User Manual

Preventive Maintenance Process


(BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc)

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 1
BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 2
Contents
Overview.....................................................................................................................................................3

Create Single Cycle Plan.........................................................................................................................5

Create Strategy Plan..............................................................................................................................13

Create Maintenance Strategy................................................................................................................13

Maintain Packages.................................................................................................................................14

Create Strategy Plan..........................................................................................................................15

Schedule Maintenance Plan..................................................................................................................21

Deadline Monitoring..............................................................................................................................24

Display list of Equipment for which Scheduled Maintenance is Due.....................................................25

List of Call Objects.................................................................................................................................26

Process Notification...............................................................................................................................27

Create Maintenance order from Notification........................................................................................31

Material Planning Against Maintenance Order..................................................................................37

Material Issue against Reservation....................................................................................................49

Display material Document................................................................................................................52

Maintenance Order Confirmation......................................................................................................55

Complete Maintenance Order (TECO)...............................................................................................58

Complete Notification........................................................................................................................63

Maintenance Order Settlement.........................................................................................................70

Business Completion of Maintenance Order.....................................................................................70

Report for the Equipment for scheduled maintenance have not been done within the schedule.....71

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 3
Overview
Business Process Description Overview
Preventive Maintenance is used to avoid system breakdowns or the breakdown of other
objects, which - in addition to the repair costs - often result in much higher costs
subsequently owing to production breakdown.
There are many benefits in using preventive maintenance within your company. It is the
generic term for inspections, preventive maintenance and planned repairs, for which the
time and scope of the work can be planned in advance.
You can use maintenance plans to describe dates and the extent of preventive and
inspection maintenance tasks which can be planned for technical objects. You can
ensure that your technical objects are always maintained on time and in this way,
ensure that they function optimally.
Integration
The Maintenance Planning component is integrated with the following components and
sub-components of the SAP System:
Plant Maintenance application component
· Maintenance task lists
· Maintenance orders
· Maintenance notifications
Materials Management application component
· Service procurement
· Service entry sheets
Quality Management application component
· Inspection characteristics
· Inspection lots
Generation of Maintenance Call Objects
The system generates maintenance call objects during the scheduling process. The
following maintenance call objects are available in the overview:
For rough planning of tasks

PM notification
For detailed planning of tasks
PM order
For detailed planning of tasks and history for the damage processed in the notification:
Maintenance notification and maintenance order
For Quality Management using the link to QM inspection characteristics:
Inspection lots

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 4
Purpose
Use this procedure to create Preventive Maintenance Plan
1. Single Cycle Plan
2. Strategy Plan
3. Multiple Counter plan

Trigger

Perform this procedure when there is a need for scheduled maintenance for the
technical objects.

Prerequisites

Technical Object (Functional Location / Equipment)


Maintenance Strategy (for Strategy Plan)
Task list
Order type / Notification type

Helpful Hints

For scheduled maintenance at a single frequency; create Single Cycle Plan. For
example: maintenance at 3Month only.
For scheduled maintenance at more than one frequency; create Strategy plan. For
example: maintenance at 1Month, 3Month, 6Month, 1 Year etc.
For scheduled maintenance with a combination of time-based and counter-based
maintenance; create multiple counter plans for example maintenance at 1Month and/or
200 running hours

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 5
Create Single Cycle Plan

SAP Menu SAP Menu---Logistics---Plant Maintenance---Preventive Maintenance---


Maintenance Planning---Maintenance Plans---Create---Single Cycle Plan

T Code Type IP41 in Command Field and press

User Menu Select corresponding Node for IP41 / Single Cycle Plan

Click on Select the Desired Maintenance


Plan Category from the List

Click on Enter Button

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 6
Click on to select task list / Gen. Task list

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 7
Click on or press F8 key on the keyboard

After execution you will find the list of task lists as below

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 8
From the above list first select the suitable Task list and click on enter button or Double
click on the suitable task list system will automatically update the task list

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 9
Once the task list was selected, System will prompt a message at
the bottom left of the screen as “A task list was selected”

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 10
Click on the “Maintenance plan scheduling parameters” tab and maintain the relevant data

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 11
Click on the “Maintenance plan additional data” tab and maintain the relevant data

Maintain the sort field

Click on to save the created single cycle plan

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 12
System will prompt for a message at the bottom left like
“Maintenance plan XXXXXXXXXXXXXXXX created”

The plan number will be system generated internal number

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 13
Create Strategy Plan
Create Maintenance Strategy
SAP Menu SAP Menu---Logistics---Plant Maintenance---Preventive Maintenance---
Maintenance Planning---Maintenance Strategies---Change

T Code Type IP11 in Command Field and press

User Menu Select corresponding Node for IP11 / Change

Click on

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 14
Maintain Packages
Double Click on Packages Folder

Click on New Entries

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 15
Click on Save

Create Strategy Plan

SAP Menu SAP Menu---Logistics---Plant Maintenance---Preventive Maintenance---


Maintenance Planning---Maintenance Plans---Create---Strategy Plan

T Code Type IP42 in Command Field and press

User Menu Select corresponding Node for IP42 / Change

Click on to get the list of possible (Strategies) entries


to select the suitable plan

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 16
Double click on the suitable strategy it will copied in the Field of Strategy

Click on Continue (Enter)

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 17
BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 18
Click on “Maintenance Plan Scheduling Parameters” Tab and maintain the relevant data

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 19
Click on “Maintenance Plan Additional data” Tab and maintain the relevant data

Select the relevant sort field

Click on Save

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 20
System will prompt a message as “Maintenance plan XXXXXXXXXXXX created”

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 21
Schedule Maintenance Plan
SAP Menu SAP Menu---Logistics---Plant Maintenance---Preventive Maintenance---
Maintenance Planning---Scheduling for Maintenance plans---Schedule

T Code Type IP10 in Command Field and press

User Menu Select corresponding Node for IP10 / Single Cycle Plan

Input the Maintenance plan number and click on enter key

Click on Start Button to schedule the


maintenance plan

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 22
Enter the cycle start date
and press enter
Click on Continue (Enter)

Click on Save

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 23
System will prompt a message that “Maintenance plan XXXXXXX
scheduled”

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 24
Deadline Monitoring
SAP Menu SAP Menu---Logistics---Plant Maintenance---Preventive Maintenance---
Maintenance Planning---Scheduling for Maintenance plans---Deadline
Monitoring

T Code Type IP30 in Command Field and press

User Menu Select corresponding Node for IP30 / Deadline Monitoring

Input the Maintenance plan number and


enter the number of interval days for Call

objects and click on Execute

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 25
Display list of Equipment for which Scheduled Maintenance is Due

SAP Menu SAP Menu---Logistics---Plant Maintenance---Preventive Maintenance---


Maintenance Planning---Scheduling for Maintenance plans---Scheduling
Overview---List Display

T Code Type IP24 in Command Field and press

User Menu Select corresponding Node for IP24 / List Display

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 26
List of Call Objects
SAP Menu SAP Menu---Logistics---Plant Maintenance---Preventive Maintenance---
Maintenance Planning---Scheduling for Maintenance plans---Scheduling
Overview---List Display

T Code Type IP24 in Command Field and press

User Menu Select corresponding Node for IP24 / List Display

Input the Maintenance Plan Number and Notification type and

Click on Execute

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 27
Process Notification

SAP Menu SAP Menu---Logistics---Plant Maintenance---Maintenance Processing---


Notification---Change

T Code Type IW22 in Command Field and press

User Menu Select corresponding Node for IW22 / Change

Input the Notification number and click on Enter

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 28
In the above screen the system status is OSNO (Out standing Notification) to change the status from

OSNO to NOPR (Notification in Process) click on Release (Green Flag)

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 29
Click on Save

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 30
System will prompt a message as “Notification XXXXXXXXXX Saved”

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 31
After the above step Decide on the requirement of Maintenance order, based on
material to be consumed from stores or need based services to be used.

Follow the below steps to Create the Maintenance order from Notification and for further
processing.

Create Maintenance order from Notification

SAP Menu SAP Menu---Logistics---Plant Maintenance---Maintenance Processing---


Notification---Change

T Code Type IW22 in Command Field and press

User Menu Select corresponding Node for IW22 / Change

Input the Notification Number and click on Enter

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 32
Click on Icon to create the order

System will prompt for a pop-up window as below

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 33
Check all the details and click on Continue

System will prompt for another pop-up window as below

Check the parameters and click on continue

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 34
Click on Save

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 35
System will prompt a message as “Order XXXXXXXXXXX saved with notification XXXXXXXXXXXX”

Maintenance Order of Order Type “BM01” created and linked to the Notification.
Status of Notification will be updated to “ORAS” (Order Assigned)

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 36
BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 37
Material Planning Against Maintenance Order

SAP Menu SAP Menu---Logistics---Plant Maintenance---Maintenance Processing---


Notification---Change or SAP Menu---Logistics---Plant Maintenance---
Maintenance Processing---Order---Change

T Code Type IW22 / IW32 in Command Field and press

User Menu Select corresponding Node for IW22 / Change or IW32 / Change

From T code IW22

Input the Notification number and click on continue

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 38
Click on change Icon

From T code IW32

Input the order number and click on continue

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 39
Click on “Components”
Tab

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 40
Click on Structure list System will prompt pop-up window

Enter the Operation number and click on continue

You will get the Materials (As per equipment BOM)list.

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 41
Double click on the Item which you want to input, the selected material will be updated in the
“Components” Tab against Item number “0010” as below

If you want to see the reservation number double click on “0010”

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 42
If you want to assign the components other than from the BOM, Place the cursor in “Component” filed

and click on or press F4 key (Possible entries) on the keyboard, system will prompt a pop-up window
as below

Input the Plant and click on continue

You will get the list of all the materials which are available in the plant 5303

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 43
Choose the right material and double click on it, the system will automatically update this material as
below

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 44
Press Enter key on the keyboard system will prompt pop-up window

Give the required operation number against which this component is

required to complete the operation and click on continue

Input the required qty

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 45
Now Release the order by clicking on the Green Flag

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 46
System will prompt a message as Order XXXXXXXX will be released after update

Click on Save

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 47
Material Issue against Reservation

SAP Menu SAP Menu---Logistics---Materials Management---Inventory Management---


Goods Movement---Goods Movement

T Code Type MIGO in Command Field and press

User Menu Select corresponding Node for MIGO / Goods Movement

Select the Goods Issue from the drop down, Input


the Reservation number generated in the

maintenance order and click on Execute Button

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 48
Click on Line item 1 and input the storage location from which you want to issue the material and select
Item Ok

Same as above select the Line item 2 and input the storage location and click on Item Ok

Note: If you want to know in which storage location the material is stored click on

After all the input Click on Check

You will find the green traffic lights if the input data is correct and then click on Post

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 49
System will prompt a message as “Document XXXXXXXX posted”

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 50
Display material Document
SAP Menu SAP Menu---Logistics---Materials Management---Inventory Management---
Goods Movement---Goods Movement

T Code Type MIGO in Command Field and press

User Menu Select corresponding Node for MIGO / Goods Movement

Select “display” from dropdown, Select “Material Document” from drop

down and Input the Document number and Execute

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 51
Click on Doc.Ino Tab and then click on

System will prompt a pop-up window as below

Double Click on the document in


which you are interested

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 52
For Example if you double click on the “Accounting Document” screen appears as below

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 53
Maintenance Order Confirmation

SAP Menu SAP Menu---Logistics---Plant Maintenance---Maintenance Processing---


Completion Confirmation---Entry---Individual Time Confirmation

T Code Type IW41 in Command Field and press

User Menu Select corresponding Node for IW41 / Individual Time Confirmation

Input the Order number which you want to confirm and click on continue or
press the enter key on keyboard

Below screen you will get the list of operation which are yet to be confirmed

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 54
Double click on the operation system will prompt for pop-up screen as below

Enter all the details like Work Centre, Personnel number, Actual work, Actual duration, Work starts on,
Work Ends on, Reason, and Confirmation Text

After all the details are maintained click on

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 55
System prompts a message as “Number of confirmations saved for order
XXXXXXXXXXXXXXXXXXX

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 56
Order status “CNF” is updated

To see the status go to order change (IW32) mode and input the order number and click on continue

Complete Maintenance Order (TECO)

SAP Menu SAP Menu---Logistics---Plant Maintenance---Maintenance Processing---


Order---Change

T Code Type IW32 in Command Field and press

User Menu Select corresponding Node for IW32 / Change

Input the Order number and click on continue

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 57
Click on “Complete (Technically)”

System will prompt pop-up window as below

Deselect by clicking on

Click on “Damage” Tab

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 58
Select the Cause code from possible
entries (F4)

Click on continue

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 59
System will prompt a message as “Order XXXXXXXXXXXX saved with notification
XXXXXXXXXXXXX

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 60
Now again to order change mode through T code IW32

The entire screen will be grayed out (no input is possible) and system will update the status with “TECO”

You can go to the


notification change mode
from here also

With above status the Maintenance order is completed.

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 61
Complete Notification
SAP Menu SAP Menu---Logistics---Plant Maintenance---Maintenance Processing---
Notification---Change

T Code Type IW22 in Command Field and press

User Menu Select corresponding Node for IW22 / Notification Change

Input the notification Number and click on Continue

Click on “Catalog Data” Tab

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 62
Input the Details and click on “Causes” Tab

Input the Details and click on “Activities” Tab

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 63
Input the details and click on “Notification” Tab

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 64
Click on Maintenance notification

System will prompt a warning message at the bottom left of the above screen as below

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 65
Check the dates and press the “Enter Key” on the keyboard to ignore the above warning message

System will prompt a pop-up window and a message at the bottom left of the screen

Click on

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 66
System will prompt a message as “Notification XXXXXXXXXX completed”
and system will update the status as “NOCO” for this notification

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 67
To see the “NOCO” status access the Notification change mode screen through T code IW22

With the above the notification is completed

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 68
Maintenance Order Settlement
At the month end, finance department will open the orders which are technically completed and
Settle them, after the settlement the actual cost of the order will be transferred to the cost centre,
And actual cost of the order will become zero. After this activity the order will be Business
Completed

Business Completion of Maintenance Order


SAP Menu SAP Menu---Logistics---Plant Maintenance---Maintenance Processing---
Order---Change

T Code Type IW32 in Command Field and press

User Menu Select corresponding Node for IW32 / Order Change

Click on “Order”

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 69
Report for the Equipment for scheduled maintenance have not been done
within the schedule
SAP Menu SAP Menu---Logistics---Plant Maintenance---Maintenance Processing---
Notification---List Editing---Display

T Code Type IW29 in Command Field and press

User Menu Select corresponding Node for IW29 / Display

BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 70
BSNL_PM_UM_01_Preventive_Maintenance_V2.0.doc Page 71