KNPC-CFP Project: Question Bank Underground Piping
KNPC-CFP Project: Question Bank Underground Piping
KNPC-CFP Project: Question Bank Underground Piping
Question Bank
Underground Piping
3)Acceptable taper-angle for Conical pipe ends of Laminated joints in GRP Piping?
a)10Deg
b)18Deg
c)15Deg
d)5Deg
4)What is the Maximum allowable distance between the supports of GRP pipes during handling and
storage?
a)5mtr
b)3mtr
c)1.5mtr
d)3.5mtr
5)How many joints are required for initial Bonders Qualification Test?
a)8jts.
b)10jts.
c)4jts.
d)2jts.
6)What type of gasket are used intended for chemical services in GRP piping?
a)Compressed asbestos fiber
b)PTFE Type
c)Neoprene rubber
d)Ring gasket
7)What is the KNPC Standard used for GRP Piping?
a)DEP 31.10.18.10
b)DEP 31.40.10.19
c)DEP 31.40.10.20
d)DEP 31.38.01.29
8)Minimum working space required on both side of pipes for buried piping system?
a)100mm
b)250mm
c)500mm
d)350mm
9) International Standard for Flanges and fittings NPS ½ through NPS 24?
a)ASME B16.9
b)ASME B16.1
c)ASME B16.5
d)ASME B16.47
12)For pipe sizes DN650 and larger in Cement lined piping what kind of connection shall be made
of?
a)Butt welded
b)Sleeve coupling
c)Threaded type
d)Bell & Spigot
14)What kind of gasket are to be used for Cement lined piping system?
a)3mm Chloroprene rubber gasket
b)Spiral wound gasket
c)Ring gasket
d)Pikotek gasket
15)What is the minimum hardening period of mortar for Normal hardening process in Cement lined
piping?
a)7days
b)28days
c)14days
d)3days
16)What kind of cutting method is not applicable for Cement lined piping?
a)Plasma cutter
b)Oxy/Acetylene type
c)Grinder with 3mm disk
d)Both a&b
19)What maximum acceptable peak to through height dimension of Single wave and Curve in
Cement lined Piping?
a)3mm
b)1mm
c)5mm
d)1.6mm
20)What kind of connection shall be made of for diameters smaller than DN650 in Cement lined
piping?
a)Butt welded
b)Sleeve joint
c)Bell & Spigot
d)Threaded joint
1. How much distance required between the insulation of a few temperate pipe and
any other objects?
a) 25 mm
b) 50 mm
c) 75 mm
d) 100 mm
2. Lack of proper back purging what type of defect will appear in SS welding?
A) Lack of fusion
B) Lack of reinforcement
C) Oxidation
D) Porosity
4. Super austenitic stainless steel (254 SMO) inter pass temperature shall be
maximum?
a) 100° C
b) 150° C
c) 200° C
d) 215° C
5. How much gap space required during fit-up for socket joints?
a) 1.0 mm
b) 1.5 mm
c) 2 mm
d) 2.5mm
7. How many months validity for the water certificate of hydro test?
a) Last 3 months
b) Last 6 months
c) Last 9 months
d) Last 12 months
8. How much vertical clearance required between the low point drains closure
flange and soil?
a) 100 mm
b) 150 mm
c) 200 mm
d) 230 mm
9. What is the maximum length of jacketed pipe spool?
a) 10 m
b) 8 m
c) 6 m
d) 4 m
10. Which letter shall be stamped on the base material of the high & low carbon
stainless steel materials?
a) “h” & “l”
b) “s” & “L”
c) “n” & “m”
d) “a” & “b”
11. How many minimum weld passes shall be applied for socket weld?
a) 6
b) 4
c) 2
d) 1
12. What is the Ferrite number requirement for all the austenitic stainless steel shop
& field weld metal deposit?
a) 15 fn to 20 fn
b) 10fn to 15fn
c) 9fn to 10fn
d) 3fn to 8fn
15. What is the preheating requirement for base metal temperature below 5°?
a) 20°
b) 30°
c) 40°
d) Approximately 50°
16. Which electrode shall be used for cement lined pipe weld joint?
a) E-6010
b) E-7018
c) E-8016
d) E-9015
17. What is the minimum size of pipe to pipe branch in cement lined piping?
a) 0.5”
b) 0.75”
c) 1”
d) 4”
18. What type of fitting shall be used 1” & ½” and smaller branches for cement lined
piping?
a) Monel coupling
b) Socklet
c) Weldolet
d) Elbow
19. What is the plywood thick ness for Cement lined piping flanged protection?
a) ½” min thk
b) 1” min thk
c) 1.1/2” min thk
d) 2” min thk
20. How many days required for pressure testing after applied cement of cement
lined piping?
a) 7 days
b) 14 days
c) 28 days
d) 48 days
1.What is the minimum distance between the edges of TWO PRESSURES containing welds?
Answer: C
a.1 inch
b.1thumb
4. What is the required tolerance for flange face to flange face and center to flange face
connection.?
Answer: A
+- 3 mm
b.4mm
c.5 mm
d.6 mm
Answer: D
a.8% without mandrel
b.5% with mandrel
c.10%
d. A/B
6. How many percent of permissible tolerance is needed for pipe wall thickness.
Answer: A
a. 12.5 %
b. 14%
c.15%
d.16%
7. What size of pipe shall be designed for full vacuum at ambient temperature.?
Answer: A
a.24 inch up
b.26 inch
c.30 inch
d.42 inch
Answer: D
b. Design Pressure
c. maximum operating pressure
d. operating pressure
e. all of the above
Answer: A
a.DEP .31.38.01.29
b. DEP.31.38.01.11
c. DEP.31.38.01.31
D.DEP.30.10.60.30
10. What is the correct minimum distance between pipes or the insulation of pipes in pipe
racks.?
Answer: A
a.75mm
b.80mm
c.90mm
d.100mm
11. What is the distance between the insulation of a low temperature pipe with any other
object.?
Answer: A
a.100mm
b.120mm
c.150mm
12. What is the minimum distance of steam trap branch connection from the closure
piping component weld.?
Asnwer: A
a.500mm
b.600mm
c.700mm
d.800mm
13. In what temperature does a carbon steel pipe ignites with having chlorine.?
Answer: A
a.250deg
b.300deg
c.320deg
d.400deg
14. Valve shall be tested for seat tightness with clean dry air at a pressure of at least
_____________
Answer: A
a.10bar(145psi)
b.100psi
c. 80psi
Answer:C
a.4mm
21. b.3mm
c.2mm
16. What is the acceptance criteria of FLANGE LATERAL ALLIGNMENT for 4inch above.?
Answer: B
a.2MM
b.3mm
c. 4mm
17. What ambient temperature is required when pneumatic pressure testing will not be
performed.?
a.7deg Celsius
b.8deg Celsius
c. 9deg Celsius
d. 10 deg Celsius
18. Pneumatic pressure testing should not be performed when the equipment metal temperature is
less than_______________
a.55deg Celsius
a.70%
b.60%
c.50%
d.80%
20.Pneumatic Leak Test Pressure is calculated based on how many percent of the design
pressure.
a. 100 %
b. 110 %
c. 150 %
d. none of the above