining wall along the area
of work.
The wall is designed to reach very great depth and sequence of
work includes:
a) Construct a guide wall
b) Excavation of the trench using bentonite slurry
c) Placement of reinforcements and pumped out bentonite slurry
d) Concrete casting
Asphalt in tanking work is laid in 3 coats to the total thickness of not less than 30mm on
horizontal surfaces and not less than 20mm on vertical faces. All internal angles (angle
fillet) are reinforced by means of a fillet 50mm on the face, formed in 2 coats.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 38
BASEMENT
Waterproof / Monolithic Structures:
Rubber Waterstops
Mohd Anuwar Simon DCQ3043 Construction Technology 3 40
BASEMENT
PVC Waterstops
Mohd Anuwar Simon DCQ3043 Construction Technology 3 41
BASEMENT
Drained / Drained Cavities:
1. Before start of work 2. Prepare perimeter walling 3. Bulk excavation 4. Excavation almost complete
5. Complete excavation work 6. Waterproofing at basement 7. Placing basement flr reinf. 8. Concreting basement floor
9. Concreting wall & column 10. Placing grd flr reinf. 11. Concreting ground floor 12. Finish work
Mohd Anuwar Simon DCQ3043 Construction Technology 3 45
BASEMENT
Sequence of Constructing Huge Basement
1. Driven sheet pile & bulk 2. Excavation, ramming bottom of 3. Lean concrete & horizontal
excavation excavation & bracing earthwork tanking
support
10. Preparing formwork for wall 11. Wall complete 12. Formwork & reinforcement for next
level
1. Bottom-up Construction
Figure shown the sequence of
operation where the diaphragm
walls formed using bentonite.
Retaining walls can from
contiguous pile, secant pile and steel
sheet pile.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 50
BASEMENT
Bottom-up Construction (cont’d)
There will have great amount of excavated soil produced during the process of
excavation.
Suitable planning for the removal of the excavated material should be made in
advance in order not to cause disruption to work and incur extra costs. Soil removal
can be done by the following ways.
i. Using manual method, by wheel barrow.
ii. Using bucket and lift to ground level by crane.
iii. Using hoist rack (opening has to be provided in the basement/excavation pit
first).
iv. Using gantry crane (opening has to be provided in the basement/excavation pit
first).
v. Using conveyor belt
vi. Using excavating machine to removal spoil, may be in stepped position in case
of very deep pit.
vii. Using dump truck but access provision has to be provided in advance (such as a
temporary ramp or the permanent vehicular access into a basement)
THANK YOU