Method Statement: Consolidated Contractors Company & Teyseer Contracting Company J.V
Method Statement: Consolidated Contractors Company & Teyseer Contracting Company J.V
Method Statement: Consolidated Contractors Company & Teyseer Contracting Company J.V
: MS-742-110
REVISION No. : 1
& PAGE : 1
TEYSEER CONTRACTING COMPANY J.V. OF :
10
METHOD STATEMENT
FOR
HYDROTESTING OF
U/G & A/G PIPING SYSTEM
MS-742-110
RAS LAFFAN – QATAR
INDEX
1. SCOPE
2. PURPOSE
3. REFERENCES
4. DEFINITIONS
5. RESPONSIBILITIES
6. SAFETY
7. GENERAL
8. TOOLS AND EQUIPMENTS
9. DOCUMENTS
10. PREPARATION
11. TEST PERFORMANCE & WITNESS
12. ATTACHMENT
12.1 TEST MANIFOLD DIAGRAM
12.2 SAMPLE TEST PACKAGE
12.3 TEST BLIND THICKNESS CHART
12.4 PIPE CLEANING INSPECTION
DOCUMENT
12.5 JHA
12.6 A/G PIPING TESTING ACTIVITY FLOW
CHART
12.7 CERTIFICATE OF TESTING
MANIFOLD
1. SCOPE
1.1 This method statement mark out the boundary of related activities in various stages
in connection with the Hydrostatic testing of underground and above ground piping
system for Ras Laffan Onshore Expansion Project.
2. PURPOSE
2.1 To make certain all adequate manpower, material, tools equipment and proper
Supervision of all safety measures in all respects are taken so that extremely
smooth
And safe Hydrostatic test can be executed.
3. REFERENCES
3.1 Project Specifications:
a) RGX-S-00-1221-001 : Basic Engineering and Site Data
b) RGX-S-00-1360-002 : Piping Material and Service Classification
c) RGX-S-00-1360-003 : Piping Fabrication, Erection, Inspection and
Testing.
GX-S-00-1360-015 : Pneumatic Testing Procedure for Piping
System.
e) RGX-S-00-13A0-007 : Technical Specification Protection and
Preservation of Equipment and materials.
f) RGX-S-00-13A0-008 : Preservation of Austenitic Stainless Steel
4. DEFINITIONS
1 4.1 Company : Ras Gas
D
4.2 Contractor : Chiyoda, Snamprogetti & Company Joint Venture
(CMS & A)
4.3 Sub-contractor : CCC/TCC
4.4 PTW : Permit to work Document issued by RAS GAS /
1
D
CMS&A/RLIC
4.5 MS : Method Statement
5. RESPONSIBILITIES
6. SAFETY
1
E File No: MS-110 CMS&A WLL RAS LAFFAN ONSHORE EXPANSION
PROJECT
CONSOLIDATED CONTRACTORS COMPANY DOCUMENT No. : MS-742-110
REVISION No. : 1
& PAGE : 5
TEYSEER CONTRACTING COMPANY J.V. OF :
10
6.7 Contractor / Sub-contractor safety officer(s) will conduct a joint walk with
subcontractor/contractor testing personnel in order to familiarize the piping
system to be tested prior to test commencing.
6.8 Proper and safe means of access/egress shall be provided and maintained D for
the workers /QCI(s) in order to carryout preparation and inspection of the
piping system to be tested.
6.9 Minimum exclusion diameter placing the pressure containing components at the
1 center point shall be10 meters in every direction. Greater distance may be
D required in specific cases.
6.10 Adequate sign boards will be placed around the barricaded areas where the
test being carried out for the awareness of the nearby working personnel who
are not involved in testing activities to keep away from the testing zone.
6.11 When venting water from the pressure test, particular care shall be taken to
ensure that water does not vent into any place where personnel working, also
to electrical tools and live panels etc.
1 6.12 JHA and Method Statement shall be attached to work permit prior to
E
commencement of pressure test and must apply during execution of testing.
D
6.13 All necessary approved PPE will be provided and worn in accordance with
the project safety manual (RGX-SS-001610-003).
6.14 Sufficient illumination of work area, storage area and access/exit routes shall
be provided while working at night.
6.15 Subcontractor to obtain necessary permit to work from contractor/company
1 prior to commencement of pressure test activities.
D
6.16 All activities shall be suspended in case of an emergency and not restarted
until the PTW has been revalidated.
7 GENERAL
8.1 The following tools and equipments shall be made available to perform the
field-testing of piping system.
1
Pressure displacement pumps.
Fill tank and isolation valves.
Filling pumps.
Certified test manifolds.
Hand tools.
Pneumatic sockets.
Torque wrenches.
Calibrated pressure gauges and Recorders as required.
1
Torque wrenches – manual – pneumatic
8.2 The test manifolds shall be tested to minimum 20% above maximum specified
test pressure before use. Each test manifolds shall have unique number.
After testing, certificate will be produced / and retained by QC.
8.3 Pressure gauges shall have a range of 1.5 to 4 times required test pressure
and the gauges shall be calibrated within the previous 30 days of test date.
Two gauges minimum shall be installed at highest and lowest point .
9. DOCUMENTS
9.2 Using marked-up set of Piping /Instrument Diagram (P&ID) in the system
1 definition the extent of the test system will be marked up by contractor (Test
Block Diagram). The contractor will divide the piping into suitable test packs.
9.3 Subcontractor shall not test through equipment without prior approval from
contractor and company.
9.4.2 The marked up isometric drawing will indicate the location of pressurization
point, pressure guage, location, vents location, removal of control valves, FE,
Flow gauge, level gauges, Strainer elements, Critical soft seated Ball valves
1 which are not required to be part of the test. (these part will be clearly marked on
D
the test block diagram As-Built.)
9.4.3 Pre-test punch list shall be prepared by SCTR upon completion of test
package
a) ‘A’ item - To be cleared before test.
b) ‘B’ item - to be cleared as post test requirements
9.4.4 Pipe Cleaning Records shall be completed and signed by CTR for 6” and larger
pipe and company for 24” and larger pipes.
1
a) Hydrostatic Test:
D
Clean and fresh water shall be used, for austenitic stainless steel
C
piping water should not contain more than 50 ppm chloride ions, Sea
water may be used for testing sea water cooling lines only. All water
shall be drained immediately upon completion of pressure test.
b) Visual Inspection:
Visual inspection shall be applied in lieu of pressure test for the
following (down stream of last isolation valves)
· Open to atmosphere
· Open-end drain
· Valves without any spools on vessels trim, etc.
9 PREPARATIONS
12. ATTACHMENT