BS 115 - Rev 1 (STUD) Guidelines For Composite Girders
BS 115 - Rev 1 (STUD) Guidelines For Composite Girders
BS 115 - Rev 1 (STUD) Guidelines For Composite Girders
Foreword to Revision 1
With the issue of BS 115, RDSO fulfilled a major requirement of field engineers regarding
guidance on quality control and execution of works related to composite construction. But the
document needs some updation based on feedback received. The feedback of Sh Pujari, ex-
SSE/Inspection/RDSO and Sh Avadhesh from Panchsheel Fasteners was instrumental in necessitating
this revision. The process/welder qualifications, surface preparation in case of painted surfaces and
angle through which bending of stud during bend test is to be performed have been changed as per
updated information available.
*******************
Foreword
Steel and concrete are most widely used construction materials for bridges these days. Both
have their advantages and disadvantages. Steel is equally good in tension, compression and shear. Being
a factory made/ fabricated structure, steel quality is better assured. But steel requires protection from
effects of corrosion. Concrete, on the other hand, is good only in compression but is a versatile material
that does not get affected by atmosphere that much. It can be poured and cast in the most efficient
shape and consequently, it is cheaper as compared with steel structures. However, concrete is mixed
and poured at site, so the quality and consistency concerns are more.
Composite construction aims to harness the good qualities of both steel as well as concrete. The
load is carried by composite member with concrete taking only compressive load and steel taking
tension as well as shear. The concrete deck shields the steel girder against rain/ sun, and hence
corrosion is minimized. Further, for railways, concrete deck ensures that ballasted deck can be provided,
which reduces maintenance requirement in track as well as the girder.
However, to harness the good qualities of both, the composite action needs to be ensured. For
this, shear connectors are very important which transfer the horizontal shear between concrete and
2/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
steel girder. RDSO has issued composite girder drawings since long and of late, their adoption in field
has increased. Lots of field people have been referring different problems being faced during
construction of composite girder to RDSO and so it was decided to issue comprehensive guidelines on
this subject.
It is hoped that these guidelines will help field engineers in understanding the subject and in
ensuring proper quality control. This is the first attempt to frame these guidelines and some errors/
discrepancies might have crept in. Feedback on these guidelines may be sent to RDSO on
directorsteel2@gmail.com or edbsrdso@gmail.com.
Lastly, Sh V B Sood, Director/B & S/SB-II RDSO and Sh Sandeep Agrawal, ADE/SB-II/RDSO among
other contributors deserve praise for their efforts to prepare these long awaited guidelines.
*****************
3/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
RDSO Guidelines for Fabrication of Composite Steel Girders including Stud Shear
Connectors
Composite girder drawings for Road Over Bridges (ROBs) and for medium span railway
bridges (upto 30.5 m span) are available which are being widely used. Currently, RDSO
drawings for composite girders with steel plate girders and RCC deck are available for 25 T
Loading 2008 for 12.2 m, 18.3 m, 24.4 m and 30.5 m spans, and ROBs of 18 m, 24 m, 30 m and
36 m spans. The floor system of Bow-String ROB girders also have composite action of slab
with cross-girders.
Reinforced concrete deck slab: The reinforced concrete slab acts as a very effective cover on
the compression side of the steel beams. This participates with the steel girder to take load
in longitudinal direction. The slab is also subjected to bending loads in transverse direction.
4/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
Shear connectors: Shear connectors provide the necessary connection between the slab and
the beams. Shear connectors provided must be capable of transferring horizontal shear at
the interface between the slab and girders with very small deformations, i.e. with no
appreciable slip between beams and slab, so that the whole structure deforms as a unit. Due
to the presence of shear connectors, total load carrying capacity of a composite girder is
higher than capacity arrived at by adding the strengths of steel girder and slab individually.
By utilizing the tensile strength of steel in the web/ bottom flange of girder and the
compressive strength of concrete in the slab acting as top flange, the bending resistance of the
combined materials is greatly increased and larger spans are made possible.
c) Importance of shear
connectors: Shear connectors are
the key component of a
composite girder. Individually,
both steel girder and the slab are
capable of taking much lesser
5/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
loads as compared to the loads carrying capacity of the composite girder. Bending of the
girder under loads induces differential deflection in steel component and RCC component
due to their different stiffnesses. This extra load carrying capacity is possible only because
of the presence of shear connectors which enable compatibility of this deformation and
hence the composite action is ensured by the shear connectors. Shear connectors have two
main functions: (1) transferring horizontal shear at the slab/girder interface; and (2)
resisting relative movements between the slab and the beams with as little movement as
possible.
d) Different types of shear connectors: The shear connectors are of two types: Rigid and
Flexible. The rigid type shear connectors take load through shear and these have very little
deformation even at their ultimate load carrying capacity. This results in concentration of
stresses in concrete/ welding near the shear connector. For the heavily loaded structures
like railways, these are not preferred due to their poor performance under fatigue. Bars,
Tees, channels etc can be used as rigid shear connectors, as shown in figure below:
Flexible shear connectors take load through bending, shear and torsion at the
connection of stud shear connectors with the parent steel. The failure in the case of flexible
shear connectors is not sudden as shear connectors are ductile and undergo large
deformations before failure. A variety of material like headed studs, channels, rebars, etc can
be used as flexible shear connectors.
6/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
3. Automatic Stud welding process: In automatic stud welding, arc welding is used to join
stud to steel member. The arc is created between tip of the shear stud and the steel
member by creating a large potential difference between the two. The tip of shear stud
needs special treatment to initiate the arc. The
process itself is required to be controlled so that the
proper profile of weld connection is created.
The Process: Electric arc stud welding involves the
same electrical, mechanical and metallurgical
principles found in any other arc welding process.
In stud welding, the amperage and the arc
duration are controlled through power source and
stud welding control system. To create the proper
distance between the stud tip and steel member
to initiate the arc, a lifting mechanism is there in
the gun to draw the stud away from the base
material. The arc is shielded from atmosphere
through a ceramic ferrule which also gives shape
to the weld profile. The gun includes a stud-
holding chuck, two legs, a foot piece and a ferrule
holder to hold the ceramic ferrule, as shown in
figure alongside.
7/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
The sequence of operations for stud welding is as follows (The stages are also
shown in figure below):
A. A stud and ferrule are loaded into the gun, and the gun is properly positioned against
the member.
B. The gun is pushed against the base material taking up the plunge, or stud length
available for burn off against the gun spring pressure. The trigger button is depressed to
start the fully controlled automatic sequence. This sequence consists of initiating the
weld current, and lifting the stud to create an arc by energizing the gun solenoid.
C. The arc duration time is completed and the stud plunged into the molten pool by means
of a spring when the gun solenoid is de-energized and turning off the weld current at
the end of the weld cycle.
D. The weld is completed and the gun is lifted off the stud and the ceramic ferrule broken
off by hitting with hammer. The installed stud is inspected for weld quality.
8/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
o Lift is the distance the gun pulls the stud away from the base material. Before the weld
is started, the stud and base metal are in contact. Lift creates an air gap that the electric
current must bridge. The current flow across the resistance of this gap creates the arc
heat to melt the stud and base material. Lift is physically set on the stud gun and is
measured when the stud weld is initiated. Lift should be set and measured by placing
the stud and ferrule on a non-conductive surface and initiating the weld cycle so that an
actual molten weld is not made.
o Time is the duration of the weld. On thin base material, a shorter time and higher
amperage can be used to achieve sufficient heat and prevent melting through the base
material. On some base materials, a longer time and low amperage improve the ductility
of the weld zone. Weld time is set on the time setting indicator of the control system.
o Amperage is a measure of the current from the power source that flows across the air
gap created by the lift. Increasing the amperage increases the weld heat. As with the
time setting, a higher amperage setting is needed for larger stud sizes. Amperage is also
set on the control system’s current setting indicator.
10/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
o Alignment is the proper centering of the stud in the ceramic ferrule so that the stud
does not contact the ceramic ferrule during lift and plunge. In absence of proper
alignment control, binding can occur. Binding can inhibit both stud lift and stud plunge
so that there is less than sufficient stud melting and less than full penetration into the
molten weld pool, resulting in a less than full strength weld.
Advantages: Stud welding has many advantages over other joining processes:-
i. The heat imparted to the base material in this process is minimum. This ensures
that there is little distortion of the base material. Thus it can be used for welding
studs after the girder is ready by welding the flanges and web.
ii. Automatic stud weld is strong. Unlike the fillet weld all around, that would be used
to weld a bolt in place, a stud weld is a full cross sectional weld. This means that full
face of the fastener is welded in place providing a strong, worry-free weld.
iii. It is a fast process. Welding a 20 mm diameter fastener will take less than one
second.
iv. It is single sided. This means that access to the other side of the work piece is not
required.
v. Requires no special skills on the part of welder and little training to install.
4. Settings of Stud Welding Process: To ensure proper quality of welds in automatic stud
welding procedure, the following aspects require attention:
Proper Position of Welding: As with normal welding, studs can be welded in different
positions such as downhand, vertical and overhead etc, as shown in figure below. Studs
of all weld base configurations and diameters can be easily welded in the downhand
position. In most applications on Indian Railways, it is possible to weld studs in
downhand position.
11/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
The vertical/ overhead positions cause an increased amount of welding sparks to fall
during welding and suitable operator protection is needed. Special spark retention
accessories available from the stud manufacturer shall be deployed to control the weld
sparks. Vertical and overhead welds require extra precautions and it ispreferable that the
stud be welded in downhand position even by manipulating the members, if feasible and
convenient.
Proper Weld Plate Cleanliness: An important parameter to ensure weld quality is the
cleanliness of the plate on which studs are to be welded. Normally this is the top flange
of the composite girders. Before starting welding of studs, the top flange should be as
clean as possible. The cleaning shall be done so as to remove heavy mill scale or heavy,
flaky rust, as well as any deleterious coating such as heavy oil, paint, galvanizing,
grease and moisture.
For providing studs, the member surface shall be cleaned by light sand blasting or by
scraping with wire brushes such as to remove the mill scale. If grease or other
contaminants are present, the surface shall be cleaned with solvents also. The prepared
surface shall not be painted or metallised in any way. Where studs are to be welded to
steel surface already painted, the weld surface should be brushed, ground or scraped to
completely remove the paint from the weld locations. It is not adequate to remove enough
paint to make electrical contact and allow the weld arc to get started, since the thickness
and volatility of the remaining paint may still have a serious adverse effect on the welds.
The surface on which studs are to be welded shall be free from paints for a distance of
minimum 50 mm from the center of any stud to be welded.
Appearance of light rust does not affect the performance of the stud welding process.
However, if the surface has become heavily corroded, cleaning shall be done again. Another
requirement is that weld splatter, ferrule pieces etc should be removed from the plate
surface so that the stud contact with the weld plate is clean and even. This will ensure good
electrical contact and current flow.
Earthing connections may be provided by screw type “C” clamps, fast action spring
clamps, or lever action hold down clamps mounted to the member being welded. The spot
where clamp is provided for earthing should also be cleaned on both sides of the plate so
that a good current path is established. Earthing spots can be cleaned very quickly with an
abrasive wheel, wire brush etc.
If required for corrosion protection, the steel surface duly fitted with studs shall be
aluminium metallised after welding of studs and their inspection is over. However, the
same shall not be painted as this would reduce the bond strength with concrete which is to
be poured subsequently.
12/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
Restriction on Galvanizing/ Other coatings on Studs: Zinc/ paints etc may contaminate
the weld metallurgy. No galvanized/coated studs shall be used on Indian railways.
Good quality concrete of slab shall provide the necessary corrosion protection to the
studs.
Checking Drawings: Before start of work, the drawings shall be checked to see if the
same are OK. The following shall be verified:
o Proper Weld Plate Thickness: The setup requires checking the combination of stud/
plates being used. To develop full steel tensile and shear capacity of the stud, plate
thickness shall normally be at least 0.5 times the stud shank diameter. For welding
plates thinner than this, extra care is required to be exercised in distortion control.
For 25 mm dia studs normally used on Indian railways, distortion will not be an issue
for plates thicker than 12 mm.
o Proper Edge Distance: Studs should be placed no closer to a base plate free edge
than the stud diameter plus 1/8 in. (3 mm) to the edge of the stud base. This distance
should be at least 1 to 1.5 in.(25 to 38 mm) from each free edge.
5. Selection of Stud Welding Operator: The stud welding operators are important to ensure
timely and proper execution of work. Inexperienced welders are likely spoil lots of welds,
causing loss as well as delay in the project. The site engineer shall ensure that the welders
being deputed for work are aware of the following:
o Knowledge regarding general principles of the process, proper equipment setup,
weld setup for the studs, general guidelines, and other literature.
o Knowledge regarding precautions to be taken during stud welding and
o Procedure for visual examination of welds done to determine if the same is
satisfactory or requires further investigation.
o Possible reasons for the poor weld being formed and remedies for the same.
13/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
A. Studs: Studs shall be made from steel conforming to ISO-13918. RDSO drawings have
specified SD1 material to be used as per design. Chemical and Mechanical
characteristics of finished stud material are as follows1:
1
Para 5.3.3.2 of ISO-13918
2
The mechanical characteristics should be as per ISO 6892-1.
14/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
Special Note: The chemical composition of IS:2062 E450 steel is quite close to the above
steel but the maximum Carbon Equivalent is only 0.52 whereas EN code requires maximum
Carbon Equivalent of 0.35. Therefore steel to IS: 2062 E450 is not suitable for studs.
Mass:Mass of stud shall be as per table A.4 of ISO 13918:2008(E). For 25 mm diameter
shear connectors (SD) with different lengths, mass values in the table are as follows: #
B. Tolerances in Length:4 The length of loose studs shall be verified as per EN code
provisions. For 25 mm, 200 mm long studs commonly used in RDSO drawings, the length
of loose stud shall be 205.5 mm, with a tolerance of ±1.5 mm.
C. Stud tip and flux: The tip shape of the shear connector may be chosen by the
manufacturer. The stud tip is supplied with flux in the form of a press-fitted aluminium
ball or aluminium spray coating.
D. Ceramic Ferrules: Compatible ferrules for the studs shall be brought for welding the
studs. The dimensions (of 25 mm studs used in most RDSO drawings) shall conform to
the following5:
3
Table A.4 of BS EN ISO 13918:2008
4
Table 10, Figure 5 of BS EN ISO 13918:2008
5
As per para 10.3 of BS EN ISO 13918:2008
15/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
Typical requirement of current for downhand welding for 25 mm dia. Studs used in
design by RDSO are:
The above current and time values are indicative only for a particular machine. It
is the responsibility of the welding machine supplier to recommend the welding
process/ parameters to be adopted.
F. Process Qualification: The welding parameters and the welder shall be qualified. For
initial qualification, minimum two studs of each type being used (total minimum 17)6
shall be welded on sample plates having similar properties to the girder part on which
these studs are to be provided. The studs shall be welded in same position as to be
welded in the actual girder part. These studs shall be checked for quality as per sub-
para (K) below. If these studs are not found satisfactory, the welding parameters shall
be adjusted or welder shall be further trained and sample studs provided again till
welding is found satisfactory. After satisfactory qualification, certificate shall be issued
by an officer of level of Assistant Engineer or above, which shall be further governed as
follows:
(i) The qualification shall be valid for two years and after that the welder shall be
qualified again by following same procedure.
(ii) For any new position /quality/size of stud, the parameters to be used are required to
be qualified only once. This need not be re-verified as long as the quality of studs is
satisfactory in field.
QUALITY ASSURANCE DURING EXECUTION: (Proforma for inspection of welded shear studs is at
Annexure I.)
G. Surface preparation: The quality assurance shall be as outlined in para 4 above. The
surface of member on which studs are to be provided shall be certified to be Ok by the
site engineer in charge of his representative before welding is taken up.
H. Inspection of studs: The raw material inspection as per sub-para (A) above shall be done
on studs during supply. Even during execution of work, few sample studs shall be
inspected randomly by inspecting officials:
(i) Dimensional check of studs shall be as per requirement.
(ii) The studs shall have proper flux at the tip.
(iii) Studs shall not be corroded and also these shall not have any coating.
6
Ref: Para 10.2.4 & Table 1 of ISO 14555:2006(E)
16/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
(iv) Completed studs shall be free of defects which can affect the application. Cracks in
the head shall be permissible, but may not exceed the value given in figure below7:
a. Machine settings: After setting the plunge/ lift and time/ amperage as per
recommendations, few trial welds shall be made to see if proper welds are being
made. If any problems are noticed, the time and amperage settings shall be adjusted.
b. Proper Alignment: The machine shall be checked for proper alignment control by
observing the movement of the chuck/stud before starting the work with a mchine.
This aspect may be seen if proper welds are not possible to be made with a particular
machine despite using proper settings.
c. Problems due to Grounding/Arc Blow: A very important parameter which affects the
weld quality is the uniformity of current around the stud. The welding arc is
electromagnetically deflected toward the grounding point or toward the larger mass of
the base plate configuration being welded. The figure below shows the ground and
edge effect patterns due to arc blow.
7
As per ISO 13918:2008(E).
17/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
Effect of (a) Ground connection, and (b) Workpiece on distortion of magnetic field
Typically, the effect of this non-uniformity is that there is a lack of fillet weld on
the periphery of the stud opposite the direction of the arc blow. This can adversely
affect weld strength and quality. In multiple rows of studs in a composite girder, the
middle row often has excellent weld whereas the side rows exhibit problems due to arc
blows.
To eliminate the problems associated with these effects, the following measures
can be taken: Either a copper or steel plate larger than the base plate to be welded,
with a center ground bolted to the bottom, can be provided temporarily below the
base plate to increase the edge distance available. Or an open box shield shall be
provided around the stud welding location. The bottom of this open box shall be
properly machined so as to have good contact with the base plate. This will provide
path to current and eliminate the grounding/ arc blow effects.
Open Box shield
Properly
machined
Temporary Copper
surface
or steel Plate
Earth
connect
Remedies for grounding/ arc blow defects
18/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
19/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
(ii) Dimensions of Welds: The dimensions of 5% welds shall be measured and verified
against the required dimensions. Typical dimensions with tolerances as per some
RDSO drawing, are as follows:
The length of weld which is not fused properly or which has improper
dimensions shall be noted. The weld collar is a butt weld and a slight variations
in the height of collar are normal and don’t affect strength of the weld as long as
the proper fusion of the stud with base metal is there. No action shall be
required for these.
Occasionally, isolated studs might have reduced collar width/ porosity/ lack of
fusion. These defects shall be noted along with the length of weld affected. Any
stud with cumulative weld-defect length less than 10% of the circumference
shall be considered acceptable and no action shall be taken.
Any stud with cumulative weld-defect length within 10% and 20% of the
circumference shall be considered ‘repairable’ provided that clustering of such
repaired studs does not exceed:
a) 1 in 6 in end quarter span.
b) 1 in 3 in middle half span.
If the defective weld clustering is more than above limits, the studs shall be
considered ‘not repairable’. Any stud with cumulative weld-defect length more
than 20% shall also be considered as ‘defective and not repairable’. All
defective/ non-reparable studs shall be replaced with good quality studs of same
diameter/ length.
For repairs/ replacing studs, paras L, M and N below shall be referred.
(iii) Verticality of studs: Studs shall generally be vertical. If welded studs are inclined,
process needs to be checked. Slightly inclined studs having good welds as per para
(ii) above shall be considered acceptable. But generally, inclined studs will have
problems of fusion etc and the process might not be completed properly. The
20/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
problem with machine that is leading to inclined studs will generally need to be
addressed.
(iv) Burn-off Length: This is an additional check on the quality of the whole process. For
25mm diameter, 200mm length which is commonly used in RDSO drawings, the
burn-off length is 5.5 mm8. For measuring this, a loose stud shall be placed next to a
welded stud and difference in height shall be noted. Incorrect burn-off length will
also be shown in the shape of the weld. The weld shape and burn-off length
together will help in diagnosing problems with the process/ quality after which
necessary corrective action can be taken.
(v) Ring Test: 1 in 20 (5%) studs shall be tested by bend test. It involves striking the side
of the head of the stud with a 2 Kg hammer. A ringing tone achieved after striking
indicates good fusion whereas dull tone indicates a lack of fusion9.
(vi) Bend Test: 1 in 100 (1%) studs shall be tested by bend test. The test consists of
bending the studs after they are allowed to cool, to an angle of approximately 60o
from their original axes by either striking the studs with a hammer on the unwelded
end or placing a pipe or other suitable hollow device over the stud and manually or
mechanically bending the stud as shown in figure below:
10
LEGEND
1-stud,
2-work piece,
3-bending tool,
α-Angle of bending
The bending shall be done in the direction opposite to any arc blow or visual
imperfection in the weld11. At temperatures below 10o C, bending shall preferably be
done by continuous slow application of load12.
L. Repairs of Repairable defective Studs: Studs identified to be ‘repairable’ as per para (I)
above by the site engineer, then it shall be repaired by 6mm size fillet weld of good
8
Table 10, Figure 5 of BS EN ISO 13918:2008
9
Para 5.5.4 (a) of BS 5400: Part 6: 1999.
10
Part of figure 1 of ISO EN 14555: 2006
11
Para 11.3(a) of ISO 14555:2006(E)
12
Paras 7.6.6.1 and 7.7.1.4 of AWS D1.1/D1.1M: 2004
21/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
quality taking care in surface preparations and execution as per clause no 26.6 of IRS B1-
2001.
M. Remedy for non-repairable defective studs: Studs identified to be ‘non-repairable’ as
per para (I) above by the site engineer, whether due to extent of defect or due to
population of such defective welded studs, may be allowed to remain as it is and equal
nos of additional studs of same quality shall be provided as near to defective studs as
possible, leaving at least 50mm gap between studs to ensure space for reinforcement
and good quality concreting. If the defective studs are clustered together, or space for
providing additional studs is not available, then few studs may be cut by gas/saws. The
studs shall be cut around 20mm from the base to ensure that the base material is not
affected.
N. Rejection of Member: If the population of defective welds is excessive and providing
additional studs and/or cutting of studs as specified above is not desirable from quality
considerations, then the member shall be rejected.
7. References:
a. Static Strength Of The Shear Connectors In Steel-Concrete Composite Beams -
Regulations And Research Analysis,By Slobodan Ranković, Dragoljub Drenić, Facta
Universitatis Series: Architecture and Civil Engineering Vol. 2, No 4, 2002, pp. 251 – 259.
b. Various types of shear connectors in composite structures: A review, ByImrose Bin
Muhit, Composite Structures Lab, Chung-Ang University, Seoul, KOREA.
c. Principles and practices of stud welding, by Harry A. Chambers
d. Steel-concrete composite bridge design guide, NZ Transport Agency research report
525, September 2013.
e. BS 5400: Part 6: 1999, Steel, concrete and composite bridges, Part 6. Specification for
materials and workmanship, steel.
f. IRS B1: 2001, Indian Railway Standard specification for fabrication and erection of steel
girder bridges and locomotive turn-tables(fabrication specification)
g. AWS D1.1/D1.1M: 2004, Structural Welding Code – Steel (American National Code)
h. IS: 3935-1966, IS:11384
i. EN 1994-2:2005, BS EN ISO 13918:2008, ISO/TR 15608:2005, ISO 6892-1:2015, ISO EN 14555:
2006(E)
j. Technical literature on studs, ferrules and welding machine from manufacturers collected from
internet: M/S Nelson Stud Welding Inc, Ohio, USA, Image Industries Inc, Wood Dale, Illinois,
USA, HBS Bolzenschweiss - Systeme Gmbh & Co, Dachau, Germany
-0-0-0-0-0-
22/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
Annexure I
Drg. No. _________________________, Span no. _________, No. of studs per span_________
Inspection Results(If answer to any question is NO, then the process needs to be checked and inspection to be repeated)
6. Surface preparation(100%):
a) Is surface free from rust/mill scale etc? Yes / No
b) Is surface free from grease/paints etc? Yes / No
c) Is the surface being cleaned of weld splatter/ broken ferrules during welding: Yes/No
7. Visual Inspection of raw material (on random samples, ~2-4%)(Only summary to be given
here, Separate register may be made for detailed record)
a) Studs
(i) Is surface free from paint, galvanizing, grease and moisture: Yes / No
(ii) Is the flux intact at the tip of the stud: Yes / No
23/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
b) Ferrules:
(i) Are ferrules broken? Yes / No
(ii) Are the ferrules properly dry Yes / No(With Over drying/ Without Over Drying)
9. Bend Test(@1%): (Only summary to be given here, Separate register may be made for
detailed record)
10. Visual Inspection of completed weld (@100%): (Only summary to be given here, Separate
register may be made for detailed record)
24/25
BS 115: RDSO Guidelines for composite construction including shear connectors (Rev 1)
-0-0-0-0-0-0-
25/25