Chapter Contents: Rate of Return One Project
Chapter Contents: Rate of Return One Project
Chapter Contents: Rate of Return One Project
Rate of Return
One Project
Lecture 26
Chapter Contents
1
Internal Rate of Return
(IROR)
• We already learnt Present Worth that is equal to the “Sum of
Present Worth of Cash inflows minus Sum of Present worth of
Cash Out flows”
2
Economical viability based on
IROR
• MARR gives firm the idea of the cost of capital for their investment (how
much capital should earn),
• So firms compare IROR with MARR
• Once you’ve calculated IROR
• If IROR > the cost of capital (MARR), then got a GOOD project (go for it!)
• If IROR < the cost of capital, then got a BAD project (don’t undertake it)
• In general, the higher the IROR, the better the project
3
IROR is relative measure
• We used MARR to calculate PW, FW etc. (a mathematical
relation determines the PW value in actual monetary units, say,
dollars or euros)….but MARR is established independent of any
particular project’s cash flows
• For the IROR values are calculated from using only the cash
flows themselves of a particular project/alternative
Calculating IROR
• IROR can be obtained from either Present Worth (PW) or
Annual Worth (AW)
• Its calculation is based on its definition “The IROR(i*) is the
interest rate that makes the present worth or annual worth of a
cash flow series exactly equal to 0”
• It can be calculated as follows:
4
Calculating IROR
• IROR can be calculated by one of the following two
methods using PW or AW :
Calculating IROR
2. Calculating i* Using Trial and Error
The general procedure of using a PW-based equation is
as follows:
i. Draw a cash flow diagram
ii. Set up the Internal rate of return equation (such as
PW =0, or AW=0 etc.)
iii. Select values of i by trial and error until the equation
is balanced
You can get two values for “i*” (by trial and error)
…within which PW is 0 (i.e. i at which PW is negative and
another “i” for which the PW positive) for given cash flows
and then interpolate a value for “i” for which the PW is
zero
5
Example 7.3: Calculating IROR using Trial and
Error Method
$15,000
0 1 2 3 4 5 6 7 8 9 10
0 = PW or PWO = PWI
0 = ―200,000 + 15000( P/A , i *,10) +300,000 Or 200,000 = 15000( P/A , i *,10) +300,000( P/F ,
( P/F , i *,10) i *,10)
6
Guidelines for good start?
1. Always remember the negative
relationship between discount
rate and PW
2. Start with a low rate 8% or 9%
and check if the value is very
negative or positive
….accordingly decrease or
increase the discount rate for
next try keeping in mind graph
shown
….. Get one +ive PW (close to 3. Or Use guideline
0)…& one –ive PW (close to 0) method for good start
….. Interpolate for getting “i” for given in book (explained
which PW is 0 on next slide)
7
Method for Good Guess
value (Optional Method)
Next slide shows an optional method
An optional method for a good guess value
start
you can apply it if you want
it is not compulsory to apply
if you do not apply we will not deduct marks
from you
• Set the equation for P/F, P/A or A/F factors, and use the
tables to get the value of “i“
• This “i“ will be a good “starting” guess for the Trial and
Error process
8
Example 7.3: Calculating IROR
using Trial and Error Method (Optional)
9
Thank You
10