Cost Overruns

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

('in INR crores)

Costs as per estimates in Final cost in march 2010


january,2008 adopted by AERA
Funding
%age of
Amount %age of total cost Amount total cost
Equity 1202 13.39% 2300 18.40%
Loans 4986 55.55% 5266 42.12%
Security Deposits 2738 30.51% 1471.51 11.77%
Internal accruals 49 0.55% 50 0.40%
DF ( Developement Fees) Not Envisaged Not Envisaged 3415.35 27.32%
Total 8975 100.00% 12502.86 100.00%
Cost
Escalation

5.00%
-13.44%
-18.74%
-0.15%
-27.32%