Ammonia and Urea Plants PDF
Ammonia and Urea Plants PDF
Ammonia and Urea Plants PDF
PLANT
Author
Prem Baboo
+919425735974
Prem.baboo@nfl.co.in , pbaboo@hotmail.com
Sr. Manager (Prod)
National Fertilizers Ltd. India
An Expert for www.ureaknowhow.com
Fellow of Institution of Engineers India
Heat Exchangers Design Specialist
1.1 Company Profile
The Vijaipur unit, which is an ISO 9001:2000 & 14001 certified, comprises of
two streams-Vijaipur-I and Vijaipur-II, which went into commercial production
in July, 1988 and March, 1997 respectively. The Complex comprises two
streams of Ammonia Plants each of 1750 MTPD & 1864 MTPD for line-I & line-
II respectively capacity (after revamped) based on “Steam reforming process” of
Haldor Topsoe, Denmark and four steams of Urea Plants each of 3030 &
3231TPD MTPD capacity for line-I & line-II (after revamped) based on
“Ammonia stripping process” of SAIPEM (erstwhile Snamprogetti),Italy and
together with all necessary utilities and infrastructure facilities. Vijaipur II is
more energy efficient than Vijaipur-I Plant due to incorporation of energy
saving Equipments & processes at the design stage itself. It is also having
provision of mixed feed (Natural Gas + Naphtha) thus giving more flexibility of
operation. Both the plants have consistently achieved high levels of capacity
utilization.
Site location
The plant site is about 30 km from the District town Guna along the National
Highway (NH-3) towards Indore. The nearest railway station is Ruthiai junction
at a distance of 6 km. A broad-gauge line connects Bina (150 km) from the East
and Kota (170 km) from the Northeast to Ruthiai. From here, another broad -
gauge line runs to Maksi 240 km away which in turn connects Bhopal and
Ratlam. Very close to the site, the rain-fed river “Chopan Nallah” flows and
another river “Parvati” is 6 km away from the site.
Infrastructure facilities
The infrastructure facilities comprises the gas pipeline, water supply, power
supply from state grid through transmission line laid by MP State Electricity
Board, Railway siding and communication facilities. These facilities are already
available at the existing plant site and only augmentation of some of the
facilities, if required, will be done.
Raw water
The existing Vijaipur fertilizer complex has permanent raw water supply
facilities from Gope-Krishna Sagar Dam nearly 15 km away from the site.
Power
At Vijaipur unit, three Gas Turbine Generator (GTG) sets each of 16 MW rating
(at ambient conditions) have been provided. The exhaust gases from GTG are
used in HRSG for generating steam. At present, two GTGs are running at around
13 MW load each.
Railway Siding
After implementation of the proposed debottlenecking scheme, the existing
railway infrastructure can handle the total traffic.
Social Infrastructure
The existing fertilizer complex has well-established residential colony
(Township) with all common facilities such as hospital, school, shopping centre,
recreation centre, guesthouse and the sports facilities etc.
Chemical fertilizers have played a vital role in the success of India's Green
Revolution and consequent self-reliance in food-grain production. The increase
in fertilizer consumption has contributed significantly to sustainable
production of food grains in the country. The Government of India has been
consistently pursuing policies conducive to increased availability and
consumption of fertilizers in the country. The Government's policy has hence
aimed at achieving the maximum possible degree of self-sufficiency in the
production of nitrogenous fertilizers based on utilization of preferred feedstock
as NG/RLNG. Presently, various fertilizer companies of the country are
planning for augmentation of their capacity of existing ammonia-urea plants
based on the study report conducted by respective process licensors/ Indian
consultant. NFL Vijaipur is also contemplating in the same line.
1.5 Need for the Revamp
The volatile international urea fertilizer market could be reason for country's
strategic policy. This is also desirable as the international market is very
sensitive to demand supply scenario. The international price of urea is mainly
governed by the demand potential of two countries i.e India and China. The
international price of urea is governed not by the cost plus profits approach but
by ‘opportunistic’ considerations. The international price of urea at present is
high and the scenario is likely to continue.
1.6 With the above consideration, NFL has initiated for capacity augmentation as
well as energy saving measures of existing Vijaipur-I & II ammonia & urea
plants. The rationale behind the proposed revamping project could be:
a] Availability of existing infrastructure facilities.
b] Lower capital cost, cost of production and retention price compared to
new project consequently lower incidence of subsidy.
c] To meet the gap in demand and supply in the country.
1.7 The specific energy norms fixed by FICC was 6.271 Gcal and reduced to 5.952
during stage-II pricing. In present scenario, NG supply is lean in nature which
makes the plant unable to convert total ammonia produced to urea due to
shortage of CO2. In case of lean gas, urea plants will not be in a position to
produce urea even at reassessed capacity. In view of above and for the survival,
NFL has got the feasibility study done by M/s. HTAS, SAIPEM and PDIL. The
study identified certain energy saving schemes. NFL is in the process for
implementation of some of these schemes. Due to implementation of these
energy saving measures, there will be capacity enhancement of
Ammonia-I of nearly150 MTPD & the plant will be able to produce 1750
MTPD(with PGR),
Ammonia-II nearly 225 MTPD & the plant will be able to produce 1864
MTPD (without PGR).
Urea-I plant will be able to produce 3030 MTPD
Urea-II plant will be able to produce 3231MTPD
To meet the shortfall of 357 MTPD CO2 in achieving the capacity of Urea
plants as stated above, a 450 MTPD Carbon-Dioxide Recovery (CDR) Plant
is to be installed.
PROCESS DESCRIPTION
Reforming
The reforming of the hydrocarbon feed takes place in two stages - first in a direct
fired primary reformer and later in an auto-thermal catalytic secondary reformer.
The hydrocarbon feed coming from the desulphurization unit is mixed with steam.
The steam/carbon ratio is 3.0. The reaction mixture is preheated in coil bank
located in waste heat recovery section of primary reformer furnace before entering
the catalyst tubes of primary reformer, where it is converted into hydrogen, carbon
monoxide and carbon dioxide by reaction inside the catalyst filled reformer tubes.
In the secondary reformer, preheated process air is added and the heat thus
generated by burning of hydrogen of the reformed gas is used for supplying heat
required for conversion of residual methane coming from primary reformer. The
methane concentration in the outlet gas from the secondary reformer is around 0.3
vol% (dry basis).
The reforming unit consisting of a primary reformer with a waste heat section, and
a secondary reformer, is briefly described below:-
Primary Reformer
The primary reformer which is of side-fired type consists of two chambers. The
chambers are placed side by side and functions as one unit. The two furnace
chambers are joined to a common flue gas duct at the top which is connected to
flue gas heat recovery section, housing heat recovery coil banks locate d at
different levels from top to bottom.
Each furnace chamber contains a number of vertically mounted micro alloy
reformer tubes filled with primary reforming catalyst. The tubes are mounted in
a single row along the centre line of the chamber. The process gas flows
downwards with the gas being distributed to the top of the tubes from a header
through "hairpins" at a temperature of about 520 oC. The gas leaves the tubes
through bottom "hairpins" and enters a refractory lined collector connected to
number of symmetrically placed high alloy hot collectors.
The tubes are heated by a number of burners located in each side wall of the
furnace chambers and arranged in horizontal rows at several elevations to
provide easy control and maintain uniform temperature profile along the length
of the catalyst tubes. In this manner, the optimal utilization of the expensive high
alloy tubes is obtained. The flue gas flow is upwards with outlet near the top of
the radiant chamber. The flue gas outlet system comprises of a common flue gas
collector mounted between the two radiation chambers. The flue gas
temperature going out of radiant chamber is about 1100oC.
Flue Gas Heat Recovery Section
The flue gas passes via the flue gas duct to the flue gas heat recovery section, in
which the sensible heat of the flue gas is utilized for the following duties.
• Preheating of hydrocarbon/steam mixture going to the primary reformer,
• Final preheating of process air for the secondary reformer,
• Final superheating of HP steam,
• Final preheating of natural gas,
• Superheating of HP steam,
• Preheating of process air for the secondary reformer,
• Preheating of natural gas,
• Preheating of combustion air,
At the outlet of the flue gas duct, the flue gas temperature is reduced to
approximately 150oC-165oC. An induced draught fan is used for discharging the
flue gas to atmosphere by venting continuously through a chimney stack.
Secondary Reformer
The gas from the primary reformer passes to the Secondary Reformer through a
refractory lined transfer line. The gas is admitted to the vessel through a top
dome-mixing chamber, where it is mixed with the process air, which has been
compressed to 38 kg/cm2g in the air compressor, and preheated to around 550 oC
in the flue gas heat recovery section. The secondary reformer is a refractory
lined vessel. The burner mixer is mounted at the top of the vessel. The vessel
contains a bed of a nickel reforming catalyst, supported by a grid of high
temperature resistant material.
The balance between the reforming reaction taking place in the primary and
secondary reformers depends to a great extent on the preheat temperatures and
the methane leakage. In practice, the firing in the primary reformer is adjusted so
that the desired outlet conditions from the secondary reformer are obtained with
the amount of process air required to maintain a hydrogen/nitrogen ratio of
approximately 3 to 1 in the make-up synthesis gas going to ammonia synthesis
loop.
The high temperatures in the primary and especially in the secondary re former
necessitate chemical resistivity of the catalysts to the constituents of secondary
reformer lining material. Particular emphasis is given with regards to the use of
catalysts free from silica and alkali, together with the use of refractory lining
material having a very low content of silica and iron. Presence of silica and iron
in higher proportions induces formation of volatile compounds which are easily
carried out of secondary reformer and deposited on the surfaces of waste heat
boiler tubes.
The process gas leaves the reforming section at about 1000oC - 1020oC. It is
cooled to about 392 oC-400oC in the waste heat boiler, where 120 kg/cm 2g
saturated steam is produced. The process gas is further cooled to 360 oC in the
steam super heater. After cooling, the gas flows to the high temperature CO
converter.
CO Conversion
The CO conversion takes place in two adiabatic stages.
The high temperature CO converter contains a Cu-promoted high temperature
shift catalyst. High activity, high mechanical strength and very low sulphur are
the main characteristics of this variety of catalyst. The low temperature CO
converter is loaded with low temperature shift catalyst, which is characterized,
by high activity, high strength, and high tolerance towards sulphur poisoning. A
top layer of a special catalyst generally termed as the guard catalyst is installed
to absorb any possible chlorine carry over in the gas and also to prevent liquid
droplets from reaching the main bed of LT shift conversion catalyst.
After reforming, about 13-14% CO is present in the gas (dry basis). In the high
temperature CO converter, the CO content is reduced to approximately 3.3 vol%,
and in the process, the temperature of the product gas is increased from 360 oC to
435 oC. HT shift reactor effluent gas is cooled in stages to around 200 oC -210 oC
before entering low temperature CO converter, in which the CO content is
reduced to approximately 0.3 vol %, while the temperature of the product gas
increases to 228 oC.
The heat content of the effluent from the high temperature CO-converter is
recovered in the trim heater, in the high pressure waste heat boiler, and in high
pressure boiler feed water preheater.
CO2 Removal
The gas leaving the CO conversion unit contains a considerable amount of
recoverable heat. Owing to the steam content of the gas mixture, this heat is
present mainly as latent heat. The waste heat in process gas is recovered in a
high pressure BFW preheater, in the stripper re-boiler, and in the de-mineralized
water preheater, E 305.
For the removal of CO2, GV process for Ammonia-II and Benfield process for
Ammonia-I are present. Main equipment in the process is the CO 2 absorber, and
the CO2 stripping columns. The absorbent solution consists of an activator. The
regenerated CO2 will be available at 40 oC and 0.15 kg/cm2g pressure, from LP
flash cooler KO drum. An electric motor driven CO 2 booster compressor shall be
used for delivering CO2 at a pressure of around 0.5 kg/cm2g at the battery limit
of urea plant.
Bulk quantity of carbon dioxide is removed from the process gas in the lower
part of the absorber, by scrubbing with flash-regenerated solution coming from
LP flash column. In the upper part of the absorber, strip-regenerated solution
generated in CO2 stripping column, is used for scrubbing.
The flash regeneration of the rich solution is performed in two stages. In the HP
flash drum, a large part of the dissolved inert components is expelled at a
pressure of around 8 kg/cm2g. The flashed gas is then compressed and recycled
to the CO2 absorber, for maximum recovery of the available CO 2. The flashed
solution from the bottom of the LP flash drum is divided and the major part of
the solution is transferred to the lower part of the absorber. Only a minor part of
the flashed solution is fed to the CO2 stripping column, where CO2 is stripped out
with steam to obtain a low residual CO2 loading. The lean solvent from the
bottom of the stripper is pumped to the top section of the CO 2 absorber.
In this way, nearly complete removal of CO2 can be achieved with de-carbonated
gas containing only 0.05 vol% CO2 (on dry basis) at the expense of very low heat
consumption.
Methanation
After CO2 removal, the de-carbonated gas contains 0.05% CO2 and 0.4% CO (dry
basis). These compounds are poisonous to the ammonia catalyst and must be
removed before the gas is pushed to the ammonia synthesis loop. This is
accomplished in the methanator, where CO and CO 2 react with H2 to form CH4,
which is harmless to the ammonia catalyst. The reaction takes place over a
nickel-based catalyst. The content of CO+CO2 is reduced to less than 5 ppm.
The inlet temperature to the reactor is maintained at around 300oC, and the
outlet temperature around 325 oC. The inlet gas is preheated by heat exchange
with the outlet gas in a feed/effluent gas-gas exchanger, with adjustment in the
inlet temperature being carried out in the trim heater.
Ammonia Synthesis
Compression
The synthesis gas is compressed from around 31 to 185-190 kg/cm2g in a
centrifugal type two/three casing synthesis gas compressor. Part of the last
casing serves the purpose of the recirculation compressor for the synthesis loop.
Synthesis Loop
The make-up gas from the compressor after cooler is introduced into the
synthesis loop between the two ammonia chillers. At this point, a
considerable part of the ammonia produced in the converter is condensed.
The mixture of the synthesis gas and liquid ammonia pass from the 2 nd chiller
to the ammonia separator, in which the liquid ammonia is separated. At the
outlet the gas contains 4.0 vol% NH3 and the temperature is 0 oC.
By the condensation of ammonia traces of impurities in the make-up gas,
such as H2O and CO2, are absorbed in the liquid ammonia phase and removed
with the liquid ammonia in the separator. In this way, the catalyst is
protected against poisoning by H 2O and CO2, and, is additionally protected
against the risk of plugging of the equipment in the loop due to formation of
ammonium carbamate, is eliminated.
In the hot heat exchanger, the gas is heated to the converter inlet temperature
by heat exchange with gas coming from the BFW preheater.
A considerable part of the heat content of the gas leaving the converter is
recovered in the waste heat boiler and in the BFW preheater. After the BFW
preheater, the gas is cooled first in the hot heat exchanger, mentioned above,
and then progressively in the heat exchangers like, the water cooler, the cold
exchanger, the 1st ammonia chiller, and the 2 nd ammonia chiller. Make-up
synthesis gas from compressor discharge is added in the pipe length between
1st and 2nd ammonia chillers.
The make-up gas contains a small quantity of inert gases like, CH 4 and Ar. In
order to prevent these gases from accumulating in the loop, a certain quantity
of gas circulating in the ammonia synthesis loop is purged.
The purge gas is vented from the ammonia synthesis loop after the 1 st
ammonia chiller, (prior to the make-up gas addition) where the concentration
of inerts in the loop is the maximum. The purge gas is sent to purge gas chiller,
where ammonia vapour in purge gas is condensed and separated in the purge
gas separator, and returned to the bottom of ammonia separator. The aqueous
ammonia is distilled in the distillation column together with aqueous
ammonia from the off-gas absorber, and the recovered ammonia is added to
the ammonia product in the let-down vessel.
The liquid ammonia is depressurized to 25 kg/cm 2g and taken to the let down
vessel, in which the gases dissolved in liquid ammonia, is liberated. The let
down gas contains a considerable amount of ammonia, which is recovered by
water wash in the off-gas absorber. The off-gases are mixed & sent to the fuel
header.
In the event product ammonia is sent to storage, it is flashed cooled to about
(-) 33oC in the flash vessel.
Refrigeration Circuit
The refrigeration circuit consists of a compressor unit, a condenser, an
accumulator and a number of chillers.
The unit is designed to operate in two modes depending on whether the
ammonia is sent to storage as cold product or, to the down stream urea plant as
hot product. Liquid ammonia flows from the accumulator, through the product
heater, to the 1st synthesis loop chiller, where it is expanded to 4.4 kg/cm2g
corresponding to a temperature of 5.8 oC. Liquid ammonia is transferred to the
2nd synthesis loop chiller, and purge gas chiller, where it is further expanded to
2.7 kg/cm2g corresponding to a temperature of 4 oC.
Evaporated ammonia from the chillers and the flash vessel, is compressed by the
ammonia compressor. The suction pressures correspond to the pressures in the
flash vessel and the chillers. After compression, the ammonia is condensed in the
ammonia condenser, and collected in the accumulator.
Inert gases accumulating in the refrigeration system are vented from the
ammonia accumulator. Ammonia is condensed in the inert vent gas chiller, and
separated in the inert vent gas separator. The gas, which still contains some
ammonia, is sent to the ammonia recovery unit. Evaporated ammonia is sent to
the ammonia compressor.
Ammonia Recovery:
Inert gas and let down gas from the let down vessel is introduced to the off -gas
absorber and ammonia is washed out with water. The aqueous ammonia from
purge gas absorber and off-gas absorber is sent to the distillation column, where
ammonia is distilled off and returned to the let down vessel.
A small quantity of air is added to carbon dioxide feed at CO2 compressor, suction
in order to passivate the stainless steel surfaces of HP loop equipment, thus
protecting them from corrosion from the reactants and reaction products.
The reaction products, leaving the reactor, flow to the upper part of stripper,
which operates at about 150 ata. It is a vertical falling film decomposer in which
the liquid is distributed on the heating surface as a film and flows by gravity to
the bottom. The HP stripper is essentially a vertical shell & tube exchanger with
heating medium on the shell side, with an extended tube side top channel head
specially designed for permitting uniform distribution of carbamate/urea
solution over the top/inlet tube sheet. In fact, each tube has an insert-type
distributor (ferrule) designed to distribute the feed uniformly around the tube
wall in the form of a film. The holes of the ferrule act as orifices and their
diameter and liquid head control the flow rate. As the liquid film flows
downwards, it is heated and decomposition of carbamate and surface
evaporation occurs. The carbon dioxide content of the solution is reduced by the
stripping action of the ammonia as it boils out of the solution. The vapour formed
(essentially ammonia and carbon dioxide) flows out from the top of the tube. The
carbamate decomposition heat is supplied by condensation of saturated steam at
23 ata.
The mixed stream of overhead gases from the stripper, and the recovered
solution from the bottom of medium pressure absorber, enters carbamate
condenser, where the condensing components of overhead gases other than the
non-condensables get condensed and the solution is recycled back to the urea
reactor, through carbamate ejector.
Condensation of overhead gases from stripper at a high pressure and
temperature permits production of steam at 6 ata in the carbamate condenser
and steam at 4.5 ata in the carbamate condenser.
The non-condensable gases coming out from the top of the carbamate separator,
consist of inert gases (passivation air plus inert with CO2 from B.L) containing
little quantities of NH3 and CO2, which are sent directly to the bottom of the
medium pressure decomposer.
Urea Purification and NH3 , CO2 recovery at Medium & Low Pressures
Urea purification and associated recovery of the overhead gases take place in
two different pressure stages as mentioned below:
• 1st stage at 18 ata pressure
• 2nd stage at 5 ata pressure
The exchangers where urea purification takes place are generally termed as
decomposers because in these equipment the residual carbamate present in urea
solution, are decomposed.
1st Purification and Recovery Stage at 18 ata Pressure
The solution, with low residual CO2 content leaving the bottom of the stripper is
expanded to a pressure of around 18 ata and enters the upper part of medium
pressure decomposer. This equipment is mainly divided into three sections.
Top Separator: The released flash gases are removed here, before the solution
enters the tube bundle.
Falling film type Decomposer: The carbamate solution is decomposed here.
Required heat is supplied by means of condensing steam at 6.0 ata (in the upper
part of the shell) and sub-cooling of steam condensate flowing out of the stripper
steam saturator (in the lower part of the shell).
Urea Solution Holder: Purified urea solution obtained from the 1st stage and
having a concentration of around 60-63% wt., is collected here.
The NH3 and CO2 rich gases, leaving the top of separator, are sent to the shell
side of the falling film vacuum pre concentrator, where they ar e partially
absorbed in aqueous carbamate solution coming from the recovery section at 5
ata.
The total heat generated in the shell side, due to
condensation/absorption/reaction of the reactants, is removed by evaporation
of urea solution, coming from the 2nd purification step. In the process,
concentration of urea solution increases to 8486% wt., thereby resulting in
considerable saving of LP steam in the vacuum concentration stage.
From the shell side of vacuum pre concentrator, the mixed phase is se nt to
medium pressure condenser, where CO2 is almost totally absorbed and
condensation/reaction heat is removed by cooling water coming from ammonia
condenser.
The mixed phase effluent from MP condenser flows to medium pressure
absorber bottom, where the released gaseous phase moves upwards across
tower and enters the rectification section. The medium pressure absorber tower
is fitted with bell cap trays. The bottom section of the tower is used for CO 2
absorption while the top part of the tower is utilised for NH3 rectification.
Pure ammonia is added as reflux to the top trays in order to balance the energy
entering the column, and to remove residual CO 2 and H2O contained in the rising
stream of gaseous ammonia and inerts. Reflux NH3 is drawn from the ammo nia
receiver, and sent to column by means of ammonia booster pump.
Saturated ammonia vapour along with inert, containing few ppm of CO 2 (20-100
ppm), and coming out from top of the rectification section, is partially condensed
in the ammonia condenser and the condensate is sent to the ammonia receiver.
Uncondensed vapours, saturated with ammonia, from ammonia receiver, goes to
ammonia recovery tower, where additional amount of ammonia is condensed
out from the vapours by scrubbing with liquid ammonia coming from the B.L.
The gaseous stream, leaving from top of ammonia recovery tower, enters at the
bottom of medium pressure falling film absorber. The residual ammonia content
in the gas is drastically reduced by absorption in a counter current downward
flow of ammonia water solution. Heat generated by ammonia absorption,
increases the temperature of descending liquid, thereby tending to impede
further ammonia absorption. To maintain the temperature at a reduced level, the
heat of absorption is removed by cooling water flowing through the shell side of
MP ammonia absorber.
The MP inert washing tower, connected to the upper part of MP ammonia
absorber, consists of three valve trays where the inert gases are subjected to last
stage of washing by means of pure water. Here the ammonia content of rising gas
stream is minimal and consequently the temperature is less sensitive to
absorption heat. Inerts containing traces of ammonia are finally vented through
the vent stack.
From the bottom of MP ammonia absorber, the NH3-H2O solution is recycled
back to the medium pressure absorber, by means of a centrifugal pump.
The MP absorber bottom effluent is recycled by means of centrifugal HP
carbonate solution pump to the synthesis recovery section.
Product Quality:
Total Nitrogen 46.4% min. (wt dry basis)
Biuret 0.8% max. (wt)
Water 0.25% max. (wt)
Particle size 1.0 to 2.4 MM 97% min.(wt) Temperature ≤ 60 oC
As suggested by HTAS the Combustion Air Preheater of heat duty 13.85 Gcal/hr
with modified plate type design has to be replaced in Primary Reformer.
CO2 Removal Section
For CO2 removal Section, HTAS has suggested revamp of present Benfield
Process (single stage regeneration) by converting it into Giammarco -Vetrocoke
(GV) i.e. two stage regeneration process. After implementation of suggested
modification, the CO2 Removal Section shall be suitable for 1750 MTPD
ammonia including PGR unit.
New HP Waste heat boiler will be installed at the down stream of existing
converter for utilisation of the reaction heat generated in the existing converter.
The existing HP Waste heat boiler will utilise the heat of reaction from the new
S-50 converter.
Synthesis Gas Compressor
With the installation of S-50 converter and Waste Heat Boiler, conversion per
pass will increase and loop pressure will come down. The above retrofits will
help in operating the plant at higher capacity.
Process Air Compressor
Due to the increased process airflow and the higher inlet pressure of the
secondary reformer, the existing Process Air Compressor cannot perform
under revamp case conditions. Hence, an additional process air compressor of
6000 Nm3/hr is to be installed to run the plant at enhanced capacity.
New Equipment
1.0 Ist Waste Heat Boiler (E-1501A)
2.0 LP GV Stripper overhead separator (B-2304)
3.0 LP Steam Boiler (E-2301)
4.0 GV Solution DMW Preheater (E-2304)
5.0 LP GV Stripper overhead condenser (E-2307)
Sl. No. Code / Name
Urea Plant
Based on enhanced capacity of Ammonia Plant with sufficient CO 2 for full
conversion to urea, the Urea plant capacity is proposed to be enhanced from
2620 MTPD to 3030 MTPD for both streams together. For enhancement case,
the bottlenecks identified and debottlenecking measure undertaken in Urea
plant are as follow:
CO2 Compressor (11/21-K-01 A)
The carbon dioxide feed drawn to the Urea Unit battery limits, from the
relevant Ammonia Unit enters the CO2 compressor, K-01, and leaves it at a
pressure of about 160 kg/cm2(g).
A new steam booster ejector shall be installed to boost the generated steam
pressure and provide the heat for decomposition of Carbamate in MP Pre -
decomposer.
MP Pre-decomposer (11/21-E-53)
Ammonia Pumps are located in Urea Plant for feeding the Synthesis loop. The
existing pumps cannot cater the desired enhanced production level and hence
two new reciprocating pumps of 20 m3/hr each shall be installed.
With enhanced capacity, during peak summer days, urea prills temperature is
expected to reach as high as 74oC with present Prilling Tower, having 28 meter
diameter and 72.5 meter freefall height, maintaining the same prill size
distribution. To bring down prill temperature at higher capacity to acceptable
limit, a new Bulk Flow Prill Cooling System of 140 te/hr capacity is proposed
for installation, as modification of existing Prilling Tower for increasing freefall
height is not a cost effective proposition.
For capacity enhancement measures, following schemes as given in below are
envisaged in Urea Plant to achieve production of 3030 MTPD:
The existing heat duty of Ammonia and Urea cooling tower is not adequate to
meet the requirement of enhanced capacity production. In Urea cooling tower,
one additional cooling tower cell of 2500 m 3/hr capacity (induced draft type)
along with new centrifugal pumps (1+1) of 2500 m 3/hr capacity shall be
installed.
Reduction in Specific Energy Consumption
The reduction Specific Energy Consumption for Ammonia & Urea from existing
energy after capacity enhancement measures as under:
(Gcal / MT)
Reduction in specific energy consumption of 0.34
Ammonia-I
Reduction in specific energy consumption of Urea-I 0.17
(taking impact of increase due to CDR plant and saving
by steam)
M/s. HTAS has submitted their report for 1800 MTPD capacity of Ammonia
Plant. Increasing the load on Synthesis section by avoiding burning of surplus
synthesis gas, addition production 64 MTPD of Ammonia shall be achieved.
Therefore, the total capacity augmentation shall be of 1864MTPD .
Primary Reformer
The fired duty of the primary reformer is higher in the revamp case than in
present operation, meaning that the load on the burners, the ID fan and the FD
is slightly higher than at Base Case conditions. The total fired duty comes out as
207 Gcal/hr, corresponding to an average duty per burner of 345,000 kcal/hr,
which is slightly higher than the maximum heat liberation of the burners as per
burner curves. Therefore, the burners shall be replaced with higher heat
release.
Secondary Reformer
The secondary reformer burner as such is adequate for the new conditions, the
nozzles are to be replaced with larger nozzles.
Synthesis Gas Compressor
The conditions for the steam turbine driver, TK 3431, will be very close to the
operating margin of the turbine.
The hydraulics of the columns in the CO2 removal section has been checked by
Giammarco-Vetrocoke (GV).Their conclusion is that the target of 1864 MTPD of
NH3 is just at the limit of the unit’s capacity, and the CO 2 slip will go up.
Replacement of packings shall be done.
Pumps
The required flow rate is slightly higher than rated flow. The pump is unable to
deliver the required flow and therefore, new larger impellers are to be
installed. The motor drive of P 3301 C is already at present load a limitation.
The motor is to be replaced with higher capacity.
P 3302 A/B, Lean Solution Pump
The required flow rate is slightly higher than rated flow. The pump is unable to
deliver the required flow and therefore, new larger impellers are to be
installed.
P 3321 A/B, Excess Condensate Pump
The pump is already at present conditions too small. New pumps shall be
installed.
4.2.7 Blowers
S-50 Converter
The higher conversion reduces the load on the refrigeration compressor in that
the dew point goes up and more condensation takes place in the water cooler.
The converted gas from the S-200 converter is cooled in the new waste heat
boiler to the correct inlet temperature to the new S-50 converter. The
converted gas from the S-50 converter is going to the existing waste heat boiler
for further heat recovery. A bypass should be installed around E-3502, boiler
feed water preheater, to achieve an outlet temperature sufficiently high to
preheat the synthesis gas in E-3503. The remaining loop configuration shall be
maintained unchanged.
Because of increase in capacity, decomposition duty will increase for the Plant.
To cater this additional decomposition duty, installation of new MP Pre -
decomposer upstream of existing MP Decomposer shall be done.
LP Steam Booster Ejector (31/41 EJ-53)
Existing Urea Melt Pump is not suitable for enhanced capacity operation.
Impeller modification shall be done for these pumps for use in the revamped
Plant.
4.3.13 Steam Condensate to BL Pump (31 P-13A/B)
Existing Pumps are not suitable to handle the extra load of enhanced capacity
operation. Impeller replacement shall be done for these pumps in the revamped
Plant.
4.3.14 Hydrolyser Feed Pump (31 P-14A/B)
Existing Pumps are inadequate to handle the extra load of enhanced capacity
operation. Impeller replacement together with new motor shall be done for
these pumps in the revamped Plant.
4.3.15 Bulk Flow Prill Cooler (31 ME-54)
With enhanced capacity of the plant, during peak summer days, urea prill
temperature is expected to reach as high as 67 deg.C. with present Prilling
Tower having 26 meter diameter and 80 meter free fall height, maintaining
same prill size distribution. To bring down Prill temperature at higher load to
acceptable limit, a new bulk flow prill cooling system shall be installed.
4.4 Revamp Measures in Offsite & Utilities
Existing Offsite and Utility facilities shall be adequate for enhanced capacity
operation of main ammonia and urea Plants.
4.4.3 Reduction in Specific Energy Consumption
The reduction Specific Energy Consumption for Ammonia & Urea from existing
energy after capacity enhancement measures as under:
(Gcal / MT)
Reduction in specific energy consumption of 0.12
Ammonia-II
Reduction in specific energy consumption of Urea-II 0.06
(taking impact of increase due to CDR plant and saving
by steam)
Carbon Dioxide Recovery Plant (CDR)
The prominent processes that are available for CO 2 recovery from flue gas are:
ABB Lummus, USA.
Mitsubishi Heavy Industries, Japan
KTI (Flour Daniel)
The process steps followed by all technologies are similar. The general process
description for CO2 recovery has been presented hereunder.
Process Description
Integration of CO2 Recovery Facility
Modification to the existing facility will include construction of a flue gas duct
connecting the CO2 Recovery Plant to the existing stack. The flue gas will be
extracted from the stack and brought to the CO2 recovery plant by a flue gas
blower. The flue gas shall be emitted directly to the atmosphere through the
stack in case of failure of the flue gas blower. Therefore, operation of the flue
gas source will not be affected by a failure of the CO 2 recovery plant. The
treated flue gas from the top of the absorber will be returned to the stack.
5.2.2 CO2 Recovery Plant
The CO2 Recovery Plant shall consist of three main & one intermittent section:
Flue gas pretreatment Section
CO2 Recovery Section, and
Solvent Regeneration Section.
Solvent Reclaiming
5.2.3 Flue Gas Pre-treatment
The purpose of flue gas cooling system is to adjust the incoming flue gas
temperature to an optimum condition for CO2 recovery.
Lower flue gas temperature is preferred for the exothermic reaction of CO2
absorption. The optimum temperature range for CO 2 recovery is between 40 oC
to 45 oC considering utility costs.
The flue gas is to be cooled through direct contact with water in the flue gas
water cooler.
5.2.4 CO2 Recovery
CO2 Recovery and flue gas wash is conducted in the CO 2 absorber. The CO2
absorber has two Main Sections- CO2 absorption section (bottom section), and
the treated flue gas washing section (top section). The conditioned flue gas
from the Flue gas water cooler; shall be introduced into the bottom section,
while the CO2 lean solvent shall be distributed evenly from the top of the
absorption section onto the packing material. The flue gas shall come into
direct contact with the solvent on the surface of the packing material, where
CO2 in the flue gas shall be absorbed into the solvent. The flue gas then shall
move upward into the treated flue gas washing section, located on the top
section of CO2 absorber. This section is similar to the Flue gas water cooler;
where the flue gas shall come into direct contact with water to be washed by
amine content in it, as well as to be cooled down to maintain water balance
within the system. The treated flue gas shall be exhausted from the top section
of the CO2 absorber to the Stack. Meanwhile, the spent solvent shall be collected
at the bottom of the absorber. The spent solvent, known as the CO 2 rich solvent,
shall be directed to the Regenerator for regeneration.
5.2.5 Solvent Regeneration
The rich solution pump shall transfer the rich solvent from the bottom of the
CO2 absorber to the lean/rich solution Heat Exchanger for the rich solvent to be
heated up by the lean solvent form the bottom of the Regenerator. The heated
rich solvent shall be then introduced into the upper section of the Regenerator,
where it shall come into contact with stripping steam. The rich solvent shall be
steam-stripped off its CO2 content through the packing material of the
Regenerator, and shall be converted to the lean solvent. Steam shall be
produced by the Regenerator Reboiler, which uses LP steam to boil the lean
solvent. The lean solvent at the bottom shall be then directed to the Lean
Solvent Pump through the Lean/Rich Solution Heat Exchanger. The lean
Solvent pump shall force the lean solvent to the Lean Solvent Cooler, where it
shall be cooled to the optimum reaction temperature of approximately 40 oC
before being reintroduced to the top of the absorption section in the CO 2
absorber.
5.2.6 Solvent Reclaiming (Intermittent Operation)
A reclaimer unit shall be provided in order to eliminate the salts. When the salt
content in the solvent is reached to the maximum set limit, the reclaimer shall
be operated to boil down the solvent so that the salts can be concentrated to be
as sludge for discharge. The expected reclaimer operation frequency shall be
low.
5.3 Capacity of CDR Plant to be installed:
The increase in specific energy of Urea due to the power and steam consumption
in CDR plant shall be 0.047 Gcal/Mt of urea.
***************************************************************************