Bill of Materials Cost Estimates
Bill of Materials Cost Estimates
Bill of Materials Cost Estimates
SUMMARY
I. SITEWORKS 63,100.00
V. REBARS 1,636,411.92
I. SITEWORKS
Mobilization 1 lot 13,500.00 13,500.00
Layout and staking 110 sq.m. 160.00 17,600.00
Clearing and grubbing 1 lot 2,000.00 2,000.00
Temporary Structure 1 lot 25,000.00 25,000.00
Temporary Safety Fence 1 lot 5,000.00 5,000.00
sub-total 63,100.00
II EARTHWORKS
Excavation 37 cu.m. 300.00 11,100.00
Backfill 28.5 cu.m. 150.00 4,275.00
Earthfill 72 cu.m. 350.00 25,200.00
Gravel Bedding 17.5 cu.m. 800.00 14,000.00
Material cost 54,575.00
Labor cost 21,830.00
sub-total 76,405.00
III. MASONRY WORKS
5" thk. CHB 2,613 pcs. 14.00 36,582.00
4" thk. CHB 5,482 pcs. 12.00 65,784.00
Portland cement 1,039 bags 230.00 238,970.00
Sand 57.5 cu.m. 1,450.00 83,375.00
10mmØ RSB @ 6M 544 pcs. 129.00 70,176.00
# 16 G.I. Tie wire 25 kls. 70.00 1,750.00
Matrial cost 496,637.00
Labor cost 198,654.80
Sub-total 695,291.80
IV. CONCRETE WORKS
Portland cement 755 bags 230.00 173,650.00
Sand 42.5 cu.m. 1,450.00 61,625.00
Gravel 84 cu.m. 800.00 67,200.00
Material cost 302,475.00
Labor Cost 120,990.00
sub-total 423,465.00
V. REBARS
16mmØRSB @ 6M 1660 pcs. 330.00 547,800.00
12mmØRSB @ 6M 890 pcs. 186.00 165,540.00
10mmØRSB @ 6M 3206 pcs. 129.00 413,574.00
# 16 G.I. Tie wire 249 kls. 70.00 17,430.00
Material cost 1,144,344.00
Labor cost 492,067.92
Sub-total 1,636,411.92
VI. FORMWORKS and SCAFFOLDING
¼" thk ordinary plywood 320 pcs. 330.00 105,600.00
2" x 3" x 12' coco lumber 1600 pcs. 138.00 220,800.00
2" x 2" x 12' coco lumber 1450 pcs. 92.00 133,400.00
Form oil 10 cont 50.00 500.00
Assorted CWN 1 keg @ 45 kgs. 120 keg 65.00 7,800.00
2" paint brush 12 pcs. 40.00 480.00
Miscellaneous items 1 lot 12,000.00 12,000.00
Material cost 480,580.00
Labor cost 192,232.00
sub-total 672,812.00
VII. TINSMITHRY WORKS
ROOFING WORKS
Ga 24 Pre-painted Tilespan Roof 85 lm 1,190.00 101,150.00
Plain-type Gutter #0.40mmx36"x8' 3 pcs 650.00 1,950.00
Fascia Board 18 pcs 300.00 5,400.00
Page 3
X. FINISHING WORKS
A. KITCHEN COUNTER GRANITE 1 lot 43,000.00 43,000.00
B. PAINTING WORKS
Davies Flat Latex Paint 20 tin 1,770.00 35,400.00
Semi-gloss Latex Paint 32 tin 2,110.00 67,520.00
Tinting Colors 1 lot 12,000.00 12,000.00
Skimcoat (@25 kgs) 34 bags 500.00 17,000.00
Polituff with Hardener 28 ltr 160.00 4,480.00
Gasa Tape 16 rolls 80.00 1,280.00
3/4" Masking Tape 24 pcs 25.00 600.00
Stopa 12 kls 85.00 1,020.00
3" Spatula 8 pcs 20.00 160.00
#100 Avox F Sanding Paper 60 mtr 130.00 7,800.00
#1 Paint Brush 16 pcs 15.00 240.00
#2 Paint Brush 8 pcs 70.00 560.00
#3 Paint Brush 8 pcs 70.00 560.00
Miscellaneous items 1 lot 5,000.00 5,000.00
C. TILEWORKS
Material cost 196,620.00
Labor cost 78,648.00
Sub-total 275,268.00
XI. PLUMBING WORKS
A. DRAINAGE SYSTEM (ORANGE PIPE)
75mm x 3.0m. PVC pipe 36 pcs. 450.00 16,200.00
100mm clean out 16 pcs. 238.00 3,808.00
90 deg. bend 75mm, elbow 27 pcs. 57.00 1,539.00
45 deg. Bend 75mm elbow 21 pcs. 57.00 1,197.00
45 deg. Bend 50mm Pvc elbow 25 pcs. 57.00 1,425.00
50mm P-trap 17 pcs. 104.00 1,768.00
100mm x 100mm stainless floor drain 22 pcs. 180.00 3,960.00
100mm 90 deg. Elbow(drain line) 75 pcs. 95.00 7,125.00
100mm drain pipe 9 pcs. 600.00 5,400.00
50mm pvc pipe (vent) 24 pcs. 325.00 7,800.00
50mm PVC elbow 90 deg 29 pcs. 32.00 928.00
50mm PVC tee 18 pcs. 46.00 828.00
B. WATER SUPPLY (BLUE PIPE)
12mm Ø x 3.0m Pvc pipe 72 pcs. 64.00 4,608.00
12mm Ø plain Tee 20 pcs. 15.00 300.00
90 deg. 12mm elbow (plain) 42 pcs. 11.00 462.00
12mm tee (threaded) 12 pcs. 60.00 720.00
90 deg. 12mm elbow (threaded) 18 pcs. 60.00 1,080.00
C. SANITARY FIXTURES
Water closet pcs -
lavatory ( pedestal type) sets -
lavatory ( counter-top type) sets -
Kitchen sink set -
Faucet sets -
Kitchen faucet sets -
Shower head, Prysfister pcs. -
Shower valve, Prysfister 7 pcs. 1,100.00 7,700.00
D. PLUMBING ACCESSORIES
1" Water Meter 1 set 4,500.00 4,500.00
1" Ø Gate Valve 1 set 2,100.00 2,100.00
1" Ø Check Valve 1 set 2,100.00 2,100.00
Teflon Tape 70 rolls 10.00 700.00
PVC Solvent 45 can 165.00 7,425.00
E. SEPTIC TANK 1 lot 25,000.00 25,000.00
D. WATERPROOFING
Mortaseal Cementitious Waterproofing (@20kg.) 32 bags 1,100.00 35,200.00
Mortaseal Flexi Waterproofing 9 Gal 690.00 6,210.00
2" paint brush 6 pcs. 75.00 450.00
Miscellaneous items 1 lot 5,000.00 5,000.00
Material cost 155,533.00
Labor cost 62,213.20
Sub-total 217,746.20
Page 5