Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Grouted Riprap

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 8

SECTION 02374

GROUTED RIPRAP

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Materials requirements and procedures for furnishing, transporting, and


installing grouted riprap and all related materials.

1.2 RELATED SECTIONS

A. Section 02075: Geotextiles

B. Section 02373: Riprap

C. Section 03055: Portland Cement Concrete

1.3 REFERENCES

A. AASHTO M 288: Geotextile Specification for Highway Applications

B. AASHTO T 27: Sieve Analysis of Fine and Coarse Aggregate

C. AASHTO T 99: Moisture Density Relations of Soils Using a 5.5 Lb.


Rammer and a 12 inch Drop

D. AASHTO T 180: Moisture Density Relations of Soils Using a 10 lb


Rammer and an 18 inch Drop

1.4 DEFINITIONS Not Used

1.5 SUBMITTALS

A. In writing, at the preconstruction conference:


1. Document the source, gradation, wear, and soundness for riprap.
Refer to Section 02373.
2. Grout mix-design.
3. Riprap Rock samples for quality assurance testing before use.

B. Riprap Source
1. Provide written certification verifying the quality of riprap existing at
the industrial source. Refer to this Section, article 1.6 paragraph
B3.

Grouted Riprap
02374 – Page 1 of 8
January 1, 2012
2. Provide historic results on rock reactivity or petrographic analysis of
the proposed materials for riprap. Refer to this Section, article 1.6
paragraph B.

C. Grout
1. Submit a grout mix design for a mix that readily flows into the open
spaces between the stones of the riprap gradation used. Refer to
this Section, article 2.2.

1.6 QUALITY ASSURANCE

A. Grouted Riprap Sample Panel


1. Construct a 4 ft long x 4 ft wide x 1½ ft thick sample panel.
Integrate the sample panel in the project quantity. Retain samples
of cements, sands, aggregates, and additives used in this sample
for comparison with materials used in the project. Reduce or revise
sample panel size according to the resident engineer directions for
small quantities less than 20 ft2.
2. Use the accepted 4 ft x 4 ft x 1½ ft sample panel as a standard to
judge consistent visual appearance, acceptable workmanship, joint
treatment, curing, cleaning, and construction techniques to be used
throughout the project.
3. Remove sample panel upon completion and acceptance of riprap
installation. The Engineer may allow the sample panel to be
integrated into the accepted work.

B. Riprap Source
1. Set up riprap source location inspection meeting with the Engineer
and source material owner before delivering materials to project
site.
2. Identify stock piling procedure.
3. Certify that “reactive” stone are not found in the quarry pit. Alkali-
silica and alkali-carbon reactions are the most frequent of these
reactions. Perform a petrographic analysis on representative
aggregate samples to determine whether reactive stones are
present in the absence of a documented 10-year use history of
quarry aggregates in commercial concrete mix designs.

C. Preconstruction Conference
1. Provide
a. Proposed source sites
b. Material test results
c. Grout mix design
d. Quality control plan

Grouted Riprap
02374 – Page 2 of 8
January 1, 2012
1.7 DELIVERY, STORAGE, AND HANDLING

A. Deliver and stock pile enough stone onsite for project.

B. Prevent contamination of the stone surfaces with clays or similar


materials.

C. Remove any stone that does not conform to this specification.


1. The Engineer may reject any stones not conforming to this
specification.

PART 2 PRODUCTS

2.1 RIPRAP ELEMENTS

A. Stone Quality
1. See Section 02373.

B. Stone Gradation
1. Provide stones for grouted riprap of 1½ to 2 ft thick that meet the
gradation requirements detailed in Table 1.

Table 1
Gradation Requirements
Stone Sizes Percent Larger Than Given Stone Size
Equivalent
Weight 1½ to 2 ft
Diameter
Grouted Riprap Thickness
(Feet)
2.25 ½ ton 0-5
1.75 ¼ ton 50 - 100
1.25 200 lb ---
1.00 75 lb 95 - 100

C. Use gradations that allow full grout penetration around the rocks.

2.2 GROUT

A. Provide grout that meets the following requirements


1. Minimum 28-day compressive strength of 3,000 psi, conform to
strength testing requirements of Section 03055.
2. Minimum air content of 5 percent.
3. Use the approved mix design desired by the contractor.
4. Use a minimum of six sacks of type II portland cement per cubic
yard of grout.
5. Add 1½ pounds of fiber mesh or equivalent per cubic yard of grout.
Grouted Riprap
02374 – Page 3 of 8
January 1, 2012
6. Do not use calcium chloride admixtures.

2.3 ACCESSORIES

A. Cement, pozzolan, aggregates, water, air-entraining admixtures and other


admixtures. Refer to Section 03055.

B. Use products to clean rock surfaces that are known to be compatible with
cementitious grouts. Use according to manufacturer’s instructions.

2.4 BEDDING MATERIALS

A. Conform to AASHTO M 288 for geotextile layer. Refer to Section 02075.

B. Provide a class of geotextile that meets the requirements for strength


detailed in Table 1 of AASHTO M 288 that is appropriate for the installation
methods used. Refer to Section 02075.

C. Provide a geotextile that meets the requirements for subsurface drainage


detailed in Table 2 of AASHTO M 288 that is appropriate for the in-situ
soils encountered. Refer to Section 02075.

D. Use imported free-draining bedding aggregate material consisting of sand,


gravel, or crushed stone following the gradation in Table 2. Do not use on-
site materials.

E. Provide 6 inches of granular bedding aggregate material under the


grouted riprap.

F. Use granular bedding gradation according to AASHTO T 27 and Table 2


requirements.

Table 2
Granular Bedding Gradation
U.S. Standard Percent by Weight Passing
Sieve Size Square Mesh Sieves
1½ - inch 100
¾ - inch 20 - 90
⅜ - inch ---
No. 4 0 - 20
No. 100 ---
No. 200 0-3

Grouted Riprap
02374 – Page 4 of 8
January 1, 2012
PART 3 EXECUTION

3.1 PREPARATION

A. Install surface and ground water control measures as needed to perform


work in dry conditions. Water control measures include but are not limited
to diversions, culverts, sumps with pumps, or other means necessary to
maintain the level of groundwater below subgrade elevation and to divert
surface water away from the work area.

B. Remove all topsoil, loose excavated materials, trees, timber debris, soft
yielding material, concrete debris, and other objectionable materials from
beneath the areas where the grouted riprap is to be placed and as shown
on the plans. Do not block natural drainage layers or horizons within the
channel bottom.

C. Place any approved on-site material and compact as specified to the


designated subgrade elevation.
1. Do not backfill depression with shattered shale materials.
2. Spread fill materials uniformly minimizing segregation.
3. Compact subgrade to 95 percent maximum density according to
AASHTO T 99 or to a 70 percent relative maximum density
according to AASHTO T 180.
4. Smooth graded areas maintaining specified slope with no more
than 3 inches change unless closer tolerances are specified.

D. Install a free draining bedding layer around the weep drains in the location
indicated on the plan sheets.
1. Provide sufficient cover to prevent crushing by riprap elements.

E. Notify the Engineer before placing riprap elements over bedding layer.

F. Do not place riprap until the Engineer has verified compaction


requirements.

3.2 PLACEMENT OF BEDDING MATERIALS

A. Place geotextile loosely with no wrinkles or folds.


1. Use care so that the geotextile is in contact with the soil.
2. Eliminate all void spaces between the geotextile and the soil
surface.

B. Overlap adjacent edges of geotextile a minimum of 18 inches or as shown


on the plans.

C. Overlap the upstream geotextile over the downstream.

Grouted Riprap
02374 – Page 5 of 8
January 1, 2012
D. Repair or replace damaged geotextile at no cost to the owner.

E. Repair damaged geotextile by placing a geotextile patch, extending 3 ft in


all directions beyond the damaged area.

F. Place free-draining bedding aggregate on the geotextile.


1. Prevent damage to the geotextile.

G. Place drainage aggregate immediately after placing the geotextile.

H. Maintain 3 inches minimum bedding aggregate thickness.


1. Finish the surface of the drainage aggregate free of mounds.

3.3 PLACEMENT OF RIPRAP ELEMENTS

A. Install the riprap in place to the specified depth.


1. Distribute larger stones uniformly.
2. Do not group stones as a substitute for larger stone.
3. Arrange individual stones as necessary by use of equipment,
grapple device, or by hand in order to maintain the specified
gradation and interlock.

B. Provide adequate access when placing stones in the grout to lower


portions of the stone to prevent voids from forming.
1. Place stones to secure a stone mass with the minimum thickness
and height indicated.

C. Provide a riprap surface conforming to the lines, grades, and adjacent


channel surfaces as shown on the plans.
1. Manipulate the stone if necessary to secure a regular surface of
graded size and mass stability.
2. Remove any stones projecting more than 10 percent above the
finished design grade of the stone layer thickness.
3. Make smooth transition without cutting or breaking stones.

D. Do not crush the weep drains extending into the underlying granular drain
material.
1. Select drain pipe materials that are compatible with the chosen
method of riprap placement.

E. Place all stones in a dry condition beginning at the toe of the slope or
other lowest point.
1. Provide weep holes of 3 inch diameter pipe penetrating the bedding
with an average spacing not to exceed 10 ft on center at the toes of
slopes.

Grouted Riprap
02374 – Page 6 of 8
January 1, 2012
F. Form all outer edges and the top of grouted riprap where construction
terminates so the surface of the work is embedded and even with adjacent
slope or ground.

3.4 RIPRAP GROUTING

A. Do not place grout mix when the daily minimum temperature is less than
40 degrees F.
1. Maintain a minimum temperature of 50 degrees F and not more
than 90 degrees F during the placement and the curing periods.

B. Do not place on frozen surfaces.


1. Cover the grouted stone and heat within a range of 50 to 90
degrees F for a minimum of 24 hours before placing grout materials
when temperature is below 40 degrees F and dropping.

C. Thoroughly wet riprap, bedrock, and foundation surfaces.


1. Allow excess water to drain.
2. Achieve a dry saturated surface condition.

D. Use low pressure to inject grout into the voids between stones by pumping
through a maximum 2 inch diameter hose.
1. Stop the flow at any time.

E. Deposit grout to fill all voids as stones are placed.


1. Secure maximum grout compaction and density.

F. Place the grout from bottom to top and use sufficient grout to fill all voids
between the stones.
1. Fill all voids with grout from the subgrade level through the stone
layer.
2. Grout must penetrate to subgrade.
3. Use a “pencil” vibrator to fill all voids between and under stones.

G. Leave grout joints recessed below the surface of the adjacent stones.
1. Leave the top surface of the stones fully exposed.
2. Immediately remove all excess grout with a stiff brush augmented
with a cleaning agent if needed.

H. Do not use grout to cover the surface of the stone.


1. Construct the grouted riprap with a rustic appearance.
2. Match the workmanship of the sample panel.

I. Do not clog the weep drainpipes or clog the filter drain materials.

Grouted Riprap
02374 – Page 7 of 8
January 1, 2012
J. Do not re-temper grout mix by adding water in field.

3.5 CURING AND PROTECTION

A. Keep exposed surfaces continuously moist for the seven-day curing


period.

B. Maintain moisture by sprinkling, fog spraying, or by covering with


continuously moistened canvas, cloth mats, straw, sand, or similar
material.
1. Protect the grout during the curing process without causing damage
to the grout surface by erosion or other mechanisms during water
or moist covering.

END OF SECTION

Grouted Riprap
02374 – Page 8 of 8
January 1, 2012

You might also like