Delay Caused by The Exceptionaly Adverse Rainy Conditions During The Original Contract Period
Delay Caused by The Exceptionaly Adverse Rainy Conditions During The Original Contract Period
Delay Caused by The Exceptionaly Adverse Rainy Conditions During The Original Contract Period
Delay caused by the exceptionaly adverse rainy conditions during the original contract period
Year Number of Allowable days for EOT 2006 Days For 2007 Days For 2008 Days For Total Days
2001 2002 2003 2004 2005 Average EOT EOT EOT For the
(Past 05 Extention
Years)
Jan 4.5 0.5 5.0 2.0 2.0 2.8 0.0 4.5 1.7 2.0 0.0
Feb 0.0 1.5 3.0 0.0 0.0 0.9 1.5 0.0 0.0 2.0 1.1
Mar 0.0 1.5 0.0 1.5 1.5 0.9 4.0 0.0 0.0 9.5 8.6
Apr 6.0 3.5 2.0 4.0 7.5 4.6 0.5 4.5 0.0 3.0 0.0
May 0.0 0.0 0.5 6.0 2.0 1.7 2.0 1.0 0.0 0.0
Jun 0.0 0.0 0.5 0.0 0.0 0.1 0.0 1.5 1.4 0.0
Jul 1.0 0.0 2.5 1.0 0.0 0.9 0.5 0.0 0.0 1.0
Aug 0.0 1.0 1.0 2.0 0.0 0.8 0.0 3.5 2.7 2.5
Sep 0.5 2.0 2.0 5.0 0.0 1.9 3.0 2.5 0.6 0.0
Oct 4.0 6.0 0.5 4.0 0.0 2.9 4.0 1.1 9.8 6.9 4.0
Nov 5.0 8.5 14.0 9.5 0.0 7.4 6.5 0.0 2.0 0.0 7.0
Dec 6.5 6.5 0.0 0.0 3.5 3.3 3.5 0.2 5.0 1.7 0.0
Total Days For the Extention 1.3 15.0 9.7 26.0
Criteria
Rainfall/mm Number of Days Allowable for EOT
RF<10 0.0
10=<RF<20 0.5
20=<RF<100 1.0
100=<RF<250 2.0
250=<RF<400 3.0
Annexure-B
Delays caused by the normal rain during the extended period of the project
Affected
Days 2 0 0 1
Criteria
Rainfall/mm Number of Days Allowable for EOT
RF<10 0.0
10=<RF<20 0.5
20=<RF<100 1.0
100=<RF<250 2.0
250=<RF<400 3.0