Paper Heavy Oil Sampling
Paper Heavy Oil Sampling
samples would fail to produce a fluid, which exhibits the same Pump to Surface
properties, under PVT analysis, as the original reservoir fluid. In the Pump to Surface (PTS) technique, the fluid that
The initial objective was to obtain appropriate volumes of might be trapped downhole, in small volume chambers, at near
reservoir fluid sample, for use in specialized PVT analyses, reservoir pressure, is instead, drawn into the low shearing
appropriate for the gas-oil emulsion forming “foamy” oil, of a PCP. The fluid is further pressurized and pumped to surface.
higher quality than was previously obtained, at an acceptable Wellhead pressure is controlled, so that at all times during
cost. The objective was later revised to include obtaining transfer to surface, the fluid from the pump discharge is
larger volumes of sample, at reservoir conditions, for PVT (4 maintained at above reservoir pressure.
liters per zone) and Special Core Analysis studies (45 liters The small pressure decrease experienced by the reservoir
from one zone). fluid, in flowing from the formation to the wellbore and up to
the pump intake, will allow some gas to be liberated. The
Background behavior of liberated solution gas in foamy oil has now been
The reservoir fluid data available for the Hamaca field in documented in various papers, e.g. SPE 68860 (Ref.2). If the
July 2000, had been obtained from PVT analyses of a limited pressure drop experienced by the crude is low and for a short
number of small volume samples. The samples were obtained, time period, the microbubbles of liberated solution gas will
by conventional downhole sampling operations, from three not coalesce to form larger bubbles, which would segregate
appraisal wells. The fluid analyses indicated a variance in under gravity. With subsequent compression, to a pressure
GOR that was unlikely to exist in the reservoir. Sampling well above reservoir pressure, and the turbulence caused by
operations had been performed over several days, using a passing through the PCP and flowing to surface, the
conventional program of low rate production, to condition the microbubbles of gas may be expected to return to solution.
near wellbore region, with samples being taken in time The initial formation GOR should therefore be preserved.
controlled, small volume chambers. It was found that, because By this system, unlimited volumes of high quality
of the viscosity of the Hamaca crude and the presence of sand, reservoir fluid sample can be obtained. In addition, the
the downhole collection vessels often became plugged and did sediment and water content of the well stream can be checked,
not fill properly. The conclusion reached was that, for future before shipping cylinders are filled. The uncertainty in
sampling operations, an improved system would be required, trapped fluid type, which exists in downhole sampling
which could be relied upon to provide high quality samples. techniques, is therefore eliminated. Critical requirements of
A detailed survey was made of the sampling equipment the system are to:
that could be made available in Venezuela and of sample (a) minimize the pressure drop required for fluids to flow from
taking procedures. The sampling techniques were constrained the formation to the pump intake,
by the requirement to make use of a rod driven progressive (b) maintain the wellhead pressure above reservoir pressure,
cavity pump (PCP). This type of pump has proven ability to while fluids are being pumped to surface, and samples are
efficiently pump high viscosity fluids, with high sediment being taken, and
content. (c) monitor the volume of fluids produced, in relation to the
Downhole sample collection systems tend to be of small tubing volume.
volume. The fluids are trapped by mechanisms that are either For zones that are found to be of low productivity, and
time controlled, annulus pressure controlled or actuated from which cannot be produced with low drawdown, there is the
surface by wireline, etc. Time control requires surface secondary benefit of obtaining atmospheric pressure samples
operations to be co-ordinated and as a result, the pre-sampling at surface.
production period may be extended or cut short, in accordance In addition, for all of the intervals tested, very valuable
with the actuation time. Annulus pressure actuated systems information was obtained regarding the formation condition,
allow sampling to be performed at an appropriate time. the formation fluid type and the ability of the sands to be
Consideration was given to running a carrier, with pressure produced. The PCP intake pressure gauge was also used to
activated sampling chambers, but the high cost, small sample record pressure build-up in specific zones, following well
volume and uncertain sample quality, led to rejection. A closure.
wireline actuated sampling device could not be used, because
of the presence of drive rods in the tubing and because, in Downhole Equipment
most cases, wireline tools cannot be run through the Faja The sampling completion was designed in accordance with
EHCO, due to its high viscosity. Probe type sampling tools, the primary requirement of minimized drawdown. Critical
run on cable, through drilling or completion fluids, were not aspects were identified as the perforations, tailpipe design and
suitable as a result of sealing problems and the pressure drop the proximity of the packer to the test zone. The low
that occurs in the probe tube, with high viscosity oil. drawdown required for sampling was also required to
During the evaluation of alternative fluid collection minimize sand production. The basic components of the PTS
methods for the project, confirmation was obtained that rod sampling test string are indicated in Fig.1 below.
driven PCP and wellhead equipment could be made available
which could allow fluids, at above reservoir pressure, to be
delivered to surface. Consideration of all aspects of the
sampling project, and the quality and volume of samples
obtainable, clearly led to the selection of the “Pump to
Surface” technique, for future PVT sampling in Hamaca.
SPE 86951 Innovative Reservoir Fluid Sampling Systems – Hamaca Project, Venezuela Page 3
Surface Equipment
As a result of the abnormally high wellhead pressure
required to be maintained, careful selection of the wellhead
equipment was required. Standard PCP/drive head completion
equipment, installed for normal production, is unlikely to be
able to be used for pump-to-surface sampling, due to the
abnormally high wellhead pressures created.
The PCP drive head and motor were required to be suitable
for many hours of low speed, high torque operation. A
mechanical rotating stuffing box with an internal seal for the
rod string was obtained, which had an appropriate pressure
rating for safe operation at FWHP up to 1500 psi. The
mechanical seal was tested with water and failed at 2500 psi.
Fig.1: Downhole Completion and Surface Systems The highest reservoir pressure encountered in the zones
sampled was about 1150 psia. The rods were driven by a
Perforations were specified which would allow low single 30hp electric motor, connected by belts.
drawdown, while maintaining control over formation Other surface equipment included a choke manifold, a
breakdown and excessive sand/sediment production. Various diesel injection package and flowlines to storage tanks. As a
recommendations were obtained from service companies result of the EHCO viscosity having high sensitivity to
regarding shot density, phasing, charge size, hole diameter and cooling, produced fluids were mixed with diesel at surface,
penetration. The final selection was perforation with wireline downstream of the choke manifold, remote from the single-
run casing guns, 4 shots/ft, 90 degree phasing, 24 gram phase sampling point.
charges, which had expected tunnel diameter of 0.70 inches A conventional test separator was not included as the
and 7.8 in. penetration. These were later changed to smaller flowrate expected was too low for efficient operation. Rate
hole diameter, deeper penetration charges, in an attempt to measurement at surface was performed by monitoring the
reduce sediment production, with unconfirmed success. level of the diluted crude oil storage tank and the pump speed.
The possible use of any kind of sediment screen was As the PCP is a constant displacement pump, rate can be
rejected, due to the potential for drawdown increase from estimated from the pump speed, nominal capacity and the
plugging. The tailpipe consisted of a perforated joint, set volumetric efficiency. At a pump speed of 100 RPM, gauge
across the perforated interval. Some sand production, during tank measurements confirmed the actual displacement rate
the clean-up period, was therefore expected. A downhole sand was about 25 BPD.
control facility was finally installed for one zone, after it was
confirmed that single-phase samples could not be obtained. Developments In The field
Oil had not yet been produced from the zone and confirmation Single-phase sampling at surface operations were
of the fluid type required atmospheric pressure samples to be conducted in Hamaca confirmation wells H-H3-C01 and H-
obtained. C4-CO2, between November 2000 and February 2001. Single-
A packer was required to be run, in preference to a torque phase sampling was successfully achieved in five separate
anchor, to avoid possible gas migration in the annulus and the zones. Formation conditions prevented successful single-phase
associated effect on sample quality. The packer, with the PCP sampling from one zone and tests in two other zones produced
above, was set as close to the top perforation as considered water only, contrary to log evaluation.
safe. No blank pipe was run between the perforated joint and Prior to the production during the sampling, limited
the packer, to avoid possible collection of liberated solution information was available regarding the productivity of each
gas in the annulus under the packer. zone, the level of consolidation of the formations sampled and
A pressure gauge was run to monitor intake pressure in some cases, the formation fluid type, as both wells had no
4 David R. Reddie, Carlon R. Robertson SPE 86951
prior production.
In general, the downhole completion design did not require
any changes. Other perforation designs were used, but no clear
preferred system was established, due to the unpredictable
variance in the quality, consolidation and productivity of the
zones.
Sand production was found to be of higher significance
than expected. Following clean up of perforation tunnels, with
each increase in PCP speed, a new wave of sediment
production would be initiated. Sediment production did
require some modification of the surface control and sample
transfer procedures.
While initial expectations were that the flowrate and Fig.2 Well Performance Data
FWHP could be controlled by fixed and variable surface
chokes, the small rate and small choke size required, were not In Fig.3, detailed downhole pressure data for the full test
compatible with the initially high volumes of sediment are provided, with the pump speed. The data confirm the low
produced. drawdown that was applied to the formation, during the full
The pre-sampling procedure was revised, so that the well sampling program.
was allowed to clean up, at constant/low PCP speed, with no
restriction at surface. When sediment percentage and grain
size had dropped to a stabilized/ minimal level, the FWHP was
gradually raised to well above reservoir pressure. The tubing
above the pump was progressively displaced with reservoir
quality crude.
In zones where sediment production did not stabilize at a
suitably low level, single-phase sampling at surface was not
attempted and atmospheric pressure samples only were
obtained.
The final established sequence of operations, after
perforation and installation of the PCP string, is summarized
below:
1) Record SIBHP. Start up the PCP to minimal speed
(75/100 rpm). Monitor FBHP/drawdown
Fig.3: Downhole Pressure Data
continuously. Record data at 1 minute intervals.
2) Monitor fluid type, by wellhead samples, and
With the very low drawdown applied in testing, the
flowrate, by gauge tank, at 30 minute intervals.
downhole pressure data clearly exhibit a considerable amount
3) When oil reaches surface, check sediment and water
of ‘noise’, which may result from the gauge being supplied
content. Continue sediment checks at 30 minute
from the same power source as the pump.
intervals. Check drawdown, adjust PCP speed if
As may be expected, in any sample taking operation,
required.
equipment has to be cleaned rigorously to avoid
4) Continue production to clean up, monitoring
contamination. With the very viscous EHCO, this may not be
flowrate, drawdown, sediment, and water. Maintain
easily performed. Between tests, operations were performed to
PCP speed constant.
clean all downhole equipment, using hot water only. The use
5) When sediment has minimized, increase wellhead
of any kind of lighter hydrocarbon or solvent, to clean
pressure gradually, by surface restriction. Take
downhole equipment, was avoided.
atmospheric pressure samples before increasing
FWHP.
Single-Phase Sampling at Surface
6) Maintain FWHP above reservoir pressure, continue
Separate to the development of equipment systems and
production until an appropriate volume has been
procedures for delivering single phase fluids to surface,
produced to displace the full sampling string to
techniques were evolved for single-phase sample collection at
single-phase fluid.
surface.
7) While maintaining FWHP above reservoir pressure,
Sediment production also created problems in sample
take single phase samples at surface.
taking. Sample transfer, direct into single-phase shipping
8) Stop the pump, close in the well for pressure build-
cylinders, proved to be impossible, as a result of sealing
up, if required.
problems with high pressure needle valves and plugging of
Typical data recorded during the clean up, conditioning
small diameter bores. In addition, initial samples, with low
and sampling period are summarized in Fig.2 below, including
(2% to 4%) sediment content, proved difficult to work with in
the wellhead pressure and BS&W.
the PVT lab. Filtration in the lab was not easily achieved.
SPE 86951 Innovative Reservoir Fluid Sampling Systems – Hamaca Project, Venezuela Page 5
Acknowledgements
The authors wish to thank Petrolera Ameriven and its
parent companies, ConocoPhillips, Petroleos de Venezuela,
S.A. and ChevronTexaco, for the opportunity to publish this
paper. We must also thank our former colleague, Darryl
Williams, SPE, and numerous service company personnel, for
their assistance in developing the systems described in this
paper.
References
1. Gipson, et al, “Hamaca Heavy Oil Project – Lessons
Learned and an Evolving Development Strategy”, SPE
paper 78990, prepared for presentation at the SPE
International Thermal Operations and Heavy Oil
Symposium and International Horizontal Well Technology
Conference held in Calgary, Alberta, Canada, 4-7
November 2002.
2. Mastmann, et al, “Predicting Foamy Oil Recovery”, SPE
paper 68860, prepared for presentation at the 2001
International Thermal Operations and Heavy Oil
Symposium, held in Porlamar, Margarita Island,
Venezuela, 12-14 March, 2001.