Agency Project Management Plan for Super
Energy Savings Performance Contracts
(Super ESPCs)
TABLE OF CONTENTS
SUMMARY......................................................................................................................................................3
3.0 SCHEDULES..........................................................................................................................................10
5.0 SAFETY...................................................................................................................................................11
6.0 COMMISSIONING...............................................................................................................................12
DRAFT
AGENCY PROJECT MANAGEMENT PLAN FOR SUPER
ENERGY SAVINGS PERFORMANCE (SUPER ESPC)
CONTRACTS
Summary
This draft project management plan is created to allow for consistent development
of project planning for energy savings projects and to create a series of master
checklists and guides for activities that must be considered in any project. The
purpose is to put forth the basic items for project management that need to be
covered, and then suggest methods of implementing a “graded approach” for the
refinement of the planing activities to coincide with the size and complexity of the
project. Depending upon the specifics of any given project, other requirements
may be necessary and can not be anticipated by this draft plan. This draft plan is
therefore, indicative of the functions that normally would be accomplished in the
management of any project, and is intended to assist Agency Project Managers in
the implementation of the ESPC Delivery Order project.
The main thrust for the development of a project management plan is to insure
proactive consideration of the activities necessary for a successful and timely
ESPC project completion.
contained herein shall be addressed for the project duration. ESCO and Agency
services and requirements should be defined in the final proposal.
Project Management defines the roles, authority, and responsibilities of the key
members of the project team. This section outlines the management approach to
maintaining cost, technical, and schedule knowledge for all parties, as well as
defines the decision making process for management of the project day-to-day
activities. Lines of communication and chains of command should be described
for all key personnel. All personnel holding permit and/or work authorization
authority should be identified. For this report we give the below-suggested list of
potential personnel to be considered for the project team as well as a checklist of
actions normally (Appendix D) requiring submittal and approval by the Agency.
Super ESPC contracts are contracted for by the Agency(s) with an Energy
Services Company (ESCO). A list of ESCOs in any region can be obtained from
the DOE Regional Office (RO). DOE Project Facilitators can be obtained for
assistance by the Agency if they want to contract for this service from DOE.
Identification of the key personnel for each major phase is critical to the project.
It should include the principle points of contact, the approval authorities, the
reviewers, and the permitting authorities, as examples. Not all personnel are
required for every phase.
AGENCY/FACILITY
Energy Manager
Facility Manager
Budget Manager
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 5
Project Manager
Contracting Officer (CO)
Contracts Specialists.
Contracting Officers Representative (COR)
Building Managers
Facility Engineers
Environmental Compliance Officer
Safety Manager
Security
Historical Protection Manager
Personnel authorizing electrical, steam, water, excavation,
etc., work permits for the facility.
ESCO
Project Manager
Financial Manager
Construction Manager
Site “Point of Contact”
Measurement & Verification Expert
Energy Engineer
Quality Control/Quality Assurance Manager
Safety Manager
Environmental Specialist
Key Subcontractor’s Point of Contact
Commissioning Engineer
The process for the development of an ESPC project is broken up into 5 phases,
depicting the areas of major focus and decision making. This draft plan will focus
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 6
on Phases 4 and 5 of the ESPC project management process, assuming that phases
1 through 3 have already been accomplished.
Phase 1: Assemble Acquisition Team, Develop Project Plan, and Partner with
an ESCO.
During Phase 3 the ESCO performs a Detailed Energy Survey, works with
the agency to develop the definition of an acceptable project, and submits
a revised proposal after receiving an “Intent to Award” and DO RFP from
the Agency. The Agency evaluates the revised proposal and proceeds with
negotiations and establishment of the final Delivery Order. The Notice of
Award, etc. is issued. M&V definition should be upgraded to Appendix I
requirements.
4.2 The list of Key Agency Personnel should be mobilized by the Agency
at this time to make sure they are budgeted and available to provide
timely support to the ESCO. Project delays cause loss of energy and
related O&M cost savings, which undermine the integrity of the
project
4.3 The Project Description should be finalized by the ESCO and should
include all the negotiated updates to the project as well as the final
engineering design configuration as approved by the agency.
4.5 The ESCO should initiate Engineering Design to finalize all ECM
configurations, prepare construction packages, and obtain agency
approval.
4.8 The project manager and appropriate team members for the Agency
should conduct weekly meetings with the ESCO to maintain current
knowledge of project status, see Appendix E for outline. Good
communications are the key to success.
4.9 The Agency should conduct monthly review meetings with their
upper management personnel to keep the Agency knowledgeable with
the project status. See Appendix F for suggested outline and topics.
The ESCO project manager should attend this meeting. Good
communications are the key to success.
4.11 Permitting requirements and Plans, as applicable for the Agency, for
hazardous material, Environmental Protection Plan, Spill
Contingency Plan, ground excavation, hot-wire work, lock & tag,
crane and rigging, power outages, etc. should be followed and
requested in a timely manner. These permits should be coordinated
by the ESCO and worked with the cognizant Agency personnel for
approval.
4.14 The ESCO should submit a commissioning plan for approval prior to
completion of construction. The Agency should review and approve
the plan. As-Built drawings shall be accomplished at this time,
preferably prior to commissioning, but definitely prior to acceptance.
Credit for energy cost savings usually coincides with completion of
commissioning, but should be as defined in the DO.
4.15 The Agency should develop Functional and Operational Test Plans
defining the requirements and duration of the testing for all
equipment installed by the ESCO, based on the approved ESCO
commissioning plan. Agency should provide Project Manager or a
representative to witness acceptance testing of ECMs as required.
5.4 Verify that the ESCO has delivered the guaranteed level of energy and
related O&M cost savings over the year through review of the
ESCO’s annual M&V report. Prepare annual savings verification
memo for contract file.
5.5 Resolve any annual true-up requirements for the energy baseline that
are required due to changes of facility use, revision of equipment, etc.
3.0 SCHEDULES
5.0 SAFETY
are not totally inclusive of all the requirements of OSHA, etc. The lists are
intended to give management and other upper level personnel enough knowledge
and direction for them to make a cursory and easy inspection to see if general
safety principles are being observed. A few such inspections will also tell the
workers that safety is important to management and must be taken seriously. The
ESCOs work crews and the Agencies personnel will be safer and a good safety
program and atmosphere will reduce the Agencies’ liability.
Agencies provide Safety & Health inspections using S&H plans as prescribed by
site-specific Agency policies and regulations.
6.0 COMMISSIONING
The ESCO shall commission each ECM to assure the government that ECMs
perform in accordance with the design intent. Design intent is defined as the
detailed technical description of the ideas, concepts, and criteria defined by the
building owner to be important, and including facility functional, operational and
environmental needs. The commissioning will be accomplished through a process
of verification and documentation, from design phase to construction acceptance
that all ECMs perform interactively and in accordance with the design
documentation and intent, and in accordance with the owner’s needs. The ESCO
shall supply to the government a commissioning plan that addresses each ECM
and the steps that will be taken in the commissioning process. The plan outline
addressing each ECM will be provided in the ESCO final proposal. Specific
ECM commissioning details will be further developed during the ECM design,
procurement and installation phases and will be developed using a graded
approach based on complexity. Specific ECM commissioning plans will be
issued for government review and approval with the design and construction
package.
Commissioning is defined as “the process of ensuring that the systems are
designed, installed, functionally tested, as capable of being operated and
maintained to perform in conformity with the design intent.” (ASHRAE, 1966)
Equipment commissioning is required to verify both that the equipment has been
properly installed per the original or the current redlined drawings, that it is
operating per manufacture specifications, and that it is interfaced properly with
the facility and is operating to the needs of the facility.
Each ECM should be acknowledged by the ESCO to be complete and ready for
inspection and commissioning.
(b) All ECMs have been through a Physical Installation Inspection to the requirements of
all Drawings and Specifications
Each ECM should be inspected to insure it is installed per the project drawings
and the component and/or system specifications. This inspection confirms all
electrical continuity and connections, lines, piping, and ducting are verified to be
properly connected, with all valves, etc. in their normal unpowered position and
all equipment is ready to be operated. Electrical wiring should have passed any
required testing to insure proper wire sizing, etc.
(c) All physical installation inspection discrepancies noted have been corrected
(d) All Items on the Project Construction Punch List completed and accepted.
The post-construction punch list shall be used to track the final completion of
construction, and shall include not only the equipment installed by the contract,
but also, all items associated with the installation of the equipment. The punch
list shall include everything from housekeeping, to construction scope, to all new
and revised equipment interfaces, etc. The intent is to have the facility back to the
pre-installation conditions, but with the new equipment installed.
(e) Appropriate training on Operations and Maintenance was conducted for each ECM
All training shall be accomplished, and videotapes made of the training for future
use to allow training of new hires and/or retraining of personnel.
(f) Operation and maintenance manuals and procedures have been provided and accepted.
Preliminary O&M manuals should be used as part of the training process and
updated and approved after completion of ECM installation, with any updates and
corrections provided to the training participants. O&M procedures should be
sufficiently detailed to allow the trained user to perform necessary maintenance.
This detail should include: lock and tag information, baseline operating
conditions, necessary calibration equipment identification and steps,
troubleshooting steps, spare parts listings and ESCO or manufacture contacts for
support.
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 14
(g) Recommended spare parts lists and spares have been provided and accepted.
The spare parts lists and spares provisioning shall be reviewed and shall include
sufficient information to maintain the ability to take advantage of all equipment
warrantees
The M&V installation shall be verified against the project proposal and with the
M&V plan to insure it is capable of providing all information necessary to
determine project performance for the periodic contractual verifications of
savings.
Utility rebates are usually only available upon completion of the equipment
installation and testing. They must be submitted for payment at this time to insure
the rebate is approved and available in a timely manner.
Warranty and registration issues are the responsibility of the ESCO, however, The
Agency should insure that this has been submitted by the ESCO.
All Delivery Order Data Submittals that are not yet satisfied by the 95%
installation complete should be noted on the construction punch list as open items
to allow tracking of their status.
The Agency declares that the project is complete and accepted. This is
co0ntractually noted by completion of the form in Appendix K, or its equivalent.
There are allowable exceptions, which are managed within the final acceptance
form, shown in Appendix K. ECMs may be installed in an off-season and cannot
be fully tested. The exceptions noted in the form in appendix K address those
issues, i.e., ECMs that install air conditioners in Mid-winter, and the reverse for
boilers.
APPENDICIES
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 16
LIST OF APPENDICES
A List of Acronyms
B Preliminary Proposal Kick-off Meeting Agenda
C Post Award Conference
D Approval/Review/Authority Items
E Weekly Meeting Agenda
F Monthly Review Agenda
G Material/Design Review Form
H M&V for ESCO Final Proposal
I Pre-Construction Checklist
J Project/ECM Acceptance/Commissioning Checklist
K Construction Completion Document
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 17
Team Introductions
Agency
ESCO
DOE COR and Project Facilitator (if FEMP Services acquired)
Scope of work
This should cover items that are exceptions…particular areas of the facility that
cannot be entered or ECMs the site has determined should not be done. Share info on
known problems any project must resolve, must-have items, nice-to-have items, etc.
Facility Master Plan information.
Potential energy related O&M Savings.
Design Intent – Commissioning Requirements Discussion.
Other Issues
Rebates from utilities.
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 19
Agency/DOE actions
Discuss agency process, approval authorities for Congressional Notification
Discuss agency funding for equipment or energy systems replacement or repair that
could be applied as buy down if impacted by ESCO proposed ECMs
Review Requirements
Agency
ESCO
DOE/PF (if FEMP Services acquired)
Proposal Requirements
Contract
Baseline & M&V
Energy versus O&M Savings
Attendee Listing
Name, phone, fax, email, address, title, agency or company, project assignment
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 20
CONFERENCE AGENDA
Team Introductions
Agency Acquisition Team
ESCO Project Team
DOE COR & Project Facilitator (if FEMP Services acquired)
Design
Design Intent Review – requirements for ECMs.
Engineering drawing approval requirements – prior to construction.
Redline authority approved for as-build drawings during construction.
Equipment data sheets submittal and approval requirements.
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 21
Outages
Utility service interruption permits approval.
Utility reconnect permits approval. (Including hot-wire permits.)
Site personnel support for outages.
Construction
Excavation permits approval requirements.
Crane movements and locations reviewed for overhead hazards.
Construction start coordination requirements. (Building manager and occupants).
Materials and equipment confirmed at job-site or scheduled to arrive prior to
need.
Establish acceptable lay-down yard and/or office space allocations for contractors.
Job/Work lists prepared and approved.
All worker certifications (welding, electrical, etc.) up-to-date.
All vehicle licensing up-to-date.
Commissioning
Commissioning Requirements
Commissioning Plan Approval
Acceptance After Completion of Commissioning.
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 22
Reviewer
Name Phone
Organization email
Action
from ESCO
Returned to
Corrections
(See Code)
Comments
Reference
Document
Approved
Approved
Received
Resubmit
Required
Approval
ESCO
Date
Date
Date
Final
with
No.
Item # C.4.6 M&V Activites
Returned to
Corrections
(See Code)
Comments
Reference
Document
Approved
Approved
Received
Resubmit
Required
Approval
ESCO
Date
Date
Date
Final
with
No.
Action
from ESCO
Returned to
Corrections
(See Code)
Comments
Reference
Document
Approved
Approved
Received
Resubmit
Required
Approval
ESCO
Date
Date
Final
Date
with
No.
Item # C.5.2 Design and Construction Standards
1 Iowa State Building Code ISBC 900.0 PI
2 NADC-ARS Construction Standard (242.1) PI
3
Item # C.5.3 ECM Quality Control Inspection Program
1 Organizational Chart PI
2 Names and Qualifications PI
3 Areas of Responsibility and Authority PI
4 Listing of Outside Organizations PI
5 Procedures for Review - Shop Dwgs, Etc. PI
6 Inspection Schedule PI
7 Procedures for Quality Control PI
8 ECM Installation Changes in Design PI
Item # C.5.4 Environmental Protection
1 Air Quality PI
2 NEPA PI
3 Waste Disposal Requirements Identified PI
Item # C.5.5 Service Interruptions
Notification/Approval 15 working days prior to
1 PI-15
work in affected building or area.
Item # C.5.6 As-Built Drawings
1 Provided Per Contract CI
2 PE Stamped CI
3 AutoCAD - 3.5" Floppy CI
Item # C.6.3 Operations of ECM's
1 Operations Procedures PI
Item # C.7.3 Maintenance of ECM's
1 Maintenance Procedures PI
Item # C.9.1 Contractor Maintenance and Repair Response Time
1 Contractor Point of Contact (Name and Phone) BA
Action
from ESCO
Returned to
Corrections
(See Code)
Comments
Reference
Document
Approved
Approved
Received
Resubmit
Required
Approval
ESCO
Date
Date
Final
Date
with
No.
The following are a suggested list of topics to be discussed with the ESCO on a
weekly or BI-weekly basis to establish the status of the project. The items
reviewed will change as the project progresses from initiation to completion.
Weekly meetings are to be attended by the Agency, the ESCO, and any of the
ESCO subcontractors required to properly obtain accurate current status.
New Resubmittal
Project Number
Comments
Initial and annual M&V costs for each measure (totals only).
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 28
PRE-CONSTRUCTION CHECKLIST
SUPER ESPC
ECM INSTALLATION and PROJECT ACCEPTANCE
Date:
_________ All ECMs have been through a Physical Installation Inspection to the requirements of all
Drawings and Specifications _________ All physical installation inspection
discrepancies noted have been corrected
_________ All Items on the Project construction Punch List are completed and accepted.
_________ Appropriate training on Operations and Maintenance was conducted for each ECM
_________ Operation and maintenance manuals and procedures have been provided and accepted.
_________ Recommended spare parts lists and spares have been provided and accepted.
_________ All Delivery Order data Submittals are complete and accepted.
_____________________________ _
Project Technical Representative
______________
Date
FEMP DRAFT PROJECT MANAGEMENT PLAN for SUPER ESPCs – 2-21-03 V1.1 30
SECTION 1B. Completion of Exceptions: (Signature in Section 1B document that the above Exceptions
List, if any, has been completed and accepted and/or funds have been accrued to complete remaining minor
exceptions and remaining project financial obligations)
All exceptions resolved. ____Funds accrued for remaining exceptions (list attached)
Assigned Performer Signature: (e.g. Major Agency Acceptance Inspection Signature:
Subcontractor)