STF Palong Timur Rev.00 Run All Bs 31.07.2018 STF Palong Timur Rev.00 Run All Bs 31.07.2018

Download as pdf or txt
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 6

STF PALONG TIMUR REV.00 RUN ALL BS 31.07.

2018 Classic Schedule Layout 31-Jul-18 01:18 PM


Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF PALONG TIMUR REV.00 RUN ALL BS 31.07.2018 389.0d 133.0d -184.0d 02-Oct-17 08:00 03-Jan-19 08:00 100% 91.61%
AM A AM
Milestone 389.0d 0.0d -184.0d 02-Oct-17 08:00 AM A
03-Jan-19 08:00 AM 0% 0%
ML-001-100 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A
02-Oct-17 08:00 AM A 100% 100%
ML-001-110 Milestone Finish STF 0.0d 0.0d -184.0d 03-Jan-19 08:00 AM 03-Jan-19 08:00 AM 100% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%

Documentation 32.0d 0.0d 02-Oct-17 08:00 AM A


07-Nov-17 05:00 PM A 100% 100%
Preparation & Submission 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
A1000 Preparation of Performance Bond 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1010 Preparation of Insurance Policies / Public Liability / Workmen's Compensation
14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1020 Preparation & Submission of Levy of CIDB 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1030 Site Registration of JKKP (DOSH) 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1040 Submission Copy of SPAN Certificate 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1050 Preparation & Submission of Lithography Expenses 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1060 Preparation & Submission of PQP / Method Statements 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1070 Preparation of Works (Contractor Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
A1080 Preparation of Works (Engineers / S.O / PD's Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
A1090 Preparation of Works (General Obligation, Project Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
A1100 Preparation of Works (Authorities Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
A1110 Preparation of Works (Environmental Protection & Enhancement) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
Civil & Structure Works 205.0d 41.0d -109.0d 06-Dec-17 08:00 AM17-Sep-18
A 05:00 PM 100% 97.24%

Preliminary Works 22.0d 0.0d 11-Dec-17 08:00 AM30-Jan-18


A 05:00 PM A 100% 100%
Setting Up of Site 12.0d 0.0d 11-Dec-17 08:00 AM21-Dec-17
A 05:00 PM A 100% 100%
A1120 Site measurement & site survey 12.0d 0.0d 11-Dec-17 08:00 AM21-Dec-17
A 05:00 PM A 100% 100%
Earthwork 12.0d 0.0d 22-Dec-17 08:00 AM30-Jan-18
A 05:00 PM A 100% 100%
A1130 Site clearance & excavation works 12.0d 0.0d 22-Dec-17 08:00 AM30-Jan-18
A 05:00 PM A 100% 100%
Water Retaining Structure 141.0d 18.0d -86.0d 06-Dec-17 08:00 AM21-Aug-18
A 05:00 PM 100% 98.72%
Wash Water Collection & Sludge Balancing Tank 141.0d 18.0d -86.0d 06-Dec-17 08:00 AM21-Aug-18
A 05:00 PM 100% 98.72%
Substructure 53.0d 0.0d 06-Dec-17 08:00 AM10-Mar-18
A 05:00 PM A 100% 100%
A1140 Install reinforcement 26.0d 0.0d 06-Dec-17 08:00 AM06-Mar-18
A 05:00 PM A 100% 100%
A1150 Install formwork 26.0d 0.0d 10-Dec-17 08:00 AM06-Mar-18
A 05:00 PM A 100% 100%
A1160 Concreting work 5.0d 0.0d 03-Feb-18 08:00 AM 10-Mar-18
A 05:00 PM A 100% 100%
Wall & Top Slab 68.0d 0.0d 22-Feb-18 08:00 AM 28-Apr-18
A 05:00 PM A 100% 100%

Page 1 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 31.07.2018 Classic Schedule Layout 31-Jul-18 01:18 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

A1170 Frame 24.0d 0.0d 22-Feb-18 08:00 AM 21-Apr-18


A 05:00 PM A 100% 100%
A1180 External finishes 18.0d 0.0d 22-Apr-18 08:00 AM A
28-Apr-18 05:00 PM A 100% 100%
A1190 Internal finishes 18.0d 0.0d 22-Apr-18 08:00 AM A
28-Apr-18 05:00 PM A 100% 100%
Backfilling & Compaction 18.0d 18.0d -86.0d 28-Apr-18 08:00 AM A
21-Aug-18 05:00 PM 100% 90%
A1210 Backfill, level & compact 18.0d 18.0d -86.0d 28-Apr-18 08:00 AM A
21-Aug-18 05:00 PM 100% 90%
Testing 6.0d 0.0d 19-May-18 08:00 AM12-Jul-18
A 05:00 PM A 100% 100%
A1200 Cleaning & Water Tighness Testing 6.0d 0.0d 19-May-18 08:00 AM12-Jul-18
A 05:00 PM A 100% 100%
Platform Structure 150.0d 41.0d -139.0d 06-Dec-17 08:00 AM17-Sep-18
A 05:00 PM 100% 92.31%
Dewatering Container (Geotube) 150.0d 41.0d -139.0d 06-Dec-17 08:00 AM17-Sep-18
A 05:00 PM 100% 92.31%
Substructure (Drain & Slab) 137.0d 5.0d -139.0d 06-Dec-17 08:00 AM06-Aug-18
A 05:00 PM 100% 100%
A1220 Install reinforcement 26.0d 0.0d 06-Dec-17 08:00 AM26-May-18
A 05:00 PM A 100% 100%
A1230 Install formwork 26.0d 0.0d 10-Dec-17 08:00 AM26-May-18
A 05:00 PM A 100% 100%
A1240 Concreting work 5.0d 5.0d -139.0d 15-May-18 08:00 AM06-Aug-18
A 05:00 PM 100% 100%
Ramp 24.0d 0.0d 22-Apr-18 08:00 AM A
11-Jun-18 05:00 PM A 100% 100%
A1250 Formwork, reinforcement, concrete & cover 24.0d 0.0d 22-Apr-18 08:00 AM A
11-Jun-18 05:00 PM A 100% 100%
Geotube 36.0d 36.0d -139.0d 23-Apr-18 08:00 AM A
17-Sep-18 05:00 PM 100% 75%
A1260 Preparation & installation 36.0d 36.0d -139.0d 23-Apr-18 08:00 AM A
17-Sep-18 05:00 PM 100% 75%
Building 205.0d 18.0d -86.0d 06-Dec-17 08:00 AM21-Aug-18
A 05:00 PM 100% 98.7%
Polymer Plant 205.0d 18.0d -86.0d 06-Dec-17 08:00 AM21-Aug-18
A 05:00 PM 100% 98.7%
Substructure (Footing, Stump, Ground Beam & Slab) 127.0d 0.0d 06-Dec-17 08:00 AM08-May-18
A 05:00 PM A 100% 100%
A1270 Install reinforcement 26.0d 0.0d 06-Dec-17 08:00 AM07-May-18
A 05:00 PM A 100% 100%
A1280 Install formwork 26.0d 0.0d 10-Dec-17 08:00 AM07-May-18
A 05:00 PM A 100% 100%
A1290 Concreting work 5.0d 0.0d 03-May-18 08:00 AM08-May-18
A 05:00 PM A 100% 100%
Frame (Upper Beam & Column) 24.0d 0.0d 23-Apr-18 08:00 AM A
15-May-18 05:00 PM A 100% 100%
A1300 Scaffold, stagging, formwork, reinforcement, t-prox, soffit & concrete 24.0d 0.0d 23-Apr-18 08:00 AM A
15-May-18 05:00 PM A 100% 100%
Ramp & Drain 18.0d 0.0d 23-Apr-18 08:00 AM A
19-Jul-18 05:00 PM A 100% 100%
A1310 Excavation, levelling, formwork, reinforcement & concrete 18.0d 0.0d 23-Apr-18 08:00 AM A
19-Jul-18 05:00 PM A 100% 100%
Roof 18.0d 0.0d 05-May-18 08:00 AM20-Jul-18
A 05:00 PM A 100% 100%
A1320 Install roof truss & covering 18.0d 0.0d 05-May-18 08:00 AM20-Jul-18
A 05:00 PM A 100% 100%
Wall 18.0d 0.0d 23-Apr-18 08:00 AM A
08-Jun-18 05:00 PM A 100% 100%
A1330 Installation of Brickwall 18.0d 0.0d 23-Apr-18 08:00 AM A
08-Jun-18 05:00 PM A 100% 100%
Accessories 18.0d 0.0d 13-Jun-18 08:00 AM 2
A1-Jul-18 05:00 PM A 100% 100%
A1340 Install frame, doors, windows, roller shutter & lockset 18.0d 0.0d 13-Jun-18 08:00 AM 2
A1-Jul-18 05:00 PM A 100% 100%

Page 2 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 31.07.2018 Classic Schedule Layout 31-Jul-18 01:18 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

External Finishes 18.0d 18.0d -86.0d 09-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 90%
A1350 External plastering & painting 18.0d 18.0d -86.0d 09-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 90%
Internal Floor & Wall Finishes 18.0d 18.0d -86.0d 04-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 95%
A1360 Floor rendering, install tiles, install GI tray, internal plastering & painting 18.0d 18.0d -86.0d 04-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 95%
Ceiling Finishes 18.0d 0.0d 17-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
A1370 Install frame, ceiling & painting 18.0d 0.0d 17-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
Pipeworks 176.0d 18.0d -86.0d 20-Dec-17 08:00 AM21-Aug-18
A 05:00 PM 100% 97%

Procurement 24.0d 0.0d 20-Dec-17 08:00 AM29-Mar-18


A 05:00 PM A 100% 100%
A1380 To procure & deliver Pipes to site 24.0d 0.0d 20-Dec-17 08:00 AM29-Mar-18
A 05:00 PM A 100% 100%
Installation 46.0d 18.0d -86.0d 01-Apr-18 08:00 AM A
21-Aug-18 05:00 PM 100% 96%
A1390 Excavation & backfilling works 24.0d 0.0d 25-Apr-18 08:00 AM A
10-Jul-18 05:00 PM A 100% 100%
A1400 Pipe laying & jointing 24.0d 0.0d 26-Apr-18 08:00 AM A
10-Jul-18 05:00 PM A 100% 100%
A1410 Connection to existing Chamber / Pipes 24.0d 0.0d 26-Apr-18 08:00 AM A
30-Apr-18 05:00 PM A 100% 100%
A1420 Miscellaneous works 18.0d 18.0d -86.0d 01-Apr-18 08:00 AM A
21-Aug-18 05:00 PM 100% 80%
Testing 6.0d 0.0d 11-Jul-18 08:00 AM A25-Jul-18 05:00 PM A 100% 100%
A1430 Cleaning & testing works 6.0d 0.0d 11-Jul-18 08:00 AM A25-Jul-18 05:00 PM A 100% 100%
Mechanical Works 254.0d 42.0d -93.0d 22-Nov-17 08:00 AM18-Sep-18
A 05:00 PM 100% 97.38%

Drawing & Material Approval 24.0d 0.0d 22-Nov-17 08:00 AM19-Dec-17


A 05:00 PM A 100% 100%
A1440 Submission of Drawing / Material for approval 12.0d 0.0d 22-Nov-17 08:00 AM05-Dec-17
A 05:00 PM A 100% 100%
A1450 Review & approval for Drawing / Material 12.0d 0.0d 06-Dec-17 08:00 AM19-Dec-17
A 05:00 PM A 100% 100%
Wash Water Collection & Sludge Balancing Tank 242.0d 42.0d -110.0d 06-Dec-17 08:00 AM18-Sep-18
A 05:00 PM 100% 92.26%
Procurement 102.0d 30.0d -110.0d 06-Dec-17 08:00 AM04-Sep-18
A 05:00 PM 100% 95.54%
A1460 Horizontal Screw Pump, Subermisble Supernatant Pump 72.0d 0.0d 06-Dec-17 08:00 AM03-May-18
A 05:00 PM A 100% 100%
A1470 FAT Wash Water Recovery Pumpset 6.0d 0.0d 05-Mar-18 08:00 AM27-Mar-18
A 05:00 PM A 100% 100%
A1480 Pipes, Fittings & Valves 30.0d 0.0d 05-Mar-18 08:00 AM21-Apr-18
A 05:00 PM A 100% 100%
A1490 Submersible Mixer 30.0d 0.0d 05-Mar-18 08:00 AM30-Mar-18
A 05:00 PM A 100% 100%
A1500 Lifting Davit, High Pressure Rubber Hose 30.0d 30.0d -110.0d 05-Mar-18 08:00 AM04-Sep-18
A 05:00 PM 100% 75%
Installation 66.0d 12.0d -110.0d 04-Jul-18 08:00 AM A18-Sep-18 05:00 PM 100% 85.71%
A1510 Construction of Horizontal Screw Pump Pit 24.0d 0.0d 05-Jul-18 08:00 AM A15-Jul-18 05:00 PM A 100% 100%
A1520 Horizontal Screw Pump, Subermisble Supernatant Pump 18.0d 0.0d 04-Jul-18 08:00 AM A19-Jul-18 05:00 PM A 100% 100%
A1530 Pipes, Fittings & Valves 18.0d 0.0d 04-Jul-18 08:00 AM A19-Jul-18 05:00 PM A 100% 100%
A1540 Submersible Mixer 12.0d 0.0d 04-Jul-18 08:00 AM A19-Jul-18 05:00 PM A 100% 100%

Page 3 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 31.07.2018 Classic Schedule Layout 31-Jul-18 01:18 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

A1550 Lifting Davit, High Pressure Rubber Hose 12.0d 12.0d -110.0d 05-Sep-18 08:00 AM18-Sep-18 05:00 PM 100% 0%
Existing Sedimentation Tank 212.0d 0.0d 06-Dec-17 08:00 AM24-Jul-18
A 05:00 PM A 100% 100%
Procurement 60.0d 0.0d 06-Dec-17 08:00 AM21-Apr-18
A 05:00 PM A 100% 100%
A1560 Submersible Sludge Pump 60.0d 0.0d 06-Dec-17 08:00 AM30-Mar-18
A 05:00 PM A 100% 100%
A1570 Pipes, Fittings & Valves 30.0d 0.0d 06-Dec-17 08:00 AM21-Apr-18
A 05:00 PM A 100% 100%
Installation 40.0d 0.0d 30-Jun-18 08:00 AM 2
A4-Jul-18 05:00 PM A 100% 100%
A1580 Submersible Sludge Pump 24.0d 0.0d 18-Jul-18 08:00 AM A19-Jul-18 05:00 PM A 100% 100%
A1590 Pipes, Fittings & Valves 24.0d 0.0d 30-Jun-18 08:00 AM 2
A4-Jul-18 05:00 PM A 100% 100%
Polymer Plant 234.0d 0.0d 06-Dec-17 08:00 AM27-Jul-18
A 05:00 PM A 100% 100%
Engineering Design 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
A1600 Engineering design for Polymer Plant & Dosing System 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
Procurement & Delivery 60.0d 0.0d 06-Dec-17 08:00 AM23-Jul-18
A 05:00 PM A 100% 100%
A1610 Metering Pumps (Diaphragm type) 60.0d 0.0d 06-Dec-17 08:00 AM21-Jul-18
A 05:00 PM A 100% 100%
A1620 Crane / Lifting Equipment 30.0d 0.0d 06-Dec-17 08:00 AM23-Jul-18
A 05:00 PM A 100% 100%
A1630 Static Mixer & Sludge Blender 30.0d 0.0d 06-Dec-17 08:00 AM14-Jul-18
A 05:00 PM A 100% 100%
Fabrication 36.0d 0.0d 02-May-18 08:00 AM12-Jun-18
A 05:00 PM A 100% 100%
A1640 Mixing & Service Tank 36.0d 0.0d 02-May-18 08:00 AM12-Jun-18
A 05:00 PM A 100% 100%
A1650 Hopper, Feeder & Pump Skid 36.0d 0.0d 02-May-18 08:00 AM12-Jun-18
A 05:00 PM A 100% 100%
A1660 Local Control Panel 30.0d 0.0d 02-May-18 08:00 AM12-Jun-18
A 05:00 PM A 100% 100%
Installation 50.0d 0.0d 14-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1670 Mixing & Service Tank 24.0d 0.0d 23-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1680 Hopper, Feeder & Pump Skid 24.0d 0.0d 23-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1690 Dosing Pipeworks 24.0d 0.0d 23-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1700 Local Control Panel 12.0d 0.0d 27-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
A1710 Jib Crane 12.0d 0.0d 24-Jul-18 08:00 AM A25-Jul-18 05:00 PM A 100% 100%
A1720 Static Mixer & Sludge Blender 12.0d 0.0d 14-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
Pipeworks 188.0d 0.0d 20-Dec-17 08:00 AM27-Jul-18
A 05:00 PM A 100% 100%
Procurement 24.0d 0.0d 20-Dec-17 08:00 AM29-Mar-18
A 05:00 PM A 100% 100%
A1730 To procure & deliver Pipes to site 24.0d 0.0d 20-Dec-17 08:00 AM29-Mar-18
A 05:00 PM A 100% 100%
Installation 24.0d 0.0d 04-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
A1740 Excavation & backfilling works 24.0d 0.0d 04-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
A1750 Pipe laying & jointing 24.0d 0.0d 04-Jul-18 08:00 AM A24-Jul-18 05:00 PM A 100% 100%
Testing 6.0d 0.0d 21-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%

Page 4 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 31.07.2018 Classic Schedule Layout 31-Jul-18 01:18 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

A1760 Cleaning & testing works 6.0d 0.0d 21-Jul-18 08:00 AM A27-Jul-18 05:00 PM A 100% 100%
Miscellaneous Works 201.0d 18.0d -86.0d 20-Dec-17 08:00 AM21-Aug-18
A 05:00 PM 100% 96.36%
Engineering Design 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
A1770 Engineering design for Motive Water System & Air Compressor 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
Procurement 61.0d 0.0d 13-Jan-18 08:00 AM 2
A1-Jul-18 05:00 PM A 100% 100%
A1780 Booster Pump 30.0d 0.0d 13-Jan-18 08:00 AM 2
A1-Jul-18 05:00 PM A 100% 100%
A1790 Air Compressor Set (2 units) 30.0d 0.0d 13-Jan-18 08:00 AM 0
A3-May-18 05:00 PM A 100% 100%
A1800 Submersible Pump (Portable & Gasoline Engine) 30.0d 0.0d 13-Jan-18 08:00 AM 2
A1-May-18 05:00 PM A 100% 100%
A1810 Portable Water jet 12.0d 0.0d 13-Jan-18 08:00 AM 2
A1-Apr-18 05:00 PM A 100% 100%
A1820 Penstock & Valves 60.0d 0.0d 13-Jan-18 08:00 AM 2
A4-May-18 05:00 PM A 100% 100%
A1830 FAT Penstock / Valves 1.0d 0.0d 26-Mar-18 08:00 AM26-Mar-18
A 05:00 PM A 100% 100%
Installation 40.0d 18.0d -86.0d 01-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 86.36%
A1840 Booster Pump Set 18.0d 0.0d 21-Jul-18 08:00 AM A25-Jul-18 05:00 PM A 100% 100%
A1850 Air Compressor Set (2 units) 18.0d 18.0d -86.0d 26-Jul-18 08:00 AM A21-Aug-18 05:00 PM 100% 50%
A1860 Penstock / Valves 30.0d 0.0d 01-Jul-18 08:00 AM A16-Jul-18 05:00 PM A 100% 100%
Electrical Works 249.0d 30.0d -98.0d 08-Nov-17 08:00 AM04-Sep-18
A 05:00 PM 100% 88.37%

Drawing & Material Approval 24.0d 0.0d 08-Nov-17 08:00 AM05-Dec-17


A 05:00 PM A 100% 100%
A1870 Submission of Drawing / Material for approval 12.0d 0.0d 08-Nov-17 08:00 AM21-Nov-17
A 05:00 PM A 100% 100%
A1880 Review & approval for Drawing / Material 12.0d 0.0d 22-Nov-17 08:00 AM05-Dec-17
A 05:00 PM A 100% 100%
Switchboard / MCC Panel 237.0d 30.0d -98.0d 22-Nov-17 08:00 AM04-Sep-18
A 05:00 PM 100% 86.96%
A1890 Procurement & fabrication of Panel 84.0d 0.0d 22-Nov-17 08:00 AM19-Jul-18
A 05:00 PM A 100% 100%
A1900 FAT Electrical Control & Switchboards 1.0d 0.0d 27-Mar-18 08:00 AM24-May-18
A 05:00 PM A 100% 100%
A1910 Installation works 30.0d 30.0d -98.0d 26-Jul-18 08:00 AM A04-Sep-18 05:00 PM 100% 50%
Submain Cabling Works for MCC-SDP-Palong 75.0d 0.0d 05-Mar-18 08:00 AM09-Jun-18
A 05:00 PM A 100% 100%
A1920 Procurement & delivery of Cable 24.0d 0.0d 05-Mar-18 08:00 AM07-Jun-18
A 05:00 PM A 100% 100%
A1930 Installation & cabling works 30.0d 0.0d 26-Apr-18 08:00 AM A
09-Jun-18 05:00 PM A 100% 100%
Distribution & Earthing System 75.0d 30.0d -98.0d 05-Mar-18 08:00 AM04-Sep-18
A 05:00 PM 100% 83.33%
A1940 Procurement & delivery 24.0d 0.0d 05-Mar-18 08:00 AM18-Jul-18
A 05:00 PM A 100% 100%
A1950 Installation & cabling works 30.0d 30.0d -98.0d 26-Apr-18 08:00 AM A
04-Sep-18 05:00 PM 100% 70%
Compound Lighting System 75.0d 30.0d -98.0d 05-Mar-18 08:00 AM04-Sep-18
A 05:00 PM 100% 72.22%
A1960 Procurement & delivery 24.0d 0.0d 05-Mar-18 08:00 AM19-Jul-18
A 05:00 PM A 100% 100%
A1970 Installation & cabling works 30.0d 30.0d -98.0d 26-Apr-18 08:00 AM A
04-Sep-18 05:00 PM 100% 50%

Page 5 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 31.07.2018 Classic Schedule Layout 31-Jul-18 01:18 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

Relocation of Existing Cabling Works 30.0d 0.0d 11-Dec-17 08:00 AM09-Jan-18


A 05:00 PM A 100% 100%
A1980 To relocate existing Cable 30.0d 0.0d 11-Dec-17 08:00 AM09-Jan-18
A 05:00 PM A 100% 100%
Miscellaneous Works 30.0d 30.0d -98.0d 01-Apr-18 08:00 AM A
04-Sep-18 05:00 PM 100% 90%
A1990 Any other neccessary works 30.0d 30.0d -98.0d 01-Apr-18 08:00 AM A
04-Sep-18 05:00 PM 100% 90%
Instrumentation Works 338.0d 114.0d -184.0d 08-Nov-17 08:00 AM11-Dec-18
A 05:00 PM 100% 63.31%

Drawing & Material Approval 24.0d 0.0d 08-Nov-17 08:00 AM05-Dec-17


A 05:00 PM A 100% 100%
A2000 Submission of Drawing / Material for approval 12.0d 0.0d 08-Nov-17 08:00 AM21-Nov-17
A 05:00 PM A 100% 100%
A2010 Review & approval for Drawing / Material 12.0d 0.0d 22-Nov-17 08:00 AM05-Dec-17
A 05:00 PM A 100% 100%
Procurement & Fabrication 84.0d 84.0d -184.0d 22-Nov-17 08:00 AM06-Nov-18
A 05:00 PM 100% 75.29%
A2020 To procure & fabricate Instrument Panel 84.0d 84.0d -184.0d 22-Nov-17 08:00 AM06-Nov-18
A 05:00 PM 100% 75%
A2030 FAT 1.0d 0.0d 27-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
Installation 30.0d 30.0d -184.0d 07-Nov-18 08:00 AM11-Dec-18 05:00 PM 100% 0%
A2040 Installation & signal cabling works 30.0d 30.0d -184.0d 07-Nov-18 08:00 AM11-Dec-18 05:00 PM 100% 0%
Infrastructure Works 24.0d 24.0d -139.0d 25-Sep-18 08:00 AM22-Oct-18 05:00 PM 100% 0%

Roadworks 24.0d 24.0d -139.0d 25-Sep-18 08:00 AM22-Oct-18 05:00 PM 100% 0%


A2050 Site clearance, levelling & compaction 18.0d 18.0d -139.0d 25-Sep-18 08:00 AM15-Oct-18 05:00 PM 100% 0%
A2060 Lay of crusher-run & premix 24.0d 24.0d -139.0d 25-Sep-18 08:00 AM22-Oct-18 05:00 PM 100% 0%
Site Handover Work 180.0d 17.0d -184.0d 07-Jun-18 08:00 AM 0
A2-Jan-19 05:00 PM 100% 12.41%

Training, Testing, Commissioning & Maintenance 180.0d 17.0d -184.0d 07-Jun-18 08:00 AM 0
A2-Jan-19 05:00 PM 100% 12.41%
A2070 Preparation of testing & report 12.0d 12.0d -184.0d 07-Jun-18 08:00 AM 2
A7-Dec-18 05:00 PM 100% 30%
A2080 Pre-commissioning 6.0d 6.0d -184.0d 15-Dec-18 08:00 AM20-Dec-18 05:00 PM 100% 0%
A2090 Setting to work 3.0d 3.0d -184.0d 22-Dec-18 08:00 AM24-Dec-18 05:00 PM 100% 0%
A2100 Commissioning & training 7.0d 7.0d -184.0d 25-Dec-18 08:00 AM01-Jan-19 05:00 PM 100% 0%
A2110 Handing over to Client 1.0d 1.0d -184.0d 02-Jan-19 08:00 AM 02-Jan-19 05:00 PM 100% 0%