Steam Turbines
Steam Turbines
Steam Turbines
Contents
1 Scope............................................................. 2
2 Conflicts and Deviations................................ 2
3 References..................................................... 2
4 Design............................................................ 3
5 Inspection and Testing................................... 5
6 Installation...................................................... 6
1 Scope
This standard defines the mandatory requirements governing the design and installation
of general and special purpose steam turbines. This standard may not be attached to or
made a part of purchase orders.
2.1 Any conflicts between this standard and other applicable Saudi Aramco
Engineering Standards (SAESs), Materials System Specifications (SAMSSs),
Standard Drawings (SASDs) or industry standards, codes and forms shall be
resolved in writing by the Company or Buyer Representative through the
Manager, Consulting Services Department, Saudi Aramco, Dhahran.
2.2 Direct all requests to deviate from this standard in writing to the Company or
Buyer Representative, who shall follow internal company procedure SAEP-302
and forward such requests to the manager, Consulting Services Department,
Saudi Aramco, Dhahran.
3 References
The selection of material and equipment and the design, construction, maintenance and
repair of equipment and facilities covered by this standard shall comply with the latest
edition of the references listed below, unless otherwise noted.
Page 2 of 11
Document Responsibility: Compressors, Gears and Steam Turbines Standards Committee SAES-K-501
Issue Date: 27 March 2016
Next Planned Update: 27 March 2019 Steam Turbines
4 Design
4.1 General
4.1.1 Normally, general-purpose steam turbines shall only be used when the
driven equipment is spared. General-purpose steam turbines shall not be
used for any of the following applications:
Having a driver rated power exceeding 2.5 MW.
Having a maximum continuous speed (MCS) exceeding 6,000 RPM.
Having steam conditions exceeding a pressure of 4,800 kPa gauge
(700 psig) and a temperature of 400°C (750°F)
Driving process gas compressors
For extraction or induction steam turbine applications
Page 3 of 11
Document Responsibility: Compressors, Gears and Steam Turbines Standards Committee SAES-K-501
Issue Date: 27 March 2016
Next Planned Update: 27 March 2019 Steam Turbines
4.1.5 The part load steam rates of the steam turbines shall be part of the
technical bid evaluation.
4.1.7 The cost of condensate loss from gland condenser drains shall be
calculated to determine if installing a condensate pumping system is
justified to recover the condensate and return it to a condensate header.
Steam pressure assisted pumps may be used for this application.
4.1.8 Packaged units shall be considered for ease of installation and for the
increased reliability obtainable when all instrumentation, piping and
electrical connections can be made under controlled conditions in the
vendor's shop. When single lift packaged units are specified, the turbine,
the gear (when required) and the driven equipment shall be mounted on a
single baseplate and shall be completely piped, wired and functionally
tested under controlled conditions at the point of manufacture.
4.2.2 The turbine casing shall be protected with a pressure relief valve
installed in the piping in accordance with SAES-J-600.
Page 4 of 11
Document Responsibility: Compressors, Gears and Steam Turbines Standards Committee SAES-K-501
Issue Date: 27 March 2016
Next Planned Update: 27 March 2019 Steam Turbines
4.3 Piping
4.4 Lubrication
For general-purpose steam turbines with steam inlet pressure of 600 # and
above, a circulating oil system shall be provided. For general-purpose steam
turbines 1000 HP and larger, pressurized oil system shall be provided regardless
of steam inlet pressure.
For the above, witnessing shall be clearly specified on the Data Sheet and the
Inspection Plan.
All steam turbines shall receive a mechanical running test, witnessed for
turbines rated above 1000 kW (1350 HP). Turbines rated 1000 kW (1350 HP)
and below shall be run tested and vendor's test certificates shall be provided.
The contract governor shall be used during the shop test when possible.
Bearings shall be inspected following the mechanical running test.
Page 5 of 11
Document Responsibility: Compressors, Gears and Steam Turbines Standards Committee SAES-K-501
Issue Date: 27 March 2016
Next Planned Update: 27 March 2019 Steam Turbines
The bearings shall inspected following the mechanical running test. Seals shall
be dismantled for inspection only in the event of an unsuccessful test.
6 Installation
Turbine inlet steam piping shall be designed to branch upwards from the main
horizontal steam header a minimum of 2.0 meters to reduce entry of condensate
slugs into the turbine. Piping installation, fit-up, and connection tolerances shall
be in accordance with SAES-L-350. Main inlet steam pipe shall be rigidly fixed
within 1.5 meters of the turbine inlet flange. Piping size shall result in steam
flow velocity limits less than that required in NEMA SM23. For all steam
turbines except general-purpose, the number and location of temperature and
pressure devices shall be in accordance with ASME PTC 6, to ensure that an
acceptable field test can be performed. As a minimum, tappings shall be located
on the piping to allow for the necessary instrumentation for testing.
Temperature and pressure local gauges and/or indicating transmitters shall be
installed with taps within 3 diameters of each steam turbine casing inlet,
extraction, induction or exhaust nozzle. A flow meter shall be installed on the
steam inlet piping on all steam turbines larger than 500 HP.
Cold springing of piping shall only be permitted when all alternative methods of
reducing piping loads have been exhausted and then only with the written
permission of the manager, Consulting Services Department.
Steam turbine block valves for the steam inlet, exhaust, extraction, and induction
shall be located within ten pipe diameters of the respective turbine flange.
Trip and throttle valves are not qualified as block valves. General-purpose
steam turbines shall have the steam inlet block valve located within five pipe
diameters of the turbine flange. Steam traps or by-pass orifices shall be installed
at the piping low points on steam inlet and induction piping.
Page 6 of 11
Document Responsibility: Compressors, Gears and Steam Turbines Standards Committee SAES-K-501
Issue Date: 27 March 2016
Next Planned Update: 27 March 2019 Steam Turbines
Header warming lines and trip and throttle valve blow down connections shall
be vented to atmosphere through a silencer discharging horizontally in a safe
direction. Piping and valves connecting to the trip and throttle valves blow
down connection shall not be smaller than the blow down flange size.
Back pressure turbines with upward exhausts shall have exhaust casing drains
and piping low point drains connected to both a valved drain to atmosphere and
a steam trap.
Inlet steam headers for inlet steam conditions with greater than 10°F superheat
shall be designed with a full diameter piping tee installed upstream of the trip
and throttle valve. Flow to the trip and throttle valve shall be from the tee
branch. The straight through run of the tee shall connect to the inlet steam
piping on one end and to a flanged piping extension of at least four diameters
length which is fit with a piping cap. The piping cap shall have a valved drain
with a steam trap and bypass to a condensate collection header.
Steam turbines operating with less than 10°F superheat at the inlet or induction
flange (not at the steam generator or steam drum) shall be furnished with an
inertial moisture separator installed not more than 10 diameters upstream of the
turbine flange. The inertial separator shall be selected for a pressure loss not
greater than 2% of the steam pressure. The separator shall assure dry and
saturated steam at the separator outlet to the turbine. The separator shall be
designed to retain a liquid collection volume equal to five separator inlet pipe
diameters with no liquid carryover to the separator steam outlet. The separator
liquid level controls shall be sized to continuously remove the amount of liquid
equal to 10% of the rated steam flow based on discharge to a condensate header
pressure to be specified. Individual alarm and trip level transmitters shall be
furnished and arranged to trip the steam turbine with sufficient time to prevent
liquid carryover into the steam turbine.
Page 7 of 11
Document Responsibility: Compressors, Gears and Steam Turbines Standards Committee SAES-K-501
Issue Date: 27 March 2016
Next Planned Update: 27 March 2019 Steam Turbines
Relief valves shall be installed between the turbine casing flange and the first
block valve at:
Turbine exhaust
Turbine extraction
Turbine induction
For condensing steam turbines, main steam condenser vacuum breaker valves
shall be furnished with an integral manual vacuum breaker. A water seal sight
glass, valved demineralized water (or condensate) source, and a piped overflow
drain with sight glass shall be provided as part of the vacuum breaker
installation. The vacuum breaker shall be installed such that the level and sight
glasses are readily visible and the manual vacuum breaker valve easily
accessible for operation from the same deck or level as the turbine inlet steam
trip valve.
6.3.1 Trip valves shall be spring supported, independent of the turbine inlet
flange and steam piping.
6.3.2 Main inlet trip valve shall be directly connected to the turbine flange.
6.3.3 In addition to the main trip valve, a trip valve shall be installed on any
extraction/induction steam line. These valves shall trip upon tripping the
main trip valve.
6.3.4 Non-return valves and induction trip valves shall be located not more
than five pipe diameters from the turbine flange being served by the
valve.
6.3.5 Non-return valves shall have a closing time not exceeding 1.5 times that
of the main steam inlet trip valve.
6.4.1 Main condenser hot-well level control shall use two valves arranged for
split range control of the condenser hot-well. One valve shall control
condensate flow to the plant condensate recovery system and the other
valve shall control condensate return to the hot-well. Condenser hot-well
level control systems using orifices are not acceptable.
Page 8 of 11
Document Responsibility: Compressors, Gears and Steam Turbines Standards Committee SAES-K-501
Issue Date: 27 March 2016
Next Planned Update: 27 March 2019 Steam Turbines
6.4.3 Water cooled condensers shall have water piping arranged to permit back
flushing of the condenser water side.
6.5 Sealing Steam Supply, Seal Leak-off, and Gland Condenser Leak-off Piping
Auxiliary sealing steam shall be supplied from the top vertical centerline of a
steam header always having a minimum of 30°C superheat. The steam turbine
Vendor shall also be informed of the entire range of steam temperatures and
pressures.
Auxiliary sealing steam supply headers shall be kept warm at all times by a
bypass orifice to a lower pressure header. The bypass orifice shall be sized
during commissioning and adjusted as needed to maintain the auxiliary sealing
steam supply above the saturation temperature at the inlet to the auxiliary
sealing steam supply control valve.
Note: The above design or equivalent is mandated for absolute assurance that liquid
will not be admitted to the turbine glands. Steam traps are not acceptable as
they require a proactive maintenance program to function properly, which is not
sustained at most operating plants. Steam trap failures are usually discovered
after-the-fact. Serious damage to the rotor during startup from cold condensate
ingress due to steam traps malfunction have been experienced.
Seal steam leak-off headers for special purpose steam turbines shall be provided
with low opening differential check valves.
Auxiliary sealing steam, sealing steam leak-off, gland condenser leak-offs and
all other auxiliary steam connections shall be well supported and shall not
impose objectionable forces on the turbine.
Gland condensers shall be installed below the centerline elevation of the steam
Page 9 of 11
Document Responsibility: Compressors, Gears and Steam Turbines Standards Committee SAES-K-501
Issue Date: 27 March 2016
Next Planned Update: 27 March 2019 Steam Turbines
turbine and shall have a minimum water leg for the drain of 1.83 m.
Gland condenser vacuum piping shall be kept as short as possible and shall be
insulated only in those locations required for personnel protection or to prevent
undue heating of turbine supports.
Gland condenser air removal ejector discharge piping shall have a liquid
drain to grade as well as a steam discharge to atmosphere at a safe location.
Ejector discharge piping shall be at least one pipe size larger than the ejector
exhaust connection. Ejector shall be made of stainless steel.
Local temperature and pressure gauges shall be installed on the gland condenser
inlet piping. Temperature gauges shall be installed in thermowells.
Air removal systems inter and after condenser drains shall use piping loop seals
whenever the required vertical height is available. Float and thermostatic traps
shall only be used when it is impossible to install piping loop seals. Strainers shall
be installed upstream of each trap inlet.
The atmospheric exhaust of the air removal system shall be furnished with a low
pressure loss variable area positive displacement flow meter for air flow
measurement.
Steam supply piping to accessory items such as sealing steam systems and ejectors
shall have in-line “Y” type strainers with valved blow downs. Header drain and
warm-up valves shall be installed adjacent to the auxiliary system supply
connection.
Installations for turbines rated 20,000 HP and above shall facilitate on-site
overhaul and maintenance, e.g., by having the required access and maintenance
space, sunshade/roof, and crane capable of lifting the heaviest component.
Page 10 of 11
Document Responsibility: Compressors, Gears and Steam Turbines Standards Committee SAES-K-501
Issue Date: 27 March 2016
Next Planned Update: 27 March 2019 Steam Turbines
For steam turbines within an enclosure and having a steam inlet temperature
higher than 382°C (720°F), a fire protection system - including fire detection,
enclosure isolation, and fire suppression systems - is required within the
enclosure. The supplied fire protection system shall be UL listed or FM
approved. For CO2 systems and other systems that create risk of asphyxiation, a
lock-out device shall be installed to disarm the system when personnel are
present. Additionally, an alarm warning device shall be provided to activate
prior to discharging the fire suppression fluid (e.g., CO2) into the enclosure.
Alternatively, fire-resistant synthetic oils may be used in lieu of the fixed fire
protection system within the enclosure, provided that life time costs of the fire-
resistant fluid are added to the equipment life cycle cost during bid evaluation.
Revision Summary
27 March 2016 Revised the Next Planned Update, reaffirmed the content of the document, and reissued as
major revision to improve steam turbine installation reliability.
Page 11 of 11