Testing and Commissioning Document For Booster Pumping Station PDF
Testing and Commissioning Document For Booster Pumping Station PDF
Testing and Commissioning Document For Booster Pumping Station PDF
FOR
........................ DIVISION
Content Pages
Process flow for Commissioning of Booster Pump Station 1-5
Method Statement - Booster Pump Station Pre & Post Commissioning 6-8
Guidelines and Checklist for Full Testing & Commissioning of Booster Pump 9
Station
General Notes for Pre-commissioning, Commissioning and Acceptance Test for 10-14
Booster Pump Station
Commissioning Checklist for Booster Pump Station 15-20
Acceptance Tests for Treatment Works 21-24
Table A : Pump Monitoring Table 25
Table B : Pump Test Certificate 26
List of Equipment 27-30
Appendix
Appendix (A) Pre-commissioning Checklist for Water Treatment Plants 1-9
Cable check sheet 10
PROCESS FLOW FOR
COMMISSIONING OF
BOOSTER PUMP STATION
Page | 1
COMMISSIONING OF NEW JBALB BOOSTER PUMP STATIONS
The commissioning of all new JBALB booster pump stations shall be carried out by designated
officers coordinated Jabatan Bekalan Air Luar Bandar (JBALB) Headquarters. The commissioning
team shall consist of the following:-
a) Jurutera Mekanikal
b) Jurutera Elektrik
c) Jurutera Awam (Projek Berkenaan)
d) Ahli Kimia
e) Penolong Jurutera
a) DWE/OIC
b) Penolong Jurutera J29
Team Formation
Page | 2
2.0 Methodology
REFRESHER/ TRAINING
As per contract (external)
To be conducted by JBALB Divisional
and JBALB HQ (recommended once
every six (6) month)
i) The commissioning team will witness the testing of all items of equipment, pipework,
fittings and appurtenant (accessories) works to ensure that they are correctly installed and
capable of proper operation.
ii) The team will witness start up and running each item of equipment separately until they are
satisfied that it is capable of proper operation.
iii) After each item of equipment has been tested separately, the various items will be run
concurrently to commission the plant.
Page | 3
3.1 In carrying out (i) to (iii) above, the team shall ensure that :-
iv) Switchboards, control panels, alarm systems, overloads, and safety equipment are tested.
v) The alignment, mounting and configuration of pumps and drives, including the direction of
rotation are checked.
vi) The various lubrication systems and greasing systems are checked, including pump shaft
lubrication and stuffing box seal requirements.
vii) The pipework valves and gauges are correctly installed and operate satisfactorily. The
appropriate valve positions shall be determined for the different modes of operation of the
plant and documented.
viii) The chemical mixing, feeding and dosing equipment shall be tested and calibrated.
xi) All other tools and equipment necessary have been provided and are in working order.
3.2 During the commissioning of the plant, the team shall ensure that:-
i) The limits of hydraulic operation of the various units of the plant are determined.
ii) The appropriate flow rate through the plant is determined to minimize “on-off” operation.
Guides on pumping rates for the raw water and treated water pumps shall be established.
iii) The clarifiers are operated with the appropriate level of coagulant to achieve a well
developed floc blanket.
v) The filters are operated sufficiently long to establish head loss characteristics and backwash
requirements.
vi) The filter backwash system and air scour are operated correctly. The correct procedure for
backwashing of the filters is determined and documented.
vii) As far as possible, the appropriate levels of dosing of chemicals for the plant are determined.
In particular the appropriate level of post dosing for pH correction is determined.
Page | 4
3.3 Documents and operation manuals
During the commissioning of the plant, the Jurutera Air Bahagian (DWE) and Penolong Jurutera/
Pembantu Teknik/Juruteknik and attendants allocated to assist the teams, will undergo “hands
on” training in preparation for accepting responsibility for operation of the plant. This training
role will be a significant aspect of the duties of the commissioning team.
3.5.1 When the plant is operating satisfactorily and treated water has been supplied into the existing
reticulation system, it will be handed over to the JBALB Bahagian staff.
3.5.2 The commissioning team will prepare four (4) copies of the commissioning report, (1) one copy
to the Regional Manager, (1) one copy to the Jurutera Bahagian and (2) two copies to JBALB
Headquarters.
3.5.3 The report shall contain as a separate section, the recommended procedure for operating the
various items of the plant including the following:
Page | 5
METHOD STATEMENT
BOOSTER PUMP STATION PRE & POST COMMISSIONING
Page | 6
METHOD STATEMENT
Booster Pump Station Pre & Post Commissioning
Background Information
Project Name
Contract No.
Page | 8
GUIDELINES AND CHECKLIST FOR FULL TESTING & COMMISSIONING
OF BOOSTER PUMP STATION
Page |9
General Notes for Pre-commissioning,
Page |10
GENERAL NOTES FOR
The following notes are intended as a guide to the completion of Pre-Commissioning and
Commissioning Works in a manner which will be consistent throughout all new Booster Pump
Stations.
These are checks which are required to be undertaken by the Mechanical/Electrical Sub-Contractor
and are supervised by Contractor’s staff. They are intended as a virtual 'check list’ to ensure that all
items of equipment have been installed correctly and have been prepared for
commissioning/operation.
These are checks which are required to be undertaken by Contractor’s staff in the presence of JBALB
staff.
It is essential that JBALB staffs are present in order to witness measurements, readings, and
observations made during these checks. For this reason, sufficient notice should be given by
Contractor to JBALB (UPT). The contractual requirement is for 21 days’ notice. It is possible however,
to advise late changes to programme by facsimile/telephone when absolutely necessary.
Guidelines and Checklist for Commissioning are intended to be applicable to ALL Booster Stations. It
is unavoidable, therefore, that certain sections will not be applicable to a particular scheme.
Inapplicable sections will normally have been crossed out or struck through before the time of
commissioning. If this is not the case, then a comment should be made by the signatories at the
bottom of sheet 3 indicating which sections have not been undertaken or witnessed.
Page |11
Specific Guidance: Pre-Commissioning /Commissioning
If the reservoir is greater than l km-from the Booster Station, pumps are stopped by a
differential pressure switch which is operated on a decrease in flow. It may not be
convenient to wait for what could amount to several hours in order to demonstrate the
correct operation of this cut-out. All that is necessary in this case is to slowly close the pump
discharge valve and note the flow at which the pump trips.
For reservoirs less than 1 km from the Booster Station, pumps are stopped by level
electrodes which respond to the conduction of an electric current between them (when
both are immersed in water). Again, correct operation can be demonstrated by lowering the
High Level electrode into the water, or by shorting the Reference and High Electrodes
momentarily.
If a low flow trip, then re-start is by an adjustable timer. All that is necessary in this case to
demonstrate correct operation, without having to wait for an excessive time, is to
temporarily adjust the timer to a value of a few minutes.
Where trip is by electrode, re-start is also by electrodes, in this case by a break in the flow of
electric current between them. (When the water level falls below the Low Level Electrode)
Correct operation can be demonstrated in this case by raising the Low Level Electrode clear
of the water surface, or by momentarily disconnecting the connection to the Low Level
Electrode.
In the case of a suction tank, trip and re-set are both by electrode and the same comments
made above apply here. In some situations, however, where there is uncertainty as to the
precise details of existing water reservoirs, it will be necessary to check correct tripping by
draining or drawing down the feed reservoir.
Page |12
5. Travelling Crane
The JKKP Certificate for the crane should be issued and available for record.
After the surge suppression equipment is commissioned, all that is required under this
section is to observe the maximum and minimum pressures indicated on the surge arrestor
pressure gauge on starting and stopping the pump from a position of pressure equilibrium.
The JKKP Certificate for the Surge Suppression Equipment should be issued and available for
record
7. Generating Sets
Bomba Approval on all Fire Protection System should be issued and available for record.
9. Chlorination System
Correct operation of pumps can only be assessed by mechanically competent and experienced
personnel. Manufacturers’ literature states that bearing temperature should checked by hand: If a
normal person can hold a bearing cover without feeling pain, then it is highly probable that the
temperature is below 60 degree C and that the bearing is running normally.
If the bearing is running hot, this does not necessarily mean that it is defective, in nine cases out of
ten it is usually found that it has been over packed with grease, and that cleaning and repacking the
bearing will reduce its operating temperature.
’Abnormal' noise and vibration is a very subjective assessment and again, should be left to
experienced personnel.
Readings are taken over the operating range of the pumps. Data are calculated and graphs drawn
SUBSEQUENT to the commissioning of the booster stations. JBALB personnel/representative should
witness the readings taken. There will be one TABLE A, and one TABLE B for each pump set.
Most of the data entered onto the Acceptance Test Guidelines will be abstracted from the Pre-
Commissioning and Commissioning Guidelines. The main purpose of the acceptance test is to
demonstrate the system as a whole will function satisfactorily over a period of 14 days (or less
depending upon the operational requirements of JBALB).
Page |13
All that is required is for JBALB representatives to acknowledge the period of operation defined as
the 'Acceptance Test’.
N.B. JBALB representatives are not being asked to 'accept' or takeover schemes. All that is
required of them is to witness the proceedings and if necessary, to draw up a 'snag list’ of
items considered incomplete or defective. This snag list, together with any comments
considered appropriate, should be referred to JBALB Divisional who are the agency
responsible for accepting schemes.
Page |14
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION
Page |15
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION
PUMP ………………………..
Compliance checked by
1. REFERENCE DOCUMENTS
Consultant
Location Plan
Scheme Specific
Pipeline Profiles
Booster Station Assembly drawings
Manufacturers Pump set test cert. (attached)
O&M manual (draft)
Witnessed by JBALB
2. PUMPS Checked by Consultant
Representative
a) Refer to Operation & Maintenance
Manual (2.2.5 Operating Procedure -
Booster Pump. Station)
b) Run each pump for 2 hours or until
Bearing temperature is constant. Check
Bearing temperature in motor and pump,
noise, vibration and gland leakage (see
table. A, Data Sheet)
Page |16
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION
Page |17
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION
(Where Surge Suppression Equipment fitted, commissioning will be carried out under
section 2)
a) Pump start Observed
Max. Min.
up: pressure
Pump shut Observed
Max. Min.
down: pressure
Pressure Set Bar
Point:
Level Set M
Point:
7. CHLORINE DOSING SYSTEM
Check all gas pipework joints for leaks using ammonia vapor.
Manufacturers pre-start up checks complete Yes No
Page |18
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION
TEST CRITERIA
- The PLC DI and Scada System shall receive the signal.
- The LED status at the PLC DI module and equipment status at Scada shall turn off when
the simulated signal is disabled.
DIGITAL
INPUT/ SCADA GRAPHIC
DESCRIPTION REMARKS
OUTPUT
ADDRESS YES NO
Page |19
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION
TEST CRITERIA
- The Scada shall give the output signal according to signal simulated.
Equip. Description :
Simulated Range : 4 – 20 mA
Input Range :
Simulated Range
Desired Value Displayed Value Remarks
(mA)
12
16
20
Page |20
ACCEPTANCE TEST FOR BOOSTER PUMP STATION
Page |21
ACCEPTANCE TEST FOR BOOSTER PUMP STATION
Surge Vessels
Suction Tank
Reservoirs
6. Equipment used for measurement Pipelines Tanks
Flow
Range of flowmeter
Comments
Pressure
Range of instrument
Comments
Level
Comments
Page |22
ACCEPTANCE TEST FOR BOOSTER PUMP STATION
Start pumping:
Stop pumping:
* These are shift times. The pump will stop and start during this period if the Storage
Reservoir fills.
Required output: 1.1 times Average Daily Year 2000 Flow
= 1.1 x ____________ = _______________
Page |23
ACCEPTANCE TEST FOR BOOSTER PUMP STATION
10. Test conducted for 14 days/ ……… (OR as agreed with JBALB)
11. OVERHEAD CRANE
Yes No
JKKP Approval Required
If Yes, JKKP Certificate
If No, JBALB Approval At Commissioning
12. DIESEL GENERATOR SET
Yes No
D.O.E Approval
13. SURGE SUPPRESSION EQUIPMENT
Yes No
JKKP Type Approval
JKKP Installation Approval
14 CHLORINE DOSING SYSTEM Yes No
Functioning in line with booster pump
Page |24
TABLE A
Page | 25
TABLE B: Unless otherwise specified Tests carried out in accordance
PUMP TEST CERTIFICATE with BS5316 Part 1, Class C
PUMP TESTED:
CUSTOMER/PROJECT:
PUMP SIZE: SERIAL NO:
INLET/OUTLET
DRIVER: IMPELLER DIA: MM DIA: MM
TYPE: ORIFICE PLATE DIA: MM
MAKE: FLOW RATE: m3/h
MODEL: RPM: TOTAL HEAD: M
POWER: AMP:
VOLTAGE: PHASE:
SUCTION PRESSURE GAUGE LEVEL: M
DISCHARGE PRESSURE GAUGE LEVEL: M
TEST FLOW DISCHARGE SUCTION V2/2g TDH VOLT AMP P.F. MOTOR PUMP RPM
NO. m3/h PRESSURE PRESSURE INPUT POWER EFF % BHP WHP EFF %
M M M M kW kW kW
Page | 26
LIST OF EQUIPMENTS
Page | 27
2. Chlorination System
2.1 Vacuum Regulator
Brand/Make
Type
Model
Heater Make
Heater Type
Power Rating V/A/W
2.2 Chlorinator
Brand/Make
Type
Model
Max Capacity kg/hr
Motor Make
Motor Type
Power Rating V/Hz
2.3 Changeover Manifold
Brand/Make
Type
Serial No.
Range
2.4 Injector
Brand/Make
Type
Serial No.
Max Capacity kg/hr
Page | 28
3. Pressure Transmitter
Instrument Brand/Make
Instrument Model
Instrument Serial No.
Measure (ie Ph,
NTU,mg/l)
Output mA
Rated current A
Voltage/Phase V/Phase
Rated Frequency Hz
Class
4 Crane
Brand/Make
Type
Model
Country
Year
Equipment Serial No.
Hoist Serial No.
PMA Registration No.
Hoisting Capacity Ton
Page | 29
5. Surge Vessel (If
Applicable)
5.1 Compressor
Brand/Make
Model
Serial No.
Piston Displacement
Max Discharge Pressure Bar
Design Duty Pressure Bar
Free Air
Noise Level dB
5.2 Motor
Brand/Make
Type
Model
Serial No
Power kW
Voltage/Phase Phase
Rated Current A
Speed Rpm
Class
Page | 30
APPENDIX
PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION
Appendix (A)
1. VALVES
2. PUMPS
3. ELECTRICAL
c) Polarity check
d) Earth Resistance of Lighting Protection System = ohms
(must be less than 10 ohms)
ii) Switchgear Protection Setting Checked by
a) Over current protection
b) Earth leakage setting
iii) Pump Motor Insulation Resistance R Y B
PUMP
PUMP
PUMP
PUMP
4. INSTRUMENTATION
Yes No
a) Installation/Assembly complete and in
accordance with drawing
b) Control cables insulation check (see attached sheet D(i))
c) Isolation and Balancing Valves, bleed screws
checked for operation over full strokes
Instrument
Instrument
Instrument
Instrument
Expected Actual
Instrument 4,00 mA mA
Instrument 4,00 mA mA
Instrument 4,00 mA mA
Instrument 4,00 mA mA
If a value differs from that expected by more than 0.01 mA, reconfirm sensor range with D.P.
range stamped on D all Tube/Orifice Plate, and then refer to manufacturers operating
instructions for procedure to set zero and coarse span.
N.B. The fine span is pre-set at the factory and should not be adjusted unless
there is reason to suspect an unexpected change in calibration. A precision
pressure source is required before adjusting the fine span potentiometer.
Confirm that the Meter Factor (written on the inside of the connection compartment)
matches the settings of " switches S1, S2, S3 and S4 and link Ll.
(Details of the calibration necessary to determine the Meter Factor are contained in
Appendix A of the Manufacturers’ Instruction Manual).
5. PUMP PROTECTION
6. MOTORS
c) P Yes No
Check thermister trip for motor over 37 kW (by
shorting thermister) PUMP
PUMP
PUMP
PUMP
Yes No
a) Tapes over breather holes removed
b) All damaged paintwork repaired
c) Alignment check Drawing Measured Permitted
(NA to monorail hoists) Dimension Dimension Tolerances
i) Crane span at each end ±6 mm
of carriages
ii) Diagonal centres of ±6 mm
crane wheels
iii) Crane span at crane ±6 mm
rail level
Yes
d) Safe work load ______________tonnes painted on frame
8. GENERATORS
Generator Unit
a) Manufacturers pre-start checks
completed (see attached sheets)
Completed
b) Insulation Tests (Resistance in M ohms)
(see attached data sheet D(i)C) Measured Required
i) Between load terminals and plant >50 MΩ
structure
ii) Between generator terminals and >50 MΩ
structure
iii) Between generator phases R.Y. >50 MΩ
R.B. >50 MΩ
B.Y. >50 MΩ
iv) Ancillary equipment: Heaters >1 MΩ
c) Continuity tests: Yes No
Phase and circuit connections checked
d) Earthing protection check Measured Required
i) Earth resistance on electrical system < 1 ohm
High Low
Rated Actual Rated Actual
l) Alarm setting high/low mm mm mm mm
Stop Start
Rated Actual Rated Actual
m) Compressor settings
start/stop mm mm mm mm
n) JKKP type approval Yes/No
o) JKKP installation approval Yes/No/NA