Actual Exam Questions: Exam ID: CA0-001 Exam Name: Certified Associate in Project Management

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

PMI

Exam ID: CA0-001


Exam Name: Certified Associate in Project Management

Actual Exam Questions


Demo Product

We also provide Practice Test Software. To Purchase Full Version OF


PDF and To Try Practice Test Software for free, visit:
http://www.prepnerds.com/CA0-001.html
http://www.PrepNerds.com

Question: 1
On what is project baseline development established?

A. Approved product requirements


B. Estimated project cost and schedule
C. Actual project cost and schedule
D. Revised project cost and schedule

Answer: B

Question: 2
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible
components of each deliverable are all part of which of the following?

A. Work breakdown structure


B. Organizational breakdown structure
C. Resource breakdown structure
D. Bill of materials

Answer: A

Question: 3
What is the definition of project plan execution?

A. Integrating all planned activities.


B. Performing the activities included in the plan.
C. Developing and maintaining the plan.
D. Execution of deliverables.

Answer: B

Question: 4
What is a tool to improve team performance?

A. Staffing plan
B. External feedback
C. Performance reports
D. Co-Location

Answer: D

Question: 5
Which type of analysis is used to develop the communications management plan?

A. Product
B. Cost benefit
C. Stakeholder
___________________________________________________
http://www.PrepNerds.com 2
http://www.PrepNerds.com

D. Research

Answer: C

Question: 6
Information distribution involves making needed information available to project stakeholders in a timely
manner. What is an output from information distribution?

A. Earned value analysis


B. Trend analysis
C. Project records
D. Performance reviews

Answer: C

Question: 7
Which type of analysis is used to examine project results through time to determine if performance is
improving or deteriorating?

A. Control chart
B. Earned value
C. Variance
D. Trend

Answer: D

Question: 8
You are assigned to implement the project control plan. What should you do to ensure the plan is effective and
current?

A. Perform periodic project performance reviews.


B. Identify quality project standards.
C. Follow ISO 9000 quality standards
D. Complete the quality control checklist.

Answer: A

Explanation:
The document control plan is an outline or guide on how physical or virtual documents will be managed
throughout the life of the project. It provides a road map for tracking documents and for adding, archiving, and
removing new documentation from the process.

Question: 9
Which of the following is an example of a risk symptom?

A. Failure to meet intermediate milestones


B. Force of nature, such as a flood
C. Risk threshold target
D. Crashing front loading or fast tracking

___________________________________________________
http://www.PrepNerds.com 3
http://www.PrepNerds.com

Answer: A

Question: 10
During what process is the quality policy determined?

A. Initiating
B. Executing
C. Planning
D. Controlling

Answer: C

Question: 11
What is one of the MAJOR outputs of activity sequencing?

A. Responsibility assignment matrix


B. Work breakdown structure update
C. Project network diagram
D. Mandatory dependencies list

Answer: C

Question: 12
Scope verification is PRIMARILY concerned with which of the following?

A. Acceptance of the work deliverables.


B. Accuracy of the work deliverables.
C. Approval of the scope statement.
D. Accuracy of the work breakdown structure.

Answer: A

Question: 13
Which of the following is an example of contract administration?

A. Negotiating the contract


B. Authorizing contractor work
C. Developing the statement of work
D. Establishing evaluation criteria

Answer: B

Question: 14
Who MUST know when a risk event occurs so that a response can be implemented?

A. Customers
B. Project sponsors
C. Project management team
D. Insurance claims department
___________________________________________________
http://www.PrepNerds.com 4
http://www.PrepNerds.com

Answer: C

Question: 15
A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the
actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost
variance?

A. -$700
B. -$200
C. +$200
D. +$500

Answer: A

Question: 16
How is quality control performed?

A. By identifying quality standards that are relevant to the project and determining how to satisfy them.
B. By monitoring specific project results in compliance with relevant quality standards and determining
corrective actions as needed.
C. By ensuring that the entire project team has been adequately trained in quality assurance processes.
D. By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to ensure conformance to
quality standards.

Answer: B

Question: 17
As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project
cost. You should calculate the forecast using which of the following methods?

A. BAC
B. EAC
C. ETC
D. WBS

Answer: B

Question: 18
How is scheduled variance calculated using the earned value technique?

A. EV less AC
B. AC less PV
C. EV less PV
D. AC less EV

Answer: C

Question: 19
___________________________________________________
http://www.PrepNerds.com 5
http://www.PrepNerds.com

The project management processes presented in the PMBOK Guide should:

A. Always be applied uniformly


B. Be selected as appropriate by the sponsor
C. Be selected as appropriate by the project team
D. Be applied based on ISO guidelines.

Answer: C

Question: 20
Who is responsible for determining which processes from the Process Groups will be employed and who will
be performing them?

A. Project sponsor and project manager


B. Project sponsor and functional manager
C. Project manager and project team
D. Project team and functional manager

Answer: C

Explanation:
The project management processes are presented as discrete elements with welldefined interfaces. However,
in practice they overlap and interact in ways that are not completely detailed here. Most experienced project
management practitioners recognize there is more than one way to manage a project. The specifics for a
project are defined as objectives that must be accomplished based on complexity, risk, size, time frame,
project team’s experience, access to resources, amount of historical information, the organization’s project
management maturity, and industry and application area. The required Process Groups and their constituent
processes are guides to apply appropriate project management knowledge and skills during the project. In
addition, the application of the project management processes to a project is iterative and many processes are
repeated and revised during the project. The project manager and the project team are responsible for
determining what processes from the Process Groups will be employed, by whom, and the degree of rigor that
will be applied to the execution of those processes to achieve the desired project objective.

Question: 21
Which of the following processes is necessary to ensure that the project employs all processes needed to meet
its requirements?

A. Perform Quality Control


B. Quality Policy
C. Perform Quality Assurance
D. Quality Planning

Answer: C

Question: 22
Which process occurs within the Monitoring and Controlling Process Group?

A. Cost Control
B. Quality Planning
C. Quantitative Risk Analysis
D. Cost Budgeting

___________________________________________________
http://www.PrepNerds.com 6
http://www.PrepNerds.com

Answer: A

Question: 23
The Define Scope process is in which of the following process groups?

A. Initiating
B. Planning
C. Monitoring & Controlling
D. Executing

Answer: B

Question: 24
Which activity is an input to the select sellers process?

A. Organizational process assets


B. Resource availability
C. Change control process
D. Team performance assessment

Answer: A

Question: 25
What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

A. Pareto
B. Ishikawa
C. Shewart-Deming
D. Delphi

Answer: C

___________________________________________________
http://www.PrepNerds.com 7
http://www.PrepNerds.com

THANKS FOR TRYING THE DEMO OF OUR PRODUCT

Visit Our Site to Purchase the Full Set of Actual CA0-001 Exam Questions With Answers.

http://www.prepnerds.com/CA0-001.html

We Also Provide Practice Exam Software That Simulates Real Exam Environment And Has
Many Self-Assessment Features. Download Free Product Demo From:

http://www.prepnerds.com/CA0-001.html

Money Back Guarantee

Check Out Our Customer Testimonials


https://vimeo.com/102521326

___________________________________________________
http://www.PrepNerds.com 8

You might also like