01 Integrity Management of CRA Pipelines - 20 December 2015 PDF
01 Integrity Management of CRA Pipelines - 20 December 2015 PDF
01 Integrity Management of CRA Pipelines - 20 December 2015 PDF
2015
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
Foreword
Although CRA materials are selected for their increased resistance to degradation in certain operating
environments, Operators have suffered compromised integrity, and in some cases failures, of CRA pipelines.
This has been verified through discussions within the Pipeline Operators Forum (POF) and wider subsea,
pipelines and corrosion communities.
CRA materials have the potential for great engineering value as a barrier to corrosion threats which can
otherwise dominate the risk profile of a pipeline; however, the current state remains that for all existing and
proposed CRA pipelines, there is a need for greater understanding of the whole life-cycle requirements with
regards to Integrity Management to ensure that these pipelines remain fit-for-purpose.
POF with this document aims to share experiences from member Operators and other contributing Companies
(e.g. inspection service providers) in order to assist colleagues within the pipeline community by highlighting
some of the key issues that need to be considered whilst developing Integrity Management Plans for CRA
pipelines.
This document has been reviewed and approved by the Pipeline Operator Forum (POF). It is stated however,
that neither the members of the POF nor the Companies they represent can be held responsible for the fitness
for purpose, completeness, accuracy and/or application of the contents of this document.
- 2 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
Acknowledgement
The Pipeline Operators Forum (POF) would like to thank BP Exploration, Shell, Petrobras, ExxonMobil, Statoil,
Total and ConocoPhillips for their cooperation in sharing best practices, lessons learned and for providing the
draft version of these Guidance Notes to the POF for further development and circulation. POF would also like
to thank GE, NDT, Quest Integrity and Halfwave for their review and technical input to section 9.
Photographs used in this Guidance Note have been provided by and are used with permission from a number
of sources.
- 3 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
Table of Contents
Foreword .....................................................................................................................................2
Acknowledgement ......................................................................................................................3
1 Scope ...............................................................................................................................5
2 Introduction ....................................................................................................................6
3 List of Acronyms ..............................................................................................................7
4 Integrity Management ....................................................................................................8
4.1 CRA Threats .............................................................................................................................. 8
4.2 Integrity Management Plan ...................................................................................................... 9
5 Design............................................................................................................................10
6 Pipe manufacture..........................................................................................................11
6.1 Manufacturing Processes ....................................................................................................... 11
6.2 QC/QA applied during pipe fabrication .................................................................................. 11
6.3 Cleanliness Requirements ...................................................................................................... 12
- 4 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
1 Scope
This document captures challenges that operating companies have experienced whilst managing the integrity
of CRA pipelines within the oil and gas industry. The main input has been from subsea (flowlines and risers) and
onshore pipelines but, where appropriate, information relating to process piping in topside or production units
has also been included.
Each pipeline operating company will have practices and procedures for developing pipeline integrity
management plans. The document is provided to assist in the development of these plans for CRA pipelines by
raising awareness of issues that can impact the integrity of the pipeline and the ability to manage the integrity
throughout the life of the pipeline.
This document is based on CRA materials for which experience has been gained in operating environments.
Typical examples are 13Cr, 316 SS, Alloy 625, Alloy 825, Duplex and Superduplex stainless steel, but the lessons
learnt can be applied to other CRA materials. The pipeline may be of solid CRA or a carbon steel carrier pipe
with CRA cladding or liner.
- 5 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
2 Introduction
Pipelines using Corrosion Resistant Alloy (CRA) materials are not common, due largely to the cost, but they are
increasing in number and length throughout the world and, although this is a maturing technology, there are
still some issues and concerns that Operators face during the operational life of these pipelines. The advantage
they offer with regard to corrosion resistance means they are now becoming more popular. Production fluids
often contain a high sulphur or CO2 content that requires the use of materials suitable for corrosive
environments. When the H2S and CO2 contents are too high for the corrosion resistance properties of carbon
steel, a CRA is often employed.
Pipelines may be of solid CRA material like e.g. 13 Chrome, Duplex Stainless Steel or Super Duplex Stainless
Steel. For onshore and offshore pipelines however, that need to achieve a balance between cost, the
mechanical properties of a CMn tube steel and the corrosion resistance properties of a CRA, clad or lined pipes
can be used. Both clad and lined pipes consist of a carbon steel pipe which has a layer of CRA in contact with
the production fluid and hence, its corrosive environment. In the case of clad pipes, the layer of CRA is applied
using different procedures that create a metallurgical bond, while in the case of lined pipe an internal CRA pipe
is connected to the external carbon steel pipe through mechanical bond.
During recent years intensive research effort has been carried out by companies and research institutions
worldwide and more information is now available regarding some stages of a CRA pipeline life, mainly design
and installation. However, limited information is available about the integrity management challenges that
Operators have faced throughout the life of a CRA pipeline. In order to contribute to fill in these gaps, POF has
conducted a survey among its members trying to identify the main issues Operators face and how they deal
with them during the full life cycle of the CRA pipelines, i.e. from design, fabrication, installation and
commissioning A questionnaire survey was conducted so that all information presented here is based mainly in
actual field experience (field proven solutions).
This document consolidates good practices and experiences from contributing Operators in order that these
may be considered by others whilst establishing Integrity Management Strategies for their CRA risers and
pipelines. The document considers the full life cycle i.e. from design, pipe fabrication, construction, installation,
commissioning, operation and decommissioning, in order to highlight potential threats and, where appropriate,
indicate possible mitigation measures to prevent impacts on the integrity of the pipeline system.
Material selection and fabrication procedures are important aspects of oil and gas production system design. If
non-suitable materials and/or fabrication procedures are selected, then premature failure may result with
potential safety and environmental damage implications , lost production and considerable costs of line repair
and/or replacement. This guidance does not cover the selection of materials or the preparation of fabrication
procedures other than to highlight the potential failure mechanisms that can have impact on the integrity of
the pipeline during operations. The selection of the CRA material appropriate for the process conditions and
the preparation of the fabrication and installation procedures require specialist knowledge and expertise.
The use of CRA materials introduces specific challenges during all stages of the pipeline life cycle from design to
operational aspects like integrity monitoring and inspection during operation. These are highlighted within this
document.
This document does not replace the need for SMEs from the pipeline Operator, or on behalf of them, to be
involved throughout all stages of the pipeline life cycle to gain assurance that the appropriate Integrity
Management Strategy is implemented and that the required levels of inspection, testing and certification are
completed.
- 6 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
3 List of Acronyms
For the purpose of this document report, the following acronyms apply:
ART Acoustic Resonance Technology
CMn Carbon Manganese
CRA Corrosion Resistant Alloy
CS Carbon Steel
EC Eddy Current
EMAT Electro Magnetic Acoustic Technology
GW Guided Waves
HISC Hydrogen Induced Stress Cracking
ID Inside Diameter
ILI In-Line Inspection
IM Integrity Management
MEC Magnetic Eddy Current
MFL Magnetic Flux Leakage
MIC Microbiologically Influenced Corrosion
NDT Non-Destructive Testing
OD Outside Diameter
PA Phased Array
PDAM Pipeline Defect Assessment Manual
QA Quality Assurance
QC Quality Control
RT Radiographic Technology
UT Ultrasonic Testing
SCC Stress Corrosion Cracking
SCR Steel Catenary Riser
SLOFEC Saturated LOw Frequency Eddy Current
SME Subject Matter Expert
SSC Sulfide Stress Cracking
TOFD Time Of Flight Diffraction
- 7 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
4 Integrity Management
4.1 CRA Threats
The first step in the integrity management of any asset is to understand and identify all potential threats to the
asset at all stages of life. A credible threat is one that is expected to result in corrosion, erosion or
environmental cracking in the pipeline or associated components, based upon a combination of the material,
loading conditions and the environment under consideration. The deterioration of a CRA pipeline is often seen
as an unlikely event since designers, installation companies and Operators tend to consider that these
materials have superior metallurgical properties and are able to withstand any eventual threat. This is
obviously not the case, since Operators have experienced issues with CRA pipelines. Whilst the use of CRA
provides increased resistance to corrosion over carbon steel, CRA pipelines can be susceptible to degradation
and therefore a detailed pipeline integrity management plan is still required. Potential threats to CRA include
but may not be limited to:
Chloride Pitting Corrosion
Hydrogen Induced Stress Cracking (HISC)
Sulphide Stress Cracking (SSC)
Stress Corrosion Cracking (SCC)
Pitting Corrosion
Crevice Corrosion
Galvanic Corrosion
Chloride Stress Corrosion Cracking
Microbiologically Influenced Corrosion (MIC)
Erosion
Abrasion
Fatigue
Both erosion and corrosion (mainly pitting) and fatigue cracking, more specifically in SCR and in flowline free
spans, are possible threats to CRA lines. Additional threats to CRA lines include sea water corrosion (as part of
construction or pre-commissioning processes) and pipe wall erosion as a result of changes in the operating
conditions (temperature, chloride, reservoir performance and sand) and/or incorrect use of the material. CRA’s
may have an increased resistance to MIC’s, however, MIC is still a threat to a CRA pipeline. CRA clad or lined
pipelines continue to be subject to the same external corrosion threat as for any other carbon-steel pipeline.
It is anticipated that the external corrosion mechanisms are controlled by coatings and cathodic protection.
However, the application of cathodic protection to a CRA pipeline may introduce the threat of HISC (see
example in figure 1). Criterion for protection to avoid HISC should be defined and implemented, usually
achieved by management of CP potentials. A recommended practice for duplex stainless steels is document
DNV-RP-F112: Design of duplex stainless steel subsea equipment exposed to cathodic protection.
- 8 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
Figure 1. – HISC of Super 13Cr due to exposure to seawater with cathodic protection applied
The IM Plan for each stage of the CRA pipeline life cycle should identify any potential for a defect to be
undetected. This will then feed into the IM Plan for the subsequent stage and will finally determine the extent
of inspection required to provide the assurance that the pipeline is fit for operation as well as the proper
adjustment to IM Strategy. Therefore IMP for CRA pipeline operation should consider all defects that have
been identified during the previous stages, the remedial actions that have been performed, the potential
defects that may have been undetected together, and any defects that may be introduced during operation.
It is important that the QA/QC activities performed at each stage is appropriate for the potential defect
morphology or threat associated with the particular risk. High levels of QA/QC during pipe fabrication, pipeline
construction, installation and commissioning are required to ensure that defects are not introduced in to the
pipeline that is to be put in to operation. The significance on monitoring the integrity of the CRA throughout all
project stages is not always well defined in project procedures or standards and the implications to the future
integrity of the pipeline is not always well understood.
If a CRA pipeline is outside the fluid service limits set for that particular material, then the pipeline may be
subject to corrosion and/or cracking. If these should occur, the failure mechanism may progress very rapidly
although this is not always the case. The significance of monitoring the critical process conditions is not always
well defined in operations procedures or IM strategies. This should be reviewed as part of the wider pipeline
revalidation program.
As any other equipment, CRA pipelines are susceptible to mechanical damage. Dents may prove difficult to
assess and fix compared to carbon steel pipelines. The Pipeline Defect Assessment Manual (PDAM) does not
currently address CRA pipelines and therefore the assessment of any defects requires specialist advice.
A CRA pipeline may consist of a number of sections which may have differing design criteria (e.g. pipeline and
riser), different installation techniques (e.g. off-shore and on-shore sections), different intervention means (e.g.
diver accessible depths or not) or differing operating conditions (e.g. large temperature differential). These
differences should be considered when developing the IM Plan and, where appropriate, different plans for
different sections should be developed.
- 9 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
5 Design
During the design phase of a project the appropriate CRA will be selected to resist chemical processes and
other degradation mechanisms that may be present during the whole life of the pipeline. The chosen CRA will
have performance limits. The key barrier to prevent deterioration of the CRA during pipeline operation is in
selecting the appropriate material for the service conditions. Established Domain Diagrams, setting out the
critical process conditions, have been validated for the intended service conditions. Where these have not been
defined and validated, requalification during the design phase of a project may be required. The material
selection should always consider the latest published data and the results of any recent industry testing that
has been carried out. Consideration should include that CRA liners and cladding can reduce the effectiveness
of internal inspection techniques, such as UT and MFL, to inspect the carbon-steel substrate.
Ensuring that the pipeline conditions remain within the performance limits of the CRA is important. The design
of the process controls and monitoring systems is critical to ensuring the integrity of the CRA pipeline. Process
conditions that may require control and monitoring include but are not limited to:
Temperature
Pressure
Strain
Cl content
H2S content
CO2 content
pH level
02 content
Particulates/ Flow Rate
Biocide/Inhibitor
Produced water content
The selection of the CRA should make due consideration of the potential for the process conditions to change
during the life of the pipeline. This could be due to the change in fluids from a particular source or could be due
to potential development of a pipeline network which introduces fluids from other sources.
The design will determine whether the pipeline will be solid CRA or a carbon steel pipeline either lined or clad
with CRA. Each of these options provides differing challenges to the ability to monitor the pipeline integrity.
Manufacturing and installation factors should also be considered when determining whether a lining, cladding
or weld overlay should be used. Lined pipe is not recommended for manufacturing bends, CRA may be applied
to seamless pipe as a lining or weld overlay, however, solid alloy may need to be used for components that
cannot be easily clad or applied with weld overlay. Cladding or weld overlay with a CRA, can offer the same
corrosion resistance as a solid equivalent of the same material. However, as a cladding, or weld overlay is
typically only a few millimeters thick, it can be subject to mechanical damage through manufacture,
installation, commissioning or inspection, as well as corrosion damage during commissioning or in-service.
Unlike a solid CRA component, damage to a thin CRA cladding or a CRA weld overlay, will result in the exposure
of a carbon steel substrate, which will suffer from higher rates of corrosion than the cladding.
In the design phase the requirement for pigging needs to be assessed for both operational efficiency and
Integrity Management. It is recommended, as a base case, that CRA pipelines should be designed with pigging
capabilities. There have been instances where CRA pipelines have been designed and installed without the
facilities required to pig the pipeline but where the requirement for pigging has been identified during
operations and therefore the facilities have had to be subsequently installed. Additionally, pigging may be of
benefit for under-deposit corrosion, MIC and flow assurance.
Once the design options have been selected a key part of the design process should be to prepare the initial
pipeline IMP, to ensure that the necessary controls can be put in place to maintain the integrity of the pipeline.
This should consider the ability to monitor and inspect the pipeline, the required analyses and tests and
procedures to be utilized to assure and demonstrate the integrity of the pipeline at all stages.
- 10 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
6 Pipe manufacture
6.1 Manufacturing Processes
In the table below an overview of CRA pipe manufacturing processes, their abbreviation and applicable
codes/standards is given.
General inspection and testing requirements are described in the codes and standards as listed in Table 1. In
addition to the requirements in these documents, Operators quite often specify extra inspection activities,
specific inspection / NDT techniques or tighten acceptance criteria.
Some of the advised additional and specific inspection techniques / criteria are:
Inspection of the (accessible) clad surface for defects or surface iron contamination with the Ferroxyl
test, as per ASTM A380 (e.g. for welded overlay surfaces). It is recommended to be applied by
experienced personnel who are familiar with the limitations of this method of testing.
Inspection of coarse grained austenitic steel (girth) welds with compression wave UT probes due to
- 11 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
the coarse grain micro-structure. Compression waves are more suitable to penetrate such welds, but
applying this technology requires additional training.
For automatic UT inspection it is advised to require a signal to noise ratio of the reference signals of at
least 12 dB (signal height from reference defect > 4 x noise level height).
PMI (Positive Material Identification) of the internal CRA weld overlay material of CRA-C pipes if
possible (e.g. for 1 out of 10 pipes).
Example shown in Figure 2 is scale on the inner surface of a CRA lined section of pipe which has been produced
due to ferrous contamination during the pipe manufacturing process. Whilst this may be superficial and the
immediate impact on the integrity of the CRA minimal, the impact during operations if left untreated could be
more significant (e.g. crevice corrosion may develop) and in particular the potential for future internal
inspection of the pipeline would be compromised.
- 12 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
7.1 Welding
Welding of CRA is a key issue as it can have a serious detrimental impact on the overall performance of the CRA
and therefore the pipeline integrity. Whilst weld procedures will be prepared, and tests carried out to qualify
the procedure, there also needs to be stringent quality control during the welding processes to ensure that the
welding is completed as intended.
Quality assurance of the weld preparation is particularly critical for CRA pipelines and components. Figure 3
shows an example of the resultant corrosion following incorrect weld preparation. The preparation for the
weld had completely removed the CRA cladding adjacent to the weld area to such an extent that, following
completion of the weld, an area of exposed carbon steel remained resulting in loss of the carbon steel and a
subsequent leak.
Figure 3. – Corrosion of a weld overlay clad flange resulting from poor weld preparation
Quality control during the welding process is also critical. Figure 4 shows an example of corrosion in a CRA clad
pipeline which was caused due to the use of carbon steel for the weld root rather than a CRA consumable. This
was not identified during the execution of the weld and could not be determined by the weld inspection. The
subsequent corrosion of the weld root eventually exposed the carbon steel section of the pipe behind the
cladding. Due to a fabrication mistake all superior performance of roll bonded clad pipe was jeopardized.
- 13 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
Figure 4. – Corrosion of clad pipeline due to incorrect material used for weld root
7.2 Installation
The way in which the pipeline is installed has the potential to impact the integrity of the CRA pipeline. For
example the design of an off-shore pipeline called for snake lay (i.e. the pipeline to be installed with a zig-zag
route) to manage excessive buckling/local bending during operations. However, the post installation in line
inspection identified that the selected pipeline profile had introduced numerous minor geometrical
deformations in the CRA liner caused through localized variations in the longitudinal stress and strain. The
deformations were either wrinkles (as shown in Figure 5), circumferential deformations close to the girth welds
or individual dent-like deformations. Whilst these do not pose an immediate threat to the integrity of the
pipeline as, in this case, the liner has remained intact further assessment was required to confirm the ability of
the liner to meet the long term requirements. The deformations also impact the ability to internally inspect the
pipeline.
- 14 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
Figure 7 provides a further example of the damage caused to a 13Cr pipeline exposed to seawater during
commissioning.
- 15 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
The Operator should determine how the baseline assessment is to be achieved. For positive validation (i.e.
based on actual inspection results) that the CRA barrier is intact throughout the pipeline, then ILI is the most
appropriate technology if the tools are correctly selected and deployed under the right conditions. However
the success and outcome will be dependent on the nature of the CRA pipeline (solid, mechanically bonded or
metallurgical clad). Alternative means of assessment, such as detailed review of project QA/QC records, may
carry more uncertainty than ILI, but may be acceptable based on review and risk assessment of the integrity
management activities that have previously been completed. The nature of the baseline assessment varies
amongst companies and applications.
The timing of any baseline survey needs to be considered. Baseline surveys could be conducted prior to
operations in order to establish the condition of the pipeline prior to the introduction of hydrocarbons.
Alternatively a baseline could be conducted following a pre-determined period of operation. Some Operators
recommend baseline surveys be conducted during both periods.
CRA materials are known to be effective for well-defined operating regimes. Therefore, if the baseline
condition is known, evidence to demonstrate that operating conditions have remained within defined limits
may possibly be considered sufficient to revalidate the pipeline against internal corrosion threats.
- 16 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
When excursions outside of defined operating limits occur an assessment will be required to determine the
potential damage that could have occurred. In such instances, it may be necessary to inspect the pipeline and
therefore the Operator needs access to the appropriate inspection technology.
The IM plan set out for the pipeline may require periodic inspection of the pipeline. The inspection may be
targeted at defects in the CRA or, for lined or clad pipelines, the carbon steel or both. Inspection of the carbon
steel may highlight instances of external defects but may also highlight areas where there are breaches in the
CRA.
There is potential to damage CRA pipelines during either routine or inspection pigging operations.
Consideration should be given to both mechanical damage and metallurgical contamination. Pig discs have
been known to fail and could lead to the pig body scoring the relatively soft CRA material. This is even more
detrimental if it occurs in clad or lined pipes and exposes the carbon steel backing material. Further, care
must be taken to avoid metallurgical contamination of CRAs, such as by designing pigs with non-carbon-steel
brushes. The risk of other metallic contaminants within the flow, such as failed chokes, valve internals etc.
should also be considered.
- 17 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
CRA pipelines can be pigged, without damage. Pigs, also referred to as tools, can be designed to inspect CRA
lines without damaging liners / cladding, avoiding metal to metal contact between pig and pipeline. Risk of
pigging should be considered prior to any ILI run. Risks include damage to the CRA, potentially sticking the tool
in the line, data reliability, and other operational risks. These risks should be considered in a risk assessment
prior to any inspection campaign.
Different types of tools are available and these can be equipped with various inspection equipment:
- Free swimming tools that can cover large distances
- Tethered (cable operated) tools for shorter distances also allowing additional features
- Crawler tools
9.1.1 UT Tools
An ultrasonic pulse generated by a transmitting/receiving transducer will travel at constant speed through a
liquid and at constant, but different, speed through steel. When passing from a liquid to steel, part of the
energy in a pulse will reflect from a solid steel surface, generating a return pulse, and part will be transmitted
into the steel, resulting in an ultrasonic pulse which propagates through the steel. When passing through steel,
most of the energy in a pulse will reflect from the outer steel surface and return to the transmitter/receiver.
The time elapse between sending and receiving the ultrasonic pulses is representative for the pipe wall
thickness and location of metal loss (internal/external if present). An example is depicted in Figure 8. The
transmission of energy across a steel/gas interface or through gas to the steel surface is much less efficient
than at a liquid/steel interface, making standard UT tools ineffective in a gas environment.
- 18 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
On a flat surface, the pulses are easily identifiable as discrete entities, whereas, where they are reflected from
an uneven surface, such as an un-machined inner surface of the pipe following weld-overlay cladding, the
pulses spread out and can merge. Furthermore, there may be more than two pulses reflected by the steel wall,
which has the potential to confuse the measurement of the timing device. Where there are concerns regarding
the surface finish, the impact should, wherever possible, be confirmed by pull-through test using sample of the
actual pipe (a pipe sample of 1m length would suffice). As a general rule, surface roughness of 0.1 to 0.2mm
will not have an impact on signal quality. Figure 9 gives an example of the UT inspection result in carbon steel
pipe with weld overlay.
- 19 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
Figure 9. – UT ILI of internal metal loss in carbon steel pipe clad with Alloy 625 weld overlay
The speed of sound within a CRA material is practically similar to carbon steel and therefore, if the CRA is
metallurgically bonded to the carbon steel there will not be reflection of the UT pulse at the interface and
hence the UT tool will record the combined material as one wall thickness. However if the materials are not
metallurgically (fully) bonded as in the case of lined pipe, the energy of the UT pulse will be reflected at the
interface generating an interface echo. For lined pipe therefore, the UT tool will record the thickness of the
CRA layer only, there will be no results recorded for the carbon steel.
Free swimming and tethered tools can be equipped with UT technology for corrosion detection (wall thickness
measurement) and crack detection.
Specially developed tethered tools are available with the Time Of Flight Diffraction (TOFD) technique. These
tools can be accurately aligned to a girth weld and used to detect and size external fatigue cracks. Tools based
on TOFD technique are better than traditional UT tools with respect to sizing of small cracks whilst traditional
UT tools are better at detection of small cracks. Therefore a combination of traditional UT, for detection of
small cracks, and TOFD for sizing of small cracks can be applied.
Martensitic CRA (e.g. 13Cr) or Austenitic/Ferritic CRA (e.g. Duplex) does have some magnetic property and
therefore it is possible to inspect these CRA using an MFL tool although the performance of the tool will be
significantly different to that in carbon steel and therefore a revised performance specification will be required.
The development of the performance specification will be required on a pipeline by pipeline basis, through
testing on sample spools.
For pipelines clad or lined with austenitic CRA it is possible to inspect the carbon steel behind CRA using MFL.
The thickness of the CRA layer causes an increased distance of the magnets and sensors from the carbon steel
layer which influences the defect detection capability of the tool. The CRA causes a sensor lift-off influencing
the magnetization and therefore any defect signals. Additionally, if the CRA layer is electrically conductive then
the transient magnetic field produced by a passing MFL tool will generate eddy-currents in the CRA layer. In
turn this will produce a magnetic field in opposition to that generated by the tool. This could potentially affect
magnetic field levels in the pipe-wall as well as defect response. The thicker the CRA layer, the lower is the
- 20 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
maximum allowable carbon steel thickness. Within limits, this effect may be compensated for by running the
inspection tool at reduced velocity. Pull through tests will be required for each application to determine the
actual impact of the CRA and to develop the appropriate performance specification for the inspection tool. It is
important that these pull through tests are performed with pipe samples representing the full range of
thickness for both the CRA and the carbon steel. Figure 10 gives a detailed example of the MFL inspection
result in carbon steel pipe with 316L clad layer.
Figure 10. – Features identified during MFL inspection of carbon steel pipeline clad with 316L - Feature
dimensions confirmed by external TOFD
In addition to the issues related to the inspection of pipelines clad or lined with austenitic steel, the MFL
inspection of pipeline clad or lined with Martensitic CRA is more complicated as the CRA layer cannot be simply
treated as increased stand-off.
The sensors on an EMAT tool can be of many different types and their performance in CRA pipe will vary.
However all will have significantly reduced inspection performance due to poor electrical conductivity and low
magnetostriction in austenitic CRA compared to regular pipeline steel. Note: magnetostriction is a property of
ferromagnetic materials that causes them to change their shape or dimensions during the process of
magnetization. This poor performance can be partially overcome by systems that move slowly compared to
typical free-swimming tools and therefore allow for increased numbers of measurements using the sensors.
For magnetic stainless steels, such as Ferritic stainless, Duplex or Martensitic, the performance of the EMAT
tool increases compared to operating in the austenitic CRA steels, potentially allowing inspection of these
materials at velocities typical for free swimming tools. However, CRA alloys differ in magnetic properties so
much that tests on sample spools of the specific pipeline alloy need to be performed to confirm the
effectiveness of the sensors in advance of an inspection run.
Another factor which will affect the EMAT tool is the physical nature of the CRA within the pipeline itself. An
EMAT tool will not be able to inspect a CRA lined pipe where there is no metallurgic bond between the CRA and
the other pipe material. For a pipe which is fully composed of CRA steel, inspection should be possible subject
to the limits described above. For a pipe where carbon steel and CRA lining are metallurgically bonded, tests on
- 21 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
sample spools must be performed to ensure that the performance of the EMAT meets the desired specification
in these materials.
9.1.4 EC Tools
Eddy current tools measure metal loss features on the inner surface of the pipeline.
In principle, the eddy current inspection technology is applicable to CRA as the required material property is its
electrical conductivity. However, the response of the inspection tool will differ from that in carbon steel.
Therefore prior to any inspection of a pipeline containing CRA pull tests will be required to determine the
actual performance of the tool.
ART is not dependent on a liquid coupler and hence it can be used in gas pipelines however the use within low
pressure pipeline needs to be assessed.
Since ART is a relatively new technique for pipeline inspection there is limited experience in general and no
examples of use within CRA pipelines have been published. Within CRA clad/lined pipelines ART is expected to
have similar challenges as traditional UT tools which require metallurgical bonding between the CRA layer and
the carbon steel if inspection of the full wall thickness is required.
- 22 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
The three different types of CRA pipelines; solid CRA, CRA clad, CRA lined; each provide specific challenges for
the assessment.
Assessments should include the capability to provide a continued effective barrier against accelerated
corrosion in addition to mechanical integrity.
The rate of pit growth is a function of temperature, pH and the presence of chloride ions. Determining the
growth rate within CRA pipelines can be complex.
POF has not been able to identify any experience of repairing CRA lined or clad pipelines. This should be
addressed in the design phase.
- 23 -
Integrity Management of CRA Pipelines
Operator Experiences and Inspection Challenges – 2015
11 Final Remarks
CRA materials have been selected for severe operating conditions due to their increased corrosion resistance
when compared to carbon steel pipes. However, to take advantage of its superior metallurgical performance
it's paramount to assure high quality levels and commitment in all stages of pipeline life cycle (e.g. material
selection, design, pipe fabrication, construction, operation, etc.). When this is not the case some failures may
occur. Because of this, and also due to potential challenges that ILI inspection tools for CRA material still face,
it's extremely relevant that additional care must be taken during design, fabrication and installation of CRA
pipelines in order to avoid potential threats into the pipeline once it is put in place.
Continued dialogue and use of best practices will continue to help improve the understanding and practice of
integrity management of CRA pipelines and will help reduce operational risks for Operators. Regular review of
the contents of this document together with root cause analysis and lessons learnt from any related pipeline
incidents is recommended.
This document highlights some of the issues to be considered whilst developing plans to manage the integrity
of CRA pipelines during manufacturing, fabrication, installation and operations. The use of structured
inspection, maintenance and repair regimes together with the management and monitoring of operating
conditions will minimise the potential for the deterioration of CRA pipelines and the potential for pipeline
failure.
- 24 -