Construction Engineering of Phu My Cable-Stayed Bridge, Vietnam
Construction Engineering of Phu My Cable-Stayed Bridge, Vietnam
Construction Engineering of Phu My Cable-Stayed Bridge, Vietnam
Bridge, Vietnam
Summary
Abstract
The Phu My Bridge will span the Saigon River between Districts 7 and 2 in Ho Chi
Minh City. The bridge will form part of a new ring road currently under construction
around Ho Chi Minh City. The ring road will be an important transport link from the
southern Mekong delta region to the central and northern parts of Vietnam.
The Phu My Bridge contract includes the design and construction of a 705m long
cable stayed main bridge with a clear span of 380m, as well as the approach
structures on either side being approximately 758m on District 7 and 638m on District
2.
The main span deck will be 27m wide. Clearance to river traffic is provided with 45m
vertical clearance in a 250m wide zone. The pylons carrying the deck are designed
as an H frame and are approximately 140m high.
The main bridge deck is designed as an insitu reinforced and partly post tensioned
concrete slab supported on longitudinal and transverse beams and suspended from
the pylons by the stay cables.
This paper describes the bridge, the method used to construct and the construction
engineering used for the stage by stage analysis of the bridge and the on site role to
control the cable forces and bridge geometry during construction of the bridge.
George has more than 16 years experience in design, construction and management
of multi-disciplinary infrastructure projects including mass transit, tunnelling, bridges
and elevated structure works. He has worked extensively within Europe and has over
10 years experience in the Asian region.
Peter has over 18 years experience in structural analysis and design of over 15 stay
cable bridges. From his stays in the USA, Korea, Hong Kong and Australia he gained
extensive knowledge on design and construction engineering.
Martin has over 5 years experience in structural analysis and design of several stay
cable bridges in different countries. In the company he is responsible for the software
application for the bridge design.
Synopsis
The Phu My Bridge will span the Saigon River between Districts 7 and 2 in Ho Chi
Minh City. The bridge will form part of a new ring road currently under construction
around Ho Chi Minh City. The ring road will be an important transport link from the
southern Mekong delta region to the central and northern parts of Vietnam.
The Phu My Bridge contract includes the design and construction of a 705m long
cable stayed main bridge with a clear span of 380m, as well as the approach
structures on either side being approximately 758m on District 7 and 638m on District
2.
The main span deck will be 27m wide. Clearance to river traffic is provided with 45m
vertical clearance in a 250m wide zone. The pylons carrying the deck are designed
as an H frame and are approximately 140m high.
The main port, which is located slightly downstream (or south) of the centre of the
city and is forecast to be re-located further downstream within the next 10 years,
generates considerable heavy goods traffic. In addition a significant amount of
goods from manufacturing in the Mekong Delta also travels up though HCMC. Such
traffic currently crosses the Saigon River at the most southerly bridge, the Saigon
Bridge, located in the central district of HCMC. A reduction of the traffic congestion
in the centre of the city is necessary to insure efficient transportation conditions and
will be realized by the creation of an inner ring road, including the large Phu My
Bridge over the Saigon River linking the Southeast quadrant to the rest of the city.
In October 2005 the client, Phu My Bridge Corporation (PMC) signed an agreement
with BBBH for the design and construction of the bridge. PMC as the Client is a
private consortium comprising Hanoi Construction Company, Investco, Cienco 620,
Thanh Danh Co, and CII. PMC has a 30 year BOT license to operate the bridge
which will be part of a toll road. The project cost is US$105 million.
3. Project Team
Construction of the bridge is being done by BBBH Consortium while the approach
viaducts have been subcontracted to Vietnamese contractor, Chau Thoi Concrete
Corporation 620 under close supervision of BBBH. Freyssinet have been engaged
as a specialist subcontractor for the installation of the cable stays, prestress, and
heavy lift.
Design of the main bridge and approach structures permanent works was split into
two packages. The main bridge design was produced in France by the consultant
Arcadis, whilst the approach structures were designed in Australia by Cardno.
A separate package was then created for the design of main bridge temporary work
and the construction engineering for the main bridge. This was a combined effort
between Cardno and Leonhardt, Andrä und Partner (LAP) from Germany. This
paper focuses on these aspects particularly the work carried out prior to construction
and the ongoing role during construction.
The chart below shows project organization for the Main Bridge
Phu My Bridge Corporation
Maunsell Vietnam
(The Employer’s
Representative)
BBBH Consortium
4.1 Substructure
The pilecap construction was carried on in many phases. As the pile cap does not lie
on the ground, a metallic frame was fixed at the top of the pile, supporting thin (20
cm) concrete slabs, on which a first pour (approximately 1.00 m) was carried out.
The rest of the pile cap is then poured when the first lift has reached sufficient
capacity to support the loads. The lateral formwork of the pile cap is made of precast
skirting panels, which extends below low water keeping the pilecap base above low
water level and ensuring a dry working area.
The pylons towers are H shaped. Each leg is a box section. The outer dimension
varies from 5.50 x 7.00 m to 3.00 x 5.00. The stay anchorages are located inside the
box. The legs are linked by 2 cross beams.
The tie down piers are located at the end of each cable stay back span. The pie
down piers are twin rectangular columns with vertical prestress supported on large
diameter bored piles. The tie down pier is used to connect the last three stay cables
on the back span. The deck slab is solid concrete and is prestressed in both the
longitudinal and transverse directions.
The total width of the main span deck is 27m, this incorporates three lanes of traffic
in each direction, two car and truck lanes, a separated motorcycle lane and footways
for pedestrians.
There are two vertical planes of stay cables. The structure of the deck is composed
of two longitudinal concrete girders linked by transverse prestressed concrete cross
girders at 5m centres. The stay cables are connected to the longitudinal edge beams
by precast anchor pods located every 10m
• Construct the lower cross beam on the pilecap, attach the piertable falsework
and the precast anchor pods for the first segments.
• Use the lower strut to lift the lower cross beam and pier table falsework. This
heavy-lift was carried out by Freyssinet and involved lifting the 1200t assembly
30m into the air. Once the cross beam was in its correct position, stitch the
lower cross beam to the tower leg;
• Once the lower cross beam was connected and stitched the pier table could
be cast. This was done in three stages; first the central 10m was cast
followed by the 10m on the side span and then the 10m on the main span. It
was important that the deck construction could start as soon as possible and
not have to wait until the completion of the towers.
• Continue building the tower legs and install the intermediate strut 70m above
the pilecap. Remove lower strut. The intermediate strut is a needle beam
used to control the forces in the tower legs. It is also used to support a catch
platform for safety during the construction of the upper cross beam;
• Install upper strut. The upper strut acts as both a brace for the tower legs and
to support the formwork for the upper cross beam. Construct the upper cross
beam, remove the intermediate and upper strut and complete the tower legs
construction.
• Install and stress the first stays between the pier table and the tower. Release
and lower the pier table formwork and then lift the form travellers into position
ready to start deck construction. At this stage the geometry of the deck is
controlled by the length of the stays more than the force since the deck was
free to pivot on the bearing. The stays were installed in 25% increments up to
75% of their installation force. At this stage another survey was carried out
prior to making a final adjustment to the cable length.
The following overall construction sequence was used for the main bridge.
d) - D7 Sidespan Closure
After 15 segments are cast the 1.5m long side span
closure is cast. A survey is carried out prior to the
closure and the deck is position by releasing the
temporary tie down cable. The pour is carried out in the
evening to limit the temperature effects on the new
concrete.
The deck is constructed in balanced cantilever starting from each tower. 10m long
segments are cast using a form traveller. The typical erection sequence is as follows
• Complete launch and raise traveller. Survey position of traveller and make
adjustment to alignment if required;
• Place precast cross girders and edge beam reinforcement cages. Required
concrete strength 40MPa;
• Start fixing deck reinforcement. Up to 25t of rebar could be placed before stay
installation;
• Install and stress stay cable. The stay cable is attached to the anchor pod
which is stressed to the traveller. The horizontal component of the load is
transferred to the previous segment via the longitudinal strut. The vertical load
component of this first stay force is kept constant at about 100t for each stay,
which helped support the traveller during casting of the concrete. Required
concrete strength 45MPa;
• Complete deck reinforcement and carry out prepour survey and cast new
Segment.
After the initial learning phase this cycle was regularly achieved in 5 days with the
sidespan cycle lagging 2 days behind the main span cycle.
BBBH engaged Cardno and LAP to carry out the construction engineering and the
design of some of the major temporary works. Prior to construction commencing on
site the Construction Engineer agrees with the contractor the following:
Once this is done the Construction Engineer models the sequence including
consideration of the time dependant effects. To do this a sophisticated stage by
stage analysis of the bridge was carried out.
It software program also possesses a powerful solver which can determine the forces
to be applied to each stay at installation such that the forces at the end of
construction are the same as those calculated by the permanent works designer.
This is done by the program which solves a set of simultaneous equations with the
constraints being the final stay forces, tower forces, etc. The input variables are the
stay stressing forces and other adjustments such as jacking prior to the closure
pours.
Once the stay forces are calculated the camber curves and support reactions will be
calculated. The purpose of the analysis was to achieve a clear understanding of the
following;
• Exact forces and deflections of all parts during all erection stages;
• Forces in the buffeting cables and temporary tie down cables;
• Forces in the temporary falsework at the hold down pier
The erection analysis was based on the results of the permanent works design and
took into account the most accurate actual parameters, dimensions and weights. In
doing this special care was taken to address
• Dead weight, actual concrete density and reinforcement content;
• Section properties;
• P/T forces;
• Shrinkage and creep values
Based on their previous experience of cable stay bridges and working in Vietnam
BBBH had a clear view of how they wished to construct the bridge such that it would
be quick and economical to build.
During the construction the role of the construction engineer included the following:
In the morning following the casting of a deck segment the following information is
obtained:
• A survey is carried out of the last four segments on the leading edge plus the
tower.
• In addition a load map is taken of the major loading on the deck such as
reinforcement stock, strand, mobile crane
• A lift off test is done on the cable on the new segment to determine the stay
force.
Adjustments to the traveller shims affect the local curvature while changes to the stay
force have a greater effect on the overall geometry of the bridge. During construction
the results from the survey were studied to check the accuracy of the analysis, some
of the variables for which sensitivity analysis was carried out included:
During the construction of the bridge deck it was noted that the deflections of the
bridge were greater than that predicted by the model. As noted there are several
possible reasons for this occurring, however, one of the more likely seemed to be an
increase in the traveller weight and deck weight. During the erection of the bridge
the stay forces were increased by 1.5% above their design values to balance these
deflections.
In summary this paper highlights some of the features used for the speedy
construction of a cable stay bridge.
The project required significant planning and design to agree and optimize the
construction methods. This involved a lot of collaboration between the contractor
and construction engineer and has resulted in relatively few issues occurring during
the construction process and a rapid achievement of the 5 day construction cycle
with a short ‘learning process’. The role of the construction engineer both in the
preconstruction and construction phase forms an important part of this team.
A contract duration of 34 months was originally anticipated with the project scheduled
to be open to traffic by the end of 2009. At the time of writing it is planned to
complete the bridge in 32 months. This will allow the bridge to be opened for traffic
in October 2009.