The Basics of Capital Budgeting: Solutions To End-of-Chapter Problems
The Basics of Capital Budgeting: Solutions To End-of-Chapter Problems
11-7 a. Project A:
CF0 = -6000; CF1-5 = 2000; I/YR = 14.
MIRR calculation:
0 1 2 3 4 5
| | | | | |
-6,000 2,000 2,000 2,000 2,000 2,000
1.14
2,280.00
(1.14)2
2,599.20
(1.14)3
2,963.09
(1.14)4
3,377.92
13,220.21
Using a financial calculator, enter N = 5; PV = -6000; PMT = 0; FV = 13220.21; and solve for
MIRRA = I/YR = 17.12%.
Payback calculation:
0 1 2 3 4 5
| | | | | |
-6,000 2,000 2,000 2,000 2,000 2,000
Cumulative CF: -6,000 -4,000 -2,000 0 2,000 4,000
Project B:
CF0 = -18000; CF1-5 = 5600; I/YR = 14.
Payback calculation:
0 1 2 3 4 5
| | | | | |
-18,000 5,600 5,600 5,600 5,600 5,600
Cumulative CF: -18,000 -12,400 -6,800 -1,200 4,400 10,000
b. If the projects are independent, both projects would be accepted since both of their NPVs are
positive.
c. If the projects are mutually exclusive then only one project can be accepted, so the project
with the highest positive NPV is chosen. Accept Project B.
d. The conflict between NPV and IRR occurs due to the difference in the size of the projects.
Project B is 3 times larger than Project A.
Project L: CF0 = -1000; CF1 = 0; CF2 = 250; CF3 = 400; CF4 = 800; I/YR = 10. Solve for NPVL =
$53.55; IRRL = 11.74%.
Since Project L has the higher NPV, it is the better project, even though its IRR is less than
Project S’s IRR. The IRR of the better project is IRRL = 11.74%.
Integrated Case
11-24
Allied Components Company
Basics of Capital Budgeting
You recently went to work for Allied Components Company, a supplier of auto
repair parts used in the after-market with products from Daimler, Chrysler,
Ford, and other automakers. Your boss, the chief financial officer (CFO), has
just handed you the estimated cash flows for two proposed projects. Project L
involves adding a new item to the firm’s ignition system line; it would take
some time to build up the market for this product, so the cash inflows would
increase over time. Project S involves an add-on to an existing line, and its cash
flows would decrease over time. Both projects have 3-year lives, because Allied
is planning to introduce entirely new models after 3 years.
Here are the projects’ net cash flows (in thousands of dollars):
0 1 2 3
| | | |
Project L -100 10 60 80
Project S -100 70 50 20
Answer: [Show S11-1 through S11-3 here.] Capital budgeting is the process
of analyzing additions to fixed assets. Capital budgeting is important
because, more than anything else, fixed asset investment decisions
chart a company’s course for the future. Conceptually, the capital
budgeting process is identical to the decision process used by
individuals making investment decisions. These steps are involved:
4. Find (a) the PV of the expected cash flows and/or (b) the
asset’s rate of return.
Answer: [Show S11-4 and S11-5 here.] Projects are independent if the cash
flows of one are not affected by the acceptance of the other.
Conversely, two projects are mutually exclusive if acceptance of
one impacts adversely the cash flows of the other; that is, at most
one of two or more such projects may be accepted. Put another
way, when projects are mutually exclusive it means that they do
the same job. For example, a forklift truck versus a conveyor
system to move materials, or a bridge versus a ferry boat.
Projects with normal cash flows have outflows, or costs, in the
first year (or years) followed by a series of inflows. Projects with
nonnormal cash flows have one or more outflows after the inflow
stream has begun. Here are some examples:
C. (1) Define the term net present value (NPV). What is each project’s NPV?
Answer: [Show S11-6 through S11-8 here.] The net present value (NPV) is
simply the sum of the present values of a project’s cash flows:
N
CFt
NPV = (1 WACC)
t 0
t .
C. (2) What is the rationale behind the NPV method? According to NPV,
which project(s) should be accepted if they are independent?
Mutually exclusive?
Answer: [Show S11-9 here.] The rationale behind the NPV method is
straightforward: If a project has NPV = $0, then the project
generates exactly enough cash flows (1) to recover the cost of the
investment and (2) to enable investors to earn their required rates
of return (the opportunity cost of capital). If NPV = $0, then in a
financial (but not an accounting) sense, the project breaks even. If
the NPV is positive, then more than enough cash flow is generated,
and conversely if NPV is negative.
Consider Project L’s cash inflows, which total $150. They are
sufficient (1) to return the $100 initial investment, (2) to provide
investors with their 10% aggregate opportunity cost of capital, and
(3) to still have $18.78 left over on a present value basis. This
$18.78 excess PV belongs to the shareholders—the debtholders’
claims are fixed—so the shareholders’ wealth will be increased by
Answer: The NPV of a project is dependent on the WACC used. Thus, if the
WACC changed, the NPV of each project would change. NPV
declines as WACC increases, and NPV rises as WACC falls.
D. (1) Define the term internal rate of return (IRR). What is each
project’s IRR?
Answer: [Show S11-10 here.] The internal rate of return (IRR) is that
discount rate which forces the NPV of a project to equal zero:
0 1 2 3
| | | |
CF0 CF1 CF2 CF3
PVCF1
PVCF2
PVCF3
0 = Sum of PVs = NPV.
N
CFt
IRR: (1 IRR)
t 0
t = $0 = NPV.
Note that the IRR equation is the same as the NPV equation, except
that to find the IRR the equation is solved for the particular
discount rate, IRR, which forces the project’s NPV to equal zero
0 1 2 3
| 18.1% | | |
-100.00 10 60 80
8.47 1/1.181
1/(1.181)
2
43.02
1/(1.181)
3
48.57
0.06 $0 if IRRl = 18.1% is used as the discount rate.
Answer: [Show S11-11 here.] The IRR is to a capital project what the YTM
is to a bond—it is the expected rate of return on the project, just as
the YTM is the promised rate of return on a bond.
D. (3) What is the logic behind the IRR method? According to IRR, which
projects should be accepted if they are independent? Mutually
exclusive?
Answer: IRRs are independent of the WACC. Therefore, neither IRRS nor
IRRL would change if WACC changed. However, the acceptability of
the projects could change—L would be rejected if WACC were
greater than 18.1%, and S would be rejected if WACC were greater
than 23.6%.
E. (1) Draw NPV profiles for Projects L and S. At what discount rate do
the profiles cross?
Answer: [Show S11-13 and S11-14 here.] The NPV profiles are plotted in
the figure below. Note the following points:
3. NPV profiles are curves rather than straight lines. To see this,
note that these profiles approach cost = -$100 as WACC
approaches infinity.
NPV
($)
50
Project L
40
Crossover Rate 9%
30
Project S
20
IRRS = 23.6%
10
0
5 10 15 20 25 WACC (%)
-10 IRRL = 18.1%
E. (2) Look at your NPV profile graph without referring to the actual NPVs
and IRRs. Which project(s) should be accepted if they are
independent? Mutually exclusive? Explain. Are your answers
correct at any WACC less than 23.6%?
Answer: [Show S11-15 here.] The NPV profiles show that the IRR and NPV
criteria lead to the same accept/reject decision for any independent
project. Consider Project L. It intersects the X-axis at its IRR,
18.1%. According to the IRR rule, L is acceptable if WACC is less
F. (1) What is the underlying cause of ranking conflicts between NPV and IRR?
Answer: [Show S11-16 here.] For normal projects’ NPV profiles to cross,
one project must have both a higher vertical axis intercept and a
steeper slope than the other. A project’s vertical axis intercept
typically depends on (1) the size of the project and (2) the size and
timing pattern of the cash flows—large projects, and ones with
large distant cash flows, would generally be expected to have
relatively high vertical axis intercepts. The slope of the NPV profile
depends entirely on the timing pattern of the cash flows—long-term
projects have steeper NPV profiles than short-term ones. Thus, we
conclude that NPV profiles can cross in two situations: (1) when
mutually exclusive projects differ in scale (or size) and (2) when
the projects’ cash flows differ in terms of the timing pattern of their
cash flows (as for Projects L and S).
Answer: [Show S11-17 here.] The underlying cause of ranking conflicts is the
reinvestment rate assumption. All DCF methods implicitly assume
that cash flows can be reinvested at some rate, regardless of what is
actually done with the cash flows. Discounting is the reverse of
compounding. Since compounding assumes reinvestment, so does
discounting. NPV and IRR are both found by discounting, so they
both implicitly assume some discount rate. Inherent in the NPV
calculation is the assumption that cash flows can be reinvested at
the project’s cost of capital, while the IRR calculation assumes
reinvestment at the IRR rate.
Answer: Whether NPV or IRR gives better rankings depends on which has
the better reinvestment rate assumption. Normally, the NPV’s
assumption is better. The reason is as follows: A project’s cash
inflows are generally used as substitutes for outside capital, that is,
projects’ cash flows replace outside capital and, hence, save the
firm the cost of outside capital. Therefore, in an opportunity cost
sense, a project’s cash flows are reinvested at the cost of capital.
Note, however, that NPV and IRR always give the same
accept/reject decisions for independent projects, so IRR can be used
just as well as NPV when independent projects are being evaluated.
The NPV versus IRR conflict arises only if mutually exclusive projects
are involved.
Answer: [Show S11-18 and S11-19 here.] MIRR is that discount rate which
equates the present value of the terminal value of the inflows,
compounded at the cost of capital, to the present value of the costs.
Here is the setup for calculating Project L’s modified IRR:
0 1 2 3
WACC = 10%
| | | |
PV of costs = (100.00) 10 60 80.00
1.10
66.00
(1.10)
2
12.10
TV of inflows = 158.10
PV of TV = 100.00 MIRR = ?
$158.10
$100 =
(1 MIRR ) 3
N
PV costs = TV N
COFt CIF (1 r )
t
N t
.
(1 MIRR )N t 0 (1 WACC ) t
t 1
(1 MIRR ) N
G. (2) What are the MIRR’s advantages and disadvantages vis-à-vis the
NPV?
Answer: [Show S11-20 here.] MIRR does not always lead to the same
decision as NPV when mutually exclusive projects are being
considered. In particular, small projects often have a higher MIRR,
but a lower NPV, than larger projects. Thus, MIRR is not a perfect
H. (1) What is the payback period? Find the paybacks for Projects L and S.
Answer: [Show S11-21 through S11-23 here.] The payback period is the
expected number of years required to recover a project’s cost. We
calculate the payback by developing the cumulative cash flows as
shown below for Project L (in thousands of dollars):
Expected NCF
Year Annual Cumulative
0 ($100) ($100)
1 10 (90)
2 60 (30) Payback is between
3 80 50 t = 2 and t = 3
0 1 2 3
| | | |
-100 10 60 80
-90 -30 50
Project L’s $100 investment has not been recovered at the end of
Year 2, but it has been more than recovered by the end of Year 3.
Thus, the recovery period is between 2 and 3 years. If we assume
that the cash flows occur evenly over the year, then the investment
H. (2) What is the rationale for the payback method? According to the
payback criterion, which project(s) should be accepted if the firm’s
maximum acceptable payback is 2 years, if Projects L and S are
independent, if Projects L and S are mutually exclusive?
H. (3) What is the difference between the regular and discounted payback
methods?
Optional Question
Answer: Regular payback has three critical deficiencies: (1) It ignores the
time value of money. (2) It ignores the cash flows that occur after
the payback period. (3) Unlike the NPV, which tells us by how much
the project should increase shareholder wealth, and the IRR, which
tells us how much a project yields over the cost of capital, the
payback merely tells us when we get our investment back.
Discounted payback does consider the time value of money, but it
still fails to consider cash flows after the payback period and it
gives us no specific decision rule for acceptance; hence, it has 2
basic flaws. In spite of its deficiency, many firms today still
calculate the discounted payback and give some weight to it when
making capital budgeting decisions. However, payback is not
generally used as the primary decision tool. Rather, it is used as a
rough measure of a project’s liquidity and riskiness.
0 1 2
| | |
-0.8 5.0 -5.0
I. (1) What is Project P’s NPV? What is its IRR? Its MIRR?
Answer: [Show S11-25 here.] Here is the time line for the cash flows, and
the NPV:
0 1 2
10%
| | |
-800,000 5,000,000 -5,000,000
NPVP = -$386,776.86.
We can find the NPV by entering the cash flows into the cash flow
register, entering I/YR = 10, and then pressing the NPV button.
However, calculating the IRR presents a problem. With the cash
flows in the register, press the IRR button. An HP-10BII financial
calculator will give the message “error-soln.” This means that
Project P has multiple IRRs. An HP-17BII will ask for a guess. If
you guess 10%, the calculator will show IRR = 25%. If you guess
a high number, such as 200%, it will show the second IRR, 400%.1
The MIRR of Project P = 5.6%, and is found by calculating the
discount rate that equates the terminal value ($5.5 million) to the
present value of costs ($4.93 million).
I. (2) Draw Project P’s NPV profile. Does Project P have normal or
nonnormal cash flows? Should this project be accepted? Explain.
Answer: [Show S11-26 through S11-28 here.] You could put the cash flows
in your calculator and then enter a series of I/YR values, get an
NPV for each, and then plot the points to construct the NPV profile.
We used a spreadsheet model to automate the process and then to
1 Looking at the figure below, if you guess an IRR to the left of the peak NPV rate, the lower
IRR will appear. If you guess IRR > peak NPV rate, the higher IRR will appear.
NPV
(Thousands of Dollars)
500
375
250
125
0
100 200 300 400 500
r (%)
-125
-250
-375