JACKHAMMER DRILLING CORP.

[DOCUMENT TITLE]

“Mud and Cementing Program for the


Drilling Plan of Panda-1
Exploration Well”
JACKHAMMER DRILLING CORP. [DOCUMENT TITLE]

WELL PLANNING

1) Well Trajectory:
PANDA-1 is planned as a vertical exploration well with the following Surface / Bottom Hole
Coordinates and Target Radius:
Latitude : 00° 44’ 01.96” S
Longitude : 118° 20’ 31.09” E
Datum : WGS-84 UTM Zone 50S
Target Radius : ±150 feet

2) Well Bore Geometry and Casing Design:


PANDA-1 is planned as a vertical deepwater exploration well with the following well bore geometry
and casing design as summarized in the attached Well Summary Sheet.

Size (OD) Weight (ppf) Grade Connection Top Bottom


30 13.6 7,800 10,500
20 12.4 L-80 10,500 12,500
14 10.9 P-110 12,500 14,885
9 5/8 9.7 N-80 14,885 17,385
7 8.6 C-75 17,385 19,685

3) Cement Planning:
The cementing program for PANDA-1 is summarized below with further details included in the
attached Well Summary Sheet.

Size (OD) Depth Lead Slurry Tail Slurry Est. TOC


30 2,700 7,800
20 2,000 10,500
14 2,385 12,500
9 5/8 2,500 14,885
7 2,300 17,385
JACKHAMMER DRILLING CORP. [DOCUMENT TITLE]

4) Rig and Drill Bit:


The Drilling Rig to be used for the PANDA-1 deepwater exploration well is the moored semi-
submersible “Ocean Monarch” rated for 10,000’ water depth provided by PT. Aquaria Prima
(Diamond Offshore Drilling Company). The proposed Drill Bit Program is as follows:
Size (OD) Type Nozzles TFA
26” Tri-Cone 3 x 22/32” 1.362 in2
1 x 18/32”
17 ½” PDC Bit 9 x 13/32” 1.317 in2
1 x 14/32”
12 ¼” x 14 ¼” BC Bit 7 x 12/32” 1.292 in2
4 x 13/32”
10 ⅝” x 12 ¼” BC Bit 5 x 13/32” 1.294 in2
2 x 14/32”
2 x 15/32”
8 ½” PDC Bit 6 x 15/32” 1.035 in2

DRILLING PROGRAM
1) Drilling Program Worksheet:
Well Type : Exploration
Well Deviation : Vertical
Rig Name / Type : Ocean Monarch / Moored Semi-Submersible
Surface Location : Latitude: 000° 44’ 01.96” S
Longitude: 118° 20’ 31.09” E

Datum : WGS-84 UTM Zone 50S


Secondary Objective : Upper Miocene Sandstone
Top @ 15,149’ TVD SS (±200’ TVD)
Bottom @ 16,786’ TVD SS (±200’ TVD)
Primary Objective : Middle Miocene Sandstone
Top @ 17,750’ TVD SS (±200’ TVD)
Bottom @ 19,597’ TVD SS (±200’ TVD)

Planned Total Depth : 19,685’ TVD RT (± 200’ TVD)


Total Time (Rig Days): 82.42 Days

Calculation for pressure:


a. From 19685 ft:
Mud Line depth = 7,400
Depth from mudline = 19,685 – 7,400 = 12,285
P = 0.052h = 0.052 x13.6 x12,285
= 8687.952 psi

b. From 17,385 ft.:


Mud Line depth = 7,400
Depth from mudline = 19,685 – 7,400 = 12,285
P = 0.052h = 0.052 x13.6 x12,285
= 6438.328 psi
JACKHAMMER DRILLING CORP. [DOCUMENT TITLE]

c. From 14,885 ft.:


Mud Line depth = 7,400
Depth from mudline = 14,885 – 7,400 = 7485
P = 0.052h = 0.052 x13.6 x 7,485
= 4242.498 psi
d. From 12,500 ft.:
Mud Line depth = 7,400
Depth from mudline = 12,500 – 7,400 = 5,100
P = 0.052h = 0.052 x13.6 x 5,100
= 2572.44 psi
e. From 10,500 ft.:
Mud Line depth = 7,400
Depth from mudline = 10,500 – 7,400 = 3,100
P = 0.052h = 0.052 x13.6 x 3,100
= 1386.32 psi

Casing Program
Preliminary Design SF

Weight Hole Depth Burst


Size Grade Thread Collapse Tensile
Casing (ppf) Size (ft RT)
Conductor 30 30 2300 1,740
Surface 20 163 L-80 26 2500 2,770 3478
Intermediate 14 92.68 P-110 17 1/2 2385 4,710 2924
Liner
9 5/8 53.5 N-80 12 1/4 2000 6,620 1350
Liner
7 38 C-75 8 1/2 2700 10,680 680

Mud Program

Interval (MD / TVD RT) Hole Mud Mud


From To Size Type Weight
19,685 17385 8½ 13.6
17,385 14885 12 ¼ 12.4
14885 12500 17 ½ 10.9
12500 10,500 26 9.7
10,500 7,800 30 8.6

Blowout Preventer Program

Casing Status BOPE Arrangement

20”, 13 5/8”, 11¾”,9 5/8”, 7” 21 ¼”, 15k psi, Annular, Double & Single Rams
JACKHAMMER DRILLING CORP. [DOCUMENT TITLE]

5) Drilling Time Curve:


JACKHAMMER DRILLING CORP.
[DOCUMENT TITLE]