Outline TOR For Feasibility Study and Detailed Design

Download as pdf or txt
Download as pdf or txt
You are on page 1of 27
At a glance
Powered by AI
The document discusses plans to improve Sri Lanka's railway network in the Western Province and Colombo Metropolitan Region to address growing traffic congestion.

The objective of the CSRP is to improve the capacity and operating speed of the railway network in the CMR by modernizing and upgrading track, signalling and telecommunication infrastructure and potentially electrifying suburban lines.

Infrastructure upgrades proposed include modernizing and upgrading track, signalling and telecommunication systems, procuring fast commuter trains, modernizing rolling stock maintenance facilities, and upgrading stations.

L3425: Transport Project Preparatory Facility

Outline Terms of Reference

Consultancy Services for Feasibility Study and Detailed Design of


Colombo Suburban Railway Project (CSRP)

A. Objective, Scope, and Implementation Arrangements

1. The Government of Sri Lanka intends to improve the railway system in the
Western Province, including the Colombo Metropolitan Region (CMR) with a population
of 5.8 million (29% of Sri Lanka’s population), which generates 43% of the country’s
GDP. The population growth in CMR is expected to be 1.5% annually until 2035 and
hence, CMR is facing growing traffic congestion. The railway system carries about 13%
of the passenger transport within CMR. The government aims to substantially increase
the share of railway in the overall passenger and freight traffic.

2. Background. The development of the railway network in Sri Lanka started in


1864. Currently, the railway network, which consists of around 1,500 route-km in ten
railway lines, is operated by the Department of Sri Lanka Railways (SLR). Almost 90%
of the railway network of the country is single track, with 126 km of double tracks, 14 km
of three tracks and 3 km of four tracks with all multiple lines located within the CMR.
The network covers much of the CMR along four major corridors, namely Main Line,
Coastal Line, Kelani Valley Line and Puttlam Line totaling to 230 km. Railway provides
an important service during the Morning an Evening peak period as it acts as a
commuter service from the outer suburbs to central Colombo.

3. There are long distance trains and commuter trains operated in the CMR. Out of
the four railway lines radiating from Colombo and serving the CMR, the Main Line,
Coastal Line and Puttlam Line are well patronized especially during peak periods. The
Kelani Valley Line is single track and not as attractive due to low train speeds and
frequencies. The Colombo Fort to Maradana section has the highest passenger volume
of 136,438 passengers per day, followed by the Maradana to Ragama section with
120,876 passengers per day. The train frequency between Maradana and Fort is 228
trains per day, transporting on an average around 950 passengers per train followed by
the Maradana to Ragama section, with 150 trains per day carrying on an average
around 750 passengers per train. The Coastal Line is also fully utilized with an average
passenger volume of 800–1,100 per train.

1
4. The average speed on the Main Line in CMR during peak traffic periods is
around 33 kilometers per hour (kph) while the speed during peak traffic periods on the
coastal line is around 28 kph. The average speed in Kelani Velley line is around 26 kph.
Long delays occur due to failures in the signalling system, and the frequent failures also
occur in the outdated communication system. The poor condition of the tracks also
contributes to long delays. High loading level is another issue on the Main Line and the
Coast Line, especially during the peak period.

5. The project will improve the capacity and operating speed of the railway network
in the CMR by modernizing and upgrading track, signalling and telecommunication
infrastructure and potentially electrifying the suburban railway lines. The project will also
support procurement of fast and modern commuter trains and modernization of rolling
stock maintenance facilities, construct and upgrade railway tracks, install new signaling
and telecommunication and upgrade railway stations to provide improved intermodal
connectivity with other modes of public transport and through park-and-ride facilities at
selected stations. The project will increase the capacity and attractiveness of the railway
system, thus increasing its market share and reducing road congestion by shifting
passengers to rail transport. The project will be designed on a modular basis to allow
future expansion.

6. Objective. The main objective is to prepare the railway project(s) ready for
investment and implementation by completing feasibility studies, detailed engineering,
safeguards planning documents, and bidding documents. All designs prepared under
this project shall enable future electric operation of the railway network with overhead
catenary system (OCS), although the OCS may not be installed in the individual
projects at an initial stage. The prepared projects and/or components shall be designed
in a modular way with a clear prioritization of components to schedule implementation in
accordance with financial resources. All improvements on existing lines shall be
designed in such a way that the disruption of ongoing operation will be minimized to a
level acceptable to SLR.

7. Scope. Following four priority railway projects in CMR have been already
identified under the ADB-funded TA for Colombo Suburban Railway Project. 1 Under this
ongoing TA, pre-feasibility studies have been conducted except for the Ragama to
Negambo (Puttlam Line). The scope of this proposed consultancy services would be to
prepare feasibility study, detailed engineering design, safeguard planning documents,
and bidding documents for four priority railway projects.

1
ADB approved a Project Preparatory Technical Assistance (PPTA) grant for $1 million on 18 December 2015 to
assess the railway system in the CMR including the corridors linking to Kandy and Galle, and improvement of the
Kelani Valley Line, and identify and prioritize interventions.

2
(i) Maradana to Padukka (Kelani Valley Line)

The Kelani Velley line extending from Maradana to Avissawella is 60 km with


daily passenger volume of 14,600. This single track railway line was
originally narrow gauge and was converted to broad gauge along the same
trace at a latter stage. It has been identified that Padukka which is 35 km
from Maradana is the best location to attract passengers from Horana
Corridor. Therefore by considering the present and future demands, the
intension is to upgrade the railway line to double track up to Padukka and to
rehabilitate the existing single track in the balance section up to
Avissawwella.

(ii) Colombo to Rambukkana (Main Line)

Rambukkana is 83 km away from Maradana and is the end station of the


double line section in the 291 km long Main Line. The section from
Maradana to Ragama is having three tracks and the rest of the section upto
Rambukkana is double track. The daily ridership is approximately 100.000
with majority of the suburban trains, serving morning peak period, start from
Rambukkana. Focusing at passenger volume by 2035, it is intended to
construct forth line in Maradana – Ragama section and third track in
Ragama- Veyangoda section and rehabilitate the double track upto
Rambukkana.

(iii) Colombo to Kaluthara South(Coastal Line)

Coastal Line of the Sri Lanka is 159 km long and Kaluthara South is 43.0 km
away from Maradana. The section from Maradana to Colombo Fort is having
four lines and the rest upto Kaluthara South is having two lines. The daily
passenger volume in the section upto Kaluthara is approximately 80.000 and
the intention is to construct third line upto Panadura and to rehabilitate the
existing double line up to Kaluthara South to cater the passenger volume
generated by 2035.

(iv) Ragama to Negambo (Puttlam Line)

Puttlam Line deviates from Main Line at Ragama runs upto Puttlam and the
line length is 133 km from Maradana with double track upto Seeduwa and
single track beyond. Sri Lanka Railway has commenced double tracking upto

3
Negambo and has almost completed upto Katunayake, at present.
Negambo is 37 km from Maradana with daily passenger volume of 20,000.

8. New railway lines and increasing number of platforms at stations in the priority
projects may also be identified. The required interventions may include climate-resilient
track rehabilitation, station upgrading, modernization of signaling and
telecommunication system, railway electrification, rolling stocks, and maintenance
facility to be identified under the ADB-funded PPTA for Colombo Suburban Railway
Project. For above four priority projects, the consultant will prepare feasibility study,
detailed engineering design, safeguard planning documents, and bidding documents.
The consultant should complete feasibility studies and detailed designs of four projects
in the order of priority. Depending on the client requirements, the details design and the
bid documents for Maradana to Padukka line (Kelani valley line) may be completed in
sections wise. As a part of the knowledge transfer process, the consultants should
closely work with SLR with the view of training the counterpart SLR engineers in railway
design. The consultant will also provide support to the procurement of civil works and
equipment upon the government’s request and provide support to ADB missions for
investment loans processing.

9. Implementation Arrangements. The Ministry of Transport and Civil Aviation


(MOT&CA) is the executing agency for the railway component of the Transport Project
Preparatory Facility. MOT&CA will implement the railway component through its Project
Management Unit and through Department of Sri Lanka Railways (SLR). An inter-
ministry steering committee chaired by the Secretary of MOT&CA will oversee and
guide the implementation. MOT&CA has established a project management unit to
engage the consultants, manage contracts, review consultant’s reports and provide
technical requirements as required.

B. Detailed Tasks of the Assignment

10. For each priority project, the consultant’s tasks include, but are not limited to the
following.

Task 1. Technical Feasibility


(i) Collect and review all available relevant studies, reports, materials,
documents, and information including findings from the PPTA.
(ii) Collect all necessary information of existing, ongoing and future planned
development works of government and private sector in and around the
project site and consult all relevant agencies/stakeholders. Take all

4
findings into consideration in the study. Support the client in carrying out
continuous coordination and consultations with all relevant stakeholders.
(iii) Examine all existing infrastructure, operational facilities, rolling stock
maintenance facilities, ICT Infrastructure, line capacity and business
opportunities and make specific recommendations for their improvement.
(iv) Finalize detailed scope of work, technical aspects & design parameter of
all components/projects in consultation with SLR and develop new design
standard, e.g., based on new rolling stock and operational procedures for
suburban trains, future railway electrification, etc. Develop design
standards for all relevant track components, bridges, stations, signaling
and telecom (Including Train Control Center) , rolling stock and workshops
that will enable future railway electrification with OCS. In addition, develop
maintenance standards by considering existing maintenance practices of
SLR and by considering the needs of the new systems.
(v) Calculate the power demand for the electric trains based on traffic forecast
and proposed operation program considering also degraded operation and
emergency operation and power demand in case of partial failures of the
power supply system; define feeding points and capacity of the
substations; develop a layout of feeding lines from the national grid that
minimizes the risk of total power failure in case of planned blockage, e.g.,
due to scheduled maintenance or failure of individual supply lines in the
national grid.
(vi) Consider effects of electromagnetic compatibility between the future
railway electrification and signaling and telecom system, as well as
external systems such as power lines, pipes, pipelines or communications
networks and define minimum safety distances to avoid interference.
(vii) Define requirements on the track structure to support return current to the
traction power substations and requirements on linkage of tracks and
bonding, installation of CWR and insulated rail joints, etc.
(viii) Assess the need and justification of the proposed components/projects for
railway improvement in CMR as outlined under the ongoing PPTA. Assess
probable effects upon project implementation including direct and indirect
effects. Assess benefits of the proposed project, not only in terms of
financial or economical, but also in terms of safety, environmental impacts,
transportation and travel costs, poverty reduction, enhancement of trade
and commercial activities likely to be created as an outcome of all the
components.
(ix) Identify the various technical solutions and various options for
implementing all the components involving construction of tracks and
bridges including signaling, telecom. and operational facilities such as

5
stations yards, maintenance sheds, etc. with a view to identify the most
suitable solution. Carry-out survey and necessary investigations covering
surrounding areas of each option for option analysis and to finalize the
most suitable solution.
(x) Seriously consider the safety issue in operating trains with different
operating specifications, higher speeds, and increased frequency.
(xi) Carry-out detailed topographical survey. The topographic works have to
be performed in relation to the required accuracy using satellite base
survey equipment (DGPS, data logger & total station) that can be used for
detailed design and construction.
(xii) Prepare topographic maps at suitable scale following international
standards which would give a good definition of all the necessary details
for good approximation concerning earthwork quantities to avoid further
problems during construction.
(xiii) Collect data on planned and existing utilities in the project area and
incorporate the information in the topographical maps.
(xiv) Finalize alignment and layouts duly considering the topography, land
formation, commercial aspects, economical and safeguard considerations,
existing infrastructures of the area, ongoing and future development plan
and schemes of both the government and private sectors in the area.
Drafts are to be consulted and presented to SLR before finalization.
Finalize 'Construction Right of Way‘ (CROW) in the final alignment
including land required temporary for railway construction and access to
the site, camp-sites or quarries etc. Scale of alignment design drawings
shall be or more detailed as appropriate at selected critical locations.
(xv) Carry-out detailed traffic, social, environmental, hydrological and other
engineering survey and detailed soil, hydrological & morphological,
environmental investigations on the finalized alignment and layouts.
Identify the need for additional survey/investigations for detailed design.
(xvi) Analyze the existing traffic of various modes of transports. Assess the
effects of the project over other modes of transportation. Assess detailed
traffic forecasts of national and local freight and passenger traffic for all
the components/projects with due consideration of other modes of
transport, other ongoing and future development plans for other modes of
transport such as Light Rail and Monorail, etc., bus service improvements
and private sectors investments.
(xvii) Conduct traffic census on existing roads crossing on railway line (both
authorized and unauthorized) and re-categorize the types and location of
level crossing gates as required based on traffic forecast. Recommend
upgradation and closure of existing level crossing gates, authorization of

6
level crossing gates, new level crossing gates to improve safety at level
crossings and measures to prevent illegal track trespassing. Coordinate
with other concerned authorities such as the Road Development Authority
(RDA) and Urban Development Authority (UDA) on the design of level
crossings and under-/overpasses.
(xviii) Review the design of existing stations, redesign if necessary, and
recommend improvements to accommodate increased traffic, based on
the traffic forecast.
(xix) Design facilities for multimodal connectivity of the railway with other public
and individual modes of transport, suggest location for bus terminals, taxi
stands, parking lots for cars, motorbikes and bikes, etc. Coordinate the
design with concerned stakeholders including local governments, UDA,
RDA, etc.
(xx) Recommend areas for commercial development in the stations such as
advertising and for supporting establishments such as coffee shops,
kiosks, food stores, restaurants, bookshops, convenience stores etc.
depending on the size and category of stations and the commercial
functions available in the station environment.
(xxi) Review the access from the road level to the platforms, calculate the
number and dimension of stairs, ramps, elevators and/or escalators
required for operation of the railway service, for degraded operation and
for emergency evacuation. Ensure access to all stations including
supporting functions such as ticket offices, waiting rooms, toilets, etc. for
elderly-children-women and disabled persons.
(xxii) Identify the locations of level crossing gates required, grade separation
between railway and road by either overpass or underpass based on
traffic forecast.
(xxiii) Review the location and status of existing bridges over the railway,
evaluate bridge condition and remaining economic lifespan, recommend
design options on how to operate the railway with the existing bridges,
considering future railway and rolling stock design, railway electrification,
etc.
(xxiv) Examine existing signaling and interlocking system and
telecommunication system. Identify the scope of work to establish
computer-based signaling and Interlocking system and optical fiber based
telecommunication system with radio communication to Train Crew,
Operation, Maintenance and Security Personnel and centralized train
control (CTC) system in all the components/projects. Interconnection and
interoperability with Electric Control Center also need to be considered.

7
The CTC shall also include facilities for passenger information system,
public address system and safety and security monitoring.
(xxv) Safety issues and interoperability with Signaling System needs to be
considered when designing rolling stock
(xxvi) Finalize the phasing of construction considering work plan, interfacing,
railway operation and signaling issues. Consultant shall make specific
recommendation to resolve interfacing issues.
(xxvii) Regular train operation must not be interrupted during the project
construction period and accordingly, phasing of construction, construction
methodology and safety measures are to be considered based on the
latest technology.
(xxviii) Develop an operation concept plan during and after construction of all the
proposed projects. Prioritizing the urban railway time schedule while
parallelly considering the long distance time schedule needs to be done.
(xxix) Finalize procurement packages and frame suitable investment projects
covering all the components mentioned. Consultant may suggest inclusion
of additional component which might be essential to achieve the full
benefit of all the components.
(xxx) Conduct mathematical hydrodynamic modeling study for major bridges
having waterway 100m and above to establish hydrological parameters for
fixation of the location of bridge, formation level of the railway track
identifying the highest flood level, catchments area at bridge openings,
identify scour & erosion in the vicinity of major bridges and river banks and
design river training works and protection works.
(xxxi) Conduct an in-depth study covering the surrounding area for fixation of
formation level of the proposed structures, recommend proper drainage
system identifying the out fall of the drainage system.
(xxxii) Examine existing rolling stock day to day maintenance facilities and
assess scope of works to establish modern, improved rolling stock
maintenance preferably for modern diesel-electric multiple units and future
electrical multiple units. Identify new rolling stock maintenance facilities
requirements for all new construction lines including stabling yards,
scheduled maintenance facilities and workshops for overhaul of the rolling
stock.
(xxxiii) Examine the age profile of existing rolling stock fleet and assess demand
of rolling stock considering replacement of old ones. Estimate additional
new rolling stock requirements with types based on traffic forecast for all
the components.
(xxxiv) Study different types of rolling stock, such as loco-driven trains, push-pull
trains and diesel-electric or electric multiple units and recommend suitable

8
rolling stock procurement program; study best way to accommodate
changes in demand based on traffic forecast by splitting and joining trains
and recommend locations for stabling facilities for surplus trains during
daytime off-peak hours.
(xxxv) Prepare Rolling stock demand analysis report on rolling stock requirement
for replacement of old-aged rolling stocks and new demand to be created
due to the projects mentioned in Section 4.
(xxxvi) Assess operation and maintenance (O&M) personnel and other
resources/facilities requirements for operation and maintenance works for
all components. Prepare capacity building plan, propose training facilities
and the maintenance tools and equipment.
(xxxvii) The study should also include conceptual engineering design and layout
plan for all necessary railway tracks, stations and yards, signaling and
telecom, bridges, culverts, over pass/fly over/underpass, level crossing
gates, other structure, residential and functional buildings, cuts and other
facilities. Prepare cost estimates for proposed project, showing foreign
and local currencies, and tax and duty elements, etc.
(xxxviii) Prepare Feasibility study report which will contain main report with
detailed scope of work, all technical aspects, drawings/layouts, cost
estimate and Resettlement Plan (RP), Land Acquisition Plan (LAP),
Environment Management Plan (EMP), Operational plan, Hydrological &
Morphological report and other required documents.
(xxxix) Review manuals and rulebooks of SLR and recommend updates and
additional documentation required due to modern technologies or new
technologies introduced in SLR such as CWR, electric train operation,
modern signaling system, etc.
(xl) Review exiting operating, time scheduling, crew management and train
controlling practices and make recommendations for improvements by
considering the train operating scenario that will be developed with the
project implementation.
(xli) Prepare maintenance standards and practices by considering the
technologies that will be utilized in the project and by considering the
allowable tolerances.
(xlii) Review existing practices of occupational safety and standards and prepare
safety code for SLR.
(xliii) Evaluate existing ICT infrastructure and organisaton’s capacity and design
an ICT Development plan for SLR

9
Task 2. Economic and Financial Assessment

(i) Prepare an economic analysis of the proposed priority projects. The


economic analysis should follow ADB’s guidelines for the economic
analysis of projects.
(ii) Provide all analysis and calculations of costs and benefits of the project to
the executing agency. Assess benefits of the proposed rail line, not only in
financial terms or economical, but also in terms of safety, environmental
impacts, time savings, savings of transportation and travel costs, poverty
reduction, increase of life standard and enhancement of trade and
commercial activities likely to be created as an outcome of the proposed
projects.
(iii) Calculate the economic internal rate of return (EIRR) for each railway
project. Undertake sensitivity analysis on the risk factor basis for various
scenarios such as changes to the capacity costs, operation and
maintenance costs, traffic volume, and construction period, etc.
(iv) Conduct willingness-to-pay and other relevant survey. In consultation with
SLR, propose appropriate fare. Calculate the financial internal rate of
return (FIRR) on the same basis of EIRR calculation.
(v) Estimate the required budget for appropriate operation and maintenance
of each project. Assess the financial sustainability by comparing the
required budget with the current budget allocation, and make
recommendations as appropriate.
(vi) Prepare relevant chapters and appendixes of the feasibility study report on
economic and financial assessment.
(vii) Develop a monitoring and evaluation framework in accordance with ADB’s
Guidelines for Preparing a Design and Monitoring Framework. Include in
the framework appropriate indicators with baseline data and targets.
(viii) Study existing railway fare structure and recommend suitable formula for
periodical revision of railway fares. Identify appropriate benchmark
indicators for fare adjustments and institutional arrangements to carry out
the periodic fare adjustments.

Task 3. Poverty and Social Assessment

(i) Conduct 20% poverty and social assessment taking into account
socioeconomic and poverty status of the project area of influence. The
baseline socio-economic survey (SES) is to be designed to capture
information on the PAPs their resources, employment, and vulnerability.
The survey data will lead to the development of management information

10
system (MIS) that will help consultation process and assist in planning and
implementation.
(ii) Conduct a benchmark video recording of the physical situation of the
dwellings and belongings as well as community assets before the
commencement of SES conducted.
(iii) Identify safeguards and non-safeguards social issues relevant to the
project’s objectives, scope and operational characteristics, and specify
verifiable social development outcomes of the project.
(iv) Identify and estimate the likely socioeconomic and poverty reduction
impacts of the project.
(v) Assess local demand for the proposed investments, employment
opportunities, child labor, HIV/AIDS and human trafficking, affordability,
gender and other social risks that would result from the project and include
measures to mitigate social impacts, if any. This will be in accordance with
ADB's Safeguard Policy Statement (2009), and ADB’s Handbook on
Social Analysis (2012).
(vi) Propose design features and measures for inclusion in the follow-on
investments (including the need for any technical assistance) to address
gender, labor, HIV, trafficking, and other social parameters identified in the
analysis above.
(vii) Conduct Stakeholder consultation with key stakeholder groups in terms of
social and economic characteristics (gender, ethnic and indigenous
minorities; socioeconomic vulnerability, etc.) who would be directly and
indirectly affected by the project’s objectives and scope, design
alternatives, likely positive and negative impacts, possible measures to
mitigate adverse impacts and other information that would be of use to the
stakeholders. Consultant shall keep the records of such stakeholder
consultations.
(viii) With the participation of stakeholders, identify and analyze the reasons
behind the vulnerability of at risk groups, including their exposure to risks.
Suggest participatory development strategies for key stakeholders to
apply when designing and implementing the project.
(ix) Collect sex-disaggregated data during poverty and social assessment for
all applicable indicators. Focus on how women may have different use or
needs when traveling by rail, and on issues of safe transport. Prepare
project specific 'gender action plan' for gender development in and around
the project location of all the projects. Identify project design elements
(policy or implementation) in which women can participate in and thus
benefit from the project.

11
Task 4. Land Acquisition and Resettlement Planning and Indigenous
Peoples

(i) For each project, carry out a screening of involuntary resettlement and
indigenous peoples’ impact in accordance with the Government’s policies
and regulations, and ADB’s Safeguard Policy Statement 2009 (SPS).
Identify whether the project is likely to lead to private land acquisition,
thus, impact on non-titleholders. The screening exercise will also include a
due diligence of past social impacts, viz., if land acquisition has been
accomplished in anticipation of the ADB project.
(ii) Identify whether the project will be located in, or pass through, areas of
significant indigenous people’s settlements, and if this is the case propose
how to specifically include indigenous peoples in project planning and
implementation in accordance with ADB’s Safeguard Policy Statement
2009 (SPS). If relevant, make an overview of population characteristics in
the project area and anticipate project impacts.
(iii) Prepare and complete the checklist for involuntary resettlement and
indigenous people screening.
(iv) Since this is ADB’s first project with SLR, experience of recent and
ongoing resettlement activities financed by ADB and similar multilateral
development agencies in Sri Lanka should be reviewed. After review, draft
a resettlement frameworks (RF) as necessary that meets the Government
and ADB policy compliance standards. The RF should define categories
for impact, eligibility of affected people for compensation and provide an
entitlement matrix covering compensation and other assistance for all
types of impacts. The RF should provide the methodology for the
calculation of compensations based on replacement cost to fully replace
the asset. The entitlement matrix should focus on assistance provided to
non-titleholders in the urban context.
(v) For the whole program and should impacts on indigenous peoples be
identified during the screening process, even if indicative, prepare an
Indigenous Peoples Planning Framework (IPPF) as necessary.
(vi) Both the RF and IPPF should be based on a consultative process with the
executing agency and ADB and draw from broad-level consultations with
the communities likely to be affected by the subprojects.
(vii) Prepare relevant chapters and appendixes of the feasibility study report on
resettlement and indigenous peoples planning. The appendixes should
include the screening checklist for each subproject; one Resettlement
Framework as necessary; one Indigenous Peoples Framework as

12
necessary (if impacts on indigenous peoples are identified during the
screening exercise).
(viii) Prepare a resettlement plan (RP) for each proposed subproject, and if
impacts on indigenous peoples are identified, an indigenous peoples plan
(IPP) in compliance with the Government’s policies and regulations and
ADB's Safeguard Policy Statement 2009 (SPS).
(ix) Based on the detailed design, determine the legal status of private land
within the right of way (RoW), verify application of customary and
traditional laws governing land tenure, usufruct rights, and leasehold.
Verify legal boundaries of the RoW with the relevant ministry.
(x) Based on the detailed design, conduct census survey of all affected
people (APs) and an Inventory of Lost Assets.
(xi) Conduct a socioeconomic assessment of all APs residing/using the
corridor of impact to collect data on family composition, details on age and
sex of all the household members, income levels and occupational
pattern, vulnerability status, legal ownership status of land (private,
traditional and customary rights, lease), asset occupancy status and skills
possessed.
(xii) Assess whether the compensation standards for all types of assets, crops,
and trees are based on replacement cost and describe in detail the
valuation methodology used. Undertake market surveys to compute
replacement value of land.
(xiii) Undertake market survey to assess the rental market in nearby areas to
ensure security of tenure for non-titleholders.
(xiv) Prepare a comprehensive income and livelihood restoration program,
supported by adequate budget, to help APs improve, or at least restore,
their incomes and livelihoods. Identify specific measures for the affected
poor, ethnic minorities, or other vulnerable households.
(xv) Conduct in-depth consultations with the APs, ensuring the involvement of
women in the process. Consultations should take the form of public
meetings, focus group discussions and one-on-one interviews. Ensure
that the consultation process is well documented and demonstrate how
the concerns of the affected persons are included to the design of the RP.
(xvi) Establish a cut-off date for eligibility criteria for non-title holders and
ensure and document that it has been publicly disseminated.
(xvii) Prepare overall budget for compensation, resettlement and rehabilitation
assistance.
(xviii) Based on the draft R&R entitlements prepare an appropriate action plan
for additional support required for the vulnerable

13
(xix) Organize workshops on draft R&R policy to receive feedback from
identified stakeholders, including implementing agency, line agencies
(specifically revenue, forest, tribal welfare, etc.), NGO and others.
(xx) Assist the SLR to develop a computerized database management system
for recording APs and lost assets. The system should reflect the present
impact on APs and accordingly the entitlements for APs are planned. The
system should be in place from the beginning of the resettlement survey.
Also, develop cadastral mapping of affected plots for construction of new
alignments using inventory map developed under the feasibility study.
(xxi) Assess the capacity of the Government in implementing the proposed RP
and IPP, and recommend improvements and actions required.
(xxii) If impacts on Indigenous Peoples are identified, prepare an Indigenous
Peoples' Development Plan to minimize adverse impacts on tribal
communities and to enhance their access to project benefits on par with
others.
(xxiii) Prepare relevant chapters and appendixes of the detailed design report on
resettlement and indigenous peoples planning. The appendixes should
include the RP for each project where resettlement impacts have been
identified; IPP for each project, where impacts on indigenous people have
been identified.

Task 5. Environmental and Climate Change Risk Assessment

(i) Carry out an environmental assessment of the project in accordance with


ADB's Safeguard Policy Statement 2009 (SPS), and the Government’s
environmental regulations and policies.
(ii) Classify the project in accordance with the environmental impact
assessment requirements under the Central Environmental Authority,
Ministry of Environment and Forests and ADB’s screening checklist for
environmental categorization according to the SPS.
(iii) Depending on the classifications, prepare IEE as per relevant guidelines
of CEA and ADB, and if EIA is required, prepare TOR that is acceptable to
CEA. In preparing the IEE and/or EIA, a minimum of the following issues
must be covered:
a) Adequate baseline data representing the environmental conditions
of the project site must be collected on physical (air, noise, surface
and ground water, soil), ecological (flora, fauna, protected areas)
and socio-economic (physical cultural resources, heritage sites,
etc.) environmental components

14
b) Potential impacts on biodiversity including modified, natural, critical
habitat (as defined in the SPS) and protected areas and necessary
measures to minimize, mitigate, and offset impacts. If the project
area has any critical or natural habitat or any critically
endangered/locally protected species, detailed back ground
information on such areas and species must be provided and the
significance of impact clearly defined. Where necessary, mitigation
may include physical measures such as design and construction of
wildlife overpass or underpass, linkage of rail signaling systems to
detection of wildlife on the rail corridor, implementation of
biodiversity conservation activities and other innovative measures.
Overall, there should be no net loss of biodiversity as a result of the
project.
c) Potential waste issues including hazardous materials and wastes
and appropriate measures for their disposal, treatment, and other
forms of management.
d) `Potential impacts on ambient air and water quality, noise levels
and soil and recommendations for suitable mitigation measures.
Impacts must be compared with the national standards and World
Bank Environmental Health and Safety (WB-EHS) standards
e) Climate change risks for the project (such as more and stronger
storm surges, sea level rise, more flooding, etc.) in consultation
with the government and ADB, and recommendations for
adaptation measures in the engineering design. The adaptation
measures must be clearly identified and the additional costs for
those measures quantified.
f) Quantification of greenhouse gas (GHG) emissions expected from
the construction activities under the project and GHG emissions
and reductions during operation of the railway lines and improved
systems. If the gross operation related GHG emissions exceed
100,000 tons per annum, provide recommendations for suitable
mitigation and/or offset measures.
g) Occupational Health Safety issues and measures for the
construction workers as well as the local communities in and
around the project site following the WB-EHS guidelines.
h) Potential impacts on physical and cultural resources including
sensitive receptors (temples, schools, hospitals, etc.) and
measures to avoid, minimize, or mitigate impacts. This must include
modelling of air pollution, noise and vibration levels during
operation stage at various distances from the edge of the rail ROW

15
with clear identification of sensitive receptors that will be impacted
due to air pollution, noise and vibration levels being higher than
baseline levels or higher than the national or WB-EHS standards.
For such receptors, clear mitigation measures must be provided.
i) Public consultations with affected people in the project area
including men, women, vulnerable or indigenous groups with clear
documentation on dates of meeting, issues discussed, and total
number of male and female participants. Consultations must also
be carried out with relevant government agencies (eg. Forest
Department, Agriculture Department, etc.) and relevant
environmental NGOs if any.
j) Grievance Redress Mechanism to address concerns and
grievances of the APs in the course of the project cycle.
k) Cumulative and induced impact assessment with recommendations
for mitigation measures to be implemented within the project, where
feasible and for implementation by other agencies responsible for
other projects.
l) Alternative analysis including the no project option (required only
for EIA under the ADB SPS.
m) Assessment of the institutional set up and capacity of the EA for
meeting environment safeguard requirements of the government as
well as ADB. Institutional and capacity needs, if any must be
identified and planned for with adequate budge provisions.
(iv) Prepare the IEE and EIA reports to fulfill the requirements of the
government and ADB.
(v) Prepare an Environmental Management Plan (EMP) and Environmental
Monitoring Plan (EMOP) to implement and monitor the mitigation
measures with clear information on costs, time frame, responsible
agencies, monitoring methods and monitoring indicators and targets.
(vi) Incorporate into the EIA/IEE report including EMPs/APs, feedback from all
relevant stakeholders including the EA, ADB, and others. Prepare an
Environment Assessment and Review Framework (EARF), if necessary.
(vii) During the feasibility study stage, the outputs will be complete IEE or EIA
reports and EARF, as necessary fulfilling requirements of both the
government and the ADB SPS, including as many site specific details as
possible. For projects with different requirements under the government
and ADB SPS (for example the government requires an EIA but ADB
requires an IEE) to the extent possible one report will be prepared to fulfill
requirements of both agencies.

16
(viii) The IEE or EIA prepared during the feasibility study stage must provide
clear recommendations for follow-up activities required during the detailed
design stage. Recommendations may include but not be limited to: (a)
updating the EMP to provide more site specific details or other updates;
(b) providing more detailed or updated information and analysis on
location, expected impact and mitigation measures on sensitive receptors;
(c) updating the number of trees required for removal; (d) conducting air
and noise impact modelling; and (e) other updates in the reports based on
design updates. The output of the detailed design stage will be the final
IEE and/or EIA reports and EARF, as necessary fulfilling requirements of
both the government and the ADB SPS.

Task 6. Detailed Engineering Design

(i) Conduct additional field survey and soil, hydrological, seismic, geometric
features, type and condition of drainage structures and foundation
investigations required for detailed design along the selected alignment.
(ii) Conduct hydrological and morphological studies for major bridges having
spanned more than 100 meters and separate reports have to be submitted
to the client.
(iii) Detailed engineering design have to be done in accordance with the
design codes/guidelines/manuals of SLR, neighboring countries and
International codes based on the findings of investigations and feasibility
study, recommendations of safeguard policy study and universal design
for the elderly & disabled persons. All bridges, culverts and sub-structures
have to be designed in accordance with related standards considering
double stacking of containers, future electric traction lines, and oversized
consignments. The alignment design shall also include all adjustments at
third-party infrastructure such as roads, utilities, power transmission lines,
etc. required to implement the project. The scale of alignment design
drawings shall be or more detailed as appropriate at selected critical
locations.
(iv) Detailed design for the railway project shall be based on the updated
conceptual design of the feasibility study and results from additional
investigations conducted. Detailed alignment design and layout plan shall
be prepared for the proposed route alignment selected in the Feasibility
Study.

17
(v) Detailed design and drawings has to include universal access for the
elderly & disabled persons such as access to the station building, parking
area and platforms by ramps and/or elevators. Detailed design and
drawings should also include gender sensitive design in all station
buildings, such as separate ticket counters, waiting areas/rooms, and
toilets for women, etc.
(vi) Prepare key map for all stations proposed in the project showing all
existing, proposed dismantling works and proposed new structures and
station yard layout.
(vii) Design multimodal facilities in the station areas as well as areas for
commercial development as recommended in the feasibility study.
(viii) Prepare detailed technical specifications for each work item, taking into
account relevant proven specifications in use in Sri Lanka and elsewhere
for similar works.
(ix) The consultant shall also be required to take into consideration the
findings and recommendations of social and environmental studies carried
out by separate consultants during preparation of detailed design and cost
estimates. Reviewing designs against anticipated social impacts and do
amendments if necessary, should also be done with consultation of SLR
(x) Update safeguard related documents such as RP, EIA and LAP,
indigenous people plan, etc. based on the detailed design. Facilitate
effective coordination and lines of communication between ADB and
relevant government agencies and line departments, organizations, and
individuals implementing safeguard aspects, including obtaining
government clearances.
(xi) Re-assess benefits and capital costs of the proposed projects and update
the economical and financial analysis based on revised cost and benefits
and other findings of detailed design.
(xii) Detailed design of upgradation and new construction of level crossing
gates re-categorized (both authorized and un-authorized) in the feasibility
study to ensure safety. Detailed design of road
flyover/overpass/underpass, pedestrian bridges etc. as recommended in
the feasibility study.
(xiii) Detailed design for establishment of computer based interlocking (CBI)
signaling system and optical fiber based telecommunication system with
radio communication for train crew etc. and centralized traffic control
center (CTCC) in all the components/projects as identified in the feasibility
study.
(xiv) Design the power supply system including transmission lines from the
existing grid to substations and the overhead catenary system (OCS) for

18
the railway lines, sectioning in stations, yards, and on the open lines and
operations control to be situated in the CTCC.
(xv) Prepare the detailed work plan/schedule covering phasing of construction
considering work plan, interfacing issues, railway operation issues, and
signaling and safety issues The plan shall also identify all additional
temporary structures and facilities required for construction logistics
purpose, access to the site through temporary roads and bridges or
similar, storage, camp-sites etc.
(xvi) Prepare detailed design for existing tracks, additional tracks for areas with
doubling and new lines including drainage, cable ducts for signaling,
telecom and electric power cables, maintenance and emergency
walkways and fencing in built-up areas. The loading standards of
bridge/culverts on the existing track have to be examined and detailed
design for required up-gradation, if required. Electrification designs to be
prepared at the end.
(xvii) Prepare detailed operational plan for construction and after construction
period. Prepare maintenance plan. Finalize operation and maintenance
(O&M) personnel and other resources/facilities requirements for operation
and maintenance works for all components
(xviii) Prepare engineering design, drawings and layout plan for railway
embankment, tracks, stations and yards, signaling and telecom, drains,
bridges, culverts, over pass/fly over/underpass, level crossing gates,
protection works, other structure, residential and functional buildings,
drainage, sanitation, electrical works, rolling stock maintenance facilities
such as wash pits, sick lines, sheds, watering facilities and passenger
amenities, operational and other facilities.
(xix) Prepare detailed design for establishment of rolling stock depots, carriage
and wagon workshop, loco workshop and fuelling facilities including all
infrastructure and allied facilities or new construction as identified in the
feasibility study.
(xx) Prepare list of maintenance tools and equipment and maintenance
schedules for each of the design componentts.

Task 7. Cost Estimates and Bidding Documents

(i) Prepare detailed cost estimate of each of the project based on detailed
design and detailed BOQ. The Consultant shall consider the findings and
recommendations of social and environmental studies and reflect those in
necessary clauses in the tender documents and cost for implementation
EMP, if any, are to be included in detailed in the cost estimate and BOQ.

19
The accuracy of the BOQ shall be within +/- 10 % for all quantities based
on the detailed design.
(ii) Prepare separate BOQ and bid documents of construction works as
phased by the consultant based on detailed in the engineering design and
detailed cost estimates following ADB’s and government’s guidelines for
procurement.
(iii) Prepare unit rate analysis report for each items included in the cost
estimate along with all background/ breakup calculation.
(iv) The cost estimate should be broken down in local and foreign currencies.
Local currency costs are again to be broken down to works, equipment,
and tax and duties.
(v) Prepare detailed scope of station-wise civil, signaling and telecom works,
level crossing gate wise works and bridge wise works and their cost
estimates to monitor the construction works.
(vi) Prepare and/or update technical specification for all components required
in the selected projects/components to be used as Employer’s
Requirements in the bid documents.
(vii) Assist the Project Management Unit in the Bidding Process and Technical
Evaluation Committees to evaluate bids

Task 8. Procurement Assistance

(i) Prepare the procurement plan and the bidding documents for each
contract package using ADB’s standard bidding document for
procurement of civil works.
(ii) Upon the client’s request, assist the government in advertising, issuing
bidding documents, responding to queries, receiving and evaluating
applications, and other procurement-related activities.

C. Consultant’s Inputs

8. The assignment will be carried out over a period of thirty six (36) months from the
date of commencement by a consulting firm. It is anticipated that about 186 person-
months of input by international consultants and 919 person-months by national
consultants will be required.

20
Table 1: Required Experts
Relevant Experience and Person-
No. Title Qualification Positions Months
International
IC01 Team Leader/ Senior Railway  professionally qualified engineer 1 34
Specialist with Bachelor degree in railway
engineering or related areas with
post- graduate degree in the
relevant field
 Min. 15 years experience
 Min. 10 years in planning,
preparation and design of railway
systems and projects, at least 5
years as project team leader for
projects of similar scale and scope
IC02 Transport Economist  Bachelor degree in economics or 1 9
engineering
 Min.15 years experience
 Min. 10 years of experience in
economic and financial analysis, 5
years of which on
transport/infrastructure projects
IC03 Rail Operation Specialist  professionally qualified engineer 1 12
with Bachelor degree in railway
engineering or related areas
 Min. 15 years of experience
 Min. 10 years of experience in rail
operation
IC04 Railway Alignment and Survey  professionally qualified engineer 1 18
Engineer with Bachelor degree in surveying,
railway engineering or related areas
 Min. 15 years experience
 Min.10 years of experience in
railway alignment design
IC05 Railway Track Engineer  professionally qualified engineer 1 15
with Bachelor degree in railway
engineering or related areas
 Min. 15 years experience
 Min.10 years of experience in
railway track engineering
IC06 Railway Bridge Engineer  professionally qualified engineer 1 10
with Bachelor and master degree in
civil engineering
 Min. 15 years experience
 Min.10 years of experience in
railway bridge/structure design
IC07 Station Architect  professionally qualified architect 1 15

21
Relevant Experience and Person-
No. Title Qualification Positions Months
with Bachelor degree in
architecture, post-graduate degree
preferred
 Min. 15 years experience
 Min. 10 years of experience in
railway station design
IC08 Power Supply Engineer  professionally qualified engineer 1 6
with Bachelor degree in electrical
engineering, post-graduate degree
preferred
 Min. 15 years of professional
experience
 Min. 10 years of experience in
railway electrical engineering
IC09 Railway Electrification  professionally qualified engineer 1 15
Engineer with Bachelor degree in electrical
engineering, post-graduate degree
preferred
 Min. 15 years of professional
experience
 Min. 10 years of experience in
railway electrification engineering
system design
IC10 Signal Engineer  professionally qualified engineer 1 10
with Bachelor degree in railway
engineering, or related areas
 Min. 15 years experience
 Min. 10 years of experience in
railway signal engineering and
system design
IC11 Telecommunication Engineer  professionally qualified engineer 1 6
with Bachelor degree in
telecommunication engineering
 Min. 15 years experience
 Min.10 years of experiences in
railway telecommunication system
design
IC12 Rolling Stock and Workshop  professionally qualified engineer 1 15
Engineer with Bachelor degree in railway
engineering, or mechanical
engineering, or related areas
 Min. 15 years experience
 Min. 10 years in railway rolling
stock, maintenance and workshop
design and operations

22
Relevant Experience and Person-
No. Title Qualification Positions Months
IC13 Environmental Specialist  Masters degree in environment 1 3
science or environmental
engineering or related areas,
 Min. 15 years experience
 Min. 10 years in
preparation/management of
environment impact assessment
IC14 Social  Masters degree in social science 1 3
Development/Resettlement  Min. 15 years of professional
Specialist experience
 Min. 10 years of experience in
social development and
resettlement for infrastructure
projects
IC15 Procurement Specialist  Bachelor degree in engineering or 1 9
construction science, post-graduate
degree preferred
 Min. 15 years of professional
experience
 Min. 10 years in
preparation/management of
construction contracts and
procurements for international
bidding
IC16 ICT Specialist  Bachelor degree in Computer 1 6
System Engineering, post-graduate
degree preferred
 Min. 15 years of professional
experience
 Min. 10 years of experience in
railway ICT engineering and system
design
Subtotal 16 186
National
NC01 Deputy Team Leader/ Senior  professionally qualified engineer 1 36
Railway Engineer with Bachelor and Master degrees
in civil/electrical/ mech engineering,
 Min. 15 years experience
 Min. 5 years in planning,
preparation and design of railway
projects
NC02 Transport Financial Analyst  Bachelor degree in finance, 2 20
economics or engineering
 Min. 10 years experience
 Min. 8 years of experience in

23
Relevant Experience and Person-
No. Title Qualification Positions Months
economic, 3 years of which on
transport/infrastructure projects
 CA/CPA equivalent preferred
NC03 Financial Analyst  Bachelor degree in accounting or 2 20
related areas
 Min. 10 years experience
 Min. 5 years of experience in
financial analysis, 3 years of which
on transport/infrastructure projects
NC04 Alignment and Survey  professionally qualified engineer 2 60
Engineer with Bachelor degree in railway/civil
engineering,
 Min. 10 years experience
 Min. 6 years of experience in
alignment design and survey
engineering
NC05 Railway Track Engineer  professionally qualified engineer 2 30
with Bachelor degree in railway/civil
engineering or related areas
 Min. 10 years experience
 Min. 6 years of experience in
railway track engineering
NC06 Railway Bridge Engineer  professionally qualified engineer 2 36
with Bachelor degree in civil
engineering, post- graduate degree
preferred
 Min. 10 years of professional
experience
 Min. 5 years of experience in
bridge/structure design
NC07 Geotechnical Engineer  professionally qualified engineer 3 42
with Bachelor degree in
geotechnical engineering
 Min. 10 years of professional
experience
 Min. 5 years of experience in
geotechnical engineering
NC08 Signal Engineer  Bachelor degree in railway/ 1 15
electrical/electronics engineering, or
related areas
 Min. 10 years of professional
experience
 Min. 5 years of experience in
railway signal engineering
NC09 Telecommunication Engineer  Bachelor degree in 1 9

24
Relevant Experience and Person-
No. Title Qualification Positions Months
telecommunication engineering or
related areas
 Min. 10 years of professional
experience
 Min.5 years of experiences in
railway telecommunication
NC10 Rolling Stock Engineer  Bachelor degree in railway/ 1 9
mechanical engineering, or related
areas
 Min. 10 years of professional
experience
 Min. 5 years in railway rolling stock.
NC11 Environmental Specialist  Bachelor degree in environment 2 48
science, environmental engineering
or related areas, post-graduate
degree preferred
 Min. 8 years experience
 Min. 3 years in
preparation/management of
environment impact assessment for
transport infrastructure projects
NC12 Social/Resettlement/Gender  Bachelor degree in social science 4 96
Specialist  Min. 8 years of professional
experience
 Min. 3 years of experience in social
development and resettlement for
infrastructure projects
NC13 Embankment Engineer  professionally qualified engineer 2 20
with Bachelor degree in civil
engineering
 Min. 8 years of professional
experience
 Min. 3 years in embankment
design
NC14 Electrical Engineer  Bachelor degree in electrical 2 20
engineering, post-graduate degree
preferred
 Min. 10 years of professional
experience

NC15 Procurement Specialist  Bachelor degree in engineering, 1 12


post-graduate degree preferred
 Min. 10 years of professional
experience
 Min. 5 years in

25
Relevant Experience and Person-
No. Title Qualification Positions Months
preparation/management of
construction contracts and
procurements for international
bidding
NC16 Quantity Surveyor  Bachelor degree in civil 3 90
engineering, quantity surveying or
other relevant subject
 Min. 5 years of professional
experience
 Min. 3 years as a quantity surveyor
in transport projects.
NC17 Structural Engineer  professionally qualified engineer 1 8
with Bachelor degree in
Structural/civil Engineering
 Min. 6 years experience
 Min. 3 year experience in structural
design for buildings
NC18 Building Design/Landscape  professionally qualified architect 1 6
Architect with Bachelor and master degree in
architecture
 Min. 8 years experience
 Min 3 years as an architect in major
construction projects with
experience in Landscape Design
NC19 Drainage Engineer  Bachelor degree in Civil 1 12
Engineering or the relevant degree
under civil engineering.
 Min. 5 years of professional
experience
Non-Key Experts
NC20 Junior Engineers  Bachelor degree in civil engineering 8 240
 Min. 2 years of experience in
highway/railway.

NC21 CAD Engineer  Bachelor degree in civil 3 90


engineering/Draftsman
 Min. 5 years of professional
experience
 Min. 2 years in preparing
engineering drawings.
Subtotal 45 919
Note:
CVs of Engineers and Technical Officers (Non-key Experts) are not required for
inclusion in the proposal and will not be evaluated. However, CVs must be
submitted to Client for approval prior to mobilization.

26
D. Output and Reporting Requirements

11. The consultant will carry out activities according to the following time schedule,
and submit reports about the activities and outputs.

Table 2: Reporting Requirements

Submission Deadline
(no. of months after
Report commencement)
1. Inception Report 1
2. Draft Feasibility Study Report for KV line 6
3. Final Feasibility Study Report for KV line 8
4. Draft Final Report and Bidding Documents for 12
Maradana to Padukka (Kelani valley line
(including the detailed design)
5. Draft Feasibility Study Report for other three 18
projects
6. Final Feasibility Study Report for other three 20
projects
7. Draft Final Report and Bidding Documents for 23
Colombo to Rambukkana (Main Line)
(including the detailed design)
8. Draft Final Report and Bidding Documents for 28
Colombo to Kaluthara (Coastal Line)
(including the detailed design
9. Draft Final Report and Bidding Documents for 33
Ragama to Negambo (Puttam Line)
(including the detailed design
10. Final Report 36

E. Facilities Provided by the Client.

12. The client will provide,


(i) Visa supporting letters and registrations for host country.
(ii) Furnished air conditioned office spaces.
(iii) Relevant available project data and reports.
(iv) Access to data, records and other information required to perform the assigned tasks.

27