Construction Cost Data Workbook
Construction Cost Data Workbook
0
COLLECTION OF CONSTRUCTION COST DATA
Introduction
DMS International, Inc. was requested to assist the World Bank with creating a
method of collecting construction cost data from member countries throughout the world
to assist with economic studies. The task of data collection is a difficult procedure and
can be prone to wide variations. Based upon our experience as construction cost
method based upon a workbook format. Our workbook defines construction line items
and quantities for relativity simple building types. In fact, four building types have been
chosen:
Residential house
Warehouse
Road
Office building
collected and analyzed by the World Bank as part of its overall economic study.
Before we explain further about our workbook format and design, reference must
be made to previous studies and methods of construction cost data collection. One
comprehensive review of past practices has been completed by Dubner and McKenzie 1.
1
This detailed study compares various methods and documents the advantages and
disadvantages of each method. The method that provides the best opportunity for data
collection was noted as the Bills of Quantity (BOQ) method. This method appears to
have advantages over the other methods but yet even with the BOQ method some
make up the total project. The project may be an office building or a warehouse. The
BOQ documents quantities for each element of the building type such as cubic meters
frequently to assist in developing tenders or bids for projects throughout the world. The
Once the quantity of concrete footing is known a unit price to cover for material, labor
and equipment is applied to develop the cost of each line item or component. The total
project is basically a summation of all the individual line items. Various levels of
sophistication in terms of measurement detail and description exist with BOQ’s but the
same principals apply. The paper prepared by Dubner and McKenzie1, suggests that
the BOQ method offers the best opportunity for data collection, though they suggest
issues that must be dealt with to allow data collection to prove more successful than in
Interpretation of specifications
Over sophistication and requirement to price detail project work break downs
2
Silke Stapel2 also highlights various issues with cost data collection along the similar
actually performed data collection on behalf of EU member states. Part of the Eurostat
Stapel 2 along similar lines as Dubner and McKenzie 1 noted some issues such as:
system
It would appear that the Eurostat data applies to advanced Countries in terms of
prices for about 15 Bills of Quantities. The typical Bills of Quantities could have up to
A Modified Approach
Line items are simple and comprise basic building materials common to most
3
Quantities and line items reflect approximate quantities according to a trade
specialty.
Projects chosen offer little complexity that would impact construction means and
methods. The projects provide materials used in nearly all construction projects
such as concrete, steel, wood, and plumbing piping, irrespective of what country
Projects chosen are easy to understand allowing the estimator to grasp the
Project content provides for the basic construction products used extensively in
any project. This limits the specification issues that provide inconsistency among
different Countries. Basic materials such as concrete are relatively similar from
Country to Country.
Designs chosen offer little complexity for pricing purposes. If the material or
component is not widely used then an opportunity exists for each individual
estimator to customize pricing based upon best local practices. This will occur to
some limited extent from Country to Country but as long as a substitute of equal
Project site work and substructures are quantified therefore minimizing project
4
Outline specifications provided show basic specifications that allow the estimator
It’s accepted that the workbook could and should only be completed by someone
inexperienced estimators would only add to the potential for erroneous data. By
keeping the models and format basic by design the chances of greater overall success
will exist. A person experienced in estimating construction costs should have little
problem working through the workbook and creating a complete price for each project.
The probability of success with the collection of cost data must be viewed in two
parts. Part one being the design and format of the actual workbook and part two being
the expertise of the person completing the workbook exercise. It would be rather foolish
estimates. The success of the workbook format will only exist if the data is priced by
3
qualified individuals. Even with qualified individuals variations will occur. Sinclair
found that even qualified estimators would not produce equal estimates given the same
information from which to create an estimate. The balance of this paper identifies this
“estimating” problem to allow the perceived problems of collecting data via workbooks to
be put totally into perspective. The author of this paper agrues that perfection of data
5
The Estimating Problem
How does an estimator estimate the cost of a construction project? For those
reader’s not familiar with cost estimating, the process involved is complex. Learning
about cost estimating will help non-cost-estimators understand what is involved and
what limitations exist when reviewing cost data generated by cost estimators.
Figure 1.1 illustrates subjective estimates attempting to hit the target, which is the actual
cost. The subjective value chosen by each estimator was considered to represent the
see that the estimates are all scattered around the target of actual cost. Hitting the
6
3. Cost of labor
There may be many or only a few work methods available. For instance, should
bricklayer with either one or two laborers? Will there be central mortar mixing or
individual mixers for each crew? How will the brickwork be constructed? Will trestles or
proper standing scaffolding be used? Where will work commence from? What
All possibilities must be investigated, and the most economical possibility should
be chosen.
The output chosen will be based on past performance, since the estimator will
assume that this performance will be repeated in the future. As will be explained later,
recording and properly documenting job site performance is helpful to the estimator
when he or she considers future projects. Manipulation of these historical data may
occur; for example, decreasing output to allow for restricted working condition.
Whatever manipulation occurs, the estimator is faced with the difficulty of trying to
7
Problem 3- Cost of labor
How much will the contractor be required to pay for labor? The estimator must
predict this cost. The labor cost will vary depending on job location, availability of skilled
labor, contract wage regulations, union or open shop labor requirements, general
This can be predicted with a fair degree of accuracy if the material in question is
in ready supply and is frequently purchased. The quantity of material required must be
accurately measured from the drawing and is not dependent on the crew performance
or work method adopted. Although the estimator must not only consider the finished in
-place quantity of material, but also must allow for a wastage factor, this factor can vary
dramatically and is highly dependent on the performance and work procedures adopted
by the crew.
This amount will depend on company policy, market condition, and many other
variables that will be discussed later. It is, as you can imagine, very important to
Problems 1-5 have been presented simply, but you can begin to imagine their
complexity.
8
An estimator has to posses the skill and expertise to assemble the known facts and
rationally solve the estimating equation. How this is done is best explained by reference
Figure 1.3 amplifies stages 5 and 6, here the estimator selects a range of most likely
values and, after a process of fine tuning and “weighing up” of the situation, the
estimator modifies his or her initial crude selection and finally selects a value that he or
9
Fig. 1.3 Fine tuning an estimate.
The thought process previously described and shown in fig.1.2 and 1.3 applies to our
hypothetical brickwork example, but generally indicates how and estimator arrives at a
solution for each separate item of the cost estimate. A total cost estimate consists of
numerous line items and specific sections relating to various trades and specialists
Location
Since a construction project’s location affects the final cost, an estimator must
considerations should be taken into account when formulating the estimate. Estimators
are aware that costs in Boston are different that costs in Miami, but not everyone is
aware that the locational variation within the Boston area or within the Miami area also
10
influence construction costs. For example, the project location may be a restricted city
center infill site or a remote country site, each having its own particular difficulties that
1. Remoteness
2. Confined sites
3. Labor availability
4. Weather
Remoteness
A remote construction site, for example, a project site located high in the Blue
Communication Problems
project: lack of communication during the construction process can result in major,
costly errors. In addition, because the project location is further away from the head
11
Transportation Problems
All material and labor must be transported to the building site. If the transport
route is poor (if, indeed, any route exists at all), then delays in material deliveries may
occur; large vehicles may damage narrow bridges or other items of property, whose
It may be necessary for the contractor to widen the existing route or construct a
bridge to allow material trailers access into the job site. The route that is proposed
bridge needs to be strengthened by the contractor. Finally, the cost of hauling items of
equipment to the job site increases as the distance increases. Given these
when distance for haulage from the depot to a remote job site is longer than the haulage
associated with other construction projects the estimator has previously worked on.
Avery4 found that if the material was fragile or hazardous, then transport costs fluctuated
widely depending on distance. He also discovered that the bulk materials with low initial
cost, such as sand and gravel, tend to be the most adversely affected by distance and
difficult transport conditions. Ferry crossing or bridges with tolls increase the basic cost
of materials.
12
Power and Water
Power and water are a necessity for building construction. Water is needed for
materials such as concrete, for cleaning the building, and for many other uses. Salt
water is not acceptable in most specifications for concrete or mortar mixing, so remote
projects without a convenient domestic water supply, even if the site has access to
thousands of gallon of seawater; require water to be trucked to the job site. The cost of
water depends on the hauling costs. In some instances wells can be dug to pump water
to the surface; of course, the costs involved must be considered in the estimate.
Confined Sites
The problems associated with confined sites generally take the form of
congestion resulting in restricted working areas resulting in low productivity from labor
and equipment. These difficulties are generally associated with downtown sites, but this
In extreme cases, congestion can limit the choice of work methods, types of
problems likely to be associated with each particular site will allow a realistic
minimized: each time an item of material is moved, its cost to install in place increases.
When materials are delivered to a confined site, the material should be used
13
immediately. If this is not possible, a storage area should be available to receive the
material, or, if possible, the material should be offloaded directly at its intended
utilization point.
The estimator needs to consider the unique logistical problems associated with
each job site. These problems, including restricted access, restricted material lay down
area, restricted equipment storage areas, and restricted location for site trailers, affect
the type of equipment that can be used, the effective management of the job, the worker
productivity, and the amount of labor involved in handling material. Since confined sites
nearly always pose logistical problems, the unit prices used by the estimator must
Labor Availability
Each location has varying amount of available skilled and unskilled labor,
depending on the condition of the local economy. If labor of any kind is not available
locally (as may be the case in remote areas), then labor must be imported from other
location. In order to move labor from one area to another, a financial incentive is usually
required. The magnitude of this incentive will vary depending on the state of the labor
comprising full time kitchen staff, dormitories, leisure facilities, etc., have been set up on
major construction project to house the contractor’s labor force. The leisure facilities
keep the labor force relaxed and occupied during any rest periods. Living and working
on a remote construction site can be very demoralizing, after a while, and by keeping
14
the morale level high, labor turnover is reduced. Generally, the cost of importing labor
Weather
Since the building process is highly weather dependent, extreme conditions can
greatly affect building costs. These extreme weather conditions include large amount of
rain or snow, occurrences of ice and frost, and high humidity and heat. Their effects on
cost include the following situation. Concrete pours in temperatures below 40 degrees
Fahrenheit require special precaution. With cold weather concreting, the cost of
admixtures, insulation the formwork, removing ice from formwork, and protecting the
freshly placed concrete from dropping below the specified temperatures must be taken
in to account by the estimator. Not only does cold weather affect concrete, but hot
weather concreting has its associated problems as well. During periods when the
and maintain the concrete below this temperature. For example, ingredients such as
the water may be cooled or chopped ice can be utilized. Another alternative is to use
liquid nitrogen to cool the concrete. Admixtures and low heat cement can be used to
control the set and hardening times of the concrete to achieve the design strength and
quality. All these precautions and procedures increase the cost of pouring, placing, and
curing concrete.
Exposed sites may have problems associated with high winds, which affect crane
and hoisting operations, and the contractor’s dust control program. Additional
15
due to high wind gusts. In areas where hurricanes occur, the estimator should consider
during, and after a hurricane. It would be prudent to allow for the costs involved in
bracing, tieing down structures providing sand banks, garaging equipment, and storing
particular materials such as doors and windows off the job site, unless safe, dry, and
Labor productivity is also associated with the weather. During poor weather
when it is cold, damp, and windy, the morale of workers exposed to adverse elements,
drops, which in turn results in a decline of productivity. During days when it may be
designer. For example, in historic Frederick, Maryland, all designs must harmonize with
the existing historical buildings. Planning committees may dictate the material
selections and configurations that designers must abide by to suit certain local
conditions.
The estimator must know if the materials specified are, in fact, locally available of if local
labor exists to carry out complicated historical work, such as ornate plaster work; if not,
intensive. If the same techniques must be repeated, then the estimator must be familiar
with the procedures involved. If workers are required to use traditional, building methods
16
with which they are unfamiliar, then a learning curve cost needs to be built into any unit
price.
The local climate also dictates the designer’s choices in mechanical and
electrical systems and in the choice of materials and design of the building envelope.
Material resources will fluctuate from location to location throughout the country, and the
designer must investigate what materials are locally and economically available.
Finally, each locality tends to have its own construction trade practices, and the
expensive, for example, when 24-hour guard service and perimeter enclosures, are
required. The level of security will depend on the risk to the project from the
Variability of Estimates
The following are where cost variances between one estimate and another can
occur:
2. Material Costs.
3. Labor Costs.
5. Work Methods.
17
6. Construction equipment costs.
8. Subcontractor quotations.
12. Cost associated with the time element of the construction project and escalation
costs.
14. Overheads.
Wendes5, commenting on the estimating ability of estimators lists the following points
3. “Okay” with subcontractor quotes if they are familiar with the work; “bomb out” if they
are unfamiliar.
18
4. At the “high school level” with their quantity take offs.
is a forecast of the anticipated future cost. Many forces can, in reality, cause the actual
cost to vary from the estimated cost. It sometimes appears to owners and management
that, when the estimate does not equal the actual costs, a mistake has been made.
Because it is an estimate, it should always be expected that the actual cost will vary
somewhat from the estimated cost. It is the job of the estimator to minimize the extent
of variance between estimate and actual cost. Any data collection system must be able
As previously discussed, the author believes that there are 19 major areas where
differences between cost estimates can exist. When compiling the cost estimate, each
of the 19 categories has to be dealt with by the estimator. In dealing with each
category, the estimator has to make several assessments, such as what subcontractor
price for drywall should be used in the cost estimate or what labor productivity shall be
used for the carpenters installing intricate millwork. The total cost estimate is made up
19
of numerous smaller cost estimates for each activity required to complete the overall
estimator has to assess and propose a monetary solution. The total cost estimate is the
Hunches.
The final assessment is subjective. The estimator will decide what productivity to allow,
or what dollar allowance or unit price to use. Even though the estimator has consulted
when compiling his or her estimate, it is the estimator who will decide what value will be
used in the estimate. This subjective act is the main reason why estimates vary. If you
give identical drawings and specifications to 100 estimators, you will get 100 different
cost estimates.
20
Fig. 1.4 Basic reasons for variances being introduced into cost estimates – the subjective assessment.
Historical Data
with their attendant advantages and disadvantages. There are some rules to be
Always understand fully how to update and project the historical data to the
present time.
project, since no
21
Always be wary of working with historical data that you are not familiar with.
Various sources of historical data are available, such as published price books,
cost information publication services, trade journals, and, most important, cost feedback
from actual projects that the estimators firm has been involved with and therefore most
knowledgeable of.
Actual cost feedback is the best information to use if it were recorded and
documented properly. The feedback cycle (see Fig 1.5) is of critical importance. In
order for estimating to be effective, feedback from the job site must occur. Actual costs
should be compared with estimated costs to inform the estimator of his or her
performance during the estimating phase. Unfortunately, the feedback process is not
carried out effectively within the industry. To quote the Business Round Table Report on
not consistently used to review and adjust the basis for estimating future projects.”
22
Fig. 1.5 Company cost feedback cycle.
cost data of similar work previously performed. The cost data, if proper feedback
procedures have been adopted, will have been refined over time to reflect accurate
costs for performing certain operations. The estimator can use these data to formulate
estimates accurately for future work. If the data to formulate are incorrectly used or
accuracy impossible. However within the limits of achievable accuracy, it can be stated
that the greater the accuracy, the higher the cost of achieving that accuracy. There is
usually a point beyond which the cost in increasing and estimate’s accuracy is greater
Figure 1.6 indicates the accuracy versus economy dilemma. As more of the
estimator’s time and effort are devoted to the preparation of the cost estimate, a point is
reached where obtaining the utmost accuracy is not economical. As we have discussed
23
Fig. 1.6 Estimating time required for a $2,000,000 building (© R.S. Means, Inc., 100 Construction Plaza,
Kingston, MA, reproduced from Mechanical and Electrical Estimating Workbook.)
Figure 1.7 indicates the general accuracy that is expected by employing varying
24
The Pareto Distribution in Estimates
The estimator will price (or at least consider) each item he has discovered, such
as cubic quantity of concrete footings, walls or slabs. These items may be in the form of
a detailed quantity take off or some other form sufficiently detailed to enable confident
estimating to occur.
Each of the items discovered by the estimator has a cost importance that varies
in magnitude. Some items are of more cost importance than others, since they form a
larger percentage of the total cost than the minor items do. The Pareto 1 effect is seen to
occur, that is, a small proportion of the items account for a very large proportion of the
cost. Investigation into the cost structure of items in Bills of Quantities by Brown 8 has
shown that, typically, 20% of the items priced contained at least 80% of the total cost.
Fig. 1.8 Pareto principle applied to estimating. (Reprinted from R. Brown, Investigating into the Feasibility
of Applying the Pareto Principle to SMM Bills of Quantities of Cost Planning, Project Report,
Loughborough University, UK.)
1
At the end of the 19th century an Italian economist, Vilfredo Pareto, developed a curve known as “Pareto’s Law of
Distribution.”
25
The Pareto effect can be used to great advantage by applying strict control over
the major items; the chance of major errors and discrepancies occurring is therefore
reduced. Owing to the time constraints involved with preparing a competitive bid, the
Pareto effect should be taken advantage of. Estimators should be quick to recognize
what the major items of cost importance are and devote attention to these items. When
faced with abnormal conditions, the search for the critical items of cost may take longer,
but the Pareto principle should still apply. Both Dubner and McKenzie 1 and Stapel2
recognized this aspect with current BOQ methods. We have attempted to provide
concise and specific line items in the modified work book approach to accomplish major
It has been noted that wide variances do occur between estimates. If 100
estimators prepared an estimate for the same project using identical drawings and
the bottom line of the estimates would be within an acceptable range of some +/- 10%
of each other. This is often the case when contractors submit bids for projects. The
bids submitted by the majority of bidders are quite often very close to each other.
Though, when examination of the bidders estimates occur, the cost difference between
each of the trades differ greatly (up to 25%) and when examination of the cost to
complete each activity within each of the trades occurs, the cost differences between
each bidders numbers can be as much as 50%. The degree of difference between
estimates will therefore differ depending on whether you are examining the bottom lines,
the trade amounts, or the cost of activities within each trade. Greater variances within
estimates occur when uncertainty exists, such as in excavation work. Our workbook
26
format excludes site work and varying site related features thus eliminating an area of
major uncertainty.
Conclusions
The modified workbook approach attempts to simplify yet increase the quality of
information received through cost data collection methods. It’s agreed by both Stapel 2
and Dubner and McKenzie1 that the preferred tool is the Bills of Quantity Method. Our
workbook format is based upon abbreviated Bills of Quantities that provide a consistent
set of line items that can be priced without difficulty by a local estimator qualified in
construction cost estimating. The line items proposed can provide information on
These levels of information can be used to formulate “basket” of data that could be
analyzed even further. Merging of the Basket of Goods Collection Method and the Bills
of Quantity Method is possible given the simplified format of the modified workbook
approach.
27
References:
1
Dubner and McKenzie, Australian Bureau of Statistics paper submitted to
2002).
3 D. Neil Sinclair, Estimating for Abnormal Conditions, Industrial Press, Inc., New
in Building Cost Techniques, edited by P.F. Brandon, E.F.N. Spon Ltd., New York,
University, UK.
28
The Promoters and Directors have raised the initial funds on their own and to start
the Project of the company. The promoters are High Net worth Individuals and
Processing Flowchart: 9 | P a g e D P R – A G R O P R O C E S S I N G
Okra, Green Peas, Red Paprika, Sweet Corn, Baby Corn, Jalepeno , Bitter Gourd,
Capsicum, French Beans etc., and Various Fruits Mangoes, Papaya, Strawberries,
Jackfruit, etc., under contract farming from the farmers. All the farmers have
around 100 acres of land in Karjat. The land is very fertile to grow all of the above
products. The Company shall provide the seeds, fertilizer and pesticides to the
farmers. The Company has entered into the agreement with all the farmers to grow
the necessary products. AAT has a confirmed buy back from the domestic and
international companies.
pepper pod type cultivar of the species Capsicum annuum. A mature jalapeño fruit
is 5–10 cm (2–4 in) long and hangs down with a round, firm, smooth flesh of 1–1.5
29
in (25–38 mm) wide. It is of mild to medium pungency, having a range of 1,000 to
while still green, it is occasionally allowed to fully ripen and turn red, orange or
yellow, and is wider and milder than the Serrano pepper. The Chile Pepper Institute
3.2. Okra The major okra producing states are Uttar Pradesh, Bihar, Orissa, West
produced from 58,400 ha with an average productivity of 11.4 mt/ha. The crop is
3.3. Green Peas Green Peas, also popularly known as “garden peas” is one of the
vegetable crops in India and basically this crop is cultivated for its green pods.
Green peas belong to Leguminaceae family. Green Peas are used in vegetable
cooking’s, in soups & frozen canned food as well. Green Pea straw is a nutritious
fodder and be used for any animal (livestock) feed. Major Green Peas Production
Assam, Haryana, Uttar Pradesh, Uttarakhand, Himachal Pradesh, Bihar and Orissa.
Some of the health benefits of Green Peas are given below. Green Peas help in
losing weight. Green Peas help in controlling blood sugar levels. Green Peas
30
Green Peas source of anti-aging, strong immune system, and high energy. Green
Peas may help in prevention of stomach cancer. Green Peas may help in
improving digestion.
3.4. Paprika Paprika is a variety of mild pepper (Capsicum annuum) that is dried,
ground and used with food either as a spice or garnish.Paprika has been used in a
dishes. In fact, paprika peppers have more vitamin C than lemon juice by
weight.They are grown much like other peppers, which means they like a well-
draining, fertile soil in a sunny area. Provided that you live in a warm climate, you
3.5. Sweet Corn Corn (maize) is native to America and has been cultivated in
Central America since 3500 BC.Corn is classified as sweet, pop, flour, silage, or
feed corn, depending on the type of carbohydrate stored in the ear. Sweet corn gets
its name from special genes that prevent or retard the normal conversion of sugar
3.6. Baby Corn Introduction of Baby Corn Baby Corn maize is one of the valued
baby corn? It is nothing but “cobs removed within 4 to 5 days after their
31
emergence”. Baby corn cultivation or methods are similar to regular commercial
maize cultivation practices. The only difference is the harvesting period or duration
of the crop. Baby corn crop duration is about 2 months whereas regular corn/maize
curries, pickles, pulav, soups, salads and snacks. Baby corn is rich in ber and
Baby corn has low glycemic index than regular corn. Hence good for controlling
blood sugar levels. Climate Requirement for Baby Corn Farming:- Baby corn crop
requires good sunlight with temperature range of 22°C to 28°C for optimal growth.
This crop does not grow well in high temperature regions exceeding
30°C.However there are baby corn varieties developed for low chilling areas.
Improved Varieties of Baby Corn in India: – There are some improved baby corn
varieties developed for good yield and short duration. Prakash, Vivek Maize
Hybrid 23,COBC 1, Vivek Maize Hybrid 25, HM-4, HIM 129,Hybrid maize 5,
32
Pusa Extra Early Hybrid maize 5, DHM 109, MTH-14, RCM 1-1,VL Makka 42,
RCM 1-3, MLY & Golden baby. Climate Requirement for Baby Corn Farming:-
Baby corn crop requires good sunlight with temperature range of 22°C to 28°C for
optimal growth. This crop does not grow well in high temperature regions
exceeding 30°C.However there are baby corn varieties developed for low chilling
areas.
3.7. Bitter Gourd Bitter gourd is one of the most popular vegetable in India. It is
grown extensively throughout India; the bitter gourd has good medicinal value as
(Hybrid), ArkaHarit, Priya and Preethi are mainly cultivated. Climate of Bitter
Gourd Farming - Mainly a warm season plant, bitter gourd thrives in hot and
humid climates. Best Soil for Bitter Gourd Farming - The best medium for the
seeds is a fertile, welldrained soil with a pH ranging from 5.5 to 6.7, enriched with
organic matter, such as compost or dried manure. But it will tolerate any soil that
provide a good drainage system (sandy loam soil, but it will grow in areas with
poorer soils.) It should be in a frost-free area and will prefer the climate with
adding organic matter before planting. Seeds soaked in water will germinate
33
3.8. Red Capsicum Coloured capsicum which also knows as “sweet pepper” or
“bell pepper” is one of the important high value vegetable crops cultivated in green
houses and to the some extent under shade net house in milder climatic regions like
markets in India like Bangalore, Hyderabad, Pune etc. It is also gaining importance
days of planting in case of green colour capsicum, 80-90 days in case of yellow
interval in green and up to 200-250 days in red and yellow. Fruits that are mature
green, yellow when it is 75% yellow and red when it is 100% red are harvested and
3.9. Carrot Carrots are easy to grow in a garden with deep, loose soil; and as you
may have guessed from the name, they are packed with beta carotene. A 1/2 cup
serving gives you four times the Recommended Daily Allowance of vitamin A in
the form of beta carotene. Growing and harvesting carrots is a great way to take
advantage of their nutritional benefits. Carrot Farming plays major role in Indian
34
economy as it is major vegetable crop in India. Best Soil for Carrot Farming -
Carrot is a cool climate season crop and when grown at 15°C to 20°C will develop
a good colour. The carrot crop needs deep loose loamy soil. It requires a pH
overshadowed by its green cousin broccoli. This edible portion of the cauliflower
is called ‘Curd’ surrounded by leaves narrower than those of cabbage. There are
two main seasonal types of cauliflower is cultivated in India they are 1) Early
season type crop 2) Late season crop. Late cauliflower types are grown for a longer
35
3.11. Chilli Chilli is one of the most valuable crops of India. The crop is grown
largely for its fruits all over the India. It is used in India as a principle ingredient of
various curries, and chutneys. It is also used for vegetables spices, condiments,
sauces and pickles. Dry chillies are used for curry powder. Red colour in chili is
Climate for Chilli Farming:- The chili is a plant of tropical and sub -tropical region
-It grows well in warm and humid climate and a temperature of 20-25°C. Low
moisture in soil during blossom development and fruit formation causes the bud,
deblossom and fruit drops. Excessive rainfall is detrimental to the crops, because it
brings about defoliation and rotting of the plant. As a rained crop, it is grown in
areas receiving an annual precipitation of 25-30 inches. Best Soil for Chilli
Farming:- Chilli can be grown in a range of soils, but black soils which retain
moisture for long periods are suitable for rain fed crop whereas well drained soils,
deltaic soils and sandy loams are good under irrigated condition. However, in hills
of Uttarakhand, chillies are grown in a wide range of soils ranging from sandy to
3.12. Ginger Ginger is a very important commercial crop grown forits aromatic
rhizomes which is used both as a spice and a medicine. Ginger of commerce is the
36
dried rhizome. It is marketed in different forms such as raw ginger, dry ginger,
bleached dry ginger, ginger powder, ginger oil, ginger oleoresin, gingerale, ginger
candy, ginger beer, brined ginger, ginger wine, ginger squash, ginger flakes etc.
Ginger produced in India, goes for domestic consumption and only a small
quantity is exported.
wild fruit and not taken up as a commercial crop. However, its one of the most
market demand and health benefits. Originally it is native to India, but today it
spread across tropical regions. Jackfruit belongs to “Moraceae”. This fruit is grown
in Malaysia, Burma and some parts of Brazil. Wild jack fruit is grown in Western
Ghats of India. Apart from consuming as fresh fruit, this is also used to prepare
some special dishes. Below are the some of the health benefits of Jackfruit:
37
Jackfruit controls the blood pressure
3.14. Papaya Papaya also known as “Carica papaya” is a tropical fruit having
commercial importance because of its high nutritive and medicinal value. Papaya
cultivation had its origin in South Mexico and Costa Rica. Papaya is a popular fruit
famous for its high nutritive and medicinal values. It comes early in bearing than
any other fruit crop, produces fruits in less than a year and the production of fruits
is quite high per unit area. Papaya is cultivated more or less on a commercial scale
in the foothills and plain valleys of all states of the north eastern region. Papaya is
(October-November).
the country. but varieties are available which can be cultivated in subtropical
climate. In India it is generally cultivated in the hills. Its main center of cultivation
38
are Nainital (district) and Dehradun in Uttar Pradesh, Mahabaleshwar
Pune, Nashik and Sangali towns. The strawberry is the most widely adapted of the
small fruits. Strawberries are grown throughout Europe, in every state of the
United States, as well as in Canada and South America. The wide variation in
climates within these regions and the wide adaptation of the strawberry plant
permit harvesting and marketing, the fruit during greater part of the year.
Strawberry is rich in Vitamin C and iron. Some varieties viz. Olympus, Hood &
Shuksan having high flavour and bright red colour are suitable for ice-cream
making. Other varieties like Midway, Midland, Cardinal, Hood, Redchief and
sq.ft area in Karjat. The company has tied up with farmers having around 100+
acres of land near the processing plant. The location of the land (Chai) is as given
below:
There is a lake named Morbe lake passing near by the location. The lake is a
perennial lake having water across the year. Thus, there is no issue for water
availability. The Mumbai JNPT port is 75 kms (1.5 hours drive) away from the
39
location of the land and the state highway is 1.5 kms away from the location of the
land. Thus, the proximity of the land is very good. The company has entered into
agreement with an international company who will provide the seeds and fertilizers
required to grow the necessary products. They will also buy the final processed and
canned products from us. Also, the company will enter into a contract farming
agreement with the farmers to provide the company with the raw products at a
fixed price during the year. A sample agreement will be shared with the financial
The company will start the construction of the factory shed from the month of
August and start procuring process of plant & machinery from the month of August
as well. The farmers will start the work of growing products on their land by the
climatic conditions. Based on that working, the company will draw the working
capital limit from the bank. The company will need to pay initially to procure the
seeds and fertilizer to give it to farmers and then procure the produce from the. In
both this cases, the payment will have to be made in advance for which there is a
need for working capital. Sales and Marketing: The company plans to have both
40
domestic and export market for its products. Internationally, the company has
already tied up to sell its products. The payment cycle will be conducive for the
company in the export markets. In the domestic market, the company plans to sell
Looking at the opportunity of inline grocery store, the company intends to tie up
with Big Basket as well. The company intends to build a strong sales and
marketing team. 5. Industry India has been bestowed with wide range of climate
fruits and vegetables. The country is the second largest producer of the Fruits
(81.285 Million tonnes) and vegetables (162.19 Million tonnes) in the world,
contributing 12.6% and 14.0% of the total world production of fruits and
vegetables respectively. (Source: Source FAO Website- February 2014 and Indian
Horticulture Database 2013) Banana, mango, citrus, papaya, guava and grape
account for major share in total fruit production across India. The major fruit
Pradesh, Tamil Nadu, Kerala and Gujarat. These eight states account for 70 per
cent of the area under fruit cultivation. Potato, tomato, onion, brinjal, cabbage,
cauliflower and tapioca account for maximum share in vegetable production in the
41
country. India is a front runner in many fruits and vegetables with share in world
• 44.1% of mango
• 42.6% Papaya
• 25.6% of banana
• 20.2% of onion
• 35.6% of cauliflower
• 37% of Okra
Out of the total production of fruits and vegetables, nearly 76 per cent is consumed
in fresh form, while wastage, and losses account for 20 to 22 per cent. Only 2 per
cent of vegetable production and 4 per cent of fruit production are being processed.
developing countries such as Brazil (70 per cent), Malaysia (83 per cent),
The vast production base offers India tremendous opportunities for export. During
2017- 18, India exported fruits and vegetables worth Rs. 8760.96 crores which
comprised of fruits worth Rs. 3298.03 crores and vegetables worth Rs. 5462.93
portion of fruits exported from the country while Onions, Okra, Bitter Gourd,
Green Chilles, Mushrooms and Potatoes contribute largely to the vegetable export
42
basket. The major destinations for Indian fruits and vegetables are UAE,
Bangladesh, Malaysia, UK, Netherland, Pakistan, Saudi Arabia, Sri Lanka and
vegetables to the world for the worth of Rs. 2,266.66 crores during the year 2013-
14. The major export destinations are United States, Saudi Arabia, United
Kingdom, Netherland, United Arab Emirates and Japan. India is also a major
exporter of Mango Pulp in the world. The country has exported 174,860.34 MT of
Mango Pulp to Saudi Arabia, Yemen Republic, Netherland, United Arab Emirates
and Sudan for the worth of Rs. 772.97 crores during the year 2017-18. India is also
a prominent exporter of dried and preserved vegetables to the world. The country
United Kingdom, United States, France and Brazil for the worth of Rs. 742.74
crores during the year 2017-18.(Source: APEDA) The fruit and vegetable
the small scale sector, having small capacities upto 250 tonnes/annum though big
Indian and multinational companies have capacities in the range of 30 tonnes per
hour or so. The prominent processed items are fruit pulps and juices, fruit based
chutneys and dehydrated vegetables. More recently, products like frozen pulps and
vegetables, frozen dried fruits and vegetables, fruit juice concentrates and
43
vegetable curries in restorable pouches, canned mushroom and mushroom products
have been taken up for manufacture by the industry. Processing of fruits and
value addition is the most effective solution to reduce the wastage. Considering the
wide-ranging and large raw material base that the country offers, along with a
consumer base of over one billion people, the industry holds tremendous
situation gives it the unique advantage of connectivity to Europe, the Middle East,
Japan, Singapore, Thiland, Malaysia and Korea. One such example indicating
India’s location advantage is the value of trade in agriculture and processed food
between India and Gulf region. Various products, such as tomato puree, canned
fruit, frozen fruit, frozen vegetables and ginger-garlic pastes, gained popularity
among Indian consumers. Frozen and canned/preserved food products are proving
to be better alternatives to fresh foods due to the convenience of storage and usage
they offer. Demand for fresh, chilled and processed fruits and a vegetable is also
increasing in modern retail. Even some small retailers have started keeping
refrigerators to stock frozen peas or corn. This trend is likely to continue over the
44
forecast period and will help drive sales and penetration of processed fruits and
vegetables in India.
processing industry and food infrastructure including food parks, distillation &
brewing of alcohol, cold storage chain and warehousing. Five-year tax holiday for
new food processing units in fruits and vegetables processing along with other
AND KEY PLAYERS :- The unorganised sector accounts for 42 per cent of India’s
the sector’s role in employment generation. Though the market falls under the
unorganised sector in the country, the organised sector has a larger share in the
secondary processing segment than the primary one. Rice mills account for the
45