Construction Pricing Models - Choosing An Appropriate Pricing Arrangement
Construction Pricing Models - Choosing An Appropriate Pricing Arrangement
Construction Pricing Models - Choosing An Appropriate Pricing Arrangement
INTRODUCTION
When negotiating a construction contract, the pricing model selected to determine the cost of the project is
arguably the most important decision the parties will make. The pricing structure not only determines the project
cost, but also results in substantially different responsibilities and opportunities for the parties, depending upon the
structure selected.
There are three basic types of pricing arrangements in construction contracts: (1) stipulated sum (also known
as fixed price or lump sum), (2) cost plus (with or without a guaranteed maximum or not-to-exceed price), and
(3) unit price. While there may be additional pricing structures in use and hybrids of the basic arrangements,
this practice note discusses these common models and outlines the pros and cons of each, as well as the costs
and benefits to both contractors and owners, respectively. As in all contractual settings, it is important to keep in
mind the negotiating power of each party, the size of the total contract, the difficulty of the project, and the level
of sophistication and experience of both the contractor and owner when selecting a pricing model. Understanding
these pricing arrangements and their respective benefits is crucial to negotiating and structuring a contractual
relationship that best fits client goals.
For complete coverage of compensation arrangements in design and construction agreements, see 2-3A
Construction Law P 3A.01 et seq.
In this model, the work is typically broken down into categories of work (plumbing, electrical, concrete, etc.) and
each category is given a value (the schedule of values) equal to the percentage of the job costs it represents. As
the work proceeds, the schedule of values is used to determine the percentage of completion and the payment
is made accordingly. When a pay application is submitted, the percentage of the project that is complete is
1
Construction Pricing Models – Choosing an Appropriate Pricing Arrangement
determined (based on the schedule of values) and the contractor is paid that percentage of the stipulated
project cost, subject to the withholding of retainage (the portion of the agreed upon contract price deliberately
held back until substantial completion to secure the contractor’s obligations).
The stipulated sum arrangement is most appropriate where simplicity of management is a consideration due
to the size of the project or the lack of sophistication or time availability of the owner’s internal management
team. For example, a one-off business owner who is building a new office may not have the time or level of
sophistication to manage the costs of a project and may simply want the certainty of knowing what the job will
cost.
For this reason, stipulated sum contracts are often utilized in a design-build delivery method where an owner
engages one party to design and build the project. It is also used in a design-bid-build delivery, where architects
and engineers are hired to design the project in advance of bidding out the construction work. The owner provides
the complete construction specifications created by the architects/engineers to a variety of contractors, and each
contractor then prepares a bid based on that contractor’s estimate of the total cost to complete the construction.
This project delivery method is often used in public works projects, where the bidding process needs to be
transparent and it has to be clear that each party is bidding from the same set of complete specifications. Similar
to design-bid-build, owners sometimes opt to utilize a design-negotiate-build project delivery method. Design-
negotiate differs from design-bid in that after the owner provides its construction specifications to contractors, the
owner will request preliminary bids and then negotiate a final stipulated sum based on the estimate as well as the
contractor’s reputation, scalability, qualifications, and experience, among other qualities. This structure is common
in the private sector where the public bidding requirements generally do not apply. For further discussion of the
design-build and design-bid-build project delivery methods, see Advantages and Disadvantages of the Primary
Construction Project Delivery Methods.
The owner may face additional problems related to the lack of incentive in such an arrangement to complete
the project in a timely manner. When a contractor has been guaranteed a lump-sum price for completion of the
2
Construction Pricing Models – Choosing an Appropriate Pricing Arrangement
work, it has less incentive to complete the work in a timely manner unless specific construction timelines, coupled
with penalties for failure to meet deadlines, are agreed to as a component of the contract. A liquidated damages
provision that affixes stipulated damages for a contractor’s failure to meet set deadlines, should be considered
when representing an owner under a fixed price contract.
For more on firm-fixed-price or lump-sum contracts, see 2-3A Construction Law P 3A.02 (introductory paragraphs
and subsection [1]).
COST-PLUS CONTRACTS
In contrast to a fixed sum contract, the administration of a cost-plus contract is far more difficult and demanding.
Under a cost-plus pricing model, the contractor will be paid the full price for all agreed-upon construction related
costs, overhead, and a fee representing the contractor’s profit. The fee may be a predetermined amount or a
percentage of the total construction costs. The idea behind a cost-plus arrangement is to allow an owner to pay
the cost of the actual work without markups for greater transparency. To avoid disputes, it is vital that the parties
specify and define what will be considered reimbursable expenses to the contractor and what is considered a cost
to the owner.
Theoretically, under a cost-plus arrangement, every component of the work, labor expenses, material costs,
equipment rentals, and other costs, are tracked throughout the project. This requires the owner to review (and
even audit) those costs to make sure only the actual cost of the work is being requested and paid. As will be
discussed below, cost-plus contracts often come with a guaranteed maximum or not-to-exceed price (GMAX
contract).
● Under this model, there is potential for the owner to achieve savings through performance efficiencies. (This
will be discussed in detail on the section below pertaining to GMAX contracts.) To achieve such cost savings,
the contract must be drafted to specifically identify reimbursable costs and should have detailed provisions
explaining how savings will be shared. Providing both the owner and contractor with a share of savings can
motivate both to work together and foster collaboration.
● This model works better than a stipulated sum model when the design is not far enough along for a contractor
to reasonably give a fixed price. The cost-plus model permits the project to go forward before the detailed
3
Construction Pricing Models – Choosing an Appropriate Pricing Arrangement
design documents are done. This also includes fast-tracked projects. By involving the contractors early on,
owners retain greater flexibility to modify designs and materials as the project proceeds along while gaining
valuable input from the contractors with regard to feasibility analysis, estimating, and value engineering. After
these preconstruction services have been undertaken, the parties are better equipped to arrive at a budget. A
project bid with incomplete drawings as a stipulated sum contract, will likely increase the overall cost.
● Similarly, under this model, a contractor can go forward with its work even with incomplete design documents
and even when costs are rising in the market, without having been locked in to a fixed price.
● This model provides more data for an institutional owner to give to its board or committees in budgeting and
planning capital improvements.
● Under this pricing arrangement, rather than selecting a contractor based solely upon the bid price, owners can
select contractors based on factors such as experience, reputation, ability, and the proposed fee.
● The open book nature of a cost-plus pricing model can also, if the owner and contractor maintain a
respectable working relationship, allow for a flexible and efficient building experience. Contractors are often
required to obtain several competitive bids for each trade involved in the project under this model, which
allows the owner to review the bids and secure the lowest cost and/or the most reputable subcontractor. This
greater degree of transparency can result in not only lower construction costs, but also result in high-end
work product and a true partnership-like relationship between the owner and contractor.
The aforementioned fast-tracked nature of cost-plus contracts may also bring increased construction costs. Since
contractors often begin construction prior to the completion of the final specifications and drawings, conflicts may
arise that must be resolved after the work has started, rather than in the design process before the work has
begun. This, in turn, may require a redesign, additional work, and costly delays in the construction schedule.
Importantly for the owner, the uncapped nature of cost-plus arrangements opens the owner to the risk of open-
ended and indeterminate construction costs. This problem may be exacerbated in situations where the
contractor’s fee is determined based on the total construction price. If the contractor’s fee is tied directly to the
final cost, the contractor has very little incentive to reduce costs on the project because as the costs go higher,
so too does the contractor’s fee. The owner can quell this uncertainty by placing a guaranteed maximum price
on the construction costs in order to predetermine a fixed maximum cost and prevent a contractor’s fee from
rising indefinitely as construction costs rise. This GMAX version of a cost-plus pricing arrangement has become
extremely popular and is discussed in the next section.
4
Construction Pricing Models – Choosing an Appropriate Pricing Arrangement
amount the owner will pay. Additionally, GMAX arrangements contractually address how any savings will be
allocated. Generally, a GMAX arrangement will provide that if the total cost of construction comes in below the
GMAX price, the owner and contractor will share in the savings on a predetermined pro rata basis. Oftentimes
the savings are allocated 50-50, but it is not unusual for the savings allocation to be negotiated depending on
the parties’ respective priorities and relative bargaining power.
The parties should also negotiate the terms of any shared savings, as there is no clear industry standard. In
doing so, it is important to note the different kinds of potential savings that may be achieved during the project.
These categories of savings include buyout savings, value engineering savings, efficiency savings, and leftover
contingency amounts. Each of these different categories of savings may have a different allocation between
owners and contractors.
It is also crucial to define which costs are included and which are excluded. The agreement should be as specific
as possible on which costs are reimbursable and which are not. Examples of typical reimbursable costs include
labor (wages, fringe benefits, supervision); subcontractors; materials; equipment; taxes; insurance; testing;
and permits. Sometimes software, lost deposits, travel expenses, legal expenses, and off-site labor fall into the
reimbursable cost category.
When negotiating reimbursable costs, the drafter should consider labor multipliers, home office costs, general
conditions, insurance costs, related party issues, and discounts and rebates.
5
Construction Pricing Models – Choosing an Appropriate Pricing Arrangement
On the other hand, examples of traditionally nonreimbursable expenses are home office expenses, overhead and
general expenses not included in the list of reimbursable expenses, capital expenses, and defective work.
An audit clause should be included in a cost-plus contract and should identify the supporting cost documents,
accounting records, and financial records which should be kept by the contractor and how long they must be
preserved. The contractor should try to narrow the categories of documents to prevent a fishing expedition
that will force the contractor to give in rather than use resources to compile and defend endless categories
of documents. The owner, on the other hand, will want detailed records to substantiate expenses. The audit
provisions should also spell out the circumstances of accessing the documents, including frequency of
inspections, place of inspection, times at which inspections can take place, and duration of the audit. The owner
will also want the right to retain third-party experts to conduct the audit.
A well-drafted and detailed cost-plus arrangement, with a GMAX price, can lead to a successful and collaborative
project.
For more on various types of cost-plus contracts, see 2-3A Construction Law P 3A.03[2] (cost plus a fixed fee); 2-
3A Construction Law P 3A.04[1] (GMAX); 2-3A Construction Law P 3A.04[2] (cost-plus-incentive-fee); 2-3A
Construction Law P 3A.04[3] (cost-plus-award-fee); 2-3A Construction Law P 3A.07 (percent of construction cost).
See Guaranteed Maximum Price Clause for a sample GMAX clause.
6
Construction Pricing Models – Choosing an Appropriate Pricing Arrangement
For additional coverage of the unit price method, see 2-3A Construction Law P 3A.02[2].
There should also be a clear understanding of how contingencies should be used. While pricing changes should
be less difficult to negotiate in a cost-plus contract than a lump-sum contract, the change order provisions should
address how the contingency will be used; general conditions issues; adjustment of the GMAX price and the
impact on the contractor’s fee.
The contract should also address the impact of delays on pricing, including whether extensions of time increase
general conditions, and whether delays require an increase in the GMAX.
CONCLUSION
Attorneys representing both owners and contractors should be aware of the various pricing arrangements
described in this practice note. When counseling a client on the optimal pricing arrangement, the attorney
should first consider the type, cost, and complexity of project; the parties’ level of experience; and the parties’
goals. In any arrangement, the attorney must be keenly conscious of isolating what costs and charges should
be incorporated in any pricing to head off potential disputes and manage expectations for both the owner and
contractor. Above all, the attorney should keep in mind that no pricing model is one size fits all.
For further discussion on selecting the appropriate compensation arrangement for the project, see 2-3A
Construction Law P 3A.09.
Learn more
LEXISNEXIS.COM/PRACTICE-ADVISOR
This document from Lexis Practice Advisor®, a comprehensive practical guidance resource providing insight from leading practitioners, is
reproduced with the permission of LexisNexis®. Lexis Practice Advisor includes coverage of the topics critical to practicing attorneys. For more
information or to sign up for a free trial, visit lexisnexis.com/practice-advisor. Reproduction of this material, in any form, is specifically prohibited
without written consent from LexisNexis.
LexisNexis, Lexis Practice Advisor and the Knowledge Burst logo are registered trademarks of RELX Inc.
Other products or services may be trademarks or registered trademarks of their respective companies. © 2018 LexisNexis 7