STF Palong Timur Rev.00 Run All Bs 31.07.2018 STF Palong Timur Rev.00 Run All Bs 31.07.2018
STF Palong Timur Rev.00 Run All Bs 31.07.2018 STF Palong Timur Rev.00 Run All Bs 31.07.2018
STF Palong Timur Rev.00 Run All Bs 31.07.2018 STF Palong Timur Rev.00 Run All Bs 31.07.2018
STF PALONG TIMUR REV.00 RUN ALL BS 31.07.2018 389.0d 133.0d -184.0d 02-Oct-17 08:00 03-Jan-19 08:00 100% 91.61%
AM A AM
Milestone 389.0d 0.0d -184.0d 02-Oct-17 08:00 AM A
03-Jan-19 08:00 AM 0% 0%
ML-001-100 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A
02-Oct-17 08:00 AM A 100% 100%
ML-001-110 Milestone Finish STF 0.0d 0.0d -184.0d 03-Jan-19 08:00 AM 03-Jan-19 08:00 AM 100% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
External Finishes 18.0d 18.0d -86.0d 09-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 90%
A1350 External plastering & painting 18.0d 18.0d -86.0d 09-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 90%
Internal Floor & Wall Finishes 18.0d 18.0d -86.0d 04-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 95%
A1360 Floor rendering, install tiles, install GI tray, internal plastering & painting 18.0d 18.0d -86.0d 04-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 95%
Ceiling Finishes 18.0d 0.0d 17-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
A1370 Install frame, ceiling & painting 18.0d 0.0d 17-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
Pipeworks 176.0d 18.0d -86.0d 20-Dec-17 08:00 AM21-Aug-18
A 05:00 PM 100% 97%
A1550 Lifting Davit, High Pressure Rubber Hose 12.0d 12.0d -110.0d 05-Sep-18 08:00 AM18-Sep-18 05:00 PM 100% 0%
Existing Sedimentation Tank 212.0d 0.0d 06-Dec-17 08:00 AM24-Jul-18
A 05:00 PM A 100% 100%
Procurement 60.0d 0.0d 06-Dec-17 08:00 AM21-Apr-18
A 05:00 PM A 100% 100%
A1560 Submersible Sludge Pump 60.0d 0.0d 06-Dec-17 08:00 AM30-Mar-18
A 05:00 PM A 100% 100%
A1570 Pipes, Fittings & Valves 30.0d 0.0d 06-Dec-17 08:00 AM21-Apr-18
A 05:00 PM A 100% 100%
Installation 40.0d 0.0d 30-Jun-18 08:00 AM 2
A4-Jul-18 05:00 PM A 100% 100%
A1580 Submersible Sludge Pump 24.0d 0.0d 18-Jul-18 08:00 AM A19-Jul-18 05:00 PM A 100% 100%
A1590 Pipes, Fittings & Valves 24.0d 0.0d 30-Jun-18 08:00 AM 2
A4-Jul-18 05:00 PM A 100% 100%
Polymer Plant 234.0d 0.0d 06-Dec-17 08:00 AM27-Jul-18
A 05:00 PM A 100% 100%
Engineering Design 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
A1600 Engineering design for Polymer Plant & Dosing System 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
Procurement & Delivery 60.0d 0.0d 06-Dec-17 08:00 AM23-Jul-18
A 05:00 PM A 100% 100%
A1610 Metering Pumps (Diaphragm type) 60.0d 0.0d 06-Dec-17 08:00 AM21-Jul-18
A 05:00 PM A 100% 100%
A1620 Crane / Lifting Equipment 30.0d 0.0d 06-Dec-17 08:00 AM23-Jul-18
A 05:00 PM A 100% 100%
A1630 Static Mixer & Sludge Blender 30.0d 0.0d 06-Dec-17 08:00 AM14-Jul-18
A 05:00 PM A 100% 100%
Fabrication 36.0d 0.0d 02-May-18 08:00 AM12-Jun-18
A 05:00 PM A 100% 100%
A1640 Mixing & Service Tank 36.0d 0.0d 02-May-18 08:00 AM12-Jun-18
A 05:00 PM A 100% 100%
A1650 Hopper, Feeder & Pump Skid 36.0d 0.0d 02-May-18 08:00 AM12-Jun-18
A 05:00 PM A 100% 100%
A1660 Local Control Panel 30.0d 0.0d 02-May-18 08:00 AM12-Jun-18
A 05:00 PM A 100% 100%
Installation 50.0d 0.0d 14-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1670 Mixing & Service Tank 24.0d 0.0d 23-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1680 Hopper, Feeder & Pump Skid 24.0d 0.0d 23-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1690 Dosing Pipeworks 24.0d 0.0d 23-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1700 Local Control Panel 12.0d 0.0d 27-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1710 Jib Crane 12.0d 0.0d 24-Jul-18 08:00 AM A25-Jul-18 05:00 PM A 100% 100%
A1720 Static Mixer & Sludge Blender 12.0d 0.0d 14-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
Pipeworks 188.0d 0.0d 20-Dec-17 08:00 AM27-Jul-18
A 05:00 PM A 100% 100%
Procurement 24.0d 0.0d 20-Dec-17 08:00 AM29-Mar-18
A 05:00 PM A 100% 100%
A1730 To procure & deliver Pipes to site 24.0d 0.0d 20-Dec-17 08:00 AM29-Mar-18
A 05:00 PM A 100% 100%
Installation 24.0d 0.0d 04-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
A1740 Excavation & backfilling works 24.0d 0.0d 04-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
A1750 Pipe laying & jointing 24.0d 0.0d 04-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
Testing 6.0d 0.0d 21-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1760 Cleaning & testing works 6.0d 0.0d 21-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
Miscellaneous Works 201.0d 18.0d -86.0d 20-Dec-17 08:00 AM21-Aug-18
A 05:00 PM 100% 96.36%
Engineering Design 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
A1770 Engineering design for Motive Water System & Air Compressor 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
Procurement 61.0d 0.0d 13-Jan-18 08:00 AM 2
A1-Jul-18 05:00 PM A 100% 100%
A1780 Booster Pump 30.0d 0.0d 13-Jan-18 08:00 AM 2
A1-Jul-18 05:00 PM A 100% 100%
A1790 Air Compressor Set (2 units) 30.0d 0.0d 13-Jan-18 08:00 AM 0
A3-May-18 05:00 PM A 100% 100%
A1800 Submersible Pump (Portable & Gasoline Engine) 30.0d 0.0d 13-Jan-18 08:00 AM 2
A1-May-18 05:00 PM A 100% 100%
A1810 Portable Water jet 12.0d 0.0d 13-Jan-18 08:00 AM 2
A1-Apr-18 05:00 PM A 100% 100%
A1820 Penstock & Valves 60.0d 0.0d 13-Jan-18 08:00 AM 2
A4-May-18 05:00 PM A 100% 100%
A1830 FAT Penstock / Valves 1.0d 0.0d 26-Mar-18 08:00 AM26-Mar-18
A 05:00 PM A 100% 100%
Installation 40.0d 18.0d -86.0d 01-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 86.36%
A1840 Booster Pump Set 18.0d 0.0d 21-Jul-18 08:00 AM A25-Jul-18 05:00 PM A 100% 100%
A1850 Air Compressor Set (2 units) 18.0d 18.0d -86.0d 26-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 50%
A1860 Penstock / Valves 30.0d 0.0d 01-Jul-18 08:00 AM A16-Jul-18 05:00 PM A 100% 100%
Electrical Works 249.0d 30.0d -98.0d 08-Nov-17 08:00 AM04-Sep-18
A 05:00 PM 100% 88.37%
Training, Testing, Commissioning & Maintenance 180.0d 17.0d -184.0d 07-Jun-18 08:00 AM 0
A2-Jan-19 05:00 PM 100% 12.41%
A2070 Preparation of testing & report 12.0d 12.0d -184.0d 07-Jun-18 08:00 AM 2
A7-Dec-18 05:00 PM 100% 30%
A2080 Pre-commissioning 6.0d 6.0d -184.0d 15-Dec-18 08:00 AM20-Dec-18 05:00 PM 100% 0%
A2090 Setting to work 3.0d 3.0d -184.0d 22-Dec-18 08:00 AM24-Dec-18 05:00 PM 100% 0%
A2100 Commissioning & training 7.0d 7.0d -184.0d 25-Dec-18 08:00 AM01-Jan-19 05:00 PM 100% 0%
A2110 Handing over to Client 1.0d 1.0d -184.0d 02-Jan-19 08:00 AM 02-Jan-19 05:00 PM 100% 0%