Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Testing and Commissioning Document For Booster Pumping Station PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 43

JABATAN BEKALAN AIR LUAR BANDAR (JBALB) SARAWAK

TESTING AND COMMISSIONING DOCUMENT

FOR

BOOSTER PUMPING STATION

............................. WATER SUPPLY,

........................ DIVISION

WORK CONTRACT NO: ……………………………………


TABLE OF CONTENTS

Content Pages
Process flow for Commissioning of Booster Pump Station 1-5
Method Statement - Booster Pump Station Pre & Post Commissioning 6-8
Guidelines and Checklist for Full Testing & Commissioning of Booster Pump 9
Station
General Notes for Pre-commissioning, Commissioning and Acceptance Test for 10-14
Booster Pump Station
Commissioning Checklist for Booster Pump Station 15-20
Acceptance Tests for Treatment Works 21-24
Table A : Pump Monitoring Table 25
Table B : Pump Test Certificate 26
List of Equipment 27-30
Appendix
Appendix (A) Pre-commissioning Checklist for Water Treatment Plants 1-9
Cable check sheet 10
PROCESS FLOW FOR
COMMISSIONING OF
BOOSTER PUMP STATION

Page | 1
COMMISSIONING OF NEW JBALB BOOSTER PUMP STATIONS

1.0 Commissioning Team

The commissioning of all new JBALB booster pump stations shall be carried out by designated
officers coordinated Jabatan Bekalan Air Luar Bandar (JBALB) Headquarters. The commissioning
team shall consist of the following:-

1.1 JBALB Headquarters

a) Jurutera Mekanikal
b) Jurutera Elektrik
c) Jurutera Awam (Projek Berkenaan)
d) Ahli Kimia
e) Penolong Jurutera

1.2 JBALB Divisional


a) Jurutera Air Bahagian (DWE)/Pegawai Meguasa Bahagian(OIC)
b) Penolong Jurutera J29

1.3 JBALB Project Management Team

a) DWE/OIC
b) Penolong Jurutera J29

Team Formation

JBALB Headquarters JBALB Project JBALB Divisional Contractor and


& Commissioning Team (Refer to namelists Consultant
Team (Refer to namelists detail)
(Refer to namelists detail)
detail)

Page | 2
2.0 Methodology

2.1 The Jurutera Mekanikal from JBALB Headquarters PRE-COMM/COMMISSIONING PROCESS


will head the commissioning team and the Jurutera (WTP/BPS)
Air Bahagian (DWE), Penolong Jurutera and
Pembantu Teknik/Juruteknik are allocated the
PRE-COMMISSIONING PROCESS
following tasks to assist in the commissioning.
What to check?
Physical and visual check of control
equipment i.e. Pumps, Valves, PLC’s, Genset,
2.2 Pembantu Kemahiran H17 & Pembantu Awam
MSB, etc as per Guidelines of Pre-
H11/14 will assist the commissioning teams and
Commissioning Checklists & Contract
will take over the plant operation after successful
Document
commissioning and handing over. In this respect,
they will get hands-on experience in the plant
operation.
COMMISSIONING PROCESS
What to check?
Individual System Checks as per Guidelines of
2.3 Project Management Team from JBALB
Commissioning Checklists and Data Sheets.
Divisional/Regional Office’s role is to be the
coordinator to instruct consultant/contractor to
execute and implement the commissioning process
as per guidelines and checklist. They will also be Commissioning
responsible to coordinate with JBALB Headquarters, successful
JBALB Bahagian & JBALB District with the
Commissioning Team to ensure that proper
guidelines and procedure is implemented prior to
ensuring the commissioning of related Water DOCUMENTATION / HANDOVER
Treatment Plant / Booster Pump Station are in Parties involved: Divisional Office and JBALB
accordance with the guidelines before handing Headquarters
over to JBALB Bahagian.

REFRESHER/ TRAINING
 As per contract (external)
 To be conducted by JBALB Divisional
and JBALB HQ (recommended once
every six (6) month)

3.0 Tasks and Duties

i) The commissioning team will witness the testing of all items of equipment, pipework,
fittings and appurtenant (accessories) works to ensure that they are correctly installed and
capable of proper operation.

ii) The team will witness start up and running each item of equipment separately until they are
satisfied that it is capable of proper operation.

iii) After each item of equipment has been tested separately, the various items will be run
concurrently to commission the plant.

Page | 3
3.1 In carrying out (i) to (iii) above, the team shall ensure that :-

i) The correct sequence of operation of the plant is checked and documented.

ii) Plant control systems are checked.

iii) Calibration of instruments is carried out.

iv) Switchboards, control panels, alarm systems, overloads, and safety equipment are tested.

v) The alignment, mounting and configuration of pumps and drives, including the direction of
rotation are checked.

vi) The various lubrication systems and greasing systems are checked, including pump shaft
lubrication and stuffing box seal requirements.

vii) The pipework valves and gauges are correctly installed and operate satisfactorily. The
appropriate valve positions shall be determined for the different modes of operation of the
plant and documented.

viii) The chemical mixing, feeding and dosing equipment shall be tested and calibrated.

ix) Load tests are carried out on lifting equipment.

x) The necessary chemical testing equipment is provided and in working order.

xi) All other tools and equipment necessary have been provided and are in working order.

3.2 During the commissioning of the plant, the team shall ensure that:-

i) The limits of hydraulic operation of the various units of the plant are determined.

ii) The appropriate flow rate through the plant is determined to minimize “on-off” operation.
Guides on pumping rates for the raw water and treated water pumps shall be established.

iii) The clarifiers are operated with the appropriate level of coagulant to achieve a well
developed floc blanket.

iv) The rate of de-sludging of the clarifiers is determined.

v) The filters are operated sufficiently long to establish head loss characteristics and backwash
requirements.
vi) The filter backwash system and air scour are operated correctly. The correct procedure for
backwashing of the filters is determined and documented.

vii) As far as possible, the appropriate levels of dosing of chemicals for the plant are determined.
In particular the appropriate level of post dosing for pH correction is determined.

Page | 4
3.3 Documents and operation manuals

The following documents shall form part of the commissioning:

i) JKR MS ISO 9001 quality procedures on water treatment process;


ii) Buku Panduan Kerja Pertukangan Atenden Loji Bekalan Air;
iii) Buku Panduan Kerja Pertukangan Atenden Pam Bekalan Air;
iv) Buku Panduan Kerja Pertukangan Atenden Enjin Bekalan Air;
v) Perinteh-Perintah Tetap Pihak Berkuasa Bekalan Air JKR;
vi) Other operation manuals for the pumps and equipment.

3.4 Refresher/Induction Training

During the commissioning of the plant, the Jurutera Air Bahagian (DWE) and Penolong Jurutera/
Pembantu Teknik/Juruteknik and attendants allocated to assist the teams, will undergo “hands
on” training in preparation for accepting responsibility for operation of the plant. This training
role will be a significant aspect of the duties of the commissioning team.

3.5 Handing Over and Documentation

3.5.1 When the plant is operating satisfactorily and treated water has been supplied into the existing
reticulation system, it will be handed over to the JBALB Bahagian staff.

3.5.2 The commissioning team will prepare four (4) copies of the commissioning report, (1) one copy
to the Regional Manager, (1) one copy to the Jurutera Bahagian and (2) two copies to JBALB
Headquarters.

3.5.3 The report shall contain as a separate section, the recommended procedure for operating the
various items of the plant including the following:

i) valve on-off schedules,


ii) switchboard operation and use of control panels and monitors.
iii) observed rate of desludging of clarifiers and backwashing of filters
iv) operation of the raw water pumps and clear well pumps to integrate the plant into the
existing system and optimize its operation.

3.5.6 An assessment of the induction training of operator staff shall be given.

Page | 5
METHOD STATEMENT
BOOSTER PUMP STATION PRE & POST COMMISSIONING

Page | 6
METHOD STATEMENT
Booster Pump Station Pre & Post Commissioning

Background Information
Project Name

Contract No.

Pre & Post Commissioning Implementation

Divisional Involvement 1. Divisional Office representative shall be present during


pre-commissioning and commissioning stage to witness
and to comment any dissatisfaction /query through
Project Management Team / Commissioning Team
representative.
2. Representative from Divisional Office shall be at least
Penolong Jurutera (PJ29) of Mechanical or Electrical to be
involved during pre-commissioning and commissioning
stage (especially M&E equipment testing.
3. Water treatment plant operator (PRAK) shall be involved
during system operational testing for the purpose of
familiarisation of new treatment plant.
4. Certificate of Practical Completion (CPC) shall be to the
satisfaction of JBALB Commissioning Team and JBALB
Divisional Office SO/SOR/OIC. This is to ensure proper
handing over and operational needs are met and achieved
as per design in the Contract.
New Pipe interconnection to 1. JBALB Project Management Team concerned shall notify
existing piping system any pipe interconnection and submit method statement
for interconnection work to JBALB Divisional Office prior
to the commencement of actual work.
2. Method statement must be agreed between Project
Management Team and Respective JBALB Divisional
Office before any work can proceed.
3. Upon agreement on the interconnection Method
Statement, the affected Divisional Office (DWE/OIC) shall
issue notice of water supply interruption to the public
prior to the execution of interconnection work either via
Corporate Communication or Information Department
(which ever) is more efficient and cost effective within a
weeks notice.
4. Any actual shutdown to the existing system shall be
done by JBALB Project Management Team or
representative from JBALB Divisional Office assisted by
the Contractor involved.
5. The interconnection work and any reinstatement work
which is affected by the interconnection process shall be
done by the contractor involved to the satisfaction of
representative of both PMT and Divisional Office.
Consumables Requirement 1. After every successful Testing and Comissioning, it is
crucial that the Appointed Contractor/Consultant
prepare and advice on the usage and quantity of
consumable required like chlorine, aluminum sulphate,
polymer and soda ash shall be made available as stock
for at least 3 to 6 months (subject to availability & plant
Page | 7
locality) for operational use after project completion
(CPC).
2. It is recommended that the information on where and
how to acquire these required consumable shall be
made known to the JBALB Divisional Office for reference
of their planning and procurement process by the users.
3. Material acquisition inclusive of M&E parts shall be
identified and JBALB Divisional Office is recommended to
acquire major parts for major pumps and dosing pump
for stock in advance for the ease of maintenance after
the end of Defect Liability Period (DLP).
Recommendation on Operational 1. Operation and maintenance manual for the water
and/Or Overall Maintenance Plan treatment plant shall be provided by the contractor to the
JBALB Divisional Office and JBALB Headquarters for
references on Operational matters.
2. JBALB Divisional Office shall produce the Maintenance
Plan which include periodic and preventive/predictive
maintenance of all major equipment i.e. Treated water
pump, submersible water intake pump and control panels.
It is recommended that all major equipment is checked
and inspected at a regular interval of three (3) months
(minimum) by Audit or representatives from JBALB
Headquarters.
3. Divisional Office shall coordinate with JBALB Headquarters
regarding procedure, schedule and costing for
maintenance of all equipment. It is advisable that this
coordination is initiated prior to the end of project’s DLP.
Recommendation on manpower 1. It is recommended that DWE/OIC’s to review their
requirement of new Water current operation setup and manpower requirement to
Treatment Plant (WTP) and Booster suit the new WTP prior to the completion of the project. It
Pump Station (BPS) would be best that proper proposal on operation of new
WTP to be worked out at the commissioning stage since
forecast on actual manpower required can be identified
clearly with the involvement of Divisional Office at this
stage.
2. For the operation of BPS, additional manpower should be
allocated sufficiently to oversee the operation of isolated
BPS. This would help to avoid or reduce the occurrence of
vandalism especially to this isolated BPS. Any failure at
this BPS will jeopardize the reliability of water supply to
which the BPS cater.

Page | 8
GUIDELINES AND CHECKLIST FOR FULL TESTING & COMMISSIONING
OF BOOSTER PUMP STATION

Page |9
General Notes for Pre-commissioning,

Commissioning and Acceptance Test

Booster Pump Stations

Page |10
GENERAL NOTES FOR

PRE-COMMISSIONING, COMMISSIONING AND ACCEPTANCE TESTING

OF BOOSTER PUMP STATIONS

The following notes are intended as a guide to the completion of Pre-Commissioning and
Commissioning Works in a manner which will be consistent throughout all new Booster Pump
Stations.

Guidelines and Checklist for Pre-commissioning (Appendix A)

These are checks which are required to be undertaken by the Mechanical/Electrical Sub-Contractor
and are supervised by Contractor’s staff. They are intended as a virtual 'check list’ to ensure that all
items of equipment have been installed correctly and have been prepared for
commissioning/operation.

Guidelines and Checklist for Commissioning

These are checks which are required to be undertaken by Contractor’s staff in the presence of JBALB
staff.

It is essential that JBALB staffs are present in order to witness measurements, readings, and
observations made during these checks. For this reason, sufficient notice should be given by
Contractor to JBALB (UPT). The contractual requirement is for 21 days’ notice. It is possible however,
to advise late changes to programme by facsimile/telephone when absolutely necessary.

Guidelines and Checklist for Commissioning are intended to be applicable to ALL Booster Stations. It
is unavoidable, therefore, that certain sections will not be applicable to a particular scheme.
Inapplicable sections will normally have been crossed out or struck through before the time of
commissioning. If this is not the case, then a comment should be made by the signatories at the
bottom of sheet 3 indicating which sections have not been undertaken or witnessed.

It is absolutely essential that Mechanically/Electrically competent personnel are delegated to


witness the commissioning of Mechanical and Electrical equipment in order to avoid protracted
discussions and arguments on methods/techniques employed to generate the data.

Page |11
Specific Guidance: Pre-Commissioning /Commissioning

1. Check pumps stop when reservoir full..........

If the reservoir is greater than l km-from the Booster Station, pumps are stopped by a
differential pressure switch which is operated on a decrease in flow. It may not be
convenient to wait for what could amount to several hours in order to demonstrate the
correct operation of this cut-out. All that is necessary in this case is to slowly close the pump
discharge valve and note the flow at which the pump trips.

For reservoirs less than 1 km from the Booster Station, pumps are stopped by level
electrodes which respond to the conduction of an electric current between them (when
both are immersed in water). Again, correct operation can be demonstrated by lowering the
High Level electrode into the water, or by shorting the Reference and High Electrodes
momentarily.

2. Check pumps restart automatically.........

If a low flow trip, then re-start is by an adjustable timer. All that is necessary in this case to
demonstrate correct operation, without having to wait for an excessive time, is to
temporarily adjust the timer to a value of a few minutes.

Where trip is by electrode, re-start is also by electrodes, in this case by a break in the flow of
electric current between them. (When the water level falls below the Low Level Electrode)
Correct operation can be demonstrated in this case by raising the Low Level Electrode clear
of the water surface, or by momentarily disconnecting the connection to the Low Level
Electrode.

3. Check pumps stop when suction tank is at low level.

Check pumps re-start automatically.............

In the case of a suction tank, trip and re-set are both by electrode and the same comments
made above apply here. In some situations, however, where there is uncertainty as to the
precise details of existing water reservoirs, it will be necessary to check correct tripping by
draining or drawing down the feed reservoir.

4. Motor rated speed + measured speed

This is determined by either an optical or a contact tachometer.

Page |12
5. Travelling Crane

The JKKP Certificate for the crane should be issued and available for record.

6. Surge Suppression Equipment.

After the surge suppression equipment is commissioned, all that is required under this
section is to observe the maximum and minimum pressures indicated on the surge arrestor
pressure gauge on starting and stopping the pump from a position of pressure equilibrium.
The JKKP Certificate for the Surge Suppression Equipment should be issued and available for
record

7. Generating Sets

Department of Environment (DOE) Approval Certificate for installation of Generating Set


should be issued and available for record.

8. Fire Protection System

Bomba Approval on all Fire Protection System should be issued and available for record.

9. Chlorination System

To check whether chlorination system synchronizes with booster pump or not.

Table A - Pump Bearings/Vibration

Correct operation of pumps can only be assessed by mechanically competent and experienced
personnel. Manufacturers’ literature states that bearing temperature should checked by hand: If a
normal person can hold a bearing cover without feeling pain, then it is highly probable that the
temperature is below 60 degree C and that the bearing is running normally.

If the bearing is running hot, this does not necessarily mean that it is defective, in nine cases out of
ten it is usually found that it has been over packed with grease, and that cleaning and repacking the
bearing will reduce its operating temperature.

’Abnormal' noise and vibration is a very subjective assessment and again, should be left to
experienced personnel.

Table B - Pump Test Sheet

Readings are taken over the operating range of the pumps. Data are calculated and graphs drawn
SUBSEQUENT to the commissioning of the booster stations. JBALB personnel/representative should
witness the readings taken. There will be one TABLE A, and one TABLE B for each pump set.

Guidelines for Acceptance Test

Most of the data entered onto the Acceptance Test Guidelines will be abstracted from the Pre-
Commissioning and Commissioning Guidelines. The main purpose of the acceptance test is to
demonstrate the system as a whole will function satisfactorily over a period of 14 days (or less
depending upon the operational requirements of JBALB).

Page |13
All that is required is for JBALB representatives to acknowledge the period of operation defined as
the 'Acceptance Test’.

N.B. JBALB representatives are not being asked to 'accept' or takeover schemes. All that is
required of them is to witness the proceedings and if necessary, to draw up a 'snag list’ of
items considered incomplete or defective. This snag list, together with any comments
considered appropriate, should be referred to JBALB Divisional who are the agency
responsible for accepting schemes.

Page |14
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

COMMISSIONING CHECKLIST FOR BOOSTER STATION

Page |15
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

Project Name ………………………………….. Pump Type …………………………………………….

Work Contract No. ………………………………………. Serial Nos. PUMP ………………………..

Booster Stations ……………………………… PUMP ………………………..

Name & Location ……………………………. PUMP ………………………..

PUMP ………………………..

Compliance checked by
1. REFERENCE DOCUMENTS
Consultant
Location Plan
Scheme Specific
Pipeline Profiles
Booster Station Assembly drawings
Manufacturers Pump set test cert. (attached)
O&M manual (draft)
Witnessed by JBALB
2. PUMPS Checked by Consultant
Representative
a) Refer to Operation & Maintenance
Manual (2.2.5 Operating Procedure -
Booster Pump. Station)
b) Run each pump for 2 hours or until
Bearing temperature is constant. Check
Bearing temperature in motor and pump,
noise, vibration and gland leakage (see
table. A, Data Sheet)

c) Take readings at approximately 25%, 50%


and 100% Discharge valves open
condition (see table B, Data Sheet)
d) Check pumps stop when reservoir-full
Actual level: m
e) Check pump re-starts automatically
Actual level: m

Page |16
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

f) Check pumps stop when


suction tank is at low level
Actual leveI: m
g) Check pumps re-start
automatically after 1 hour
(if water is available)
Actual leveI: m

3. MOTORS PUMP PUMP PUMP PUMP

a) Rate speed (rpm)


Measured speed.(rpm)
b) (full load)

4. OVERHEAD TRAVELLING CRANE Yes No

a) Alignment check complete


b) Manufacturers test certificate attached
Vertical Deflection test of crane bridge
caused by hoist plus SWL in central Span
Position Def
Permitted max. def. (Span - 750) Def
d) Load hook through full travel
e) Crane travelled full length with SWL
f) JKKP type approval
g) JKKP installation approval & Certificate
(See Attached Certificate)

5. DIESEL GENERATOR SET

a) Manufacturers Test Certificate attached


b) D.O.E. Application
Rated Actual
c) Oil pressure switch kPA kPA
operation
O O
d) Water temperature switch C C
operation
e) Engine overspeed switch rpm rpm
operation

Page |17
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

f) Trip-on control circuit voltage failure


g) Noise measurement (dBA) North South East West
Measured 3 m from exhaust
Measured 3 m from outer wall
h) Test generator over six Yes No
consecutive starts

6. SURGE SUPPRESSION EQUIPMENT

(Where Surge Suppression Equipment fitted, commissioning will be carried out under
section 2)
a) Pump start Observed
Max. Min.
up: pressure
Pump shut Observed
Max. Min.
down: pressure
Pressure Set Bar
Point:
Level Set M
Point:
7. CHLORINE DOSING SYSTEM

Check all gas pipework joints for leaks using ammonia vapor.
Manufacturers pre-start up checks complete Yes No

Satisfactory Unit Yes No


Chlorine
Dosing
Chlorine
Dosing
Chlorine
Dosing
Check operation changeover panel.
Commissioning complete, system ready for use. Yes No

Checked By Certified by Witnessed by JBALB


Commissioning completed
Contractor Consultant Representative
Name
Signature
Designation
Date

Page |18
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

Project Name : Capacity : m3/hr


Work Contract No. : Operation : hr/d
TELEMETRY SYSTEM

Station Name: ……………………………………………….


1. I/O Check
PROCEDURE
- For input/Output signal to/from the PLC DI Card. Use signal simulator or wire to
simulate at the respective terminal block, simulate the selector switch, push button and
equipment.
- Verify Correct input/output status at PLC DI Card and indicating light/alarm
annunciator and Graphic Scada System.

TEST CRITERIA
- The PLC DI and Scada System shall receive the signal.
- The LED status at the PLC DI module and equipment status at Scada shall turn off when
the simulated signal is disabled.
DIGITAL
INPUT/ SCADA GRAPHIC
DESCRIPTION REMARKS
OUTPUT
ADDRESS YES NO

Certified by Witnessed by JBALB


Checked by Contractor
Consultant Representative
Name
Signature
Designation
Date

Page |19
COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

Project Name : Capacity : m3/hr


Work Contract No. : Operation : hr/d
2. ANALOG INPUT/OUTPUT SIGNAL TO/FROM SCADA ( PLC LOGIC TEST )
PROCEDURE
1. Determine the loop is internally powered or externally powered from the
schematic diagram.
2. Connect the + and – wires of the signal injector to the 4-20mA inputb terminals
at…(Station Name)….……..Panel and set the signal injector according to the loop
power condition.
3. Simulate the signal to 0%, 25%, 50%, 75%, 100% of the instrument range.

TEST CRITERIA
- The Scada shall give the output signal according to signal simulated.

Equip. Description :
Simulated Range : 4 – 20 mA
Input Range :

Simulated Range
Desired Value Displayed Value Remarks
(mA)

12

16

20

Commissioning complete systems ready for use.

Certified by Witnessed by JBALB


Checked by Contractor
Consultant Representative
Name
Signature
Designation
Date

Page |20
ACCEPTANCE TEST FOR BOOSTER PUMP STATION

ACCEPTANCE TEST FOR BOOSTER PUMP STATION

Page |21
ACCEPTANCE TEST FOR BOOSTER PUMP STATION

Project Name ……………………………………………….

Work Contract No. ……………………………………………….

1. Design Assumption: (See attached sheet)

2. Start Date for Test:

3. JBALB Required From:

4. JBALB State Representative Required for JBALB Valve/Filling

Operation From: …………………………………… to ……………………………

5. Disinfection successfully completed: Pipelines

Surge Vessels

Suction Tank

Reservoirs
6. Equipment used for measurement Pipelines Tanks

Flow

Range of flowmeter

Head loss through flowmeter

Comments

Pressure

Range of instrument

Comments

Level

Comments

Page |22
ACCEPTANCE TEST FOR BOOSTER PUMP STATION

7. CRITERIA FOR PASSING TEST

Booster Station Name:


Operating hours: hr/day

Start pumping:
Stop pumping:

* These are shift times. The pump will stop and start during this period if the Storage
Reservoir fills.
Required output: 1.1 times Average Daily Year 2000 Flow
= 1.1 x ____________ = _______________

8. Pipelines Year 2000 Flow Required Recorded


Flow* Measured Pressure Pressure

* or highest available flow (see attached graph)


9. Reservoir Name
Overflow measured at full pump output (outlet
valve closed, inlet valve held open)
Bypass flow (if applicable)
Required year 2000 inflow
Actual max. pumped inflow
Peak outflow measured

Page |23
ACCEPTANCE TEST FOR BOOSTER PUMP STATION

10. Test conducted for 14 days/ ……… (OR as agreed with JBALB)
11. OVERHEAD CRANE
Yes No
JKKP Approval Required
If Yes, JKKP Certificate
If No, JBALB Approval At Commissioning
12. DIESEL GENERATOR SET
Yes No
D.O.E Approval
13. SURGE SUPPRESSION EQUIPMENT
Yes No
JKKP Type Approval
JKKP Installation Approval
14 CHLORINE DOSING SYSTEM Yes No
Functioning in line with booster pump

15. Checked By Certified by Witnessed by JBALB


Contractor Consultant Representative
Signature
Name
Designation
Date

Page |24
TABLE A

Bearing Check 40 -60 C


Time (Every Abnormal Noise Any leaks
Motor Pump
Hour) and/or vibration visible
Inner Outer Inner Outer

Certified by Witnessed by JBALB


Checked By Contractor
Consultant Representative
Name
Signature
Designation
Date

Page | 25
TABLE B: Unless otherwise specified Tests carried out in accordance
PUMP TEST CERTIFICATE with BS5316 Part 1, Class C

PUMP TESTED:
CUSTOMER/PROJECT:
PUMP SIZE: SERIAL NO:
INLET/OUTLET
DRIVER: IMPELLER DIA: MM DIA: MM
TYPE: ORIFICE PLATE DIA: MM
MAKE: FLOW RATE: m3/h
MODEL: RPM: TOTAL HEAD: M
POWER: AMP:
VOLTAGE: PHASE:
SUCTION PRESSURE GAUGE LEVEL: M
DISCHARGE PRESSURE GAUGE LEVEL: M

TEST FLOW DISCHARGE SUCTION V2/2g TDH VOLT AMP P.F. MOTOR PUMP RPM
NO. m3/h PRESSURE PRESSURE INPUT POWER EFF % BHP WHP EFF %
M M M M kW kW kW

Checked By Contractor Certified by Consultant Witnessed by JBALB Representative


Name
Signature
Designation
Date

Page | 26
LIST OF EQUIPMENTS

1. Treated Water Pump


Pump Brand/Make
Pump Model
Pump Serial No.
Pump Head m
Design Flow Rate m3/hr
HP
Power kW
Rated current A
Voltage/Phase V/Phase
Motor Brand/Make
Motor Model
Motor Serial No.
Motor Speed rpm
Motor Frequency Hz
Class

Page | 27
2. Chlorination System
2.1 Vacuum Regulator
Brand/Make
Type
Model
Heater Make
Heater Type
Power Rating V/A/W
2.2 Chlorinator
Brand/Make
Type
Model
Max Capacity kg/hr
Motor Make
Motor Type
Power Rating V/Hz
2.3 Changeover Manifold
Brand/Make
Type
Serial No.
Range
2.4 Injector
Brand/Make
Type
Serial No.
Max Capacity kg/hr

Page | 28
3. Pressure Transmitter
Instrument Brand/Make
Instrument Model
Instrument Serial No.
Measure (ie Ph,
NTU,mg/l)
Output mA
Rated current A
Voltage/Phase V/Phase
Rated Frequency Hz
Class

4 Crane
Brand/Make
Type
Model
Country
Year
Equipment Serial No.
Hoist Serial No.
PMA Registration No.
Hoisting Capacity Ton

Page | 29
5. Surge Vessel (If
Applicable)
5.1 Compressor
Brand/Make
Model
Serial No.
Piston Displacement
Max Discharge Pressure Bar
Design Duty Pressure Bar
Free Air
Noise Level dB
5.2 Motor
Brand/Make
Type
Model
Serial No
Power kW
Voltage/Phase Phase
Rated Current A
Speed Rpm
Class

Page | 30
APPENDIX
PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

Appendix (A)

PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

Appendix (A) Page | 1


PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

Project Name ……………………………………………………… Pump Type ………………………………………..


Work Contract
No. ………………………….……………………... Serial Nos. Pump ………………………..
Booster Stations .…………………………………………….… Pump ………………………..
Name & Location ……………………………………………… Pump ………………………..
Pump ………………………..

1. VALVES

Function Checks Direction Open Seats


a) Washdown/Priming
Valves
b) Suction Valves
c) Discharge Valves
d) Non-Return Valves
e) Air Release Valves

2. PUMPS

i) Manufacturers Pre-Start Up Checks (see attached PUMP PUMP PUMP PUMP


sheets) completed
ii) Alignment Checks
See manual Parallel (mm) Angular (mm)
for No.
procedure PUMP PUMP PUMP PUMP PUMP PUMP PUMP PUMP
Reading with 1
pipework 2
uncoupled
3
4
Reading with 1
pipework 2
coupled
3
4
Manufacturers tolerance: Parallel ………………… mm
Angular ………………. mm

Appendix (A) Page | 2


PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

3. ELECTRICAL

i) Earthing Protection Check S.B PUMP PUMP PUMP PUMP


a) Earth Resistance on Electrical
Systems (must be 1 ohm or less)
b) Insulation
Resistance Cables ……………….. See attached data sheet D (i) A

c) Polarity check
d) Earth Resistance of Lighting Protection System = ohms
(must be less than 10 ohms)
ii) Switchgear Protection Setting Checked by
a) Over current protection
b) Earth leakage setting
iii) Pump Motor Insulation Resistance R Y B
PUMP
PUMP
PUMP
PUMP

4. INSTRUMENTATION

Yes No
a) Installation/Assembly complete and in
accordance with drawing
b) Control cables insulation check (see attached sheet D(i))
c) Isolation and Balancing Valves, bleed screws
checked for operation over full strokes
Instrument
Instrument
Instrument
Instrument

Appendix (A) Page | 3


PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

d) Instrument lines clear of obstruction,


Yes No
flushed through and checked for leaks
Instrument
Instrument
Instrument
Instrument

e) Check Zero Calibration of Primary Loop Element:


With balancing valves on DP transmitter open, energise supply to instruments and measure
loop current after 10 minutes

Expected Actual
Instrument 4,00 mA mA
Instrument 4,00 mA mA
Instrument 4,00 mA mA
Instrument 4,00 mA mA

If a value differs from that expected by more than 0.01 mA, reconfirm sensor range with D.P.
range stamped on D all Tube/Orifice Plate, and then refer to manufacturers operating
instructions for procedure to set zero and coarse span.

N.B. The fine span is pre-set at the factory and should not be adjusted unless
there is reason to suspect an unexpected change in calibration. A precision
pressure source is required before adjusting the fine span potentiometer.

Appendix (A) Page | 4


PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

f) Check Integrator/Analogue Converter Calibration:

Confirm that the Meter Factor (written on the inside of the connection compartment)
matches the settings of " switches S1, S2, S3 and S4 and link Ll.

(Details of the calibration necessary to determine the Meter Factor are contained in
Appendix A of the Manufacturers’ Instruction Manual).

Refer to 'Analogue Converter Scaling’ a page 10 of the Manufacturers’ Instruction Manual


for the procedure to check the calibration.
Zero Proportion or FS
Expected Actual Expected Actual
Instrument 0,00 mA mA mA mA
Instrument 0,00 mA mA mA mA
Instrument 0,00 mA mA mA mA
Instrument 0,00 mA mA mA mA

5. PUMP PROTECTION

a) Low Level Probe in suction tank m


b) High Level Probe in suction tank m
c) High Level Probe in receiving reservoir m
d) D.P. switch in discharge pipeline m3/h

6. MOTORS

a) Check motor insulation


resistance R B Y
PUMP
PUMP
PUMP
PUMP

Appendix (A) Page | 5


PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

b) Check rotation correct P Yes No


PUMP
PUMP
PUMP
PUMP

c) P Yes No
Check thermister trip for motor over 37 kW (by
shorting thermister) PUMP
PUMP
PUMP
PUMP

7. OVERHEAD TRAVELLING CRANE

Yes No
a) Tapes over breather holes removed
b) All damaged paintwork repaired
c) Alignment check Drawing Measured Permitted
(NA to monorail hoists) Dimension Dimension Tolerances
i) Crane span at each end ±6 mm
of carriages
ii) Diagonal centres of ±6 mm
crane wheels
iii) Crane span at crane ±6 mm
rail level
Yes
d) Safe work load ______________tonnes painted on frame

Appendix (A) Page | 6


PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

8. GENERATORS

Generator Unit
a) Manufacturers pre-start checks
completed (see attached sheets)
Completed
b) Insulation Tests (Resistance in M ohms)
(see attached data sheet D(i)C) Measured Required
i) Between load terminals and plant >50 MΩ
structure
ii) Between generator terminals and >50 MΩ
structure
iii) Between generator phases R.Y. >50 MΩ
R.B. >50 MΩ
B.Y. >50 MΩ
iv) Ancillary equipment: Heaters >1 MΩ
c) Continuity tests: Yes No
Phase and circuit connections checked
d) Earthing protection check Measured Required
i) Earth resistance on electrical system < 1 ohm

ii) Polarity verified Yes No


iii) Generator neutral earthing Yes No
e) Battery Checks Measured
i) Standing voltage measured Volts
ii) Starting voltage measured Volts
iii) Specific gravity
iv) Level of electrolyte
v) Trickle charger checked for correct Amps
operation

Appendix (A) Page | 7


PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

f) Fuel system Yes No


i) Fuel tank level sensors checked for
correct operation of pump and alarms
ii) Fuel lines purged of air
g) Before starting Yes No
i) All lubrication systems checked as correct

ii) Ambient temperature of area


iii) Cooling water gauge reading
h) Fire/safety Yes No
i) Fire extinguishers installed and fully
charged
ii) Fire fuel shut-off valve checked (remove
fusible link)

9. SURGE SUPPRESSION EQUIPMENT

a) Compressors: Compressor A Compressor B


Manufacturers pre-start up checks
complete (see attached sheets)
b) Pipeline length m
c) Double orifice vented NRV's: No.
d) Double orifice inflow check NRV's: No.
e) Vessel size m3
f) Outlet size mm
g) Outlet NRV Yes/No
h) Normal operating pressure kPA
i) PRV setting kPA
j) Maximum surge pressure kPA
k) Minimum Surge pressure kPA

Appendix (A) Page | 8


PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

High Low
Rated Actual Rated Actual
l) Alarm setting high/low mm mm mm mm
Stop Start
Rated Actual Rated Actual
m) Compressor settings
start/stop mm mm mm mm
n) JKKP type approval Yes/No
o) JKKP installation approval Yes/No/NA

Above checks satisfactorily completed.

Checked By Supervised by Witnessed by JBALB


Contractor Consultant Representative
Name
Signature
Designation
Date

Appendix (A) Page | 9


PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION

CABLE CHECK SHEET


Project Name: ………………………………………………. Capacity: …………………………………. m3/hr

Work Contract hr/d


Operation: ………………………………
No.: …………………………………………………..

Site Location: …………………………………………………


Resistance (M ohms)
Power/Control Cables
Cable From: Cable
1-E 2-E 3-E 4-E 5-E
Name To: Type

Values should exceed 1 MΩ

The above checks have been completed satisfactorily.

Checked By Certified by Witnessed by JBALB


Contractor Consultant Representative
Name
Signature
Designation
Date

Appendix (A) Page | 10

You might also like