Moblization Plan
Moblization Plan
Moblization Plan
PROJECT TITLE
KGOC – GAS & CONDENSATE EXPORT SYSTEM
ONSHORE WORKS – AL KHAFJI
PROJECT NO:
9395M-000
DOCUMENT NO:
KGOC-MOB-001
DOCUMENT TITLE:
N/A
This document contains proprietary information of SUBCONTRACTOR and is to be returned upon request. Its contents may not be copied,
disclosed to third parties, or used for other than the express purpose for which it has been provided without the written consent of
SUBCONTRACTOR
KGOC-MOB-001.PDF Page 1 of 9
SUBCONTRACT NO: 9395M-000 PAGE 2 of 9
DOCUMENT NO: KGOC-MOB-001 REV: 0
DOCUMENT TITLE: Project Mobilization Plan
PROJECT: KGOC – GAS & CONDENSATE EXPORT SYSTEM
This mobilization plan is applicable for the project titled, “KGOC – GAS & CONDENSATE
EXPORT SYSTEM”.
This document sets out the strategy for execution of construction works and the early
mobilization works on site. This will help gain valuable time and enable the early civil works
to start on site. It highlights the early project activities which would demonstrate to the
COMPANY, Contractor understanding of the project activities necessary to kick start the
project, kick start the early construction works and prepare for Manpower and Equipment
mobilization to site.
Insurance and Indemnities will be arranged from the local banks and will be submitted and
kept current throughout the duration of the project.
Since timely construction execution is the key success factor for this project, Civil work shall
be awarded to the approved subcontractor in first month of project schedule. Formal order and
approval from Contractor / Company will be regularized after the kick off meeting.
KGOC-MOB-001.PDF Page 2 of 9
SUBCONTRACT NO: 9395M-000 PAGE 3 of 9
DOCUMENT NO: KGOC-MOB-001 REV: 0
DOCUMENT TITLE: Project Mobilization Plan
PROJECT: KGOC – GAS & CONDENSATE EXPORT SYSTEM
Contractor understands that the Letter of Assistance duly signed by Contractor / COMPANY
is required to procure security passes for people and equipment. Manpower and Equipment
deployment schedules are being finalized at the moment and Letter of Assistance will be
duly requested from the COMPANY.
Contractor will have sufficient Job Performers duly trained and certified by COMPANY and will
interact with the Operational / Control Section Managers for securing the Work Permit on a
daily basis.
Subcontractor will interact with Contractor/COMPANY for a handover of the actual brown field site
with appropriate benchmarks / boundaries and reference datums as per the layout plan for the
project. The Benchmarks / Reference Datums from Contractor/COMPANY will be marked
and verified against those in reference drawings. These will be maintained and protected
throughout the duration of the project.
KGOC-MOB-001.PDF Page 3 of 9
SUBCONTRACT NO: 9395M-000 PAGE 4 of 9
DOCUMENT NO: KGOC-MOB-001 REV: 0
DOCUMENT TITLE: Project Mobilization Plan
PROJECT: KGOC – GAS & CONDENSATE EXPORT SYSTEM
It is essential that the establishment of the objectives and responsibilities take place as early
as possible after contract award. Target would intend to meet with the client’s team to:
The kick-off meeting will assist in the formation of the working principles to be adopted by the
TARGET team. The meeting will align the teams and develop working principles to ensure that
the project is carried out in an efficient and cost effective manner
To improve better coordination single point contact with project team shall be established
and the Project Manger will be the person authorized for all official communications
It shall be ensured that all relevant personnel are aware of the project requirement
and their responsibility.
Subcontractor quality plan and coordination procedure shall be established which described
coordination with Contractor in detailed.
As can be seen from the project hierarchy, the Project Manager is the focal point of
subcontract for the subcontractor. The Project Manager reports to the Project Sponsor of the
Division who reports to the Executive Management of Target Engineering. The Project Manager
is independent and is responsible for the techno commercial issues of the project.
KGOC-MOB-001.PDF Page 4 of 9
SUBCONTRACT NO: 9395M-000 PAGE 5 of 9
DOCUMENT NO: KGOC-MOB-001 REV: 0
DOCUMENT TITLE: Project Mobilization Plan
PROJECT: KGOC – GAS & CONDENSATE EXPORT SYSTEM
Manpower resources as attached in our Technical offer shows the manpower deployment
schedule. This will be further reviewed and reissued once more details are known and
activities are started. We understand that all the manpower planned to be deployed have
to have the Oil Field Security Pass and have to have the induction training completed.
List of construction equipment as attached in our Technical offer shows the Equipment
deployment schedule. This will be further reviewed and reissued once more details are
known and activities are started. We understand that all the equipment planned to be
deployed must have the Oil Field Security Pass / HSE.
The Quality Management System (QMS) for the project will be in accordance with ISO
9001:2008. The QMS which will be documented by means of a Project Quality Plan and will
provide systematic and planned control of all quality related activities during procurement,
fabrication, construction (including pre-commissioning) and commissioning up to Final
Acceptance.
A dedicated QA/QC manager will be provided for the project together with his team of
disciplines wise QC Supervisors & Inspectors. The QA/QC organization will be independent
of construction and will functionally report to Corporate QA/QC Manager, while
administrative reporting will be to the Project Manager based on site.
The objective of the QMS will be to provide for Quality at every stage of the project.
Subcontractor will carry out a full criticality assessment exercise on every discipline area /
system to enable individual minimum quality program / control to be implemented during
the procurement and construction activities for each level of criticality.
The Quality Plan amongst other requirements calls for scheduled internal audits, corrective
and preventive actions, control of documents and records and management reviews of the
QMS on a quarterly basis, offering an effective mechanism for ensuring adequacy,
compliance and improvements based on the ISO 9004:2009.
KGOC-MOB-001.PDF Page 5 of 9
SUBCONTRACT NO: 9395M-000 PAGE 6 of 9
DOCUMENT NO: KGOC-MOB-001 REV: 0
DOCUMENT TITLE: Project Mobilization Plan
PROJECT: KGOC – GAS & CONDENSATE EXPORT SYSTEM
The Quality Plan will address the all the requirements of the ISO 9001 : 2008 standard and
will include -
• Project Specific Quality Policy• Narrative description of how contractor will satisfy
the requirements of ISO 9001:2008 for each stage of the design, procurement ,
construction and commissioning
• Key Performance Indicators / Objectives for the project
• Project Organization & Key Personnel Responsibilities
• List of Project Specific Procedures especially :
All Vendors and Subcontractors will be subjected to an assessment / review before being
submitted for Contractor approval. They will be obligated by Purchase Order / Subcontract
Agreement to comply with the approved Quality Plan for the project and to comply with
back to back requirements with the Subcontract Agreement, Specification including Quality
Management System.
All vendors/ subcontractors project related documentation including procedures and drawings
and quality related documentation will be reviewed by Subcontractor before onward submission
to Contractor/COMPANY.
KGOC-MOB-001.PDF Page 6 of 9
SUBCONTRACT NO: 9395M-000 PAGE 7 of 9
DOCUMENT NO: KGOC-MOB-001 REV: 0
DOCUMENT TITLE: Project Mobilization Plan
PROJECT: KGOC – GAS & CONDENSATE EXPORT SYSTEM
The Health, Safety & Environment Management System (HSEMS) for the project will be
in accordance with COMPANY HSE Management System of COMPANY and compatible
with the ISO 14001:2009 Environmental Management System standard.
The HSE MS which will be documented by means of a Project HSE Plan and will provide
systematic and planned control of all health, safety and environment related activities during
procurement, fabrication, construction (including pre-commissioning) and commissioning
activities including handover.
The objective of the HSE MS will be to ensure risks are identified and control measures are in
place throughout the project stages of Procurement, Construction, Inspection and Testing and
Handover. It also aims at achieving a defect free facility with health, safety and environmental
aspects designed into the facility offering ease and safety of operations, maintenance, and
access throughout the life of the facility. The other objective is to meet the requirements of the
HSE Policy of the project and to reduce the HSE risks to the PROJECT, EXISTING FACILTIES,
and the people involved in construction at all phases and during operations demonstrably to
a level that is As Low as Reasonably Practical (ALARP).
Subcontractor will -
• Commit to meet defined, measurable HSE targets (to be agreed with Contractor)
• Comply with all applicable laws and regulations and apply internationally recognized
standards where local laws and regulations do not exist.
• Hold all levels of line management accountable for HSE issues and for the development
of positive attitudes in themselves and those whom they supervise.
KGOC-MOB-001.PDF Page 7 of 9
SUBCONTRACT NO: 9395M-000 PAGE 8 of 9
DOCUMENT NO: KGOC-MOB-001 REV: 0
DOCUMENT TITLE: Project Mobilization Plan
PROJECT: KGOC – GAS & CONDENSATE EXPORT SYSTEM
All Subcontractor employees involved in the project will comply with the HSE requirements of
the project documented by the HSE Plan, project specific policies and procedures by
Subcontractor and that of the CONTRACTOR / COMPANY.
KGOC-MOB-001.PDF Page 8 of 9
SUBCONTRACT NO: 9395M-000 PAGE 9 of 9
DOCUMENT NO: KGOC-MOB-001 REV: 0
DOCUMENT TITLE: Project Mobilization Plan
PROJECT: KGOC – GAS & CONDENSATE EXPORT SYSTEM
KGOC-MOB-001.PDF Page 9 of 9