Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Construction Notes: General: Concrete Work: Reinforcement Notes

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF PUBLIC WORKS


AND HIGHWAYS
OFFICE OF THE BUILDING OFFICIAL

CONSTRUCTION NOTES CEBU CITY

RECOMMENDING APPROVAL:

HEAD CIVIL/STRUC'L. SECTION DATE

APPROVED:

BUILDING OFFICIAL DATE

CONCRETE WORK :
GENERAL : REINFORCEMENT NOTES :
1. CONCRETE QUALITY SHALL BE AS FOLLOWS :
1. THESE DRAWINGS ARE TO BE READ IN CONJUNCTION WITH ALL ALL REINFORCING BARS SHALL CONFORM TO ASTM A615 DEFORMED STEEL.
OTHER RELEVANT DRAWINGS AND SPECIFICATIONS AND WITH SUCH ALL BARS SHALL BE GRADE 40 fc' (MPa) Max. Agg. (mm) MAX W/C
WRITTEN INSTRUCTIONS AS MAY BE ISSUED DURING THE COURSE
OF THE CONTRACT. PILE CAPS CONCRETE 24.1 20 0.57
2. ALL DISCREPANCIES SHALL BE REFERRED TO THE CLIENT FOR
RESOLUTION BEFORE PROCEEDING. WHERE CONFLICT ARISES BETWEEN PRECAST CONCRETE PILES 34.5 20 0.57
THE SPECIFICATIONS AND NOTES AND/OR DRAWINGS, IN 1. COVER TO REINFORCEMENT
PRINCIPLE THE NOTES AND DRAWINGS SHALL TAKE PRECEDENCE OVER SHALL BE : Fc' - MINIMUM 28-DAY CHARACTERISTIC CONCRETE COMPRESSIVE STRENGTH
THE SPECIFICATIONS UNO. ALL DIMENSIONS RELEVANT TO SETTING OUT ALL SURFACES
Max Agg. - MAXIMUM AGGREGATE SIZE
AND OFF-SITE WORK SHALL BE VERIFIED BEFORE CONSTRUCTION IS
COMMENCED. THESE DRAWINGS SHALL NOT BE SCALED. Max W/C - MAXIMUM WATER - CEMENT RATIO
PRECAST CONCRETE 50 MM (ALL FACES)
3. WORKMANSHIP AND MATERIALS ARE TO BE IN ACCORDANCE 2. CEMENT SHALL CONFORM TO ASTM C150, TYPE 1.
PILE CAPS 100 MM (BOTTOM), 75 MM (TOP & SIDES)
WITH THE SPECIFICATIONS. ALL CONCRETE INCLUDING SLABS ON GROUND, SHALL BE VIBRATED. IF NECESSARY
2. USE NECESSARY BAR CHAIRS, SUPPORT AND SPACERS BARS TO PLACE PROVIDE ADDITIONAL TAMPING IN THE COVER ZONE. DEEP SECTIONS SHALL BE
STEEL IN ITS CORRECT POSITION DURING CONCRETING. REVIBRATED PRIOR TO FINAL FINISHING TO REDUCE THE EFFECTS OF PLASTIC SETTLEMENT.
DESIGN CRITERIA : 3. ALL REINFORCEMENT SHALL BE AS SHOWN ON THE DRAWINGS, 3. ALL CONCRETE SHALL BE CURED BY KEEPING EXPOSED SURFACES CONTINUOUSLY WET FOR
DESIGN LOADINGS IS BASED ON PLAN PROVIDED BY MEKA BETON 7 DAYS AFTER POURING.
4. REINFORCEMENT IN SLABS MUST BE PLACED IN ACCORDANCE WITH THE
SANTRALLERI DRAWINGS. COGS AND HOOKS TO BE STANDARD IN ACCORDANCE WITH ACI318 AS 4. CONSTRUCTION JOINTS SHALL BE PROPERLY FORMED AND USED WHERE SHOWN ON THE
SHOWN ON DRAWINGS. PLAN. CONSTRUCTION JOINTS SHALL BE INTENTIONALLY ROUGHENED BY ANY APPROVED MEANS
TO EXPOSE AGGREGATE.

SPLICING AND ANCHORAGE LENGTH SCHEDULE : 5. CONCRETE EPOXY BOND SHALL BE PROVIDED ON THE CONTACT SURFACE OF THE PRE-CAST
AND CAST-IN-PLACE CONCRETE. EPOXY BONDING TO BE USED SHALL HAVE WRITTEN APPROVAL
MIN. LAP SPLICE BY THE ENGINEER.
BAR ANCHORAGE STANDARD LAP SPLICES
UNIT LENGTH OF COL
FORMWORK : DIAMETER LENGTH HOOK (m)
(m)
WEIGHT REINFORCEMENT
6. ROUGHEN SURFACE OF PRECAST MEMBERS IN CONTACT WITH NEW CONCRETE.
TENSION BAR COMP. BAR INDIVIDUAL BARS
(mm) (m) (kg/m)
FORMWORK SHALL NOT BE STRIPPED UNTIL THE CONCRETE STRENGTH 90 DEG 180 DEG 133 DEG TOP BAR BOT BAR TOP BAR BOT BAR W/ TIES W/ SPIRAL
IS SUFFICIENT TO SUPPORT THE LOADS WITHOUT EXCESSIVE 10 mm 0.60 0.10 0.13 0.10 0.42 0.30 0.42 0.30 0.617 0.30 0.30
DISTORTION OR CRACKING. NOT WITHSTANDING THIS REQUIREMENT 12 mm 0.60 0.14 0.16 0.12 0.42 0.30 0.42 0.30 0.889 0.30 0.30
HOWEVER, THE FOLLOWING MINIMUM STRIPPING TIMES SHALL APPLY. 16 mm 0.60 0.22 0.18 0.14 0.73 0.52 0.87 0.62 1.580 0.52 0.47 DRIVEN PILE INSTALLATION :
20 mm 0.60 0.30 0.20 0.20 1.10 0.78 0.90 0.65 2.469 0.65 0.58
WALL FORMS 4 DAYS (MIN) 25 mm 0.68 0.40 0.28 0.26 1.40 1.00 1.40 1.00 3.858 0.80 0.73 1. ALL PILES SHALL BE HANDLED, PITCHED AND DRIVEN IN ACCORDANCE
SLAB SIDES > 1000 DEEP 4 DAYS (MIN) 28 mm 0.86 0.48 0.38 1.76 1.26 1.53 1.09 4.840 0.90 0.82 WITH THE SPECIFICATION.
SLAB SIDES < 1000 DEEP 3 DAYS (MIN) 32 mm 1.12 0.56 0.43 2.31 1.65 1.74 1.24 6.327 1.03 0.93
SUSPENDED SLABS SOFFITS 7 DAYS (MIN) 2. PILES SHALL BE DRIVEN TO ACHIEVE THE MINIMUM EMBEDMENT REQUIRED
36 mm 1.38 0.61 0.48 2.95 2.10 2.00 1.40 8.000 1.20 1.05
FOR A NOMINATED CAPACITY OF 27 TONS AND SHALL BE DETERMINED USING
PRECAST CONCRETE ENGINEERING NEWS FORMULA IF DRIVEN USING PILE HAMMER & FROM GAUGE
NOTES :
PROVIDE ALL EXPOSED EDGES AND CORNERS WITH 20mm CHAMFERS READING IF USING PUSH-PILE DRIVING METHOD.
1. ACI SECTION 12.4 STATES THAT:
OR FILLETS U.N.O. DEVELOPMENT LENGTH OF INDIVIDUAL BARS WITHIN A BUNDLE IN TENSION OR COMPRESSION SHALL BE 3. DRIVING RECORD SHALL BE TAKEN FOR ALL PILES.
THAT FOR THE INDIVIDUAL BAR. INCREASED 20 PERCENT FOR THREE-BAR BUNDLE AND 33 PERCENT
FOR FOUR-BAR BUNDLE. 4. ENSURE PILE TOPS REMAIN SAFE DURING CONSTRUCTION.

FOUNDATION NOTES : 2. FOR COLUMNS AT ANY LEVEL NO MORE THAN ALTERNATE BARS SHOULD BE SPLICED NOT MORE
THAN 33% OF THE BARS SHALL BE SPLICED WITHIN THE REQUIRED LAP LENGTH MINIMUM DISTANCE
5. UNDERTAKE AN AS CONSTRUCTED SURVEY, WHICH
IDENTIFIES TRUE VERSUS THEORETICAL PILE POSITIONS AND PILE LENGTHS.
THE DESIGN OF FOUNDATIONS ARE BASED ON THE FINAL BETWEEN TWO ADJACENT BAR SPLICES SHALL BE 600MM.
REPORT ON THE OFF-SHORE SOIL DRILLING FOR THE PROPOSED
3. TOP BARS ARE HORIZONTAL BARS WITH MORE THAN 300 MM DEPTH OF CONRETE CAST BELOW
PIER AND RECLAMATION PREPARED BY ACCREDITED GEOTECHNICAL
ENGINEERING COMPANY
THE REINFORCEMENT. BACKFILLING WORK :
1. BACKFILLING SHALL BE DONE AT EVERY 300mm LIFTS AND COMPACTED
4. AS MUCH AS POSSIBLE SPLICES SUBJECTED TO TENSILE STRESSES ARE DISCOURAGE. THESE
SHOULD BE AVOIDED OR PROVIDED WITH STANDARD HOOKS. ACCORDING TO ASTM D-698 WITH MINIMUM MDD 95% OF OPTIMUM.
ONLY APPLICABLE ABOVE WATER LEVEL.
2. BACKFILL MATERIALS SHALL CONFORM TO ITEM 104 OF DPWH
SPECIFICATIONS FOR PUBLIC WORKS AND HIGHWAYS 2013 EDITION,
VOLUME II.
3. BACKFILLING AT THE PROPOSED AREA FOR RECLAMATION (FOR FUTURE DEVT.)
ARE NOT INCLUDED IN THIS WORK AND CONSIDERED IN FUTURE CONSTRUCTION.
4. A 75mm BACKFILL ALLOWANCE SHALL BE PROVIDED ABOVE THE FINISH
GRADE LEVEL TO COMPENSATE THE EXPECTED 75mm SETTLEMENT OF
BACKFILL MATERIALS.

DRAFTED BY:
FROM THE OFFICE OF: SEAL PROJECT TITLE: #1014 PROJECT OWNER: SHEET CONTENTS: THIS DRAWING IS ISSUED FOR: SHEET NO.
FL
AS BUILT ESTIMATE
DATE:
PRC NO.: DATE: 21 AUGUST 2018 BIDDING FABRICATION
67949 10-12-93

ERWIN J. PONCE PTR NO.: DATE:


BATCHING PLANT FOUNDATION CEBU LINK JOINT VENTURE (CLJV) AS SHOWN
REVISION
-
BUILDING PERMIT

CONSTRUCTION
OWNER'S APPROVAL

PRESENTATION
S01
CIVIL ENGINEER 16932226 01-04-2018

PLACE: TIN:
IMPORTANT: ALL MEASUREMENTS ARE TO BE VERIFIED ON SITE BY THE CONTRACTOR. ALL DISCREPANCIES
ARE TO BE IMMEDIATELY REPORTED TO THE DESIGNER. THIS DRAWING ACTING AS AN INSTRUMENT OF SERVICES
S02
ADDRESS: POB., LILOAN, CEBU LOCATION: SRP, CEBU CITY ADDRESS: 10F INSULAR LIFE BLDG., AYALA BUSINESS PARK, CEBU CITY IS THE INTELLECTUAL PROPERTY OF THE ARCHITECT AND CANNOT BE REPRODUCED WITHOUT THEIR WRITTEN CONSENT.
MANDAUE CITY 129-167-593

You might also like