Culvert Manual
Culvert Manual
Culvert Manual
CULVERT MANUAL
AN INTRODUCTION TO HYDRAULICS,
DESIGN AND CONSTRUCTION
CULVERT MANUAL
AN INTRODUCTION TO HYDRAULICS,
DESIGN AND CONSTRUCTION
MODULE SUBJECT
PREFACE
A INTRODUCTION
B NON-REINFORCED CONCRETE PIPES
C OTHER TYPES OF CULVERTS
D STRESS FUNCTION OF PIPES
E HYDROLOGY
F LOCATION AND ALIGNMENT
G CULVERT FOUNDATION
H EROSION PROTECTION
I MASONRY
J RING FABRICATION
K AGGRESSIVE ENVIRONMENTS
L ROUTINE MAINTENANCE
APPENDICES
CULVERT MANUAL ABBREVIATIONS AND GLOSSARY
PAGE NOS
PREFACE i
A INTRODUCTION
A-1 DEFINITION............................................................................................................................A 1
A-2 SELECTION OF CULVERT TYPE .........................................................................................A 2
E HYDROLOGY
E-1 CATCHMENT AND FLOOD LEVELS.....................................................................................E 1
E-2 SIZING OF STRUCTURES ...................................................................................................E 3
G CULVERT FOUNDATION
G-1 GENERAL .............................................................................................................................. G 1
G-2 BEDDING............................................................................................................................... G 3
G-3 LAYING OF CONCRETE PIPES ........................................................................................... G 4
G-4 HAUNCHING OF PIPES........................................................................................................ G 6
G-5 BACKFILLING........................................................................................................................ G 8
H EROSION PROTECTION
H-1 HEADWALLS AND WINGWALLS ........................................................................................ H 1
H-2 APRONS AND CURTAIN WALLS ........................................................................................ H 5
H-3 ENERGY DISSIPATORS ………........................................................................................... H 7
H-4 OTHER STRUCTURES ………….. ....................................................................................... H 8
I MASONRY
I-1 GENERAL….. .......................................................................................................................... I 1
CULVERT MANUAL ABBREVIATIONS AND GLOSSARY
J RING FABRICATION
J-1 GENERAL …………................................................................................................................ J 1
J-2 SELECTION OF MANUFACTURING SITE……….. ............................................................... J 2
J-3 CASTING……………………. .................................................................................................. J 3
J-4 LOADING AND TRANSPORTATION……………………. ....................................................... J 6
J-5 PRODUCTION PLANNING AND MONITORING ................................................................... J 7
J-6 KEY NOTES …………………. ................................................................................................ J 8
K AGGRESSIVE ENVIRONMENTS
K-1 CORROSIVE ACTION ……………........................................................................................K 1
L ROUTINE MAINTENANCE
L-1 GENERAL …. ......................................................................................................................... L 1
M GLOSSARY
N REFERENCES
APPENDICES
1-A EXAMPLE OF A FLOOD CALCULATION…. ........................................................................ 1 A
1-B EXAMPLE OF SIZING A STRUCTURE …............................................................................ 1 B
2 TYPICAL WORK PROGRAMME FOR A SINGLE LINE CULVERT ….................................... 2
3 EXCAVATION DEPTH OF CULVERT TRENCHES …. ........................................................... 3
A
INTRODUCTION
CONTENTS
DEFINITION…….……………………………………………… A-1
CONTENTS
GENERAL……………………………………...……………… B-1
C
OTHER TYPES OF
CULVERTS
CONTENTS
CONTENTS
LOAD DISTRIBUTION..………………………….………….. D-1
E
HYDROLOGY
CONTENTS
CONTENTS
GENERAL……...………………………………….………….. F-1
RAMPS……….…………………………………...………….. F-4
CONTENTS
GENERAL……..……………………………………………… G-1
BEDDING…………………………….……..………………… G-2
BACKFILLING………………..……………………………… G-5
H
EROSION PROTECTION
CONTENTS
CONTENTS
GEN
ERAL……...……………………………………………… I-1
J
RING FABRICATION
CONTENTS
GENERAL………...…………...…………….…………...…… J-1
CASTING……………………………………….………...…… J-3
CONTENTS
CONTENTS
GENERAL……...…………………………………………….… L-1
GLOSSARY AND
REFERENCES
CONTENTS
GLOSSARY……………………………………………………. M
REFERENCES...………………………………………………. N
APPENDICES
CONTENTS
This Manual has been prepared with cognisance of the needs of the
Roads Department Training School in Lusaka, and caters for different
categories of trainees ranging from gang leaders to engineers.
It is hoped that the principles outlined in this Manual will help to avoid
some of the pitfalls that are frequently repeated in respect of
watercourses, siltation and erosion, and the consequent high costs
incurred during maintenance and rectification.
Page i February 06
CULVERT MANUAL PREFACE
ACKNOWLEDGEMENTS
This Manual has been produced for the Roads Department Training
School in Lusaka.
Carl-Eric Hedström
Technical Adviser (CTA)
Roads Department Training School / Roads Department
Lusaka, Zambia.
May 2000.
February 06 Page ii
CULVERT MANUAL INTRODUCTION A
DEFINITION A-1
Culverts and bridges perform similar tasks; the difference lies mainly
in their size. However bridges usually accommodate longer spans.
They consist of free-standing abutments and separate articulated
superstructures which carry the traffic.
- low cost;
- simple to construct;
Page A 1 February 06
CULVERT MANUAL INTRODUCTION A
February 06 Page A 2
CULVERT MANUAL NON-REINFORCED CONCRETE PIPES B
GENERAL B-1
ADVANTAGES
DISADVANTAGES
- They are not suitable for diameters larger than 900 mm as they
become very heavy and difficult to handle without a crane.
Fill
Existing Road Level
Page B 1 February 06
CULVERT MANUAL OTHER TYPES OF CULVERTS C
ADVANTAGES
- Flexible steel pipes are able to withstand the massive dead load
of high embankments or the live load forces from highway,
railway and airport traffic under shallow covers.
DISADVANTAGES
Page C 1 February 06
CULVERT MANUAL OTHER TYPES OF CULVERTS C
ADVANTAGES
- They are easier to lower into trenches without breaking, and are
less sensitive to construction traffic load before proper backfilling
has been carried out.
- They can accommodate higher dead and live load forces, such
as those under high embankments, than non-reinforced
concrete pipe culverts.
Ø 12 A - 1
2
Ø 12 A - 1
1
6Ø8
1 Ø8A-1
3
February 06 Page C 2
CULVERT MANUAL OTHER TYPES OF CULVERTS C
DISADVANTAGES
Page C 3 February 06
CULVERT MANUAL OTHER TYPES OF CULVERTS C
ADVANTAGES
DISADVANTAGES
February 06 Page C 4
CULVERT MANUAL OTHER TYPES OF CULVERTS C
ADVANTAGES
- They are more durable than any other type of culvert in non-
aggressive environments.
DISADVANTAGES
- They require very skilled labour, who are conversant with steel
bending/fixing, shuttering work and concrete mixing, i.e. having
knowledge of concrete technology.
- The construction time for box culverts built in situ is fairly long.
Road Road
Overfill H Overfill H
A
A
Key Key
D
D
Constr. Constr.
Constr.
Joint Joint
Joint
B
B
Blinding Blinding
Concrete Concrete
C W C
C W C W C
Page C 5 February 06
CULVERT MANUAL STRESS FUNCTION OF PIPES D
Rigid concrete pipes do not act in this way as deflection due to the
vertical load is negligible. Thus the horizontal earth pressure is very
small resulting in unfavourable pressure distribution around the pipe.
Consequently rigid pipes rely mostly on their inherent strength to resist
external loads.
Rupture
Page D 1 February 06
CULVERT MANUAL STRESS FUNCTION OF PIPES D
283kN/m2 97kN/m2
97
283
Figure D.4 illustrates pressure cell readings from actual load tests
under 10.7 metres of fill, carried out by the Roadway Committee of the
American Railway Engineering Association (AREA).
The tests illustrate clearly that flexible pipes in compacted backfill have
less load transmitted to them than the weight of the column of earth
over the pipe.
Rigid pipes have a load greater than the earth column transmitted to
them.
February 06 Page D 2
CULVERT MANUAL HYDROLOGY E
INTRODUCTION
Page E 1 February 06
CULVERT MANUAL HYDROLOGY E
The accuracy with which flood estimates can be made depends on the
amount and quality of relevant information available. Practical
experience under local conditions and the application of sound
judgement are particularly important in determining the data needed
for the estimation of design storm.
February 06 Page E 2
CULVERT MANUAL HYDROLOGY E
RAINFALL
I) the duration
and
Zambia has a very distinct rainy season, with the heaviest rainfall
normally recorded during the months of November to March.
Page E 3 February 06
MEAN MONTHLY, MAX/MIN ANNUAL AND HIGHEST DAILY RAINFALL
February 06
MONTHLY MEAN (mm) ANNUAL (mm) DAILY (mm)
STATION
Jan Feb March April May June July Aug Sept Oct Nov Dec Mean Max Min Max
CULVERT MANUAL
1. Choma 206 157 102 11 5 1 0 1 4 29 101 110 727 1,286 254 134
10. Zambezi 171 215 120 4 1 0 0 0 7 41 173 155 887 1,324 526 72
THIS TABLE HAS BEEN PREPARED BASED ON DATA FOR PERIOD FROM 1993 TO 1998, PROVIDED BY THE METEOROLOGICAL DEPARTMENT
E
E-1
Page E 4
CULVERT MANUAL HYDROLOGY E
Step 3 The occurrence period (in years) is selected for the worst
possible flood situation;
STEP 4
STEP 2
Page E 5 February 06
CULVERT MANUAL HYDROLOGY E
For major structures the assessment is based on specific data from the particular
project area. However, for small numbers of minor crossings, it may be sufficiently
accurate to use the diagram in Figure E.4, which should largely reflect typical
average Zambian rainfall intensities.
90 100 110 120 130 140 150 160 170 180 190 200
TIME OF CONCENTRATION (IN MINUTES)
10 YEAR
PERIOD
FLOOD
80
70
60
50
2 YEAR
1
0
PERIOD
FLOOD
40
30
20
10
0
160
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
February 06 Page E 6
CULVERT MANUAL HYDROLOGY E
RUNOFF
b) Climatic factors
c) Area of catchment
Page E 7 February 06
CULVERT MANUAL HYDROLOGY E
e) Slope of catchment
f) Permeability/Infiltration
Cover is taken to mean any material or plants covering the soil and
providing protection from the impact of rainfall.
As rainfall - runoff data are seldom available for small catchments, the
use of the Rational Method is recommended.
This method has been one of the most widely used methods for
predicting peak discharges on ungauged catchments. The principle
risk in the use of this method is the subjectiveness in selecting a
representative runoff coefficient C. It is recommended that direct
application of the Rational Formula be limited to catchments of minor
importance and less than about 10 km2 in area.
Q = CxIxA
3.6
February 06 Page E 8
CULVERT MANUAL HYDROLOGY E
Where
0.87 x L2 0.385
Tc = ( 1000 x S )
Where
Page E 9 February 06
CULVERT MANUAL HYDROLOGY E
RUNOFF COEFFICIENT C = CS + CK + CV
CS (TOPOGRAPHY) CK (SOILS) CV (VEGETATION)
VERY FLAT <1 % 0.03 SAND & GRAVEL 0.04 FOREST 0.04
The design flow derived from the Rational Method is checked against
the highest flood levels determined from experience or local advice,
the calculation of the cross sectional area of the channel in flood
conditions and the estimated storm water flow velocity at the site.
February 06 Page E 10
CULVERT MANUAL HYDROLOGY E
Having determined the quantity of water which will pass through the
culvert, the next step is to design a structure of sufficient capacity to
discharge the expected flood volume. The required waterway area is
calculated by dividing the discharge over the velocity according to
following formula:
Q
A=
V
Where
Page E 11 February 06
CULVERT MANUAL HYDROLOGY E
The ratio between water depth in the upstream channel and the inlet
height is normally defined as Headwater / Culvert Depth Ratio.
February 06 Page E 12
CULVERT MANUAL HYDROLOGY E
On the basis of the peak flow discharge for the selected return period
and the headwater - culvert depth ratio, the required number and size
of pipes can is determined using a nomograph as shown in Figure E.7.
Page E 13 February 06
CULVERT MANUAL HYDROLOGY E
February 06 Page E 14
CULVERT MANUAL HYDROLOGY E
Q = 1.2m3/sec
V = 1.9m/sec
Page E 15 February 06
CULVERT MANUAL HYDROLOGY E
H = Hu - Hd
Where
The diagram in Figure E.8 depicts a typical energy line and operating
head for a culvert. It should be noted that the gradient of the energy
line for a culvert is always falling and located above the water surface.
Energy Line
H
Hu
Hd
February 06 Page E 16
CULVERT MANUAL HYDROLOGY E
It can further be said that the Culvert Operating Head (H) also equals
to the sum of main energy losses as follow:
H = He + Hf + Ho
Where
He = (V2/2g) x Ke
Hf = (V2/2g) x (f x L/D)
Ho = (V2/2g) x Ko
Where
The coefficients Ke and f depend on the entry size and shape. For a
typical concrete culvert the following values can be used:
Therefore
Figure E.9 illustrates the head and water surface for various depths of
headwater, while Figure E.10 provides a typical example for
calculating the required Culvert Operating Head.
Page E 17 February 06
CULVERT MANUAL HYDROLOGY E
Figure E.9 – Head (H) and Water Surface for Various Depths of Headwater
Example A
H
Hu
Example B
H
Hu
Example C
Hu H
Example D
Hu H
February 06 Page E 18
CULVERT MANUAL LOCATION AND ALIGNMENT F
GENERAL F-1
Culvert location deals with the horizontal and vertical alignment of the
culvert with respect to both the stream and the road. It is important for
the hydraulic performance of the culvert, stream stability, construction
and maintenance costs, as well as for prevention of damage by
erosion.
Page F 1 February 06
CULVERT MANUAL LOCATION AND ALIGNMENT F
GENERAL F-1
Figure F.1 – Reducing Water Velocity using Check Dams and Drop Inlets
February 06 Page F 2
CULVERT MANUAL LOCATION AND ALIGNMENT F
GENERAL F-1
It is also important that the culvert invert is set at the same level as the
natural streambed.
Culverts are frequently set low to avoid humps on the road above.
This results in silting and consequent reduction in the waterway area.
EFFECTIVE HEIGHT
H1
EFFECTIVE AREA H2
Figure F.3 – Ditch Layout (with Lowered Ditches and Widened Side Slopes)
Page F 3 February 06
CULVERT MANUAL LOCATION AND ALIGNMENT F
GENERAL F-1
An abrupt change in direction of flow at the inlet and outlet can result
in severe erosion or wash out when heavy rains cause maximum flow
to occur.
- The ideal grade line for a culvert is one that produces neither
silting nor excessive scour.
February 06 Page F 4
CULVERT MANUAL CULVERT LOCATION F
Old channel
New channel
The above figure clearly illustrates that a stream should have as direct
as possible an entrance and exit to a culvert. Abrupt changes in
direction will cause turbulence and the likelihood of scouring in some
parts of the stream and silting in others.
Page F 5 February 06
CULVERT MANUAL LOCATION AND ALIGNMENT F
February 06 Page F 6
CULVERT MANUAL LOCATION AND ALIGNMENT F
- Point bars form on the inside of stream bends, and culvert inlets
placed at bends in streams will be subjected to deposition in the
same manner. This effect is most pronounced in multiple-barrel
culverts with the barrel on the inside of the curve often
becoming almost totally clogged with sediment deposits.
Page F 7 February 06
CULVERT MANUAL LOCATION AND ALIGNMENT F
RAMPS F-4
For culverts in flat terrain, the vertical alignment of the road usually
needs to be adjusted to achieve adequate cover of the culvert barrel.
The road may need to be ramped over the culvert. The ramp should
have a gradient of less than 5%, and extend at least 20 metres either
side of the culvert (refer to Figure F.6 below) to achieve a smooth and
acceptable vertical alignment.
This method should be used in flat areas and for watercourses with
shallow gradients, because in these circumstances a culvert set too
low simply silts up, while a culvert set too high would cause silting
upstream and possibly erosion at the outfall.
Raising the vertical alignment (road profile) in some locations will also
allow/improve drainage discharge to the adjoining land (the gradient
should be carefully studied at the discharge side).
Figure F.6 above shows a typical example of raised road profile over a
culvert (ramping) in order to allow the culvert to be installed at the
correct invert level.
February 06 Page F 8
CULVERT MANUAL LOCATION AND ALIGNMENT F
W = 5.50 m
C/L
H(c/L) = 2.00m
S = 1:2 S = 1:2
(50%) (50%)
G=3%
A B
L (outlet) = ?? L(inlet) = ??
carriageway = 5.50 m
height of embankment (at centre line) = 2.00 m
side slope ratio = 1:2 (50%).
Page F 9 February 06
CULVERT MANUAL LOCATION AND ALIGNMENT F
3%
The horizontal distance from A to B has now been established, but the
culvert is designed to be laid on a slope of 3%. The actual length is
calculated as follows:
February 06 Page F 10
CULVERT MANUAL LOCATION AND ALIGNMENT F
On some minor roads, ditches cross small entrances and are blocked
either deliberately or by the action of traffic.
Where pipe culverts are installed, they are often placed away from the
road to reduce the length. It is better for long term performance of the
road to install pipe culverts at the outset and locate them as shown in
figure below.
Alternative location
Entrance
for culvert
side
Ditch
Preferred location
C
L Road
Where ditches are spaced away from the carriageway, culverts should
be built from ditch to ditch, not just across the width of the pavement,
in order to move the location of possible erosion damage away from
the pavement. Building the culvert long enough to reach the base of
the embankment also reduces the additional cost of building high
headwalls.
Page F 11 February 06
CULVERT MANUAL CULVERT FOUNDATION G
GENERAL G-1
The foundation should be checked for hard or soft spots due to rocks
or low load bearing capacity soils. The following measures should be
noted:
Page G 1 February 06
CULVERT MANUAL CULVERT FOUNDATION G
GENERAL G-1
February 06 Page G 2
CULVERT MANUAL CULVERT FOUNDATION G
BEDDING G-2
The pipe should be laid on specified bedding material shaped to fit the
lower one-tenth of the external diameter as illustrated below, in order
to give proper support to the barrel (Figure G.3 a). The shape of the
bed should be controlled with a culvert template. Experience has
shown that this is not easy to achieve in in-situ material; therefore the
alternative shown in Figure G.3 b) below is more practical and easier
to carry out.
The width of the trench should be equal to the external diameter plus
0.60m, while the depth of trench should in principle be equivalent to
the diameter plus the cover. For further information with regard to
depth of excavation for different soil types (subgrade) is given in
Appendix 3.
Selected
Material
Min. D/10
0.20m
Page G 3 February 06
CULVERT MANUAL CULVERT FOUNDATION G
Laying of pipes and backfilling the trench should take place as soon as
possible after excavating the trench. This minimises problems and
delays due to surface or groundwater which cause instability of the
trench and limits the duration of possible traffic obstruction periods.
The figure below shows the use of profiles (grade boards), set at a
fixed height above the invert level of the pipe (e.g. 1.0 m is very
common) and the level controlled by use of a traveller.
Sight Rail
a
b
C/L Rod
c
Legend:
a = Sighting line
b = Centre line
c = Profile height above invert
February 06 Page G 4
CULVERT MANUAL CULVERT FOUNDATION G
Traveller/Boning Rod
Invert level
Page G 5 February 06
CULVERT MANUAL CULVERT FOUNDATION G
(CONCRETE) (CONCRETE)
f f
D
e
e h
h
b b
a d a a d a
c c
Haunching is not only used for pipes under high embankments, but
can also be used to reduce the cover when it is not feasible to have a
hump on the road.
February 06 Page G 6
CULVERT MANUAL CULVERT FOUNDATION G
Page G 7 February 06
CULVERT MANUAL CULVERT FOUNDATION G
BACKFILLING G-5
Backfilling may be completed the same day as the pipes have been
laid and sealed. However, the internal joints should be checked after
backfilling and repaired if necessary. Headwalls should preferably be
constructed before backfilling takes place, as this will allow all mortar
joints and work to gain strength before backfilling.
Backfill should be carried out in layers of 150 mm, and should be well
compacted with hand-rammers. Backfill may require the addition of
water to bring it to the field moisture content necessary for efficient
compaction.
Heavy equipment must not be allowed to pass over the culvert until an
adequate cushion of compacted backfilling has been placed over it.
When the road has to be kept open to traffic during construction, the
culvert may be constructed in two halves so as to avoid costly
diversions.
Care must be taken to protect both the culvert works and the traffic
during and after working hours.
February 06 Page G 8
CULVERT MANUAL CULVERT FOUNDATION G
BACKFILLING G-5
Ground linel
Max. otb15mm layer
after compaction
Page G 9 February 06
CULVERT MANUAL EROSION PROTECTION H
Page H 1 February 06
CULVERT MANUAL EROSION PROTECTION H
Cost Diagram
Cost of Headwalls plus Pipe
Headwall
Cost
Pipe Cost
Culvert length
February 06 Page H 2
CULVERT MANUAL EROSION PROTECTION H
Page H 3 February 06
CULVERT MANUAL EROSION PROTECTION H
Figure H.7 – Inlet and Outlet Protection for Culverts with Low Water
Velocity
Seal
H’
Min. H’/3
Figure H.8 – Inlet and Outlet Protection for Culverts with High Water
Velocity
Stone
Stone
Gravel
Min. H’/3
Stone
Curtain wall
February 06 Page H 4
CULVERT MANUAL EROSION PROTECTION H
Figure H.9 – Erosion Pattern for Culvert Outlet without Apron or Other
Erosion Protection Measures
Plan
Section
High headwater depth can result in seepage under the structure and
through the embankment. This seepage can be very dangerous
particularly in soils of poor grading, such as silts and fine sands,
because it can result in piping (refer to Figure H.10 below) which can
cause failure of the structure and the embankment.
Page H 5 February 06
CULVERT MANUAL EROSION PROTECTION H
Figure H.11 – Apron and Curtain Wall for Inlet with Moderate Water
Velocity
Stone
H
Stone
Min 1.50 m Min H/3
February 06 Page H 6
CULVERT MANUAL EROSION PROTECTION H
Figure H.12 – Apron and Curtain Wall for Inlet with High Water Velocity
Min 2.00 m
Toe Heel
Figure H.13 – Apron and Curtain Wall for Outlet with Moderate Water
Velocity
Min 2.00 m
Figure H.14 – Apron and Curtain Wall for Outlet with High Water Velocity
Min 3.00 m
Heel Toe
Page H 7 February 06
CULVERT MANUAL EROSION PROTECTION H
Plan
Section
The figure below shows different methods used for the dissipation of
energy.
February 06 Page H 8
CULVERT MANUAL EROSION PROTECTION H
RIP-RAP
- it is relatively cheap
- it is flexible and often finds its own effective level
- it is easy to install and repair.
variable 1.00
Grouted Rip-Rap
variable
0.50
1.00
1.00
Grouted Rip-Rap
variable
Page H 9 February 06
CULVERT MANUAL EROSION PROTECTION H
Isometric:
Plan:
Side Elevation:
Notes:
1. For multi-barrel reinforced concrete pipe culverts, the top width of the trapezoidal ditch outlet
shall be equal to the sum of spacing between pipes and three times the pipe diameter.
2. Placement of grouted rip-rap shall start at the bottom level first.
3. Mortar shall be placed on prepared slope just prior to the placement of rip-rap stones.
Stones shall be hand-rammed into the mortar with additional mortar placed between stones
as required. The length of trapezoidal ditch shall be determined by the design engineer to
suit actual field conditions.
February 06 Page H 10
CULVERT MANUAL EROSION PROTECTION H
Isometric:
Plan:
Side Elevation:
Notes:
1. Placement of grouted rip-rap shall start at the bottom level first.
2. Mortar shall be placed on the prepared slope just prior to the placement of rip-rap stones.
Stones shall be hand-rammed into the mortar with additional mortar placed between stones
as required.
3. The length of stepped ditch shall be determined by the design engineer to suit actual field
conditions.
Page H 11 February 06
CULVERT MANUAL EROSION PROTECTION H
Where stones are not readily available, one of the following methods
can be used.
Logs can be used by lining them across the streambed and extending
them into the stream banks for anchorage. This is depicted in Figure
H.19 below. For additional stability steel clamps can be used to tie the
logs to one another.
Jute sacks filled with soil can also be used as an alternative to stone
lining. The soil can be mixed with about 5 % of cement for extra
stability. The sacks should not be overfilled. They should be tied
either with soft galvanized wire or strong string, so that they do not
open, even if handled roughly. The sacks should be laid flat in layers,
one layer covering the joints of the layer below.
February 06 Page H 12
CULVERT MANUAL EROSION PROTECTION H
Page H 1 February 06
CULVERT MANUAL EROSION PROTECTION H
Cost Diagram
Cost of Headwalls plus Pipe
Headwall
Cost
Pipe Cost
Culvert length
February 06 Page H 2
CULVERT MANUAL EROSION PROTECTION H
Page H 3 February 06
CULVERT MANUAL EROSION PROTECTION H
Figure H.7 – Inlet and Outlet Protection for Culverts with Low Water
Velocity
Seal
H’
Min. H’/3
Figure H.8 – Inlet and Outlet Protection for Culverts with High Water
Velocity
Stone
Stone
Gravel
Min. H’/3
Stone
Curtain wall
February 06 Page H 4
CULVERT MANUAL EROSION PROTECTION H
Figure H.9 – Erosion Pattern for Culvert Outlet without Apron or Other
Erosion Protection Measures
Plan
Section
High headwater depth can result in seepage under the structure and
through the embankment. This seepage can be very dangerous
particularly in soils of poor grading, such as silts and fine sands,
because it can result in piping (refer to Figure H.10 below) which can
cause failure of the structure and the embankment.
Page H 5 February 06
CULVERT MANUAL EROSION PROTECTION H
Figure H.11 – Apron and Curtain Wall for Inlet with Moderate Water
Velocity
Stone
H
Stone
Min 1.50 m Min H/3
Page H 7 February 06
CULVERT MANUAL EROSION PROTECTION H
Figure H.12 – Apron and Curtain Wall for Inlet with High Water Velocity
Min 2.00 m
Toe Heel
Figure H.13 – Apron and Curtain Wall for Outlet with Moderate Water
Velocity
Min 2.00 m
Figure H.14 – Apron and Curtain Wall for Outlet with High Water Velocity
Min 3.00 m
Heel Toe
February 06 Page H 8
CULVERT MANUAL EROSION PROTECTION H
Plan
Section
The figure below shows different methods used for the dissipation of
energy.
Page H 9 February 06
CULVERT MANUAL EROSION PROTECTION H
RIP-RAP
- it is relatively cheap
- it is flexible and often finds its own effective level
- it is easy to install and repair.
variable 1.00
Grouted Rip-Rap
variable
0.50
1.00
1.00
Grouted Rip-Rap
variable
February 06 Page H 10
CULVERT MANUAL EROSION PROTECTION H
Isometric:
Plan:
Side Elevation:
Notes:
1. For multi-barrel reinforced concrete pipe culverts, the top width of the trapezoidal ditch outlet
shall be equal to the sum of spacing between pipes and three times the pipe diameter.
2. Placement of grouted rip-rap shall start at the bottom level first.
3. Mortar shall be placed on prepared slope just prior to the placement of rip-rap stones.
Stones shall be hand-rammed into the mortar with additional mortar placed between stones
as required. The length of trapezoidal ditch shall be determined by the design engineer to
suit actual field conditions.
Page H 11 February 06
CULVERT MANUAL EROSION PROTECTION H
Isometric:
Plan:
Side Elevation:
Notes:
1. Placement of grouted rip-rap shall start at the bottom level first.
2. Mortar shall be placed on the prepared slope just prior to the placement of rip-rap stones.
Stones shall be hand-rammed into the mortar with additional mortar placed between stones
as required.
3. The length of stepped ditch shall be determined by the design engineer to suit actual field
conditions.
February 06 Page H 12
CULVERT MANUAL EROSION PROTECTION H
Where stones are not readily available, one of the following methods
can be used.
Logs can be used by lining them across the streambed and extending
them into the stream banks for anchorage. This is depicted in Figure
H.19 below. For additional stability steel clamps can be used to tie the
logs to one another.
Jute sacks filled with soil can also be used as an alternative to stone
lining. The soil can be mixed with about 5 % of cement for extra
stability. The sacks should not be overfilled. They should be tied
either with soft galvanized wire or strong string, so that they do not
open, even if handled roughly. The sacks should be laid flat in layers,
one layer covering the joints of the layer below.
Page H 13 February 06
CULVERT MANUAL MASONRY I
GENERAL I-1
DRY MASONRY
Page I 1 February 06
CULVERT MANUAL MASONRY I
GENERAL I-1
MATERIALS
February 06 Page I 2
CULVERT MANUAL MASONRY I
GENERAL I-1
Section Elevation
Bond min. ¼ of stone length
Stretcher
Header
Joints 1 to 4 cm
Page I 3 February 06
CULVERT MANUAL RING FABRICATION J
GENERAL J-1
Although culvert costs may comprise only a small part of the total cost
of the road, culverts are of critical importance to the drainage system.
It is therefore imperative that their demand is met, and that the quality
of culvert rings is high and sustained.
0.60m Ø 1½ RINGS/MANDAY
0.90m Ø 1 RING/MANDAY
Page J 1 February 06
CULVERT MANUAL RING FABRICATION J
The advantage of casting culvert rings at site is that the culvert rings
are ready where they are wanted. On the other hand, the
disadvantages are that each site would require skilled labourers to
cast the culvert rings and the required materials must be stored at site.
Thus it is more difficult to control the quality of the outputs.
February 06 Page J 2
CULVERT MANUAL RING FABRICATION J
CASTING J-3
The pouring of the concrete into the moulds must be completed within
30 minutes of mixing. Before concrete is poured, it must be ensured
that the moulds are clean and contact areas properly oiled with a
mixture of 2 parts diesel and 1 part used engine oil. Figure J.1
illustrates the importance of having inner and outer moulds correctly
centred. Rings with uneven wall thickness will be weak and will
probably break during transportation or in situ loading.
Page J 3 February 06
CULVERT MANUAL RING FABRICATION J
CASTING J-3
CEMENT
(50kg Bag) 0.48 0.84 1.68 0.58 1.02 2.04
SAND
(m3; loose) 0.034 0.059 0.118 0.030 0.053 0.106
AGGREGATE
(m3; loose) 0.067 0.118 0.235 0.061 0.106 0.213
February 06 Page J 4
CULVERT MANUAL RING FABRICATION J
CASTING J-3
The moulds should not be removed until the day after pouring; in
cooler high altitude areas an extra day will be required. Stripping
should be carried out very carefully to avoid damage to the fresh rings.
The moulds should be cleaned immediately and oiled ready for reuse.
Moulds should also be treated with care to avoid damaging or
distorting them.
The concrete rings must not be moved for one week. They must be
cured by being kept wet and protected from direct sunshine during this
first week. This can be achieved by covering the rings with sacks or
banana leaves, which are then sprinkled with water from time to time
to keep the concrete surfaces moist. If the water supply is sufficient,
an effective method of curing is to fill the fresh rings with water. After
curing the rings should be stored for a further 3 weeks before they are
transported to the road site. Rings should always be stored end-on.
Page J 5 February 06
CULVERT MANUAL RING FABRICATION J
Loading is done by carefully rolling the rings onto the vehicle. If the
casting site is permanent, an earth ramp and retaining wall can be
constructed for this purpose.
The rings must be carefully unloaded using wooden planks and ropes
to restrain them. They should be unloaded directly at the culvert site if
possible to avoid double handling.
February 06 Page J 6
CULVERT MANUAL RING FABRICATION J
Page J 7 February 06
CULVERT MANUAL RING FABRICATION J
February 06 Page J 8
CULVERT MANUAL AGGRESSIVE ENVIRONMENTS K
CORROSIVE ACTION K- 1
Aggressive
Carbon Dioxide (CO2) mg/l 15-30 30-80 > 80
Page K 1 February 06
CULVERT MANUAL AGGRESSIVE ENVIRONMENTS K
Besides ensuring that the materials are of adequate quality, the single
most important factor influencing both strength and durability of
concrete is the water:cement ratio of the mix. When specifying
concrete the maximum free water/cement ratio by weight should be
limited to 0.5.
weak
10 12 15 20 25 30 35 40
Water (litres per pocket)
February 06 Page K 2
CULVERT MANUAL ROUTINE MAINTENANCE L
GENERAL L-1
In order to function properly, a culvert must retain the full opening over
its complete length. In addition, the upstream approaches and the
downstream area must be free of obstructions.
Floating debris carried by water, like tree branches and bushes, etc, is
a great danger to culverts as the debris can completely block the
culvert inlet.
Where light erosion of the streambed has taken place, the eroded
areas should be filled with 30 cm stone blocks, or as available, to
produce a rough energy dissipator. Block pitching or rip-rap should
preferably extend beyond the eroded area. If larger sized stone are
available, these can also be used. In the dry season or when the
water flow is low or non-existent, the blocks can be grouted with lean
concrete of ratio 1:4:8.
If stones are not available, logs can be used. These should be lined
across the streambed and should extend into the stream banks for
anchorage.
Jute sacks filled with soil can also be used as an alternative to stone
lining. The soil can be mixed with about 5% cement for extra stability.
Page L 1 February 06
CULVERT MANUAL GLOSSARY M
10. Stone Masonry - Special Public Works Programmes, (SPWP) ILO & UNDP.
13. Technical Manual for Labour Based Road Rehabilitation Works - Roads
Department Training School, Ministry of Works and Supply, Zambia, in
association with Norconsult A.S., Nairobi, 1999.
INTRODUCTION
This appendix gives an example for calculating the discharge (Q) from
a given catchment area and the required waterway area (A) of the
culvert the discharge will pass through.
Other Bridges 25 to 50
Culverts 5 to 10
Drifts 5
Irish Bridge 5
0.87 x L2 0.385
Tc = ( 1000 x S ) (hours)
b) Now use the Tc to obtain the Rainfall Intensity (I) from the
diagram in Figure E.4, Section E – 1 page E 6, which gives an
intensity of 82 mm/hour (for example see Figure 1A.1 below).
60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
TIME OF CONCENTRATION (IN MINUTES)
10 YEAR
PERIOD
FLOOD
50
2 YEAR
PERIOD
FLOOD
40
30
20
10
0
160
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
Q= CxIxA
3.6
Where:
Example:
Q= Flood peak at catchment exit (m3/sec)
According to TRRL Overseas Road Note 9*, the peak discharge for
small catchment areas up to 15 km2 is often between 1 and 2 m3/sec
per 25 hectares.
*TRRL - Transport and Research Laboratory, Overseas Unit,
Crowthorne, Berkshire, UK.
We shall choose a velocity of 2.5 m/sec for this example, and use the
Area-Velocity Formula to calculate the required waterway area.
A = Q = 17.3 m3/sec = 6.9 m2
V 2.5 m/sec
Assumption:
D = 1.75 m (assumed to be corrugated steel pipes)
H/D = 1.2 (according to culvert site conditions)
The nomograph reading will result in:
Q = 6.1 m3/sec (capacity per culvert line)
V = 2.6 m/sec (considered to be within limits)
This implies the number of lines required is:
APPENDIX
Check periodically for possible settlement of ramp and
overfill until final handing over of works. (Bi-monthly)
Appendix 2 / Page 1
2-A
Total staff days required (excluding for works during defects liability period) 40
2
Note:
Indicates Critical Path (Activity can not commence unless previous one has been substantially completed)
CULVERT MANUAL APPENDIX 3
Profiles I -VI
Fair
Poor soils
Standard trench
Total trench Total trench Total trench
depth according to
excavation depth excavation depth excavation depth
bedding and
in good material in fair material in poor material
haunch profile*
(m) (m) (m) (m)
φ 450 φ 600 φ 900 φ 450 φ 600 φ 900 φ 450 φ 600 φ 900 φ 450 φ 600 φ 900
mm mm mm mm mm mm mm mm mm mm mm mm
Insitu Material 0.76 1.01 1.51 0.76 1.01 1.51 - - - - - -
Profile I 1.00 1.33 1.91 1.00 1.33 1.91 1.20 1.73 2.51 1.50 2.33 3.41
Profile II 1.00 1.33 1.91 1.00 1.33 1.91 1.20 1.73 2.51 1.50 2.33 3.41
Profile III 0.89 1.18 1.68 0.89 1.18 1.68 1.09 1.58 2.28 1.39 2.18 3.18
Profile IV 0.96 1.18 1.53 0.96 1.18 1.53 1.16 1.58 2.13 1.46 2.18 3.03
Profile V 1.00 1.33 1.91 1.00 1.33 1.91 1.20 1.73 2.51 1.50 2.33 3.41
Profile VI 0.99 1.33 1.91 0.99 1.33 1.91 1.19 1.73 2.51 1.49 2.33 3.41
Good 0 0 0
Additional Fill According to
Fair 0.20 0.40 0.60
Subgrade (m)
Poor 0.50 1.00 1.50
* According to Technical Manual, Appendix H - 4 / Page 6 - 8
The above figure/diagram can be used as a “Rule of Thumb” for determination of depth of
excavation of pipe trenches, but for very difficult subgrade conditions, foundations should be
designed following approved engineering procedures.
Further information on trench widths and bedding and haunch profile dimension is provided in the
Technical Manual, Appendix H – 4.