Gail Gas Limited City Gas Distribution Project Dewas
Gail Gas Limited City Gas Distribution Project Dewas
Gail Gas Limited City Gas Distribution Project Dewas
CLIENT JOB -
NO.
PROCESS DESIGN BASIS
TOTAL 9
SHEETS
DOCUMENT NO 11 0290 01 03 04 001
1 INTRODUCTION................................................................................................. 3
2 PROCESS DESCRIPTION ................................................................................. 4
3 DESIGN BASIS..................................................................................................... 6
3.1 Demand.............................................................................................................. 6
3.2 Supply Conditions and Salient Parameters ................................................... 6
3.3 STEEL RING PIPELINE DESIGN PARAMETERS .................................. 7
4 SOFTWARE .......................................................................................................... 8
5 ABBREVIATIONS ............................................................................................... 9
Document No.
PROCESS DESIGN BASIS Rev
110290-01-03-04-001 A
SHEET 2 of 9
1 INTRODUCTION
GAIL Gas Ltd (GGL) is the agency for transportation and supply of piped Natural
Gas and/or R-LNG to various domestic, commercial & industrial consumers and
CNG for vehicle transportation sections in the Dewas City within the Municipal
Limits.
The receipt of gas from the source and its transportation and distribution is intended
to be by means of a main steel pipeline downstream of CGS operating at 14-19
kg/cm2(g) pressure. Supply to individual consumers within the city shall be through
MDPE grid downstream of DRS.
Document No.
PROCESS DESIGN BASIS Rev
110290-01-03-04-001 A
SHEET 3 of 9
2 PROCESS DESCRIPTION
In order to supply gas to various consumers in the City, metered and filtered gas
taken from CGS shall be fed to the main steel pipeline laid strategically in the city.
The City Gate Station has been proposed in Industrial Area No.3. Natural Gas from
the CGS is fed into single pipeline supplying gas to the city network. The pressure at
the downstream of CGS shall be 19 kg/cm2(g). A Primary network of steel pipeline
shall connect the various CNG stations and District Regulating Stations (DRS) for
further gas supply distribution to automotive and PNG consumers. The main grid
line is laid alongside roads and highways. The main steel pipeline is of approx. 35
km length operating at 11-19 kg/cm2(g).
Areas Covered:
Areas which are covered under Dewas City Gas Distribution project are as below
S. No. Charge Area Code Description
1 CA-01 BSNL Administrative Building
2 CA-02 Ranbaxy Laboratories Ltd.
3 CA-03 Tata International Limited
Document No.
PROCESS DESIGN BASIS Rev
110290-01-03-04-001 A
SHEET 4 of 9
4 CA-04 District Court
5 CA-05 Mendichauki
6 CA-06 District Masschussets General Hospital
7 CA-07 Kirloskar Brothers Limited
8 CA-08 Dewas Railway Station
9 CA-09 Srishti Club
10 CA-10 Holy Higher Secondary School
11 CA-11 Mahla
Document No.
PROCESS DESIGN BASIS Rev
110290-01-03-04-001 A
SHEET 5 of 9
3 DESIGN BASIS
The metered and filtered gas from CGS is fed to the main steel network. Gas supply
condition and other basis for the process design are detailed in sections below.
This section defines the basic design parameters used for design of Main Steel
Network and associated facilities for the present as well as future use.
3.1 Demand
Consolidated total Demand of Dewas for City Gas Distribution Project for period of
25 years including Domestic, Commercial, Industrial and Automobile sectors is
333235 SCMD.
The demand of gas in Dewas city in different categories for 10th and 25th year are as
below: -
Demand of 25th year has been considered for Process Design work.
Document No.
PROCESS DESIGN BASIS Rev
110290-01-03-04-001 A
SHEET 6 of 9
Reqd. Pressure at customer ends : 11 kg/cm2 (g) (minimum)
Soil temperature : 25ºC (1.0 meter below ground level)
Gas specific gravity : 0.7
Gas Composition
Methane : 83.00%
Ethane : 6.83%
Propane : 3.65%
i-Butane : 0.61%
n-Butane : 0.77%
Carbon Dioxide : 4.67%
Nitrogen : 0.07%
Document No.
PROCESS DESIGN BASIS Rev
110290-01-03-04-001 A
SHEET 7 of 9
4 SOFTWARE
The following softwares shall be used for the Process engineering of this project:
Document No.
PROCESS DESIGN BASIS Rev
110290-01-03-04-001 A
SHEET 8 of 9
5 ABBREVIATIONS
Document No.
PROCESS DESIGN BASIS Rev
110290-01-03-04-001 A
SHEET 9 of 9