Programa Completo Completacion Inicial
Programa Completo Completacion Inicial
Programa Completo Completacion Inicial
Well drilled on Jun, 2015, UTE B pad; Lower T was found as a potential producer zone.
WORKOVER OBJECTIVE.
• RIH Cement bond logs along 7" liner, Schlumberger. Depth control is not necessary.
• M/U Wireline Guns and RIH to perforate ''Lower T'' SST, Interval: 10,485' - 10,517' MD (32').
• Complete well with ESP REDA 400 D460N / 152 stages / 108 HP on 3 1/2” new tubing.
WELL DATA:
NOTES:
This UTE program takes precedence over all other programs issued by any Service Company. Any
program discrepancies should be reported to the Quito office.
All Wireline operations: cased hole logs and production tests needs to be done in the presence of the
UTE field production Engineer.
Production tests are to be done in the presence of the UTE field production Engineer & Chemical
Department.
Refer to figure 1 for more details related to the current mechanical condition of this well.
UTE 1: IC Program 1
RESERVOIRS DATA:
1. Record and post Company Man office, Rig Manager office and Driller console the following information:
1.1 Maximum allowed wellhead pressures; bop rating, casing and liner collapse & yield pressure.
1.2 Pump pressure at minimum pumping speed.
1.3 Detailed information of well completion:
1.3.1 All casing, liner and workstring capacities
1.3.2 Workover fluid properties such as weight, viscosity, salinity. Record any properties change.
1.3.3 After each BHA change ( artificial lift or work string)
1.4 Bop’ stack arrangement & choke manifold arrangement
2. Always stop operations when any kick indicator is noticed; pick up the string 15 ft; shut off pumps and
check for flow after the first of these warning signs (take minimun 5 mins to wait the reaction of the well
flowing or not):
1.1 Increase in flow return rate (controlling the well)
1.2 Tripping out/in work string or artificial lift equipment
1.3 Gain in pit volume (PVT)
1.4 Decrease in circulation pressure and increase in the pump speed (spm)( while controlling well)
1.5 Cut brine weight coming out & changes of the brine properties
3. Shut-in the well immediately after confirm well flowing with the following procedure: (first sound kick alarm
once)
1.1 Pick up to correct space out
1.2 Close annular preventer (if sicp > 1,000 psi , so close pipe ram)
1.3 open choke line valve (hcr)
1.4 Verify that well is shut-in
1.5 Record string (SIDPP) and annular pressures (SICP) every minute, until pressures stabilize. SICP must
be under MASP (SICP < MASP)
1.6 Record the total gain on the pits (PVT in bbls)
4. Notify supervisors & calculate the kill sheet (it is recommended the driller method)
UTE 1: IC Program 2
Note: Kill sheet should be update for each single well and for each well section.
5. Always, bleed off any accumulated pressure before open annular. All personnel must be cover and far
away from the bushings.
Workover Procedure
PRELIMINARY PROCEDURE
1. Advice and review planned activities with UTE Petroleum Engineering & Quito office.
2. M&RU Rig and all related equipment to UTE 1 (UTE B Pad). Ensure rig tanks are clean. MIX Biocide at
1000 ppm and corrosion inhibitor at 300 ppm into filtrated FRESH WATER.
3. Nipple up 11” BOP and function test.
4. MU & RIH test plug, land it into “B” section.
5. Pressure test BOP with 250 PSI low and 2000 PSI high (Annular Preventor to 750 psi high) for 10 minutes.
6. Retrieve test plug.
MILLING PROCEDURE
1. PU and RIH the following:
6” bit
2 – 4 ¾ DC
4 ¾” Jar
2 – 4 ¾ DC
NOTE: 4 ¾” Motor could be required.
2. RIH with milling assembly on 3 ½” DP and tag TOL (TIW X-PAK Hanger).
NOTE: TOL @ 8,890 ft MD / 8,598 ft TVD.
3. Continue RIH to tag of cement, starts rotary and drill out with controlled parameters.
4. Continue RIH to PBTD @ 10,691 ft MD (Landing Collar).
NOTE: Circulating viscous fluid in case it needed.
5. POOH bit and make stands with 3 ½’’ drill pipe.
UTE 1: IC Program 3
5. POOH and stand back DP and LD DC’s, bit and scraper.
NOTES:
Isolate tank capacity to mix approximately 900 bbls. casing volume of Fresh filtered water
Make sure that solids content in Fresh water is below 10 microns. A filter unit is to be used to
accomplish the 10 microns requirement.
Biocide and corrosion inhibitor are from Schlumberger.
Add 20 gallons of biocide in each 500 barrel of water to obtain 1000 ppm.
Add 6 gallons of corrosion inhibitor each one in each 500 barrels of water to obtain the required 300
ppm.
Add KCL to get 8,4 ppg.
Send one liter of brine sample to UTE Chemical Department.
LOGGING PROCEDURE:
1. Rig up Schlumberger wire line unit.
2. Perform cement quality evaluation with USIT-CBL-VDL-GR-CCL tools over interval 8,890’ – 10,691’ MD.
NOTES:
Depth control is not necessary.
Logs to be run under pressure. Apply and maintain 500 psi on surface. Use shooting nipple &
stuffing box.
Ensure PBTD is tagged with logging string, and depth recorded.
E-mail log results to the Quito office (Drilling & UTE Departments).
A remedial cementing program will be issued and sent to the rig if required.
3. Release pressure on surface and POOH logging string.
4. L/D logging string & RD Schlumberger W/L unit.
UTE 1: IC Program 4
1. Conduct an ESP procedural / safety meeting.
2. Pull wear bushing; pressure test rams and bonnet.
3. Pick up and Make up 5 ½” Casing shroud in Rotary table.
4. Pick-up lower ESP motor with sensor attached.
5. Land motor on worktable and test motor integrity and sensor.
6. Install MLE cable to motor pothead and test MLE through upper pigtail. Test sensor.
Note: Install chemical double capillary, one from centralizer and the other from intake.
7. Continue to make-up ESP section to the Motor shroud.
8. Remove ESP handling clamp and run in hole.
9. Pick-up ESP cable shieve and hang and align in derrick.
10. Feed cable end over shieve and anchor on rig floor.
11. Run in hole until upper pigtail end is reached.
12. Prepare cable ends and splice to maintain ESP cable as per procedures.
13. Make up upper BHA to the new ESP assembly: 400 P4 / 465 stages / 216 HP.
NOTES:
BHA above ESP discharge :
o 1 ea. 3-1/2” EUE joint of tubing. (New)
o 3 ½” EUE x 2.75” R Nipple (with standing valve installed). (New WTF).
o 3 ½” EUE tubing to surface (Class ‘’A’’)
14. Continue to run in hole with tubing, Megger cable (2.5 KV max. reverse polarity) and check sensor
operation and pressure test tubing every 2,000ft at 1,000 psi for 10 minutes.
15. RIH ESP assembly al maximum 10 stands per hour. (As PIR proposal).
16. Driller should be made aware of when tests are being performed so no tubing movement is carried out until
tests have been completed.
UTE 1: IC Program 5
30. Bleed all pressure from test port and tree. Reinstall the port plugs.
31. Recover BPV from Tubing Hanger.
32. Shut in tree “C” section.
33. Perform final connector installation at surface
34. Confirm rotation and perform initial rotation test to rig tank. (make with 50 bbls).
35. Not recover standing valve from “R” nipple.
36. Turn well to Engineering Department. Initiate ESP production test and monitor results.
37. Release rig (email notification from Engineering Dept. must be received prior to rig movement.)
UTE 1: IC Program 6
UTE 1 Well – UTE B Pad ANDESPETROLEUM
CURRENT DIAGRAM TAPIR NORTH 17 IC
WELL NAME: TAPIR NORTH 17 LOCATION: Tapir B, cellar 7 DATE: 15-Jul-15
GL ELEV, f t: 941.82 Ft Prepared by:
RT, ft: 36.5 Ft SURFACE LOCATION: E 9909683.09m
RT ELEV, f t: 978.32 Ft N 291040.24m
Maximum well deviation: 18.63º @ 8871 ft MD / 8592 ft TVD ( J MODIFIED PROFILE WELL)
M ulti B o wl 13 3/8" P si x
A Section
13 5/8" x 5000 Slick Lo ck
UTE 1: IC Program 7
UTE - UTE 1 Well
UTE 1: IC Program 8
UTE 1: IC Program 9
Fig. 2 – Charge Analysis Proposal
UTE 1: IC Program 10
UTE 1: IC Program 11
Fig. 3 – Logs.
UTE 1: IC Program 12
UTE 1: IC Program 13
UTE 1: IC Program 14
Fig. 4 - Survey
UTE 1: IC Program 15
UTE 1: IC Program 16
UTE 1: IC Program 17
UTE 1: IC Program 18
UTE 1: IC Program 19
Fig. 5 – ESP desing – Proposal
UTE 1: IC Program 20
UTE 1: IC Program 21
Fig. 6 – Tapir Norte 17 – Proposal
UTE 1: IC Program 22
Fig. 7 – Current BOP Diagram
UTE 1: IC Program 23