AS3000 Checklist
AS3000 Checklist
AS3000 Checklist
Electrical installations
Inspected by:
Inspection date:
1.2 All wiring installed according to AS3000 Wiring rules in addition to AS3012 requirements. Yes No
2.1.2 All electrical equipment and lighting supplied from a 30mA RCD protected circuit Yes No
breaker(s).
2.1.3 Source of supply identified. Yes No
2.3.1.1 Switchboard readily accessible. Yes No
2.3.2.1 (c) Live parts effectively protected and warning sign attached along an electric shock Yes No
symbol.
2.3.2.1 (d) Insulated tie bar for extension leads to prevent strain on socket /outlet Yes No
2.3.2.1 (e) Switchboard door is lockable, non-removable without a tool and
fitted with a retention device to stay in open position.
2.3.2.1 (e) Switchboard has means of safe entry of leads and label: KEEP CLOSED –RUN LEADS Yes No
THROUGH BOTTOM
2.3.3 Switchboard mounted on a polo, structure, wall or suitably designed free standing design. Yes No
2.4.1 Switchboard gas a main isolation switch capable of isolation all downstream circuits. Yes No
2.4.2 Main switch capable of being locked or within a lockable space. Yes No
2.4.3 Main switch labelled appropriately: MAIN SWITCH or DISTRIBUTION BOARD ISOLATION SWITCH Yes No
or similar.
2.5.3 Construction wiring installed in appropriate conduit to protect against mechanical damage. Yes No
2.5.4 Construction wiring labelled with yellow tape with words ‘construction wiring’ at distances not Yes No
longer than 5m.
www.act.gov.au/accesscbr
Electrical installations
2.7.3 Emergency lighting adequate for safe exit of workers (if applicable). Yes No
2.8.1 If a lift shaft is present, the final sub-circuit feeding it is locked and tagged to prevent inadvertent Yes No
isolation of supply.
2.9 Socket outlets in site sheds and other transportable structures are RCD protected. Yes No
3.8.3 Portable equipment including power leads are inspected at three-monthly intervals. Yes No
3.8.3 Switchboards, wiring and site sheds are inspected at six-monthly intervals. Yes No
3.10 Register available for equipment and includes records of testing and tagging. RCD trip time results Yes No
and list of repaired equipment.
Action required:
Re-inspected by:
Compliance date:
www.act.gov.au/accesscbr