Group Technology-Based Shipbuilding
Group Technology-Based Shipbuilding
1988
http://hdl.handle.net/10945/23258
DEPARTMENT OF OCEAN ENGINEERING
MASSACHUSETTS OF TECHNOLOGY
INSTITUTE
CAMBRIDGE, MASSACHUSETTS 02139
by
THESIS
Course XIII A & B H42ISS May 1988
THE IMPACT OF GROUP TECHNOLOGY-BASED SHIPBUILDING METHODS
ON NAVAL SHIP DESIGN AND ACQUISITION PRACTICES
by
NAVAL ENGINEER
and
at the
May, 1988
by
ABSTRACT
Page
ABSTRACT 2
ACKNOWLEDGEMENTS 3
TABLE OF CONTENTS 5
LIST OF TABLES 7
LIST OF FIGURES 8
CHAPTER 1 - INTRODUCTION 10
1 . 1 Background 10
References to Chapter 1 15
2.1.1 Introduction 16
2.1.2 The Basic Process 17
2.1.3 The Conventional Period 19
2.1.4 The Total Package Procurement Period. . 22
2.1.5 The Post McNamara Period 26
2.1.6 The Current Period 37
2.3.1 Introduction 46
2.3.2 Group Technology 46
2.3.3 Product-Oriented Work Breakdown
Structures 49
2.3.4 Planning for Production 53
2.3.5 Process Flow Lanes 60
2.3.6 Zone Construction Methods 62
2.3.7 Accuracy Control 73
3 . 1 Introduction 80
APPENDICES 141
Page
Page
CHAPTER 1
INTRODUCTION
1 . 1 Background
result, too many weapon systems cost too much, take too loni
10
.
shipbuilding productivity.
naval ships
11
. .
terns take years to design and test before they are ready for
the hardware. During World War II, the entire Navy Depart-
ships
development
12
of quality and the ability to fulfill naval mission require-
13
production; process flow lanes; zone construction, outfit-
ing program, and the SSBN 726 class Trident ballistic mis-
14
,
REFERENCES TO CHAPTER 1
2. Storch, R. L. Hammon C. P.
, , and Bunch, H. M.
,
land, 1988.
15
CHAPTER 2
2.1.1 Introduction
which began in the early 1960's and ended about 1969, the
post McNamara period which ended about 1979, and the current
16
.
periods
have changed over the years, the basic process remains much
of a new system.
17
The Navy and other services are charged with identify-
[2] .
effort and for the weapons systems which emerge from the
18
2.1.3 The Conventional Period
19
trial base. Of course, regional political and economic
The basis for the claims was usually a dispute over inter-
20
)
Conventional Period
— Navy
|-« » |
— Navy
« or Design Agent-»»|-« Shipbuilder — »-|
Contract Definition
Concept
Formulation
Navy i
*"
Ship-
ABC
Ship- Ship-
builder builder builder
Shipbuilder i .
W-»-
Detail
—^"Design ——
Single
Production
Shipbuilder ( s
21
.
ships
analysis techniques;
detailed specifications;
schedule demands);
22
f) introduction of producibili ty and innovation into
23
detailed construction plans, management plans, and a com-
nance .
24
the previous period - large cost and schedule overruns.
and found that cost estimates for them had increased $33.4
25
) ,
at key milestones,
guidance void that was not formally filled until the issu-
26
ance of Department of Defense Directive 5000.1, "Acquisition
27
material command in brief "single sheet characteristics"
28
directly) developed a conceptual design for the ship class
29
The key practice which grew from recognition of the
the "f ly-bef ore-you-buy" policy and was used in the Navy's
and
tion program into the design of the follow ships. The LBTFs
30
was to review and evaluate the status of major defense sys-
DSARC presentation.
tors was realized. The fixed price contracts and the lack
31
)
32
.
and
the planned monthly rate and their PERT network reports [33]
action
33
,
CV r ACWP - BCWP
SV = BCWS - BCWP
34
office concern.
the lead ship under a cost plus fee type of contract. The
35
,
contracts
tracts ,
ations ,
36
2.1.6 The Current Period
(ASN(S&L)) [40].
37
* unusual or compelling urgency
* industrial mobilization
* international agreement
* authorization or requirement by statute
* national security considerations
* and public interest considerations. [41]
ers has become intense over the last decade. This competi-
ers .
the bitter claims era of the 1960s and early 1970s [42].
38
product quality. The objective of streamlining is to iden-
[43] .
39
WORKING WORKING WORKING WORKING
OPNAV GROUP
SCIB
GROUP
SCIB
GROUP
SCIB
GROUP
TOR OR TLR
CDR
SPECS.
DOP PDR DWGS
FEASIBILITY PRELIMINARY CONTRACT m
NAVSEA STUDIES DESIGN DESIGN rfp
40
all the principal warfare sponsors and other high-
used on the DDG 51 design. And LHD , SWATH TAGOS , MSH, and
41
COMBINATIONS
OF EARLIER
APPROACHES
DEPENDING ON
ACQUISITION
PLAN
CENTRALIZED 1980s
MANAGEMENT
NAVY DESIGN
-FARM OUT BY TASKS
DESIGN TO COST
SHIPBUILDER
INVOLVEMENT
TOTAL PACKAGE 1970s
PROCUREMENT
CONTRACTOR DESIGN
SYSTEMS ANALYSIS
NAVY 1960s
IN-HOUSE DESIGN
PRELIMINARY
DESIGN
CONTRACT DESIGN
PRE 1960s
42
warship are such that this approach will be increasingly
43
)
44
evaluate the impact on work processes of even the smallest
[48].
in one hour the work for which three man-hours were required
Act of 1970. This act contained the authority for the joint
45
ferred to Japan and, after significant development, how they
46
.
production
47
.
skills
This means that the same problem area does not imply identi-
completed sequentially.
48
tion and coding. However, classification of the elements of
were the same thing. They are not and the distinction is
Table 2.1. The last two groups are used primarily for cost
49
000 General Guidance and Administration
100 Hull Structure
200 Propulsion Plant
300 Electric Plant
400 Command and Surveillance
500 Auxiliary Systems
600 Outfit and Furnishings
700 Armament
800 Integration/Engineering
900 Ship Assembly and Support Services
50
ance with an interim product view is a product-oriented
zones and are the basis for the zone dominance seen in
shipbuilding management.
51
:.
Two product aspects, system and zone, are means for dividing
other two product aspects, problem area and stage, are means
follows
of facilities required)
problem
52
* Stage - a division of the production process by
53
-VP€ OF WORK AXIS ^OCDUCT ASPECTS AJ<IS
PAINT
Pf P»
PROOUCT RESOURCES
MIS
MATERIAL I'll
MANPOWER 1*2)
FACILITIES 1*31
DtPENSES 1**1
BASIC DESIGN
FUNCTIONAL DESIGN
BY SYSTEM
TRANSITION DESIGN
INTERRELATIONSHIP OF
SYSTEMS 4 ZONES
OETAIL DESIGN
SPECIFICATION OF
INTERIM PROOUCTS
BY ZONE.AREA/STAGE
/i/ORK P»C*AGE
PRODUCTIVITY VALUE
ANALYSES
^o""
^_
ACCEf TABLE
POODU CT1VITV
'
^
^^>
54
.
duction .
orientation
building .
55
]
Tra/islofm»lion
m accounting
pnm«nlY
56
divided into:
* Basic Design (In Navy parlance this includes all
57
—
TRANSITION CX S>Gn
'
ASUWdLT I
[-•
PLAN
BLOCK
construction PLAN CUTTING
PROPH.E
PLAN
SUPERSTRUCTURE
ASSJM3LY
PLAN
ROUGH CUTTING
general PLAN SUB-ASStMBLY
arrangement
FAS. 1
LANE PLAN
ASS.
PLAN
CUTTING
PLAN
J
MiOSw»
SECTION COMPOS.TES WORK INSTRUCTION 4 MATERIAL DETAIL CESiGnORawnGS
PIPE CLTTTINO
PI PINO PLAN
MACHINERY i
DIAGRAM) r"
ANO
->lPl*<i PIPE PIECE
ARRANGEMENT PI«*NG AND COMPONENTS MLf
- M ANUF-
MLS COMPONENTS PiTTInC 0« LANE PLAN
ARRANGEMENT UNIT
f
PIPING MLF
P°«L,M'NARY PIPING PIPING FITTING OR
2LCCX OtAGIUM ARRANGEMENT UNIT
PLAN ORAwinG
COMPONENTS
SYSTEMS COMPONENTS FITTING 0«
a. plan ARRANGEMENT UNIT
01 e C»AW1NQ CABLE
a CA8LE CUTTING
o J LIST
PLAN
CABLE) I
il ;vi*»inG
i 1
1
WIPING PiTTtHG 0«
5 2. ARRANGEMENT UNIT MLF -J
N _ WIRING
OIAGRAM OM*w/iNG
>* o c
e " - §
2%=
to
3
0.0
I MLS COMPONENTS
COMPONENTS
FITTING
ARRANGEMENT
DRAWING
« IS * »rt
jj j J JZ
PIPING A.NO MLP
STEEL COMPONENTS
FITTING OR UNIT
22 2 2 PIPING DRAWING
I I I
I
DIAGRAM I
CUflNlTuPE
22 Piping anO
FITTING
Drawing MATERIAL
COMPONENTS r— LIST
AHRANGEMENT
jOinES COMPONENTS
SYSTEMS components manuf ano
PLAN fitting purchase
DRAWING Plan
58
group technology apply to design as well as to production.
coordinate all production work and allow time for the tran-
oriented. This gives both the yard and the Navy accurate
59
larly where functional designers are required to identify
60
. '
NUL L ERECT on
INI GRATED W- H
ON BOARD
OUT 11 IINC
f
SHAPf SHAPE
BUM » UP
BUM I U<" —
TART
z
SIMILAR WO«"
CONIINI IN
SMALL
OUANTIT*
o
INTFflNAI - '
PLATE
MMH *« won* TRAMF FOn
1 UNIENl IN
•;< largf
z - 1
quantity PANEL
If
PART FOR
FLAT
PANEL
FLAT
PANEL
1
FLAT
PANEL
Block
<
'
.
MARKING
o
PLA1( JOINING &
,'AG( MATERIAL CUTTING
RENDING ASSEMBLY EGG BO« FHAMiNG ASSEMBLY
SUB(ULX>
MATERIAL PARI FARHIi AtiQN ASSEMBLY BLOCK ASSEMBL V
f -/t
Dl CK ( OMIfiNf N»
1
Df CK
CURVED
BLOCK
P I
DECK
CURVED
BLOC"
P I
,
DECK
CURVED PL
BLOCK -o C
~©
1
R
. 1
-»»
MACHINFRV
CURVED PL
BLOCK
MACHINFRV
CURVED P I
BLOCK B
MACHINERY
CURVEO P"L
BLOCK
-© ©©
ACCOMW
1
FIAT
BLOCK
P I
ACCOMW
FLAT PL
BLOCK
ACCOMM
Fl
BLOCK
AT PL
h© ©5e
61
)
62
PRODUCT WORK
BREAKDOWN
STRUCTURE
(PWBS)
PIPE PIECE
FAMILY
MANUFACTURING
(PPFM)
HULL BLOCK
CONSTRUCTION ZONE OUTFITTING ZONE PAINTING
METHOD METHOO METHOD
(ZOFM) (ZPTM)
(HBCM)
63
.
painting
ment .
Within each level other than the top two, the interim
64
Figure 2.11 HBCM Manufacturing Levels [57]
65
expensive but highly efficient facilities, and achieve man-
the various types of work packages that are needed for work
work packages denote the process flow lanes for hull con-
wise free to devise zones which best suit their system. So,
66
product asrects COOES
plan-o: MFC
LEVEL LEVEL
ZONE AREA staoe ZONE AREA STAQE
UJ
CI
O 2 3 TEST
.J
3 5
r X
1 7 SHIP UJ O UJ
9 Z
o 5 £ $
< z < UJ
u.
a.
ERECTION
5?
•" ' -
BACK NIL
PRE ERECTION
2 «
FLAT CURVED
PANEL PANEL PRE -ERECTION NIL
a
JOINING NIL
4 4 ASSEMBLY
5 3
Z »o CD O
GO u
ASSEMBLY
i
3 BENCH NO NIL
6
SUB-BLOCX BIM.T-OR
2
PART PART
ASSEMBLY
UJ
BENDING NIL
< £
3 a.
is J" a
7 s UJ
I MARKING 4 CUTTING I o a o
1
< ?° < O
a da £2 5 a. (j a u
f?
z
c
± <
u. o. PLAYE
z < z 2 NIL
Q.
a.
JOINING
67
nization are sometimes called pallets. Pallets sequenced in
the order they are built make up the ship's outfitting plan.
68
OPERATION
anO
TEST
ON-aOAMO
OUTTTTTINO
ON-BLOCK
OUTFITTING
OKANO-uNrr OUANO-UNIT
jOihimo JOIHIMO
69
As in HBCM , interim products with similar product
ing interval between one coat and the next coat must be
70
COO€»
HMtt tttrw9
LXVO. uvtt
ZONI AIWA STAO* ZDNE AIWA STAO*
OPERATION
I s
TEST
WfLOMQ Mt.
2
SPECIALTY/ SPEC4ALTYI a
I
veld* no
z<J
f 3 NH. Oft
z z
03
.OININQ
LAflOS-
sta
ii H
UNIT
WELDING
3 <
I 2 3 ?
SIZE
UNIT
§8
II
oall£tiz)no
1
ji 3 is.
• 1 COMPONENT MANUPACTUHINa
z!5
0E3IGN ANO 3a
MATERIA!. O
pwepaaat>on 3
71
NlSH
r,
3AINT
FINISH FINISH-
UNOER-COAT UNOEB-COAT
PAINT PAINT
72
to minimize surface preparation and painting rework caused
73
PRX30UCT ASPECTS COOES
PLANQ MTO
LEVEL LEVEL
ZONE AREA STAGE ZONE AREA STAGE
PAINTING NIL
SI
z
i5uj2o J _ <
'OUCM UP SI ui 20
j3 2*w 3 3 'J
O. i-* P.U.
i 4 < 3 u. y O 5 --J -
J a z 1
Z SO. z 3 CLEANING < a
s$ 1 S
?11 »a z 3
u. Z
SURFACE PREPARATION
PAINTING AFTER
NIL
OVERTURNING
TOUCH UP AFTER NIL < 01
OVERTURNING _ <
$2* 2
CLEANING AFTfR Z'2* 82
*2 OVERTURNING Ow 3 5 a
: 3 <3 = ?z is
3tf
SURFACE PREPARATION NIL x <o < a
AFTER OVERTURNING » a
z 3 s
? ?2 < 2 PAINTING z
IA, a
rOUCH UP
g
CLEANING
SURFACE PREPARATION a
a
PAINTING M
AFTER
OVERTURNING 5
UJ
CLEANING 8
AFTER NIL
ill OVERTURNING
Zai
JO
uiO
3U
.' Ou. j
SURFACE PREPARATION J J Q
: 2 igs AFTER
<t
_ u* ^
OvER t URninG 2 5 S3
z a S 1 9 < IS
< ii a. 2
3
3AINTING
Z z
:leaning
SURFACE PREPARATION
PAINTING 2 ui
3
i 1 < o <
1
il I| ul
£* <
O a
SHOT BLASTING r
M
74
.
engineering
racy [ 58 ] .
75
,
2. Ibid.
4. Ibid.
December, 1972.
8. Ibid.
11. Ibid.
Boston, 1974.
13. Ibid.
14. Ibid.
August, 1973.
18. Ibid.
76
... ..
.
22. Ibid.
23. Ibid.
24. Ibid.
25 Fox , op ci t
32 Fox , op cit
34 . Fox , op cit
36 Fox , op ci t
77
. . . .
38 Fox , op ci t
41. Ibid.
February 1985 ,
46. Ibid.
47. Ibid.
78
54. Expanded Ship Work Breakdown Structure Naval Sea
,
57. Ibid.
79
CHAPTER 3
MODERN SHIPBUILDING
3 . 1 Introduction
80
nology shipbuilder. Application of group technology prin-
General Concepts
instruction design.
81
In the Navy context, basic design includes the design
82
)
Conventional-
FEASIBILITY STUDIES
CONCEPT DESIGN
BIDS
PRELIM. CONTRACT ANO DETAILED LEAD SHIP
DESIGN DESIGN AWARD DESIGN CONSTRUCTION
(YEARS)
Group Technology- I
similar to
the above Lead Ship
( years
A - Functional Design
B - Transition Design
83
ting work instruction. A material list for manufacturing a
These include:
* assembly sequences
* welding sequences
* coating requirements
* work sites
84
, ,
ing program.
* general arrangements
* ship ' s lines
* midship section,
* machinery arrangement,
* other specific space arrangements,
85
* electric one-line diagrams,
* contract specifications.
* weight estimates,
* longitudinal strength,
* Bonjean curves,
* tank capacities,
* hydrostatics,
* damaged stability,
* loading conditions,
* wake survey,
* resistance,
* HVAC analysis,
* propeller design,
* shafting arrangement.
86
* defines blocks of maximum size and weight allowed by
Examples
3.1 summarizes this effect for the Navy's TAO 187 shipbuild-
yard Division chief engineer during the TAO 187 program [3],
87
Conventional Group Technology
Construction Construction
Table 3.1 Engineering Efforts for the TAO 187 [3] [4]
»•• LAV
kAUMCM
ON
eoatatcT CAT
A«fA«« l.AUc^^• » ,,,,
o
Kill. l ,
MOOUCTIOH
88
dale's Program Services Division. [4] As can be seen in
cate this was indeed the case for the TAO 187. See Figure
to solve this problem in the DDG 51, SSN 21, and TAGOS 19
89
, ,
opments ,
components
shell
space arrangements,
the weight impacts did not adversely affect the ship [7],
90
Attribute Result
Accessibility Improved
Operability Improved
Maintainability Improved
91
When most or all of the drawings in the Navy's contract
with this problem. These programs include the DDG 51, SSN
21, TAGOS 19, and LSD 44 (Cargo Variant) programs. For the
92
.
only at a minimal level. Most spent far more than they were
contract
93
. .
detail
94
1
r Hiw materia]
-SO teste components
(Basic iMicertii
standards) -SuacUrd fixings
'Design iu_acUxd»
-Produce on «ag.
— SOT- standards
(Eagineer'g 4ns pecaoa
Saipbldg. Jtandajds) standards
Standards
- SD1 Machinery Standard drwg.
-SD2 Practice drwir.
S03 Components k Amng
SD standard drwg.
(Standard -S04 Standard diagrams
drawings) -SOS Design manuals
"— SD6 Production manuals
-U^±^i.J--A
&&
l
j -
r i
i(T!
O 0=
a p
JL
95
FLAT ^4AK€ OIVISION
MAIN R.OOP PA2-4.7
^JEAS£ EXTRACTOR
SO 2 OBAIN PUMP
NO 2 *A IN CONO p UNP
NO I DRAIN PUMP
.NO I MAIN CONO PUMP
NO 2 L.O.PUMP ^_
NO I
"a
L.O.PUMP^-^Qi —T- 1
47
42 *4
A) BASE MOOULE
R.AT S4AME OIVISION
MAIN ?LOOR F42-*7 GREASE EXTBAC'OP-
ORAI n PUMP^f .
<rn\
NO 2 OPAINn pump .
.
Jj i-gv *%^ /
NO 2 MAIN CONO PUMP
NO ORAlN PUMP
I
:< ,1b
NO I MAIN COM3 PUMP -<"^ t. i±
NO 2 L.O.PUMP-
NO I
"a
L.O.PUMP^^Qj
47
42 44
I I I I I I I I I
1 5 FOIO 092
ATKtSP>€PZC ORAIN v*
INACTION TV*
96
Figure 3.7 Standard Outfit Unit Module [8]
97
commercial ship design and construction than in naval ship
Unfortunately, over the years not much effort has gone into
and they have proliferated to the point where the whole sys-
98
3.2.4 Design Changes in a Group Technology
Engineering Environment
* Navy
- correction of errors discovered in specifications
or contract drawings
over time
tions
tract award
99
* Contractor
- revised fitting stages
- revised equipment or component locations
- revised manufacturing process
- revised material availability or sources
- revision of hull structure
- resolution of a design reservation.
ence problems.
ules more than compensate for the greater expense and impact
100
of design changes.
Also, since the TAO 187 is an auxiliary ship and not a com-
of changes on the TAO 187 program was minimal and the first
101
was planned for installation in an existing hull ( DD 963
102
.
departments
ment system
103
Single Multi- Single Multi-
System system System system
00D light
Pallet truck
Rudder stock
seal
Vertical
package
conveyor
Strain gage
Gasket
material
Direction of greater
engineering impact
104
be remembered that this analysis applies to only the engi-
note that test results did not conclusively confirm that the
105
,
Number of Estimated
Documents Man-hours
"Drawings" 18 280
Supervision and
staff 516
Checking 430
Production
planning 172
and control
Finance and
administration 91
Administrative 225
or 2.54 man-years
106
lar breakdown was not available for IS but the total number
for the first few ships of the class. Then, after most
gram .
107
have been freed from the need to develop individual detail
108
. ) .
3.3 CAD/CAM
* estimating
* accounting
* purchasing
* numerical control (N/C) operations
* robotics
* accuracy control
* quality assurance
109
: . .
* inventory control
includes
* cost data
* material lists.
functions
110
BASIC DESIGM- COMPUTE* *• CONTRACT PLANS
STAGS DATA BASE
DESIGN REFINEMENT
COMPUTER
DATA SASE UPDATED CONTRACT PLANS
SHIPYARD CONSTRUCTION
REQUIREMENTS * PLANNING
(E.J., WELDING, PIECE nARKS
SLOCK NUMBERS i ETC.)
LOFTING INFORMATION
'ERECTION STOCK
REQUIREMENTS)
COMPUTER
DATA BASE
NUMERICAL CONTROL
LOFTING (N/C) TAPES
AND WORK INSTRUCTIONS
111
The ultimate goal of a CIM system is improvement in
112
TAPE TO OWNER FOR
APPROVAL OF OESIGN
TAPE TO CLASSIFICATION
SOCIETY FOR APPROVAL OF
DESIGN
113
As mentioned earlier, a fully developed CIM system
gram [ 21 ] .
114
CALS system.
those digital products and use them as the basis for all
115
FOLLOW YARD
NAVSEA DESIGN AGENT SHIPBUILDER PLANNING YARD
DIGITIZED
CAO/CAE ENGINEERING
PRELIMINARY/
DETAILED DESIGN
CAM
DESIGN DATA/
CONTRACT DESIGN PRODUCT MOOEL PRODUCT MOOEL
DATA INTEGRATE RAM
SUPPORT CONSIDERATIONS
INFLUENCE
NAVSEA
DESIGN
CALS * SHIPBOARD
LSA SYSTEM NETWORK MCLUOMG STORAGE
REPOSITORIES * RETRIEVAL
SUPPORTABILITY
FEEDBACK
DESIGN AGENT/NAVY THRU
EXPERT SYSTEMS MAINTENANCE
a HISTORY DATA.
AUTOMATED DIGITAL LOGISTICS PRODUCTS
ETC.
PROCESSES
116
EARLY STAGE
DESIGN
(NAVSCA/AOENT)
LEAD VARO
O.D. A CONST.
FOLLOW VARO
0.0. A CONST.
LOGISTIC SUPPORT
TECN DATA
© FLEET
PRO00CT ©
GENERATION TRAINING
SUPPLY © DATA
REPOSITORY
PLANNING VARO ©
(NAVV/COMLI ©
OTHER NAVY
USES
MODERNIZATION
I NAVY/COM L >
TIME
117
3 . 4 Work Breakdown Structures WBS and Cost and ( )
The WBS that makes the most sense for group technology-
[24] .
118
.
that result are not only expensive but also lead to the Navy
progress
119
shipbuilder. Appendix C provides further details.
ling units which are numbered from 000 to 799. The units'
120
schedule and cost reporting. Figure 3.12 depicts the physi-
121
I 1
90) 104
J — / I
1 L .,/
U)
!
1*9
1
|».
10)
1 1) "^n
702 '11 /
11) ,„ 10) its 113 111
u* 1*4 139 »4 '••/
!)• !!• t 11* 10* 10* 11* 124 701
1)1 '" 111 101 10) 11) 111 Ul 14) 10
1)1
» 111 121 in
i
3
212 101 104 11* ui 132 U) Ml TOO
1
/ 1
11 u
122
. .
123
) . . .
124
\JO •* LSO 44 LSD "
1, 1
, 1 1 ,1,1,1
«? J
S ii
*' I?
¥ !
EL
125
for transitions from a system to a zone and then back to a
costs. But does the data indicate these savings are con-
for the TAO 187, 188, 189, and 190. It is clear that some
126
Ship Recurring Production Costs
127
.
ing contract that has been completed and has used the group
results
128
.
REFERENCES TO CHAPTER 3
2. Ibid.
7. Ibid.
11. Ibid.
16. Ibid.
129
19. Lamb, T., "CAD/CAM in Shipbuilding", Washington
Society of Professional Engineers, Bremerton, Washington,
January 1983.
,
21. Ibid.
26. Ibid.
29. Cost Data Summary Reports for the TAO 187 Ship-
building Program, Avondale Industries, Inc., 31 December
1987.
130
.
CHAPTER 4
4 . 1 Conclusions
cost
131
.
accrue
132
. . .
4 . 2 Recommendations
As has been discussed, significant advances have been
costs
recommendations are:
* The Computer Aided Logistics Support program deserves
strong support from the highest levels in DoD and the Navy.
It has great potential for very large cost savings for the
Navy.
expanded
encouraged
133
* The Navy needs to find a way to facilitate the use of
134
equally between the ship itself and its combat system and
the NSRP.
135
struction facilities and methods vary widely among ship-
ods used in its own shipyard and provide the Navy with a
producibility methods.
136
.
pump and heater packages, lube oil filter and cooler pack-
* Hull Form:
stiffeners
- maximum use of uniform stiffener sizes
- use of flat innerbottoms
137
.
* Machinery:
- increasing commonalty of equipment (standardiza-
tion )
runs
access
* Combat Systems
138
)
design stages
139
.
encouraged
140
APPENDICES
141
. .
APPENDIX A
employment of WBSs
- It establishes a standard system-oriented family tree
government's solicitation.
- The project summary WBS is structured by the DoD com-
ponent .
vidual contractor.
142
.
ments .
contract WBS.
- The lowest level of the extended contract WBS for
143
Summary WBS and Definitions of Ship Systems as Defined
144
APPENDIX B
project WBS.
145
.
contract WBS.
- The lowest level of the extended contract WBS (level
ESWBS Organization
in MILSTD 881A
tems/equipments
- Level 7 - Equipment.
146
APPENDIX C
November 1980
managed.
struction methods.
Product Orientation
- The interim product is viewed as the focal point of
147
- Use of a PWBS results in natural work packages, ideal
that shipyard.
PWBS Organization
processes, etc.)
148
Thesis
H effr
0n
The
. impact of
f Sroup
tec hnolo£
V .
g m et h ° ds
«*P des ig n on navaI
tl0 and
« Practiced aCquis i-
Thesis
H42155 Hetrrun
c.l The impact of g^-oup
technology-based ship-
building methods on naval
ship design and acquisi-
tion practices.
fi*j&
:%*«>: