Fórmulas: PMBOK - PMI: Cod. Nombre Descripción EV
Fórmulas: PMBOK - PMI: Cod. Nombre Descripción EV
Fórmulas: PMBOK - PMI: Cod. Nombre Descripción EV
EAC Estimate At Completion What we currently expect the total cost to be. Current cost + Bottom up (redone) estimate of remaining
AC + Bottom-up ETC cost. Used when original estimate was flawed.
BAC / CPI Currently, the total cost estimate per (cumulative) performance.
AC + (BAC – EV) Used when there is no variance from BAC. Most common on exam.
AC+[ (BAC-EV)/( CPI*SPI)] Current cost + Remaining work TBD.