Tutorial Manual Plaxis V7.2
Tutorial Manual Plaxis V7.2
7.2
Tutorial Manual
TABLE OF CONTENTS
TABLE OF CONTENTS
1 Introduction...........................................................................1-1
2 Getting started......................................................................2-1
2.1 Installation...............................................................................................2-1
2.2 General modelling aspects.......................................................................2-1
2.3 Input procedures......................................................................................2-3
2.3.1 Input of Geometry objects...........................................................2-3
2.3.2 Input of text and values................................................................2-3
2.3.3 Input of selections........................................................................2-4
2.3.4 Structured input...........................................................................2-5
2.4 Starting the program................................................................................2-6
2.4.1 General settings...........................................................................2-6
2.4.2 Creating a geometry model..........................................................2-8
i
TUTORIAL MANUAL
ii PLAXIS Version 8
INTRODUCTION
1 INTRODUCTION
PLAXIS is a finite element package that has been developed specifically for the analysis
of deformation and stability in geotechnical engineering projects. The simple graphical
input procedures enable a quick generation of complex finite element models, and the
enhanced output facilities provide a detailed presentation of computational results. The
calculation itself is fully automated and based on robust numerical procedures. This
concept enables new users to work with the package after only a few hours of training.
Though the various lessons deal with a wide range of interesting practical applications this
Tutorial Manual is intended to help new users become familiar with P LAXIS. The lessons
should therefore not be used as a basis for practical projects.
Users are expected to have a basic understanding of soil mechanics and should be able
to work in a Windows environment. It is strongly recommended that the lessons are
followed in the order that they appear in the manual. The tutorial lessons are also
available in the examples folder of the P LAXIS program directory and can be used to
check your results.
The Tutorial Manual does not provide theoretical background information on the finite
element method, nor does it explain the details of the various soil models available in
the program. The latter can be found in the Material Models Manual, as included in the
full manual, and theoretical background is given in the Scientific Manual. For detailed
information on the available program features, the user is referred to the Reference
Manual. In addition to the full set of manuals, short courses are organised on a regular
basis at several places in the world to provide hands-on experience and background
information on the use of the program.
1-1
TUTORIAL MANUAL
2 GETTING STARTED
This chapter describes some of the notation and basic input procedures that are used in
PLAXIS. In the manuals, menu items or windows specific items are printed in Italics.
Whenever keys on the keyboard or text buttons on the screen need to be pressed or
clicked, this is indicated by the name of the key or button in brackets, (for example the
<Enter> key).
2.1 INSTALLATION
For the installation procedure the user is referred to the General Information section in this
manual.
For each new project to be analysed it is important to create a geometry model first. A
geometry model is a 2D representation of a real three-dimensional problem and consists of
points, lines and clusters. A geometry model should include a representative division of the
subsoil into distinct soil layers, structural objects, construction stages and loadings.
The model must be sufficiently large so that the boundaries do not influence the results of
the problem to be studied. The three types of components in a geometry model are
described below in more detail.
Points:
Points form the start and end of lines. Points can also be used for the
positioning of anchors, point forces, point fixities and for local refinements of the
finite element mesh.
Lines:
Lines are used to define the physical boundaries of the geometry, the model
boundaries and discontinuities in the geometry such as walls or shells,
separations of distinct soil layers or construction stages. A line can have several
functions or properties.
Clusters:
Clusters are areas that are fully enclosed by lines. P LAXIS automatically
recognises clusters based on the input of geometry lines. Within a cluster the
soil properties are homogeneous. Hence, clusters can be regarded as parts of
soil layers. Actions related to clusters apply to all elements in the cluster.
After the creation of a geometry model, a finite element model can automatically be
generated, based on the composition of clusters and lines in the geometry model. In a
finite element mesh three types of components can be identified, as described below.
2-1
TUTORIAL MANUAL
Elements:
During the generation of the mesh, clusters are divided into triangular elements.
A choice can be made between 15-node elements and 6-node elements. The
powerful 15-node element provides an accurate calculation of stresses and
failure loads. In addition, 6-node triangles are available for a quick calculation
of serviceability states. Considering the same element distribution (for example
a default coarse mesh generation) the user should be aware that meshes
composed of 15-node elements are actually much finer and much more flexible
than meshes composed of 6-node elements, but calculations are also more time
consuming. In addition to the triangular elements, which are generally used to
model the soil, compatible plate elements, geogrid elements and interface
elements may be generated to model structural behaviour and soil-structure
interaction.
Nodes:
A 15-node element consists of 15 nodes and a 6-node triangle is defined by 6
nodes. The distribution of nodes over the elements is shown in Figure 2.1.
Adjacent elements are connected through their common nodes. During a finite
element calculation, displacements (ux and uy) are calculated at the nodes.
Nodes may be pre-selected for the generation of load-displacement curves.
Stress points:
In contrast to displacements, stresses and strains are calculated at individual
Gaussian integration points (or stress points) rather than at the nodes. A 15-
node triangular element contains 12 stress points as indicated in Figure 2.1a
and a 6-node triangular element contains 3 stress points as indicated in Figure
2.1b. Stress points may be pre-selected for the generation of stress paths or
stress-strain diagrams.
2-3
TUTORIAL MANUAL
at the right side of each spin edit to increase or decrease its value by a predefined
amount.
Radio buttons:
In a window with radio buttons only one item may be active. The active
selection is indicated by a black dot in the white circle in front of the item.
Selection is made by clicking the left mouse button in the white circle or by
using the up and down arrow keys on the keyboard. When changing the
existing selection to one of the other options, the 'old' selection will be
deselected. An example of a window with radio buttons is shown in Figure 2.3.
According to the selection in Figure 2.3 the Pore pressure distribution is set
to
General phreatic level.
Check boxes:
In a window with check boxes more than one item may be selected at the same
time. The selection is indicated by a black tick mark in a white square.
Selection is made by clicking the left mouse button in the white square or by
pressing the space bar on the keyboard. Another click on a preselected item
will deselect the item. An example of three check boxes is shown in Figure 2.4.
Combo boxes:
A combo box is used to choose one item from a predefined list of possible
choices. An example of a window with combo boxes is shown in Figure 2.5. As
soon as the ▼ arrow at the right hand side of the combo box is left clicked with
the mouse, a pull down list occurs that shows the possible choices. A combo
box has the same functionality as a group of radio buttons but it is more
compact.
Group boxes:
Group boxes are rectangular boxes with a title. They are used to cluster input
items that have common features. In Figure 2.6, the active tab sheet contains three
group boxes named Stiffness, Strength and Alternatives.
2-5
TUTORIAL MANUAL
It is assumed that the program has been installed using the procedures described in the
General Information part of the manual. It is advisable to create a separate directory in
which data files are stored. PLAXIS can be started by double-clicking the Plaxis input
icon in the PLAXIS program group. The user is asked whether to define a new problem or
to retrieve a previously defined project. If the latter option is chosen, the program lists
four of the most recently used projects from which a direct choice can be made.
Choosing the item <<more files>> that appears first in this list will give a file requester
from which the user can choose any previously defined project for modification.
The second tab sheet is shown in Figure 2.8. In addition to the basic units of Length,
Force and Time, the minimum dimensions of the draw area must be given here, such
that the geometry model will fit the draw area. The general system of axes is such that
the x-axis points to the right, the y-axis points upward and the z-axis points towards the
user. In PLAXIS a two-dimensional model is created in the (x,y)-plane. The z-axis is used
2-7
TUTORIAL MANUAL
for the output of stresses only. Left is the lowest x-coordinate of the model, Right the
highest x-coordinate, Bottom the lowest y-coordinate and Top the highest y-coordinate of
the model.
In practice, the draw area resulting from the given values will be larger than the values
given in the four spin edits. This is partly because PLAXIS will automatically add a small
margin to the dimensions and partly because of the difference in the width/height ratio
between the specified values and the screen.
Main Menu
Toolbar (Geometry)
Toolbar (General)
Ruler
Ruler
Draw area
Origin
Main menu:
The main menu contains all the options that are available from the toolbars, and
some additional options that are not frequently used.
Rulers:
At both the left and the top of the draw area, rulers indicate the physical
coordinates, which enables a direct view of the geometry dimensions.
Draw area:
The draw area is the drawing sheet on which the geometry model is created.
The draw area can be used in the same way as a conventional drawing program.
The grid of small dots in the draw area can be used to snap to regular positions.
Origin:
If the physical origin is within the range of given dimensions, it is represented by a
small circle, with an indication of the x- and y-axes.
Manual input:
If drawing with the mouse does not give the desired accuracy, then the Manual
input line can be used. Values for x- and y-coordinates can be entered here by
typing the corresponding values separated by a space. The manual input can also
be used to assign new coordinates to a selected point or refer to an existing geometry
point by entering its point number.
2-9
TUTORIAL MANUAL
Go to output program New Open Save Print Zoom out Selection Undo
Geometry Hinge and Node-to-node Tunnel Rotation fixity Distributed Point Load
Geogrid Well Material sets
line Rotation Spring anchor designer (plates) Load system A system B
Plate Interface Fixed-end Standard Prescribeded Distributeded Point Load Drain Generate Define initial
anchor fixities Displacement Load system B system A mesh conditions
Help can be obtained from the user interface by pressing <F1> on the keyboard. This
will provide background information on the selected part of the program.
For detailed information on the creation of a complete geometry model, the reader is
referred to the various lessons that are described in this Tutorial Manual.
In the previous chapter some general aspects and basic features of the P LAXIS program
were presented. In this chapter a first application is considered, namely the settlement of
a circular foundation footing on sand. This is the first step in becoming familiar with the
practical use of the program. The general procedures for the creation of a geometry
model, the generation of a finite element mesh, the execution of a finite element
calculation and the evaluation of the output results are described here in detail. The
information provided in this chapter will be utilised in the later lessons. Therefore, it is
important to complete this first lesson before attempting any further tutorial examples.
3.1 GEOMETRY
A circular footing with a radius of 1.0 m is placed on a sand layer of 4.0 m thickness as
shown in Figure 3.1. Under the sand layer there is a stiff rock layer that extends to a
large depth. The purpose of the exercise is to find the displacements and stresses in the soil
caused by the load applied to the footing. Calculations are performed for both rigid and
flexible footings. The geometry of the finite element model for these two situations is
similar. The rock layer is not included in the model; instead, an appropriate boundary
condition is applied at the bottom of the sand layer. To enable any possible mechanism in
the sand and to avoid any influence of the outer boundary, the model is extended in
horizontal direction to a total radius of 5.0 m.
In the first calculation, the footing is considered to be very stiff and rough. In this
calculation the settlement of the footing is simulated by means of a uniform indentation
3-1
TUTORIAL MANUAL
at the top of the sand layer instead of modelling the footing itself. This approach leads to a
very simple model and is therefore used as a first exercise, but it also has some
disadvantages. For example, it does not give any information about the structural forces in
the footing. The second part of this lesson deals with an external load on a flexible
footing, which is a more advanced modelling approach.
General Settings
The first step in every analysis is to set the basic parameters of the finite element model.
This is done in the General settings window. These settings include the description of
the problem, the type of analysis, the basic type of elements, the basic units and the size
of the draw area. To enter the appropriate settings for the footing calculation follow
these steps:
• In the Project tab sheet, enter “Lesson 1” in the Title box and type “Settlements
of a circular footing” in the Comments box.
• In the General box the type of the analysis (Model) and the basic element type
(Elements) are specified. Since this lesson concerns a circular footing, choose
Axisymmetry from the Model combo box and select 15-node from the Elements
combo box.
• The Acceleration box indicates a fixed gravity angle of -90°, which is in the
vertical direction (downward). In addition to the normal gravity, independent
acceleration components may be entered for pseudo-dynamic analyses. These
values should be kept zero for this exercise. Click the <Next> button below the tab
sheets or click the Dimensions tab.
• In the Dimensions tab sheet, keep the default units in the Units box (Unit of
Length = m; Unit of Force = kN; Unit of Time = day).
• In the Geometry dimensions box the size of the required draw area must be
entered. When entering the upper and lower coordinate values of the geometry to
be created, PLAXIS will add a small margin so that the geometry will fit well within
the draw area. Enter 0.0, 5.0, 0.0 and 4.0 in the Left, Right, Bottom and Top
edit boxes respectively.
• The Grid box contains values to set the grid spacing. The grid provides a
matrix of dots on the screen that can be used as reference points. It may also be
used for snapping to regular points during the creation of the geometry. The
distance between the dots is determined by the Spacing value. The spacing of
snapping points can be further divided into smaller intervals by the Number of
intervals value. Enter 1.0 for the spacing and 1 for the intervals.
• Click the <OK> button to confirm the settings. Now the draw area appears in
which the geometry model can be drawn.
3-3
TUTORIAL MANUAL
Hint: In the case of a mistake or for any other reason that the general settings need
to be changed, you can access the General settings window by selecting the
General settings option from the File menu.
Geometry Contour
Once the general settings have been completed, the draw area appears with an indication
of the origin and direction of the system of axes. The x-axis is pointing to the right and
the y-axis is pointing upward. A geometry can be created anywhere within the draw
area. To create objects, you can either use the buttons from the toolbar or the options
from the Geometry menu. For a new project, the Geometry line button is already
active.
Otherwise this option can be selected from the second toolbar or from the Geometry
menu. In order to construct the contour of the proposed geometry, follow these steps:
Select the Geometry line option (already pre-selected).
• Position the cursor (now appearing as a pen) at the origin of the axes. Check
that the units in the status bar read 0.0 x 0.0 and click the left mouse button
once. The first geometry point (number 0) has now been created.
• Move along the x-axis to position (5.0; 0.0). Click the left mouse button to
generate the second point (number 1). At the same time the first geometry line
is created from point 0 to point 1.
• Move upward to position (5.0; 4.0) and click again.
• Move to the left to position (0.0; 4.0) and click again.
• Finally, move back to the origin (0.0; 0.0) and click the left mouse button
again. Since the latter point already exists, no new point is created, but only an
additional geometry line is created from point 3 to point 0. P LAXIS will also
detect a cluster (area that is fully enclosed by geometry lines) and will give it a
light colour.
• Click the right mouse button to stop drawing.
Hint: Mispositioned points and lines can be modified or deleted by first choosing
the Selection button from the toolbar. To move a point or line, select the point
or the line and drag it to the desired position. To delete a point or a line, select
the point or the line and press the <Delete> button on the keyboard.
Unwanted drawing operations can be removed by clicking the Undo button
from the toolbar or by selecting the Undo option from the Edit menu or by
pressing <Ctrl><Z> on the keyboard.
> Lines can be drawn perfectly horizontal or vertical by holding down the
<Shift> key on the keyboard while moving the cursor.
The proposed geometry does not include plates, hinges, geogrids, interfaces, anchors or
tunnels. Hence, you can skip these buttons on the second toolbar.
Hint: The full geometry model has to be completed before a finite element mesh
can be generated. This means that boundary conditions and model parameters
must be entered and applied to the geometry model first.
Boundary Conditions
Boundary conditions can be found in the centre part of the second toolbar and in the
Loads menu. For deformation problems two types of boundary conditions exist:
Prescribed displacements and prescribed forces (loads).
In principle, all boundaries must have one boundary condition in each direction. That is
to say, when no explicit boundary condition is given to a certain boundary (a free
boundary), the natural condition applies, which is a prescribed force equal to zero and a
free displacement.
To avoid the situation where the displacements of the geometry are undetermined, some
points of the geometry must have prescribed displacements. The simplest form of a
prescribed displacement is a fixity (zero displacement), but non-zero prescribed
displacements may also be given. In this problem the settlement of the rigid footing is
simulated by means of non-zero prescribed displacements at the top of the sand layer.
3-5
TUTORIAL MANUAL
To create the boundary conditions for this lesson, follow these steps:
Click the Standard fixities button on the toolbar or choose the Standard
fixities option from the Loads menu to set the standard boundary conditions.
• As a result PLAXIS will generate a full fixity at the base of the geometry and
roller conditions at the vertical sides (ux=0; uy=free). A fixity in a certain
direction appears on the screen as two parallel lines perpendicular to the fixed
direction. Hence, roller supports appear as two vertical parallel lines and full
fixity appears as crosshatched lines.
Hint: The Standard fixities option is suitable for most geotechnical applications. It
is a fast and convenient way to input standard boundary conditions.
In addition to the new point (4), a prescribed downward displacement of 1 unit (1.0 m) in
a vertical direction and a fixed horizontal displacement are created at the top of the
geometry. Prescribed displacements appear as a series of arrows starting from the
original position of the geometry and pointing in the direction of movement.
Hint: The input value of a prescribed displacement may be changed by first clicking
the Selection button and then double-clicking the line at which a prescribed
displacement is applied. On selecting Prescribed displacements from
the
Select dialog box, a new window will appear in which the changes can be
made.
> The prescribed displacement is actually activated when defining the
calculation stages (Section 3.2.2). Initially it is not active.
3-7
TUTORIAL MANUAL
The input of material data sets can be selected by means of the Material Sets button on
the toolbar or from the options available in the Materials menu.
To create a material set for the sand layer, follow these steps:
Select the Material Sets button on the toolbar.
• Click the <New> button at the lower side of the Material Sets window. A new
dialog box will appear with three tab sheets: General, Parameters
and Interfaces (see Figure 3.6 and Figure 3.7).
Figure 3.6 General tab sheet of the soil and interface data set window
• In the Material Set box of the General tab sheet, write “Sand” in the
Identification box.
• Select Mohr-Coulomb from the Material model combo box and Drained from
the Material type combo box (default parameters).
• Enter the proper values in the General properties box and the Permeability box
according to the material properties listed in Table 3.1.
• Click the <Next> button or click the Parameters tab to proceed with the input
of model parameters. The parameters appearing on the Parameters tab sheet
depend on the selected material model (in this case the Mohr-Coulomb model).
See the Material Models manual for a detailed description of different soil models and their
corresponding parameters.
Figure 3.7 Parameters tab sheet of the soil and interface data set window
• Enter the model parameters of Table 3.1 in the corresponding edit boxes of the
Parameters tab sheet.
• Since the geometry model does not include interfaces, the third tab sheet can be
skipped. Click the <OK> button to confirm the input of the current material
data set. Now the created data set will appear in the tree view of the Material
Sets window.
• Drag the data set “Sand” from the Material Sets window (select it and hold
down the left mouse button while moving) to the soil cluster in the draw area
and drop it (release the left mouse button). Notice that the cursor changes shape
to indicate whether or not it is possible to drop the data set. Correct assignment
of a data set to a cluster is indicated by a change in colour of the cluster.
• Click the <OK> button in the Material Sets window to close the database.
3-9
TUTORIAL MANUAL
Hint: Existing data sets may be changed by opening the material sets window,
selecting the data set to be changed from the tree view and clicking the
<Edit> button. As an alternative, the material sets window can be opened by
double-clicking a cluster and clicking the <Change> button behind the
Material set box in the properties window. A data set can now be assigned to
the corresponding cluster by selecting it from the project database tree view and
clicking the <Apply> button.
> The program performs a consistency check on the material parameters and
will give a warning message in the case of a detected inconsistency in the
data.
Mesh Generation
When the geometry model is complete, the finite element model (or mesh) can be
generated. PLAXIS allows for a fully automatic mesh generation procedure, in which the
geometry is divided into elements of the basic element type and compatible structural
elements, if applicable.
Figure 3.8 Axisymmetric finite element mesh of the geometry around the footing
The mesh generation takes full account of the position of points and lines in the
geometry model, so that the exact position of layers, loads and structures is accounted
for in the finite element mesh. The generation process is based on a robust triangulation
principle that searches for optimised triangles and which results in an unstructured mesh.
Unstructured meshes are not formed from regular patterns of elements. The numerical
performance of these meshes, however, is usually better than structured meshes with
regular arrays of elements. In addition to the mesh generation itself, a transformation of
input data (properties, boundary conditions, material sets, etc.) from the geometry model
(points, lines and clusters) to the finite element mesh (elements, nodes and stress points)
is made.
In order to generate the mesh, follow these steps:
Click the Generate mesh button in the toolbar or select the Generate
option from the Mesh menu.
After the generation of the mesh a new window is opened (Output window) in
which the generated mesh is presented (see Figure 3.8).
• Click the <Update> button to return to the geometry input mode.
Hint: The <Update> button must always be used to return to the geometry input,
even if the result from the mesh generation is not satisfactory.
Initial Conditions
Once the mesh has been generated, the finite element model is complete. Before starting
the calculations, however, the initial conditions must be generated. In general, the initial
conditions comprise the initial groundwater conditions, the initial geometry
configuration and the initial effective stress state. The sand layer in the current footing
project is dry, so there is no need to enter groundwater conditions. The analysis does,
however, require the generation of initial effective stresses by means of the K0-
procedure.
The initial conditions are entered in separate modes of the Input program. In order to
generate the initial conditions properly, follow these steps:
Click the Initial conditions button on the toolbar or select the Initial
conditions option from the Initial menu.
3-11
TUTORIAL MANUAL
• First a small window appears showing the default value of the unit weight of
water (10 kN/m3). Click <OK> to accept the default value. The groundwater
conditions mode appears. Note that the toolbar and the background of the
geometry have changed compared to the geometry input mode.
The initial conditions option consists of two different modes: The water pressures mode and
the geometry configuration mode. Switching between these two modes is done by the
'switch' in the toolbar.
Since the current project does not involve water pressures, proceed to the
geometry configuration mode by clicking the right hand side of the 'switch'
(Initial stresses and geometry configuration). A phreatic level is
automatically placed at the bottom of the geometry.
Click the Generate initial stresses button (red crosses) in the toolbar or
select
the Initial stresses option from the Generate menu. The K0-procedure
dialog
box appears.
• Keep the total multiplier for soil weight, ΣMweight, equal to 1.0. This means
that the full weight of the soil is applied for the generation of initial stresses.
Accept the default values of K0 as suggested by PLAXIS and click <OK>.
Figure 3.9 Initial stress field in the geometry around the footing
Hint: The K0-procedure may only be used for horizontally layered geometries with
a horizontal ground surface and, if applicable, a horizontal phreatic level. See
Appendix A or the Reference Manual for more information on the K0-
procedure.
> The default value of K0 is based on Jaky's formula: K0 = 1-sinϕ. If the value
was changed, the default value can be regained by entering a negative value
for K0.
• After the generation of the initial stresses the Output window is opened in
which the effective stresses are presented as principal stresses (see Figure 3.9).
The length of the lines indicates the relative magnitude of the principal stresses
and the orientation of the lines indicates the principal directions. Click the
<Update> button to return to the Input program geometry configuration mode.
After the generation of the initial stresses, the calculation can be defined. After
clicking the <Calculate> button, the user is asked to save the data on the hard
disk. Click the <Yes> button. The file requester now appears. Enter an
appropriate file name and click the <Save> button.
Figure 3.10 The Calculations window with the General tab sheet
The Calculations window consists of a menu, a toolbar, a set of tab sheets and a list of
calculation phases, as indicated in Figure 3.10.
The tab sheets (General, Parameters and Multipliers) are used to define a
calculation
phase. This can be a loading, construction or excavation phase, a consolidation period or
3-13
TUTORIAL MANUAL
a safety analysis. For each project multiple calculation phases can be defined. All
defined calculation phases appear in the list at the lower part of the window. The tab
sheet Preview can be used to show the actual state of the geometry. A preview is only
available after calculation of the selected phase.
When the Calculations program is started directly after the input of a new project, a first
calculation phase is automatically inserted. In order to simulate the settlement of the
footing in this analysis, a plastic calculation is required. P LAXIS has a convenient
procedure for automatic load stepping, which is called Load Advancement. This
procedure can be used for most practical applications. Within the plastic calculation, the
prescribed displacements are activated to simulate the indentation of the footing. In
order to define the calculation phase, follow these steps:
• In the Phase ID box write (optionally) an appropriate name for the current
calculation phase (for example “Indentation”) and select the phase from which
the current phase should start (in this case the calculation can only start from
phase 0 - Initial phase).
• In the General tab sheet, select Plastic from the Calculation type combo box.
• Click the <Parameters> button or click the Parameters tab.
Figure 3.11 The Calculations window with the Parameters tab sheet
Additional steps (250) and select the Standard setting from the Iterative
procedure box. See the Reference Manual for more information about the
calculation control parameters.
• From the Loading input box, select Staged Construction.
• Click the <Define> button.
• The Staged Construction window appears, showing the currently active
geometry configuration. Select the prescribed displacement by double-clicking the
top line. A dialog box will appear.
• In the Prescribed Displacement dialog box the magnitude and direction of the
prescribed displacement can be specified, as indicated in Figure 3.12. In this case
enter a Y-value of -0.1 in both input fields, signifying a downward
displacement of 0.1 m. All X-values should remain zero. Click <OK>.
• Now click the <Update> button to return to the Parameters tab sheet of the
calculations window.
The calculation definition is now complete. Before starting the first calculation it is
advisable to select nodes or stress points for a later generation of load-displacement
curves or stress and strain diagrams. To do this, follow these steps:
3-15
TUTORIAL MANUAL
Click the Select points for curves button on the toolbar. As a result, a window
is opened, showing all the nodes in the finite element model.
• Select the node at the top left corner. The selected node will be indicated by 'A'.
Click the <Update> button to return to the Calculations window.
• In the Calculations window, click the <Calculate> button. This will start the
calculation process. All calculation phases that are selected for execution, as
indicated by the blue arrow (→) (only one phase in this case) will, in principle, be
executed in the order controlled by the Start from phase parameter.
Hint: The <Calculate> button is only visible if a calculation phase that is selected
for execution is focused in the list.
During the execution of a calculation a window appears which gives information about the
progress of the actual calculation phase (see Figure 3.13). The information, which is
continuously updated, comprises a load-displacement curve, the level of the load
systems (in terms of total multipliers) and the progress of the iteration process (iteration
number, global error, plastic points, etc.). See the Reference Manual for more
information about the calculations info window.
When a calculation ends, the list of calculation phases is updated and a message appears in
the corresponding Log info memo box. The Log info memo box indicates whether or
not the calculation has finished successfully. The current calculation should give the
message 'Prescribed ultimate state fully reached'.
To check the applied load that results in the prescribed displacement of 0.1 m, click the
Multipliers tab and select the Reached values radio button. In addition to the reached
values of the multipliers in the two existing columns, additional information is presented
at the left side of the window. For the current application the value of Force-Y is
important. This value represents the total reaction force corresponding to the applied
prescribed vertical displacement, which corresponds to the total force under 1.0 radian
of the footing (note that the analysis is axisymmetric). In order to obtain the total footing
force, the value of Force-y should be multiplied by 2π (this gives a value of about 1100
kN).
Hint: Calculation phases may be added, inserted or deleted using the <Next>,
<Insert> and <Delete> buttons half way the Calculations window.
> Check the list of calculation phases carefully after each execution of a (series
of) calculation(s). A successful calculation is indicated in the list with a green
check mark (√) whereas an unsuccessful calculation is indicated with a red
cross (×). Calculation phases that are selected for execution are indicated by a
blue arrow (→).
> When a calculation phase is focused that is indicated by a green check mark
or a red cross, the toolbar shows the <Output> button, which gives direct
access to the Output program. When a calculation phase is focused that is
indicated by a blue arrow, the toolbar shows the <Calculate> button.
3-17
TUTORIAL MANUAL
• The presentation combo box in the toolbar currently reads Arrows. Select
Shadings from this combo box. The plot shows colour shadings of the total
displacements. An index is presented with the displacement values at the colour
boundaries.
• Select Contours from the presentation combo box in the toolbar. The plot
shows contour lines of the total displacements, which are labelled. An index is
presented with the displacement values corresponding to the labels.
Hint: In addition to the total displacements, the Deformations menu allows for the
presentation of Incremental displacements. The incremental displacements
are
the displacements that occurred within one calculation step (in this case the
final step). Incremental displacements may be helpful in visualising an
eventual failure mechanism.
• Select Effective stresses from the Stresses menu. The plot shows the effective
stresses as principal stresses, with an indication of their direction and their
relative magnitude (see Figure 3.15).
Hint: The plots of stresses and displacements may be combined with geometrical
features, as available in the Geometry menu.
Click the Table button on the toolbar. A new window is opened in which a
table is presented, showing the values of the Cartesian stresses in each stress
point of all elements.
The project is now modified so that the footing is modelled as a flexible plate. This
enables the calculation of structural forces in the footing. The geometry used in this
exercise is the same as the previous one, except that additional elements are used to
model the footing. The calculation itself is based on the application of load rather than
prescribed displacements. It is not necessary to create a new model; you can start from
the previous model, modify it and store it under a different name. To perform this,
follow these steps:
• Select the previous file (“lesson1” or whichever name it was given) from the
Create/Open project window.
3-19
TUTORIAL MANUAL
• Select the Save as option of the File menu. Enter a non-existing name for the
current project file and click the <Save> button.
• Select the geometry line on which the prescribed displacement was applied and
press the <Del> key on the keyboard. Select Prescribed displacement from the
Select items to delete window and click the <Delete> button.
Click the Plate button in the toolbar.
• Move to position (0.0; 4.0) and click the left mouse button.
• Move to position (1.0; 4.0) and click the left mouse button, followed by the
right mouse button to finish the drawing. A plate from point 3 to point 4 is
created which simulates the flexible footing.
• Select Plates from the Set type combo box in the Material Sets window.
• Click the <New> button. A new window appears where the properties of the
footing can be entered.
• Write “Footing” in the Identification box and select the Elastic material type.
• Enter the properties as listed in Table 3.2.
• Click the <OK> button. The new data set now appears in the tree view of the
Material Sets window.
• Drag the set “Footing” to the draw area and drop it on the footing. Note that the
cursor changes shape to indicate that it is valid to drop the material set.
• Close the database by clicking the <OK> button
Hint: If the Material Sets window is displayed over the footing and hides it, move
the window to another position so that the footing is clearly visible.
Hint: Regeneration of the mesh results in a redistribution of nodes and stress points.
In general, existing stresses will not correspond with the new position of the
stress points. Therefore it is important to regenerate the initial water pressures
and initial stresses after regeneration of the mesh.
Initial conditions
Back in the Geometry input mode, click the <Initial conditions> button.
Since the current project does not involve pore pressures, proceed to the
Geometry configuration mode by clicking the 'switch' in the toolbar.
Click the Generate initial stresses button, after which the K0-procedure
dialog box appears.
• Keep ΣMweight equal to 1.0 and accept the default value of K0 for the single
cluster.
• Click the <OK> button to generate the initial stresses.
• After viewing the initial stresses, click the <Update> button.
3-21
TUTORIAL MANUAL
• Click the <Calculate> button and confirm the saving of the current project.
Calculations
• In the General tab sheet, select for the Calculation type: Plastic.
• Enter an appropriate name for the phase identification and accept 0 - initial
phase as the phase to start from.
• In the Parameters tab sheet, select the Staged construction option and click the
<Define> button.
• The plot of the active geometry will appear. Click the load to activate it. A
Select items dialog box will appear. Activate both the plate and the load by
checking the check boxes to the left..
• While the load is selected click the <Change> button at the bottom of the
dialog box. The distributed load - load system A dialog box will appear to
set the loads. Enter a Y-value of -350 kN/m2 for both geometry points. Note that
this gives a total load that is approximately equal to the footing force that was
obtained from the first part of this lesson.
• (350 kN/m2 x π x (1.0 m)2 ≈ 1100 kN).
• Close the dialog boxes and click <Update>.
Check the nodes and stress points for load-displacement curves to see if the
proper points are still selected (the mesh has been regenerated so the nodes
might have changed!). The top left node of the mesh should be selected.
• Check if the calculation phase is marked for calculation by a blue arrow. If this
is not the case double-click the calculation phase or right click and select Mark
calculate from the pop-up menu. Click the <Calculate> button to start the
calculation.
Hint: Multiple (sub-)windows may be opened at the same time in the Output
program. All windows appear in the list of the Window menu. PLAXIS follows
the Windows standard for the presentation of sub-windows (Cascade, Tile,
Minimize, Maximize, etc). See your Windows manual for a description of
these standard possibilities.
A Curve generation window now appears, consisting of two columns (x-axis and
y-axis), with multi select radio buttons and two combo boxes for each column. The
combination of selections for each axis determines which quantity is plotted along the
axis.
3-23
TUTORIAL MANUAL
• For the X-axis select the Displacement radio button, from the Point combo box
select A (0.00 / 4.00) and from the Type combo box Uy. Also select the
Invert sign check box. Hence, the quantity to be plotted on the x-axis is the
vertical displacement of point A (i.e. the centre of the footing).
• For the Y-axis select the Multiplier radio button and from the Type combo box
select ΣMstage. Hence, the quantity to be plotted on the y-axis is the amount of the
specified changes that has been applied. Hence the value will range from 0 to 1,
which means that 100% of the prescribed load (350 kN/m 2) has been applied
and the prescribed ultimate state has been fully reached.
• Click the <OK> button to accept the input and generate the load-displacement
curve. As a result the curve of Figure 3.17 is plotted in the Curves window.
Hint: The Curve settings window may also be used to modify the attributes or
presentation of a curve.
Hint: To re-enter the Curve generation window (in the case of a mistake, a
desired
regeneration or modification) you can click the Change curve settings
button
from the toolbar. As a result the Curve settings window appears, on which
you should click the <Regenerate> button. Alternatively, you may open the
Curve settings window by selecting the Curve option from the Format
menu. > The Frame settings window may be used to modify the settings of the
frame.
This window can be opened by clicking the Change frame settings
button
from the toolbar or selecting the Frame option from the Format menu.
This lesson illustrates the use of PLAXIS for the analysis of submerged construction of an
excavation. Most of the program features that were used in Lesson 1 will be utilised here
again. In addition, some new features will be used, such as the use of interfaces and
anchor elements, the generation of water pressures and the use of multiple calculation
phases. The new features will be described in full detail, whereas the features that were
treated in Lesson 1 will be described in less detail. Therefore it is suggested that Lesson
1 should be completed before attempting this exercise.
This lesson concerns the construction of an excavation close to a river. The excavation is
carried out in order to construct a tunnel by the installation of prefabricated tunnel
segments. The excavation is 30 m wide and the final depth is 20 m. It extends in
longitudinal direction for a large distance, so that a plane strain model is applicable. The
sides of the excavation are supported by 30 m long diaphragm walls, which are braced by
horizontal struts at an interval of 5.0 m. Along the excavation a surface load is taken into
account. The load is applied from 2 meter from the diaphragm wall up to 7 meter from
the wall and has a magnitude of 5 kN/m2/m.
The upper 20 m of the subsoil consists of soft soil layers, which are modelled as a single
homogeneous clay layer. Underneath this clay layer there is a stiffer sand layer, which
extends to a large depth.
23 5 2 30 2 5 23
5 kN/m2/m 5 kN/m2/m
Strut
10
Diaphragm wall
Sand
10
The bottom of the problem to be analysed is taken at 40 m below the ground surface.
Since the geometry is symmetric, only one half (the left side) is considered in the
analysis. The excavation process is simulated in three separate excavation stages. The
diaphragm wall is modelled by means of a plate, such as used for the footing in the
previous lesson. The interaction between the wall and the soil is modelled at both sides
4-1
TUTORIAL MANUAL
by means of interfaces. The interfaces allow for the specification of a reduced wall
friction compared to the friction in the soil. The strut is modelled as a spring element for
which the normal stiffness is a required input parameter.
For background information on these new objects, see the Reference Manual.
4.1 GEOMETRY
General settings
• Start the Input program and select New project from the Create / Open project
dialog box.
• In the Project tab sheet of the General settings window, enter an appropriate
title and make sure that Model is set to Plane strain and that Elements is set to
15-node.
• In the Dimensions tab sheet, keep the default units (Length = m; Force = kN;
Time = day) and enter for the horizontal dimensions (Left, Right) 0.0 and 45.0
respectively and for the vertical dimensions (Bottom, Top) 0.0 and 40.0. Keep
the default values for the grid spacing (Spacing=1m; Number of intervals =
1).
• Click the <OK> button after which the worksheet appears.
Hint: Within the geometry input mode it is not strictly necessary to select the
buttons in the toolbar in the order that they appear from left to right. In this
case, it is more convenient to create the wall first and then enter the separation of
the excavation stages by means of a Geometry line.
> When creating a point very close to a line, the point is usually snapped onto
the line, because the mesh generator cannot handle non-coincident points and
lines at a very small distance. This procedure also simplifies the input of
points that are intended to lie exactly on an existing line.
> If the pointer is substantially mispositioned and instead of snapping onto an
existing point or line a new isolated point is created, this point may be
dragged (and snapped) onto the existing point or line by using the Selection
button.
> In general, only one point can exist at a certain coordinate and only one line
can exist between two points. Coinciding points or lines will automatically be
reduced to single points or lines. The procedure to drag points onto existing
points may be used to eliminate redundant points (and lines).
The interfaces: Click the Interface button on the toolbar or select the
Interface
option from the Geometry menu. The shape of the cursor will change into a
cross with an arrow in each quadrant. The arrows indicate the side at which the
interface will be generated when the cursor is moved in a certain direction.
• Move the cursor (the centre of the cross defines the cursor position) to the top
of the wall (30.0; 40.0) and click the left mouse button. Move to the bottom of the
wall (30.0; 10.0) and click again. According to the position of the 'down' arrow at
the cursor, an interface is generated at the left hand side of the wall. Similarly, the
'up' arrow is positioned at the right side of the cursor, so when moving up to the
top of the wall and clicking again, an interface is generated at the right hand side of
the wall. Move back to (30.0; 40.0) and click again. Click the right mouse button to
finish drawing.
4-3
TUTORIAL MANUAL
Hint: Interfaces are indicated as dotted lines along a geometry line. In order to
identify interfaces at either side of a geometry line, a positive sign ( ⊕) or
negative sign () is added. This sign has no physical relevance or influence
on the results.
The strut: Click the Fixed-end anchor button on the toolbar or select the Fixed-
end anchor option from the Geometry menu. Move the cursor to a position 1
metre below point 6 (30.0; 39.0) and click the left mouse button. A properties
window appears in which the orientation angle and the equivalent length of the
anchor can be entered. Enter an Equivalent length of 15 m (half the width of
the excavation) and click the <OK> button (the orientation angle remains 0°).
Hint: A fixed-end anchor is represented by a rotated T with a fixed size. This object
is actually a spring of which one end is connected to the mesh and the other
end is fixed. The orientation angle and the equivalent length of the anchor
must be directly entered in the properties window. The equivalent length is
the distance between the connection point and the position in the direction of
the anchor rod where the displacement is zero. By default, the equivalent
length is 1.0 unit and the angle is zero degrees (i.e. the anchor points in the
positive x-direction).
> Clicking the 'middle bar' of the corresponding T selects an existing fixed-end
anchor.
The surface load: Click the Distributed load - load system A. Move the
cursor to (23.0; 40.0) and click. Move the cursor 5 m to the right to (28.0; 40.0)
and click again. Right click to finish drawing. Click the Selection tool and
doubleclick the distributed load and select Distributed Load (System A)
from the list. Enter Y-values of -5 kN/m2.
Boundary Conditions
To create the boundary conditions, click the Standard fixities button on the
toolbar. As a result, the program will generate full fixities at the bottom and
vertical rollers at the vertical sides. These boundary conditions are in this case
appropriate to model the conditions of symmetry at the right hand boundary
(center line of the excavation). The geometry model so far is shown in Figure
4.2.
Material properties
After the input of boundary conditions, the material properties of the soil clusters and
other geometry objects are entered in data sets. Interface properties are included in the data
sets for soil (Data sets for Soil & interfaces). Two data sets need to be created; one for
the clay layer and one for the sand layer. In addition, a data set of the Plate type is
created for the diaphragm wall and a data set of the Anchor type is created for the strut.
To create the material data sets, follow these steps:
Click the Material sets button on the toolbar. Select Soil & interfaces as the
Set type. Click the <New> button to create a new data set.
• For the clay layer, enter 'Clay' for the Identification and select Mohr-Coulomb
as the Material model. Since only long-term effects of the excavation are
considered here, we will not take into account the undrained behaviour. Hence, the
material type is set to Drained.
• Enter the properties of the clay layer, as listed Table 4.1, in the corresponding
edit boxes of the General and Parameters tab sheet.
Click the Interfaces tab. In the Strength box, select the Manual radio
button. Enter a value of 0.5 for the parameter Rinter. This parameter relates the
strength of the soil to the strength in the interfaces, according to the equations:
tan ϕinterface = Rinter tan ϕsoil and cinter = Rinter csoil
4-5
TUTORIAL MANUAL
where:
csoil = cref (see Table 4.1)
Hence, using the entered Rinter-value gives a reduced interface friction and
interface cohesion (adhesion) compared to the friction angle and the cohesion in
the adjacent soil.
Table 4.1. Material properties of the sand and clay layer and the interfaces
Parameter Name Clay Sand Unit
layer layer
Material model Model Mohr- Mohr- -
Coulomb Coulomb
Type of material behaviour Type Drained Drained -
Soil unit weight above phreatic level γunsat 16 17 kN/m3
Soil unit weight below phreatic level γsat 18 20 kN/m3
Permeability in hor. direction kx 0.001 1.0 m/day
Permeability in ver. direction ky 0.001 1.0 m/day
Young's modulus (constant) Eref 10000 40000 kN/m2
Poisson's ratio ν 0.35 0.3 -
Cohesion (constant) cref 5.0 1.0 kN/m2
Friction angle ϕ 25 32 °
Dilatancy angle ψ 0.0 2.0 °
Strength reduction factor inter. Rinter 0.5 0.67 -
• For the sand layer, enter 'Sand' for the Identification and select Mohr-Coulomb
as the Material model. The material type should be set to Drained.
• Enter the properties of the sand layer, as listed Table 4.1, in the corresponding
edit boxes of the General and Parameters tab sheet.
• Click the Interfaces tab. In the Strength box, select the Manual radio button.
Enter a value of 0.67 for the parameter Rinter. Close the data set.
• Drag the 'Sand' data set to the lower cluster of the geometry and drop it there.
Assign the 'Clay' data set to the remaining four clusters (in the upper 20 m). By
default, interfaces are automatically assigned the data set of the adjacent
cluster.
Hint: Instead of accepting the default data sets of interfaces, data sets can directly
be assigned to interfaces in their properties window. This window appears
after double-clicking the corresponding geometry line and selecting the
appropriate interface from the Select dialog box. On clicking the <Change>
button behind the Material set parameter, the proper data set can be selected
from the Material sets tree view.
Hint: In addition to the Material set parameter in the properties window, the Virtual
thickness factor can be entered. This is a purely numerical value, which can
be used to optimise the numerical performance of the interface. Non-
experienced users are advised not to change the default value. For more
information about interface properties see the Reference Manual.
• Set the Set type parameter in the Material sets window to Plates and click the
<New> button. Enter “Diaphragm wall” as an Identification of the data set and
enter the properties as given in Table 4.2. Click the <OK> button to close the
data set.
• Drag the Diaphragm wall data set to the wall in the geometry and drop it as
soon as the cursor indicates that dropping is possible.
Hint: The radio button Rigid in the Strength box is a direct option for an interface
with the same strength properties as the soil (Rinter = 1.0).
• Set the Set type parameter in the Material sets window to Anchors and click the
<New> button. Enter “Strut” as an Identification of the data set and enter the
properties as given in Table 4.3. Click the <OK> button to close the data set.
• Drag the Strut data set to the anchor in the geometry and drop it as soon as the
cursor indicates that dropping is possible. Close the Material sets window.
4-7
TUTORIAL MANUAL
Mesh Generation
In this lesson some simple mesh refinement procedures are used. In addition to a direct
global mesh refinement, there are simple possibilities for local refinement within a
cluster, on a line or around a point. These options are available from the Mesh menu. In
order to generate the proposed mesh, follow these steps:
Click the Generate mesh button in the toolbar. A few seconds later, a
coarse mesh is presented in the Output window. Click the <Update> button to
return to the geometry input.
• From the Mesh menu, select the Global coarseness option. The Element
distribution combo box is set to Coarse, which is the default setting. In order to
refine the global coarseness, one could select the next item from the combo box
(Medium) and click the <Generate> button. Alternatively, the Refine global
option from the Mesh menu could be selected. As a result, a finer mesh is
presented in the Output window. Click the <Update> button to return.
• Corner points of structural elements may cause large displacement gradients.
Hence, it is good to make those areas finer than other parts of the geometry. Click
in the middle of the lowest part of the wall (single click). The selected geometry
line is now indicated in red. From the Mesh menu, select the option Refine line.
As a result, a local refinement of the indicated line is visible in the presented mesh.
Click the <Update> button to return.
Hint: The mesh settings are stored together with the rest of the input. On re-entering
an existing project and not changing the geometry configuration and mesh
settings, the same mesh can be regenerated by just clicking the Generate
mesh
button on the toolbar. However, any slight change of the geometry will result
in a different mesh.
> The Reset all option in the Mesh menu is used to restore the mesh generation
default setting (Global coarseness = Coarse and no local refinement).
Initial conditions
The initial conditions of the current project require the generation of water pressures, the
deactivation of structures and loads and the generation of initial stresses. Water
pressures (pore pressures and water pressures on external boundaries) can be generated
in two different ways: A direct generation based on the input of phreatic levels and
groundwater heads or an indirect generation based on the results of a groundwater flow
calculation. The current lesson only deals with the direct generation procedure.
Generation based on groundwater flow is presented in the second part of the Lesson 4
(see Section 6.2).
Within the direct generation option there are several ways to prescribe the water
conditions. The simplest way is to define a general phreatic level, under which the water
pressure distribution is hydrostatic, based on the input of a unit water weight. The
general phreatic level is automatically assigned to all clusters for the generation of pore
pressures. It is also used to generate external water pressures, if applicable. Instead of the
general phreatic level, individual clusters may have a separate phreatic level or an
interpolated pore pressure distribution. The latter advanced options will be demonstrated in
the first part of Lesson 3 (see Section 5.2). Here only a general phreatic level is
defined at 2.0 m below the ground surface.
In order to generate the proper initial pore pressures, follow these steps:
Click the Initial conditions button on the toolbar.
Hint: When a project is newly created, the water weight is presented directly on
entering the Groundwater mode. On re-entering an existing project the
input of the water weight can be accessed by selecting the Water weight
option from the Geometry menu in the Groundwater mode.
Click <OK> to accept the default value of the unit weight of water, which is 10
kN/m3. The Groundwater conditions mode then becomes active, in which
the Phreatic level button is already selected. By default, a General phreatic
level is generated at the bottom of the geometry.
• Move the cursor to position (0.0; 38.0) and click the left mouse button. Move
45 m to the right (45.0; 38.0) and click again. Click the right mouse button to
finish drawing. The plot now indicates a new General phreatic level 2.0 m
below the ground surface.
Hint: An existing phreatic level may be modified using the Selection button from
the toolbar. On deleting the General phreatic level (selecting it and pressing
the <Del> key on the keyboard), the default general phreatic level will be
created again at the bottom of the geometry. The graphical input or
modification of phreatic levels does not affect the existing geometry.
> To create an accurate pore pressure distribution in the geometry, an additional
geometry line can be included corresponding with the level of the
groundwater head or the position of the phreatic level in a problem.
Click the Generate water pressures button (blue crosses) on the toolbar.
Now the Water pressure generation window appears.
• From the Water pressure generation window, select the Phreatic level radio
button in the Generate by box and click the <OK> button.
• After generating the water pressures, the result is displayed in the Output
window. Click the <Update> button to return to Groundwater conditions mode.
After the generation of water pressures and before the generation of initial effective
stresses, parts of the geometry that are not active in the initial state must be deactivated.
This option is used initially to deactivate geometry parts (clusters or structural objects)
that are to be constructed at later calculation stages. P LAXIS will automatically
deactivate loads and structural elements in the initial geometry configuration.
4-9
TUTORIAL MANUAL
In the current project, the diaphragm wall and the anchor are initially not present and
should be inactivate for the initial geometry. The K0-procedure for the generation of
initial stresses will not take into account the inactivate geometry clusters.
Proceed to Geometry configuration mode by clicking the 'switch' in the toolbar.
• Check that the wall and the strut in the geometry are inactive. Inactive elements
are coloured grey. Make sure that all soil clusters remain active.
Hint: Inactive clusters are white, just like the background, whereas active clusters
have the colour of the corresponding material set. Inactive structural objects
are grey, whereas active structures have the basic colour as used during the
creation of the geometry model.
Click the Generate initial stresses button in the toolbar. The K0-
procedure dialog box appears.
• Keep the total multiplier for soil weight equal to 1.0. Accept the default values
for K0 and click the <OK> button.
• After the generation of the initial effective stresses, the result is displayed in the
Output window. Click the <Update> button to return to the Initial
configuration mode.
• Click the <Calculate> button. Select <Yes> in response to the question about
saving the data and enter an appropriate file name.
4.2 CALCULATIONS
and strength of selected components of the finite element model. The current lesson
explains the use of this powerful calculation option for the simulation of excavations.
The excavation, as considered in this example, is to be carried out in five phases. The
separation of the three excavation phases was taken into account during the creation of
the geometry model by introducing geometry lines in the appropriate positions. In order to
define the five calculation phases, follow these steps:
Hint: You can also enter or change the values of the load at this time by double-
clicking the load and entering a value. If a load is applied on a structural
object such as a plate, load values can be changed by clicking the load or the
object. As a result a window appears in which you can select the load. Then
click the <Change> button to modify the load values.
• Click the <Update> button to finish the definition of the construction phase. As
a result, the Staged construction window is closed and the
Calculations
window reappears. The first calculation phase has now been defined and saved.
4-11
TUTORIAL MANUAL
Hint: Note that in PLAXIS the pore pressures are not automatically deactivated when
deactivating a soil cluster. Hence, in this case, the water remains in the
excavated area and a submerged excavation is simulated.
Figure 4.3 The Calculations window with the Parameters tab sheet
Hint: To select the desired nodes, it may be convenient to use the Zoom in option on
the toolbar to zoom into the area of interest.
In this example, all calculation phases should successfully finish, which is indicated by
the green check boxes in the list. In order to check the values of the ΣMstage multiplier,
click the Multipliers tab and select the Reached values radio button. The
ΣMstage
parameter is displayed at the bottom of the Other box that pops up. Verify that this value
is equal to 1.0. You also might wish to do the same for the other calculation phase.
In addition to the displacements and the stresses in the soil, the Output program can be used
to view the forces in structural objects. To examine the results of this project, follow
these steps:
4-13
TUTORIAL MANUAL
To plot the shear forces and bending moments in the wall follow the steps given below.
• Double-click the wall. A new window is opened showing the bending moments
in the wall, with an indication of the maximum moment (see Figure 4.6). Note that
the menu has changed.
4-15
TUTORIAL MANUAL
• Select Shear forces from the Forces menu. The plot now shows the shear
forces in the wall.
Hint: The Window menu may be used to switch between the window with the forces
in the wall and the stresses in the full geometry. This menu may also be used
to Tile or Cascade the two windows, which is a common option in a Windows
environment.
• Select the first window (showing the effective stresses in the full geometry)
from the Window menu. Double-click the strut. A new window is now opened
showing the strut force in kN/m. This value must be multiplied by the out of
plane spacing of the struts to calculate the individual strut forces (in kN).
• Click the Go to curves program button on the toolbar. As a result, the load-
displacement curves program is started.
• Select New chart from the Create / Open project dialog box and select the file
name of the excavation project from the file requester.
• In the Curve generation window, select for the X-axis the Displacement radio
button and point A (e.g. 30.0;30.0) and from the Type combo box select the
item |U|. Select for the Y-axis the Multiplier radio button and from the Type
combo box ΣMstage.
• Click the <OK> button to accept the input and generate the load-displacement
curve. As a result the curve of Figure 4.7 is plotted.
Sum-Mstage
1.0
0.8
0.6
0.4
0.2
0.0
0.0 0.02 0.04 0.06 0.08 0.1
|U| [m]
The curve shows the construction stages. For each stage, the parameter ΣMstage
changes from 0.0 to 1.0. The decreasing slope the curve of the last stage indicates that the
amount of plastic deformation is increasing. The results of the calculation indicate,
however, that the excavation remains stable at the end of construction.
4-17
TUTORIAL MANUAL
River embankments may be subjected to varying water levels. The change in water level
and the resulting change in the pore pressure distribution influences the stability of the
embankment. PLAXIS may be used to analyse the influence of pore pressure changes on
the deformation and stability of geotechnical structures. This feature is used here to
study the behaviour of the river embankment during the increase of the water level, as
shown in Figure 5.1. A special problem related to such a situation is the possible uplift
of the lowlands behind the embankment. This is due to the fact that the light soft soil
layers cannot sustain the high pore pressures that arise in the permeable sand layer
below. This effect may reduce the stability of the embankment.
The embankment in Figure 5.1 is 5 m high and consists of relative impervious clay. The
upper 6 m of the subsoil consists of soft soil layers, of which the top 3 m is modelled as
a clay layer and the lower 3 m as a peat layer. The soft soil layers are nearly
impermeable, so a short-term variation in the river water level hardly influences the pore
pressure distribution in these layers. Below the soft soil layers there is a deep permeable
sand layer, of which the upper 4 m are included in the finite element model. It is
assumed that the water in the sand layer is in contact with the river, which means that
the hydraulic head in the sand layer follows the river water level variation closely.
Figure 5.1 Geometry of the river embankment subjected to a changing water level
The geometry of Figure 5.1 is modelled with a plane strain geometry model. The finite
element mesh is based on the 15-node elements. The units used in this example are
meters for length, kiloNewton for force and day for time. The dimensions of the
geometry are 65 m in horizontal direction and 15 m in vertical direction. The full
geometry can be created using the Geometry line option. The Standard fixities option
is
used to define the boundary conditions. The suggested geometry model is shown in
Figure 5.2.
5-1
TUTORIAL MANUAL
20 5 20 20
5
3
3
Material sets
Three material layers are adopted for the soil. The properties are given in Table 5.1.
Friction angle ϕ 24 20 35 °
Dilatancy angle ψ 0.0 0.0 0.0 °
Open the material data base and create three data sets named 'Clay', 'Peat' and 'Sand'
with the model parameters as listed above. The interface properties are not relevant in
this example. Note that the Material type of the clay and peat layers is Undrained,
whereas the sand layer is Drained. Drag the data sets to the respective layers in the
geometry model (see Figure 5.1).
Mesh generation
This example, in which an uplift situation is modelled, is sensitive to the degree of
refinement of the mesh. Therefore the Global coarseness is set to Medium in the
Mesh menu. In addition, larger displacement gradients may be expected at the right
hand embankment toe. In order to model that part of the geometry more accurately, select
the geometry point of the embankment toe and select Refine around point from the
Mesh menu. As a result, the element size around the embankment toe is modified to half
the average element size. The generated mesh is shown in Figure 5.3.
Initial conditions
The geometry contains a non-horizontal soil surface. Therefore the K0-procedure
cannot be used to calculate the initial stress field. Instead the initial stresses must be
calculated by means of 'Gravity loading'. This is a calculation option that will be
explained in Section 5.2. The activation of water pressures is always done together with the
soil weight, but the generation of water pressures may be done in advance. In order to
generate the proper initial water pressures, follow these steps:
• Click the <Initial conditions> button.
• Accept the default value of the water weight (10 kN/m3).
• Enter a general phreatic level from point (0.0; 10.0) to point (65.0; 10.0).
• Generate the pore pressures from the phreatic level by clicking the Generate
water pressures button and subsequently clicking the <OK> button.
• In the Output window, check the pore pressure distribution and click the
<Update> button.
• Back in the Input window, click directly on the <Calculate> button. Do not
generate the initial stresses according to the K0-procedure.
• Save the input under an appropriate name.
5-3
TUTORIAL MANUAL
Hint: If initial stresses were generated by mistake, they can be reset by entering the
K0-procedure, entering a value of ΣMweight = 0 and pressing the <Generate>
button.
5.2 CALCULATIONS
The calculation consists of two phases. First the initial stress field has to be calculated
since this has not been done during the input of the initial conditions. The calculation of
the initial stresses can be done in a plastic calculation where the multiplier for the soil
weight is increased from 0.0 to 1.0. A calculation of this sort is called Gravity loading.
This procedure is recommended when the soil surface, the layering or the phreatic level
is non-horizontal. Gravity loading always results in an equilibrium stress state, whereas
the K0-procedure does not in the case of a non-horizontally layered subsoil. During
Gravity loading both the soil weight and the pore pressures (that were generated
previously) are activated.
Hint: Since the initial stresses are not subject to undrained behaviour, it is important
that undrained behaviour is disabled during gravity loading. This can be done
by selecting Ignore undrained behaviour in the Parameters tab sheet
of the
Calculations window.
> In contrast to the K0-procedure, the calculation of initial stresses by means of
gravity loading results in displacements. These displacements are not realistic,
because the embankment is modelled as it appears in reality and the
calculation of the initial stresses should not influence the displacements
computed later in the analysis. These unrealistic displacements can be reset to
zero at the start of the next calculation phase by selecting Reset
displacements
to zero in the next phase.
The second calculation phase is the increase of the river water level, and the pore
pressure, in the sand layer. This is done in the Staged construction mode. In order to
define the two calculation phases correctly, follow this procedure:
Figure 5.4 General phreatic level for generation of external water pressures
• Click the Selection button and select the cluster of the clay layer (including the
embankment).
• While the clay layer cluster is marked, click the Phreatic level button and draw
a phreatic level through the points (0.0; 10.0), (65.0; 10.0). This 'Cluster
defined' phreatic level only applies to the indicated cluster (see Figure 5.5).
Figure 5.5 has been edited to only show the phreatic level for the clay layer. The
general phreatic level is not indicated.
5-5
TUTORIAL MANUAL
• Click the Selection button and select the cluster of the sand layer.
• While the sand layer is marked, click the Phreatic level button and draw a
phreatic level through the points (0.0; 15.0), (65.0; 13.0). This phreatic level
only applies to the sand layer cluster. Figure 5.6 only shows the phreatic level for
the sand layer; other phreatic levels are not indicated.
• Click the Selection button and double-click, or click using the right mouse
button, the intermediate peat layer. As a result, a Cluster Pore pressures
• Click the Generate water pressures button to generate the water pressures
according to the ultimate situation.
• The pore pressure distribution is presented as principal stresses (by means of
crosses) in the Output window. Click the Cross section button and draw a
vertical line through the top of the embankment to the bottom of the geometry. As a
result, the pore pressure distribution over all three layers is displayed in a separate
window. In addition to the hydrostatic part of the pore pressure distribution
in the clay and sand layers, the plot shows the linear increase in pore pressure
through the peat layer.
Hint: A cross section can be drawn perfectly horizontal or vertical by holding down
the <Shift> key while drawing the cross section.
5-7
TUTORIAL MANUAL
5.3 OUTPUT
After the calculation has finished, click the <Output> button to view the results of the
second calculation phase. The Output program will now display the deformations of the
embankment due to the change of the water level. The plot clearly shows the uplift of
the soft soil layers behind the embankment and the movement of the embankment itself.
This becomes even clearer if you select Total increments from the Deformations
menu
(see Figure 5.8).
On selecting Effective stresses from the Stresses menu, it can be seen that at the top
of the sand layer at the right hand side of the model the effective stresses are nearly zero
(see Figure 5.9). This is due to the increase in pore pressures in the sand layer. From the
stress plot it can also be seen that the movement of the embankment causes a passive
stress state in the clay layer behind the embankment.
Figure 5.9 Effective stresses in embankment after the increase of the water level
The undrained behaviour in the clay and peat layers causes excess pore pressures to
develop. The excess pore pressures can be viewed by selecting Excess pore
pressures from the Stresses menu (see Figure 5.10).
Figure 5.10 Excess pore pressures after the increase of the water level
5-9
TUTORIAL MANUAL
6.1 INPUT
10 2 20 2 5
10 kPa 5 kPa
fill 3
7
ground
sand Excavation level anchor
5
loam
The relevant part of the soil consists of three distinct layers. From the ground surface to a
depth of 3 m there is a fill of relatively loose fine sandy soil. Underneath the fill, down to a
minimum depth of 15 m, there is a more or less homogeneous layer consisting of dense
well-graded sand. This layer is particular suitable for the installation of the ground anchors.
In the initial situation there is a horizontal phreatic level at 3 m below the ground
surface (i.e. at the base of the fill layer). Below the sand layer there is a loam layer,
which extends to large depth.
6-1
TUTORIAL MANUAL
Geometry model
The problem can be modelled with a geometry model of 80 m width and 20 m
height. The proposed geometry model is given in Figure 6.2. A ground anchor
can be modelled by a combination of a node-to-node anchor and a geogrid
(yellow line). The geogrid simulates the grout body whereas the node-to-node
anchor simulates the anchor rod. In reality there is a complex three-dimensional
state of stress around the grout body. Although the precise stress state and
interaction with the soil cannot be modelled with this 2D model, it is possible
in this way to estimate the stress distribution, the deformations and the stability
of the structure on a global level, assuming that the grout body does not slip
relative to the soil. With this model it is certainly not possible to evaluate the
pullout force of the ground anchor.
The diaphragm walls are modelled as plates. The interfaces around the plates are used to
model soil-structure interaction effects. They are extended under the wall for 1.0 m.
Interfaces should not be used around the geogrid that represent the grout body.
The excavation is constructed in three excavation stages. The separation between the
stages is modelled by geometry lines. Create the basic geometry model as presented in
Figure 6.2. The standard fixities can be used to generate the proper boundary conditions.
18 10 2 20 2 5 23
3
3
Node-to-node anchor 4
(21.0; 11.0) (59.0; 11.0)
13 3
(18.0; 9.0) (26.0; 9.0) (54.0; 9.0) (62.0; 9.0)
(23.0; 6.0)
(57.0; 6.0) 5
Material properties
The soil consists of three distinct layers. Enter three data sets for soil & interfaces with the
parameters given in Table 6.1.
Hint: The extended part of an interface is not used for soil-structure interaction and
should therefore have the same strength as the surrounding soil. This can be
achieved with a strength reduction factor Rinter = 1.0, which is automatically
adopted in the Rigid selection. If necessary, a separate material data set must
be created for the extended part of an interface. In addition, the extended part
of an interface should not influence the flow field. This is achieved by
deactivating the interface when generating the pore pressures.
The properties of the concrete diaphragm wall are entered in a material set of the Plate
type. The concrete has a Young's modulus of 35 GPa and the wall is 0.35 m thick. The
properties are listed in Table 6.2.
6-3
TUTORIAL MANUAL
For the properties of the ground anchors, two material data sets are needed: One of the
Anchor type and one of the Geogrid type. The Anchor data set contains the properties
of the anchor rod and the Geogrid data set contains the properties of the grout body. The
data are listed in Tables 6.3 and 6.4.
Mesh generation
For the generation of the mesh it is advisable to set the Global coarseness parameter to
Medium. In addition, it is expected that stress concentrations will occur around the two
grout bodies, and so a local refinement is proposed here. Select the four geogrids
simultaneously (use the <Shift> key) and select Refine line from the Mesh menu. This
process results in a mesh of approximately 590 elements.
Initial conditions
In the initial conditions, a water weight of 10 kN/m 3 is entered. The initial water
pressures are generated on the basis of a horizontal general phreatic level at y = 17 m
(through points (0; 17.0) and (80.0; 17.0).
Initially, all structural components are inactive. Hence, make sure that the plates, the node-
to-node anchors and the geogrids are deactivated. The surface loads are also initially
inactive. The initial stress field is generated by means of the K0-procedure using the default
K0-values in all clusters.
6.2 CALCULATIONS
The calculation consists of six phases. In the first phase the walls are constructed and the
surface loads are activated. In the second phase the first 3 m of the pit is excavated
without connection of anchors to the wall. At this depth the excavation remains dry. In
the third phase the first anchor is installed and pre-stressed. The fourth phase involves
further excavation to a depth of 7 m, including the de-watering of the excavation. This
involves a groundwater flow analysis to calculate the new pore water distribution, which is
a part of the definition of the third calculation phase. In the fifth phase the second
anchor is installed and pre-stressed and the sixth phase is a further excavation (and
dewatering) of to the final depth of 10 m.
All calculation phases are defined as Plastic calculations using Staged construction
as
Loading input and standard settings for all other parameters. The instructions given
below are limited to a description of how the phases are defined within the Staged
construction mode.
Phase 1:
• Activate the walls.
• Activate the surface loads and assign a load value. Enter a Y-value = -10 kPa
for the load on the left side and -5 kPa for the load on the right side of the
excavation.
Phase 1
Phase 2:
• De-activate the upper cluster of the excavation.
Phase 2
Phase 3:
• Activate the upper geogrids
6-5
TUTORIAL MANUAL
Phase 3
Phase 4:
• Deactivate the second cluster of the excavation.
head=13m
head=17m
head=17m
Closed boundary
Phase 4
Now the boundary conditions for the groundwater flow calculation have to be entered.
At the side boundaries, the groundwater head remains at a level of 17.0 m. The bottom
boundary of the problem should be closed. The flow of groundwater is triggered by the
fact that the pit is pumped dry. At the bottom of the excavation the water pressure is
zero, which means that the groundwater head is equal to the vertical level (head = 13.0
m). This condition can be met drawing a new general phreatic level and performing a
groundwater flow calculation. Activating the interfaces during the groundwater flow
calculation prevents flow through the wall.
Figure 6.3 Active pore pressure contours resulting from groundwater calculation
6-7
TUTORIAL MANUAL
Phase 5:
• Activate the lower geogrids
• Double-click the lower node-to-node anchors. In the Anchor window, select the
Adjust pre-stress force box and enter a pre-stress force of 200 kN/m.
Click <OK> to close the window.
Phase 5
Phase 6:
• Deactivate the third cluster of the excavation.
• Click the 'switch' to go to the water pressures mode.
• The boundary conditions were already defined in phase 3. They are still valid
for the current groundwater calculation. However it is now necessary to lower the
water level within the excavation to the new construction depth. In order to do this,
draw a new General phreatic level from (0.0; 17.0) through points (30.0;
10.0), (50.0; 10.0) and (80.0; 17.0). Click the Generate water pressures
button and select Groundwater flow from the Generate by box and click
<OK> to start the groundwater flow calculation.
• After the groundwater calculation has finished, click the <OK> button in the
calculation window and view the results in the Output window. Click the
<Update> button to return to the staged construction mode.
head=17m
head=17m
head=10m
Closed boundary
Phase 6
After all calculation phases have been defined, some points for load-displacement
curves should be selected (for example the connection points of the ground anchors on the
diaphragm wall). Start the calculation by clicking the <Calculate> button.
6.3 OUTPUT
Figure 6.4 (a) to (e) show the deformed meshes at the end of calculation phases 2 to 6.
In the final situation, the walls have moved about 8 cm forward and the excavation
bottom has risen just over 5 cm. Behind the wall there is a small settlement trough.
(a) phase 2
(b) phase 3
(c) phase 4
6-9
TUTORIAL MANUAL
(d) phase 5
Figure 6.5 shows the principal effective stresses in the final situation. The passive stress
state beneath the bottom of the excavation is clearly visible. It can also be seen that there are
stress concentrations around the grout anchors.
Figure 6.6 shows the bending moments in the left diaphragm wall in the final state. The
two dips in the line of moments are caused by the anchor forces.
The anchor force can be viewed by double-clicking the anchor. When doing this for the
results of the third and the fifth calculation phase, it can be checked that the anchor force is
indeed equal to the specified pre-stress force.
Figure 6.6 Bending moments in the left diaphragm wall in the final stage
In the previous example the Mohr-Coulomb model was used to model the soil
behaviour. Although the Mohr-Coulomb model is often used it lacks particular aspects
of soil behaviour such as the difference in stiffness between virgin-loading and
unloading-reloading. Such aspects are taken into account in more advanced models like
the Hardening Soil model. In the excavation modelled here the soil below the excavation
is mainly subjected to unloading and subsequently shows a relatively stiff behaviour.
The soil next to the wall is mainly subject to shear stresses and subsequently shows a
less stiff behaviour. Though this soil behaviour could be captured by creating different
clusters with different soil parameters below and next to the excavation pit, it is easier
and more reliable to use the Hardening Soil model. Therefore, the same project is now
modified so that all soil layers are modelled using the Hardening Soil model instead of
the Mohr-Coulomb model. It is not necessary to create a new model; you can start from
the previous model, modify it and store it under a different name.
In order to modify the soil material sets take the following steps:
• In PLAXIS Input open the previous file (“lesson4” or whichever name it was
given) and save it under a different name.
6-11
TUTORIAL MANUAL
• Open the material sets database and double-click the first material data set
“Fill”. This will open the material data set window. From the Material model
combo box select Hardening Soil and proceed to the Parameters tab sheet.
Enter values for refEoed , 50ref ,Eur , m and in the Advanced model parameters
K
window for pref, νur and nc0 according to Table 6.5. Please note that the
Advanced model parameters can be found by clicking the <Advanced> button
K
on the Parameters tab sheet. The value of nc0 is equal to 1-sin(ϕ) and will be
automatically calculated by PLAXIS after entering a value of “-1” in the
K0nc input box.
• Repeat this for all material data sets according to Table 6.5.
• Continue to the initial conditions and regenerate the initial stresses. Though the
initial stresses remain the same the regeneration is needed in order to generate
the isotropic pre-consolidation stresses pp. Please note that it is not necessary to
regenerate the mesh or the initial pore pressures.
• After regenerating the initial stresses save the project and continue to P LAXIS
Calculations.
• In PLAXIS Calculations make sure all phases are selected for calculation (blue
arrows) and calculate the project.
Hint: The Hardening Soil parameters have been derived from the Mohr-Coulomb
parameters by setting the E50 of the Hardening Soil model in the midpoint of
E
each layer to the Eref of the Mohr-Coulomb model and deriving ref50 from this
at the reference level pref=100 kPa (see eq. 5.2 of the Material Models
E E E 3
manual). refoed and ref urare assumed to be equal to ref50 and Eref50 respectively.
Figure 6.7 shows the deformed mesh at the end of the final calculation phase. The walls have
moved in approximately 7 cm and the excavation bottom has risen 3 to 4 cm.
A detailed comparison of the results from the Mohr-Couloumb and the Hardening Soil
cases yields some important differences:
• The excavation bottom rises less in the HS case than in the MC case; this is due
to unloading behaviour of the Hardening Soil model. The Hardening Soil
model behaves much stiffer in unloading than the Mohr-Coulomb model does, as
the Mohr-Coulomb model has only a single stiffness.
• The inward movement of the walls is less in the HS case than in the MC case;
again this is due to the different unloading behaviour.
• The settlement trough is larger in the HS case than in the MC case. This is due
to the difference in vertical movement of the walls for both cases; for the
Mohr-Coulomb model the excavation bottom rises more due to the softer
unloading behaviour and pushes up the walls, which in turn influences the
settlement trough.
• The structural forces in the walls are higher in the HS case than in the MC case.
6-13
TUTORIAL MANUAL
Practical cases have proven that for excavations, where the unloading behaviour of the soil
is very important, the Hardening Soil model gives more realistic results than the Mohr-
Coulomb model.
The construction of an embankment on soft soil with a high groundwater level leads to
an increase in pore pressure. As a result of this 'undrained behaviour' the effective stress
remains low and intermediate consolidation periods have to be adopted in order to
construct the embankment safely. During consolidation the excess pore pressures
dissipate so that the soil can obtain the necessary shear strength to continue the
construction process.
This lesson concerns the construction of a road embankment in which the mechanism
described above is analysed in detail. In the analysis three new calculation options are
introduced, namely a consolidation analysis, an updated mesh analysis and the
calculation of a safety factor by means of phi/c-reduction.
7.1 INPUT
Figure 7.1 shows a cross section of a road embankment. The embankment is 16.0 m
wide and 4.0 m high. The slopes have a slope of 1:3. The problem is symmetric, so only
one half is modelled (in this case the right half is chosen). The embankment itself is
composed of loose sandy soil. The subsoil consists of 6.0 m of soft soil. The upper 3.0 m
of this soft soil layer is modelled as a peat layer and the lower 3.0 m as clay. The
phreatic level coincides with the original ground surface. Under the soft soil layers there is
a dense sand layer, which is not included in the model.
Geometry model
The embankment shown in Figure 7.1 can be analysed with a plane strain model. For
this example 15-node elements are utilised. The standard units for Length, Force and
Time are used (m, kN and day). A total width of 40 m is considered in the geometry
model, starting from the embankment centre. The full geometry can be drawn using the
Geometry line option. The deformations of the deep sand layer in Figure 7.1 are
assumed to be zero. Hence, this layer is not included in the model and a fixed base is
used instead.
7-1
TUTORIAL MANUAL
The Standard fixities can be used to define the boundary conditions. The geometry
model is shown in Figure 7.2.
Initial conditions
In the Initial conditions the water weight is set to 10 kN/m 3. The water pressures are
fully hydrostatic and based on a general phreatic level through the points (0.0; 6.0) and
(40.0; 6.0).
In addition to the phreatic level, attention must be paid to the boundary conditions for
the consolidation analysis that will be performed during the calculation process. Without
giving any additional input, all boundaries are draining so that water can freely flow out
of all boundaries and excess pore pressures can dissipate in all directions. In the current
situation, however, the left vertical boundary must be closed because this is a line of
symmetry, so horizontal flow should not occur. The right vertical boundary should also
be closed because there is no free outflow at that boundary. The bottom is open because
below the soft soil layers the excess pore pressures can freely flow into the deep and
permeable sand layer (which is not included in the model). The upper boundary is
obviously open as well. In order to create the appropriate consolidation boundary
conditions, follow these steps:
Click the Closed consolidation boundary button (yellow line) in the toolbar.
• Move to the upper point of the left boundary (0.0; 10.0) and click this point.
Move to the lower point of the left boundary (0.0; 0.0) and click again. Click the
right mouse button to finish this closed boundary.
• Move to the upper point of the right boundary (40.0; 6.0) and click. Move to
the lower point (40.0; 0.0) and click again. Finish this closed boundary.
• Click the Generate water pressures button to generate the water pressures and
the consolidation boundary conditions.
After the generation of the water pressures, click the 'switch' to modify the initial
geometry configuration. In the initial situation the embankment is not present. In order
to generate the initial stresses therefore, the embankment must be deactivated first.
Click once in the two clusters that represent the embankment, just like in a staged
construction calculation. When the embankment has been deactivated (the
corresponding clusters should have the background colour), the remaining active
geometry is horizontal with horizontal layers, so the K0-procedure can be used to
calculate the initial stresses. The suggested K0-values of the clay and peat layer (based on
Jaky's formula: K0 = 1-sinϕ) can be accepted. After the generation of the initial stresses
the input is complete and the calculations can be defined.
7-3
TUTORIAL MANUAL
7.2 CALCULATIONS
The embankment construction consists of two phases, each taking 5 days. After the first
construction phase a consolidation period of 200 days is introduced to allow the excess
pore pressures to dissipate. After the second construction phase another consolidation
period is introduced from which the final settlements may be determined. Hence, a total of
four calculation phases have to be defined.
A consolidation analysis introduces the dimension of time in the calculations. In order to
correctly perform a consolidation analysis a proper time step must be selected. The use
of time steps that are smaller than a critical minimum value can result in stress
oscillations. The consolidation option in P LAXIS allows for a fully automatic time
stepping procedure that takes this critical time step into account. Within this procedure
there are three main possibilities: Either consolidate for a predefined period, including
the effects of changes to the active geometry (Staged construction), consolidate until
all
excess pore pressures in the geometry have reduced to a predefined minimum value
(Minimum pore pressure) or consolidate for a given number of steps, using
incremental
multipliers to globally increase load systems in time or to apply rate loading
(Incremental multiplier). The first two possibilities will be used in this exercise.
To define the calculation phases, follow these steps:
• The first calculation stage is a Consolidation analysis, Staged construction. In
the General tab sheet select Consolidation from the Calculation type
combo box. In the Parameters tab sheet, enter a Time interval of 5 days.
Select Staged construction for the Loading input and click the <Define>
button. Activate the first part of the embankment in the Geometry configuration
window and click the <Update> button. Back in the Calculation window, click the
<Next> button to introduce the next calculation phase.
• The second phase is also a Consolidation analysis, Staged construction. This
time no changes to the geometry are made as only a consolidation analysis to
ultimate time is required. Enter a time interval of 200 days and click the
<Next> button to introduce the next calculation phase.
• The third phase is once again a Consolidation analysis, Staged construction.
After selecting Staged construction in the Parameters tab sheet enter a
Time interval of 5 days. Click the <Define> button and activate the second
part of the embankment. Click <Update> and enter the next phase.
• The fourth phase is a consolidation analysis to a minimum pore pressure. In the
Parameters tab sheet, select Minimum pore pressure from the Loading
input box and accept the default value of 1 kN/m2 for the minimum pressure.
Before starting the calculation, click the Select points for curves button and select
the
following points: As Point A, select the toe of the embankment. The second point (Point
B) will be used to plot the development (and decay) of excess pore pressures. To this end,
a point somewhere in the middle of the soft soil layers is needed, close to (but not actually
on) the left boundary. After selecting these points, start the calculation.
During a consolidation analysis the development of time can be viewed in the upper part of
the calculation info window. In addition to the multipliers, a parameter Pmax occurs,
which indicates the current maximum excess pore pressure. This parameter is of interest in
the case of a Minimum pore pressure consolidation analysis, where all pore pressures
are specified to reduce below a predefined value.
7.3 OUTPUT
After the calculation has finished, select the third and the fourth phase simultaneously
(hold the <Ctrl> key on the keyboard while selecting these phases) and click the
<Output> button. The Output window now shows the two deformed meshes, one after
the undrained construction of the final part of the embankment and one after full
consolidation.
Figure 7.5 Excess pore pressure contours after consolidation to Pexcess < 1.0 kN/m2
7-5
TUTORIAL MANUAL
Considering the results of the third phase (undrained construction), the deformed mesh
shows the uplift of the embankment toe and hinterland due to the undrained behaviour.
On evaluating the total displacement increments, it can be seen that a failure mechanism
is developing (see Figure 7.3). In addition, Figure 7.4 shows the excess pore pressures
distribution. It is clear that the highest excess pore pressure occurs under the
embankment centre.
It can be seen that the settlement of the original soil surface and the embankment
increases considerably during the fourth phase. This is due to the dissipation of the
excess pore pressures, which causes consolidation of the soil. Figure 7.5 shows the
remaining excess pore pressure distribution after consolidation. Check that the
maximum value is below 1.0 kN/m2.
The Curves program can be used to view the development, with time, of the excess pore
pressure under the embankment. In order to create such a curve, follow these steps:
• Click the Go to curves program button in the upper left corner of the Output
window.
• Select New chart and select the current project from the file requester.
• In the Curve generation window, select Time for the x-axis. For the y-axis,
select Pore pressure - Excess pore pressure and select the point in the
middle of the soft soil layers (Point B) from the Point combo box. After
clicking the <OK> button, a curve similar to Figure 7.6 should appear.
Figure 7.6 clearly shows the four calculation phases. During the undrained construction
phases the excess pore pressure increases with a small increase in time while during the
consolidation periods the excess pore pressure decreases with time. In fact,
consolidation already occurs during construction of the embankment, as this involves a
small time interval. From the curve it can be seen that more than 700 days are needed to
reach full consolidation.
Excess PP [kN/m2]
0
-10
-20
-30
-40
0 200 400 600 800
Time [day]
In the design of an embankment it is important to consider not only the final stability, but
also the stability during the construction. It is clear from the output results that a failure
mechanism starts to develop after the second construction phase.
It is interesting to evaluate a global safety factor at this stage of the problem, and also for
other stages of construction.
In structural engineering, the safety factor is usually defined as the ratio of the collapse
load to the working load. For soil structures, however, this definition is not always
useful. For embankments, for example, most of the loading is caused by soil weight and
an increase in soil weight would not necessarily lead to collapse. Indeed, a slope of
purely frictional soil will not fail in a test in which the self weight of the soil is increased
(like in a centrifuge test). A more appropriate definition of the factor of safety is
therefore:
S maximum
Safety factor =
S available
needed for
equilibrium
Where S represents the shear strength. The ratio of the true strength to the computed
minimum strength required for equilibrium is the safety factor that is conventionally
used in soil mechanics. By introducing the standard coulomb condition, the safety factor
is obtained:
c −σ n tanϕ
Safety factor =
cr − σ n tanϕ r
Where c and ϕ are the input strength parameters and σ n is the actual normal stress
component. The parameters cr and ϕr are reduced strength parameters that are just large
enough to maintain equilibrium. The principle described above is the basis of the
method of Phi/c-reduction that can be used in P LAXIS to calculate a global safety factor.
In this approach the cohesion and the tangent of the friction angle are reduced in the
same proportion:
c
tanϕ
c r = = ΣMsf
tanϕ r
The reduction of strength parameters is controlled by the total multiplier ΣMsf. This
parameter is increased in a step-by-step procedure until failure occurs. The safety factor is
then defined as the value of ΣMsf at failure, provided that at failure a more or less
constant value is obtained for a number of successive load steps.
The Phi/c-reduction calculation option is available in PLAXIS from the Calculation
type
list box on the General tab sheet. If the Phi/c-reduction option is selected the
Loading
input on the Parameters tab sheet is automatically set to Incremental multipliers.
7-7
TUTORIAL MANUAL
To calculate the global safety factor for the road embankment at different stages of
construction, follow these steps:
• Click the Go to calculations program button to focus the Calculations window.
• We first want to calculate the safety factor after the first construction stage.
Therefore introduce a new calculation phase and select Phase 1 in the Start
from phase list box.
• In the General tab sheet, select a Phi/c-reduction calculation.
• In the Parameters tab sheet the number of Additional steps is automatically set
to 100 (instead of the default value of 250). In order to exclude existing
deformations from the resulting failure mechanism, select the Reset
displacements to zero option. The Incremental multipliers option
is already
selected in the Loading input box. Click the <Define> button to enter the
Multipliers tab sheet.
• On the Multipliers tab sheet, check that the first increment of the multiplier that
controls the strength reduction process, Msf, is set to 0.1. The first safety
calculation has now been defined.
• We now want to define the calculation of the safety factor after the second
construction stage. Therefore introduce a new calculation phase and select
Phase 3 as the phase to start from. This can be done in the General tab sheet of
the Calculation program by clicking the combo box start from phase and
choosing Phase 3.
• In the General tab sheet select Phi/c-reduction from the Calculation type
combo box.
• In the Parameters tab sheet select the Reset displacements to zero option, select
Incremental multipliers and click the <Define> button.
• In the Multipliers tab sheet check that Msf is set to 0.1.
• Finally we want to know the final safety factor of the embankment. Therefore
introduce one more calculation stage and let it start from the fourth calculation
phase.
Evaluation of results
Additional displacements are generated during a phi/c-reduction calculation. The total
displacements do not have a physical meaning, but the incremental displacements in the
final step (at failure) give an indication of the likely failure mechanism. In order to view
the mechanisms in the three different stages of the embankment construction, select the
phases 5, 6 and 7 simultaneously (use the <Ctrl> key) and click the <Output> button.
Select for all windows the Total increments from the Deformations menu and
change
the presentation from Arrows to Shadings. The resulting plots give a good impression of
the failure mechanisms (see Figure 7.7). The magnitude of the displacement increments
is not relevant.
Figure 7.7 Shadings of the total displacement increments indicating the most
applicable failure mechanism of the embankment in the final stage
The safety factor can be obtained from the Calculation info option of the View menu.
The Multipliers tab sheet of the Calculation information window represents the
actual values of the load multipliers. The value of ΣMsf represents the safety factor,
provided that this value is indeed more or less constant during the previous few steps.
7-9
TUTORIAL MANUAL
Sum Msf
1.4
1.2
Figure 7.8 Evaluation of safety factor for three stages of the construction process
The best way to evaluate the safety factor, however, is to plot a curve in which the
parameter ΣMsf is plotted against the displacements of a certain node. Although the
displacements are not relevant, they indicate whether or not a failure mechanism has
developed. In order to evaluate the safety factors for the three situations in this way,
follow these steps:
• Click the Go to curves program button to start the Curves program.
• Select a New chart and select the road embankment file from the file requester.
• In the Curve generation window, select the total displacement of the
embankment toe (Point A) for the x-axis. For the y-axis, select Multipliers and
select ΣMsf from the Type combo box. As a result, the curve of Figure 7.8
appears.
The maximum displacements plotted are not relevant. It can be seen that for all curves a more
or less constant value of ΣMsf is obtained. Hovering the mouse cursor over a point on the
curves, a box showing the exact value of ΣMsf can be obtained.
As can be seen from the output of the Deformed mesh at the end of consolidation
(stage 4), the embankment settles over half a metre within two years of the start of
construction. Part of the sand fill that was originally above the phreatic level will settle
below the phreatic level. As a result of buoyancy forces the effective weight of the soil
that settles below the water level will change, which leads to a reduction of the effective
overburden in time. This effect can be simulated in PLAXIS using the Updated mesh and
Updated water pressures options. For the road embankment the effect of using
these options will be investigated.
Open the current project in the Input program and select Save as from the File menu.
Save the project under a different name. Now click the Go to Calculation
program button and open the new project. All phases will be marked for calculation. To
change the calculation to an Updated mesh analysis, do the following:
• Select Phase 1 and click the Advanced button below the Calculation type list
box. Check the Updated mesh and Updated water pressures options in the
Advanced general settings window. Click <OK> to return to the calculation
window.
• Repeat this step for all calculation phases 2, 3 and 4.
• Delete phases 5, 6 and 7.
• Start the calculation.
When the calculation has finished, open the Curves program to compare the settlements
for the two different calculation methods.
• Select a New chart and select the road embankment calculation using updated
mesh from the file requester.
• In the Curve generation window select time for the x-axis and select the total
displacement of the embankment toe (Point A) for the y-axis.
To compare those with the displacements from the calculation without the updated mesh
option, add a curve from the previous calculation, without the updated mesh option.
• From the File menu, choose to Add curve, from another project.
• From the file requester, select the road embankment calculation without
updated mesh.
• In the Curve generation window, select the same point (Point A), for which
deformation versus time will be plotted. Click <OK> to add the curve.
The default graph generated also includes the displacements calculated during the Phi/c-
reduction stages. These displacements are not of interest at the moment and can be
removed from the curve.
• Select Curve from the Format menu and click the <Phases> button.
• In the Select phases window, deselect the Phi/c-reduction phases, i.e. phases 5,
6 and 7. Click <OK> to return to the Curve settings window and click <OK>
again to update the graph.
Now only the displacements during the construction and consolidation phases are
plotted. To change the vertical scale of the graph:
• Select Graph from the Format menu and change the Scaling of the Y-axis to
Manual. Enter a maximum value of 0.5. Click <OK> to update the graph.
7-11
TUTORIAL MANUAL
In Figure 7.9 it can be seen that the settlements are less when the Updated mesh
and
Updated water pressures options are used. This is partly because the Updated
mesh
procedure includes second order deformation effects by which changes of the geometry
are taken into account, and partly because the Updated water pressures
procedure
results in smaller effective weights of the embankment. This last effect is caused by the
buoyancy of the soil settling below the (constant) phreatic level. The use of these
procedures allows for a realistic analysis of settlements, taking into account the positive
effects of large deformations.
Displacement [m]
0.5
0.4
0.3
Normal mesh
0.2
Updated mesh
0.1
0 0 200 400
600 800 1000
Time [day]
Figure 7.9 Settlements of the toe of the embankment using updated mesh calculation
PLAXIS has special facilities for the generation of circular and non-circular tunnels and
the simulation of a tunnel construction process. In this chapter the construction of a
shield tunnel in medium soft soil and the influence on a pile foundation is considered. A
shield tunnel is constructed by excavating soil at the front of a tunnel boring machine
(TBM) and installing a tunnel lining behind it. In this procedure the soil is generally
over-excavated, which means that the cross sectional area occupied by the final tunnel
lining is always less than the excavated soil area. Although measures are taken to fill up
this gap, one cannot avoid stress re-distributions and deformations in the soil as a result
of the tunnel construction process. To avoid damage to existing buildings or foundations
on the soil above, it is necessary to predict these effects and to take proper measures.
Such an analysis can be performed by means of the finite element method. This lesson
shows an example of such an analysis.
5m 10 m 15 m
+3.0 m
0.0 m
piles
clay
pile toe
-10.0 m
sand
-12.0 m
deep clay
-17.0 m
deep sand
-22.0 m
Figure 8.1 Geometry of the tunnel project with an indication of the soil layers
The tunnel considered in this lesson has a diameter of 5.0 m and is located at an average
depth of 20 m. The soil profile indicates four distinct layers: The upper 13 m consists of
soft clay type soil with stiffness that increases approximately linearly with depth. Under
the clay layer there is a 2.0 m thick fine sand layer. This layer is used as a foundation
layer for old wooden piles on which traditional brickwork houses were built. The pile
foundation of such a building is modelled next to the tunnel. Displacements of these piles
may cause damage to the building, which is highly undesirable. Below the sand layer there
is a 5.0 m thick deep loamy clay layer.
8-1
TUTORIAL MANUAL
This is one of the layers in which the tunnel is constructed. The other part of the tunnel
is constructed in the deep sand layer, which consists of dense sand and some gravel.
This layer is very stiff. As a result only 5.0 m of this layer is included in the finite
element model; the deeper part is considered to be fully rigid and modelled by
appropriate boundary conditions. The pore pressure distribution is hydrostatic. The
phreatic level is located 3 m below the ground surface (at a level of y = 0 m). Since the
situation is more or less symmetric, only one half (the right half) is taken into account in
the plane strain model. From the centre of the tunnel the model extends for 30 m in
horizontal direction. The 15-node element is adopted for this example.
8.1 GEOMETRY
The basic geometry including the four soil layers, as shown in Figure 8.1 (but excluding
the tunnel and the foundation elements), can be created using the geometry line option.
Since the ground surface is located at 3.0 m above the reference level, the Top parameter
is taken at +3.0 m in the General settings and the Bottom at -22.0 m. For the
generation
of the tunnel we will use the tunnel designer, which is a special tool within P LAXIS that
enables the use of circle segments (arcs) and lines to model the geometry of a tunnel.
The tunnel considered here is the right half of a circular tunnel and will be composed of
four sections. After generating the basic geometry, follow these steps to design the
circular tunnel:
Click the Tunnel button in the toolbar. The Tunnel designer window appears,
with a number of options in its toolbar for creating tunnel shapes. Select Half
tunnel - Right half from the toolbar.
• The tunnel designer will show a default (half) tunnel shape composed of three
sections of which the lower one (Section 1) is selected, as indicated in Figure
8.2. The right side of the window shows some geometrical values.
• Keep the Type of tunnel on the default value of a Bored tunnel. Make sure that
the lower tunnel section is selected (if not, select it by clicking with the mouse in
the lower section).
• The values in the table represent the properties of the first tunnel section. For a
circular (bored) tunnel the radius can be entered here. Enter a radius of 2.5 m. The
result of this action is directly visible in the drawing.
• The value below the radius represents the angle over which the section extends.
Enter an angle of 90 degrees (which is the maximum angle of one section).
• The local x- and y-coordinates of the first arc centre point is always located at
the local origin (x=0; y=0) for a bored tunnel.
• Make sure that the options Shell and Interface are selected for this section.
• Proceed to the next section (2) by clicking the right arrow at the bottom of the
window. Alternatively, you may click the second tunnel section in the designer
window.
Hint: A shell and interface can be assigned directly to all tunnel sections by clicking
the corresponding buttons at the top of the tunnel window.
> A tunnel lining consists of curved plates. The lining properties can be
specified in the material database for plates. Similarly, a tunnel interface is
nothing more than a curved interface.
> In the tunnel as considered here the sections do not have a specific meaning as
the tunnel lining is homogeneous and the tunnel will be constructed at once.
> In general, the meaning of sections becomes significant when:
> It is desired to excavate or construct the tunnel (lining) in different stages.
> Different tunnel sections have different lining properties.
> One would consider hinge connections in the lining (hinges can be added after
the design of the tunnel in the general drawing area).
> The tunnel shape is composed of arcs with different radii (for example NATM
tunnels).
8-3
TUTORIAL MANUAL
• In the Shape group box there are two parameters. The Symmetric tunnel
parameter can be selected for whole tunnels. The Circular tunnel option is
automatically selected for bored tunnels.
• The tunnel has now been completely defined. Click the <OK> button to close
the tunnel designer.
• Back in the draw area, the tunnel must be included in the geometry model. This
is done by entering the global position of the origin of the local tunnel axes.
Click the existing point at position (0.0; -17.0) (5.0 m above the bottom of the
geometry model). The tunnel will be drawn with its centre at this location.
The wooden piles below the building are end bearing piles. Only a small part of the total
bearing capacity results from skin friction. To correctly model this behaviour, the piles
will be modelled using a combination of plates and node-to-node anchors. The building
itself will be represented by a stiff plate founded on the node-to-node anchors.
• Draw three separate plates from (5.0;-10.0) to (5.0;-11.0), from (15.0;-10.0) to
(15.0;-11.0) and from (5.0;3.0) to (15.0;3.0).
• Connect the top of the pile toes to the foundation plate using node-to-node
anchors, as indicated in Figure 8.1.
Boundary conditions
• Click the Standard fixities button to apply the appropriate boundary conditions.
In addition to the standard displacement fixities, fixed rotations are introduced to
the upper and lower point of the tunnel lining.
Hint: In the Standard fixities option, a plate that extends to a geometry boundary
that is fixed in at least one direction obtains fixed rotations, whereas a plate
that extends to a free boundary obtains a free rotation.
Material properties
The material properties for the four different soil layers are listed in Table 8.1. For all
layers the material behaviour is set to drained since we are interested in the long term
deformations.
For the upper clay layer we use the advanced option to let the stiffness increase with
depth. Therefore a value of Eincrement is entered in the Advanced parameters window. The
value of Eref becomes a reference value at the reference level yreference. Below yreference the
actual value of E increases with depth according to: E(y) = Eref + Eincrement (yreference - y).
The data sets of the two lower soil layers include appropriate parameters for the tunnel
interfaces. In the other data sets the interface properties just remain at their default
values. Enter four data sets with the properties as listed in Table 8.1 and assign them to
the corresponding clusters in the geometry model. To enter the advanced parameters for
the Clay data set, click the <Advanced> button in the Parameters tab sheet.
In addition to the four data sets for the soil and interfaces, three plate and one anchor data
set have to be created. The properties for those plates are listed in Table 8.2 and Table 8.3.
Assign the Lining data set to the tunnel lining and the Pile toe data set to the two pile toes.
The building data set is assigned to the foundation plate representing the building. The
weight of this beam also represents the load of the entire building. Assign the Pile data set to
the two node-to-node anchors.
8-5
TUTORIAL MANUAL
Mesh generation
In this example the 15-node element is used as the basic element type. This means that
the mesh is more accurate than when using the 6-node element. The global coarseness
parameter can remain at its default value (Coarse). It can be expected that stress
concentrations occur around the tunnel and the pile toes. Therefore the mesh should be
refined in these areas. Select the two clusters inside the tunnel and use the Refine cluster
option in the Mesh menu. Select the two plates representing the pile toes and select
Refine line from the Mesh menu.
Initial conditions
The water weight should be taken 10 kN/m 3. The water pressures can be generated on the
basis of a general phreatic level at a level of y = 0.0 m.
Before generating the initial stresses, make sure that the building, piles, pile toes and
tunnel lining are deactivated. The K0-procedure can be used to generate the initial
effective stresses with the appropriate values of K0.
8.2 CALCULATIONS
• Click the 'switch' to proceed to the water pressures mode. Click the Selection
button and select both soil clusters inside the tunnel simultaneously (using the
<Shift> key). Double-click one of the clusters while holding the <Shift> key.
This will show the Cluster pore pressure distribution window. In this
window
select Cluster dry and click <OK> to return to the water pressure mode.
• Click the Generate water pressures button to generate the water pressures. In
the resulting plot it can be seen that there are indeed no water pressures inside
the tunnel. Click the <Update> button to return to the water pressures mode.
• Within the water pressures mode, click the <Update> button to return to the
calculations window.
In addition to the installation of the tunnel lining, the excavation of the soil and the de-
watering of the tunnel, the volume loss is simulated by applying a contraction to the
tunnel lining. This contraction will be defined in a staged construction calculation phase:
• Click the <Next> button to introduce a next calculation phase.
• Select a plastic calculation, Staged construction and click the <Define> button.
• Double-click the centre of the tunnel to open the Tunnel contraction window.
Enter a contraction of 2% and click <OK> to return to the geometry mode and
<Update> to return to the calculations window.
• Select some characteristic points for load-displacement curves (for example the
corner point at the ground surface above the tunnel and the corner points of the
building).
• Start the calculations.
Hint: The contraction of the tunnel lining by itself does not introduce forces in the
tunnel lining. Eventual changes in lining forces as a result of the contraction
procedure are due to stress redistributions in the surrounding soil or to
changing external forces.
8.3 OUTPUT
After the calculation, select the last two calculation phases and click the <Output>
button. The Output program is started, showing the deformed meshes at the end of the
calculation phases.
As a result of the second calculation phase (removing soil and water out of the tunnel)
there is some settlement of the soil surface and the tunnel lining shows some
deformation. In this phase the axial force in the lining is the maximum axial force that will
be reached. The lining forces can be viewed by double-clicking the lining and selecting
force related options from the Force menu (see Figure 8.3).
8-7
TUTORIAL MANUAL
Figure 8.3 Axial forces and Bending moments in the lining after the second phase.
The third calculation phase shows the results due to the simulation of the volume loss.
The deformed mesh indicates a settlement trough at the ground surface, which is
influenced by the presence of the building. (see Figure 8.4). The plot of effective
stresses, Figure 8.5, shows that arching occurs around the tunnel. This arching reduces
the stresses acting on the tunnel lining. As a result, the axial force in phase is lower than
that after the second calculation phase. The bending moments, however, are larger (see
Figure 8.6). The influence of the tunnel contraction on the foundation can be seen in a
plot of the relative shear stresses or plots of the displacements of the pile toes.
Figure 8.6 Axial forces and bending moments in the lining after the third phase
8-9
TUTORIAL MANUAL
During both the tunnel boring and the contraction phase the soil around the tunnel is
unloaded. The tunnel exercise will now be calculated using the Hardening soil model as
this model incorporates a difference in stiffness behaviour between unloading or
reloading and virgin loading.
In order to change the project take the following steps:
• Open the previously calculated tunnel project in PLAXIS Input and save it under
a different name.
• Open the material sets database and change the four soil material sets from
Mohr-Coulomb to Hardening Soil using the parameters given in Table 8.4.
• Go to the initial conditions and regenerate the initial stresses using OCR=1 and
POP=0 for all clusters.
• Save the project and continue to PLAXIS Calculations. Make sure all phases are
selected for calculation and recalculate the project.
Hint: The Hardening Soil parameters have been derived from the Mohr-Coulomb
parameters by setting the E50 of the Hardening Soil model in the midpoint of
E
each layer to the Eref of the Mohr-Coulomb model and deriving ref50 from this
at the reference level pref=100 kPa (see eq. 5.2 of the Material Models
E E E 3
manual). refoed and ref urare assumed to be equal to ref50 and Eref50 respectively.
ref
E ur
Power for stress law m 1.0 0.5 0.9 0.5 -
Reference stress pref 100 100 100 1000 kN/m2
Output results show the same tendencies as when the Mohr-Coulomb model was used,
which is described in Section 8.3.
After the tunnel construction phase there are some clear differences between both cases:
• In the HS case the tunnel is less deformed due to the stiffer soil behaviour; this
results in approximately 20% smaller bending moments in the HS case while the
axial forces remain the same.
• Due to the stiffer soil behaviour underneath the tunnel in the HS case the tunnel
experiences significantly less uplift. This results in a deeper settlement trough at
ground level compared to the Mohr-Coulomb model.
8-11
TUTORIAL MANUAL
During the tunnel contraction phase both cases show similar displacements around the
tunnel but there is a distinct difference in the displacements at a distance of the tunnel.
• With the Hardening Soil model the soil around the tunnel is subject to lower
strain levels so that the soil behaves more like a rigid block and the
displacements around the tunnel due to contraction are therefore still fully
noticeable at ground level. This causes a deeper settlement trough and also up
to 10% higher structural forces in the foundation plate of the existing building.
Finally it should be noticed that the bending moments at the top of the lining reduce
considerably in case of Hardening Soil compared to Mohr-Coulomb, due to the reduced
deformation of the lining.
New Undo Zoom in Geometry line Standard fixities Soil & interfaces Basic element type
Open Copy Zoom out Plate Total fixities Plates Global coarseness
Save Reset view Geogrid Vertical fixities Geogrids Refine global
Save as Table Node-to-node anchor Horizontal fixities Anchors Refine cluster
Print Rulers Fixed-end anchor Rotation fixity (plates) Refine line
Work directory Cross hair Interface Prescribed displacements Refine around point
Pack Project Grid Tunnel Distributed load system A Reset All
Import Axes Hinge & rotation spring Distributed load system B Generate
General settings Snap to grid Drain Point load system A
(Recent projects) Point numbers Well Point load system B
Exit Chain numbers
A-2
INITIAL CONDITIONS MENU
Point numbers
Chain numbers
PLAXIS Version 8
CALCULATION MENU
A-3
OUTPUT MENU (1)
Cross section:
Deformations Stresses
Plates: Deformations Forces
Total displacements Effective normal stresses
Total displacements Axial forces
Horizontal displacem. (x) Total normal stresses
Horizontal displ. Shear forces
Vertical displacements Shear stresses
Vertical displ. Bending moments
Phase displacements Cartesian effective stresses
Phase displacements Hoop forces
Total increments Cartesian total stresses
Total increments Force envelopes
Horizontal increments (x) Overconsolidation ratio
Horizontal incr. (x)
Vertical increments Effective mean stresses (p')
Vertical increments
Normal strain Total mean stresses (p)
Shear strain Deviatoric stresses (q)
Interfaces: Deformations Stresses
Cartesian strains Active pore pressure
Total displacements Effective normal stresses
Normal strain increments Excess pore pressure
Horiz. displ. (x) Shear stresses
Shear strain increments Groundwater flow
Vertical displ. Shear stresses (z)
Cartesian strain increments Groundwater head
Phase displacements Relative shear stresses
Degree of saturation
Total increments Active pore pressures
Horiz. increments Excess pore pressures
Vertical increments
Relative displ.
Relative increm.
A-6
CURVES MENU
PLAXIS Version 8
APPENDIX B - CALCULATION SCHEME
Start
Yes Horizontal No
surface
Ready
B-1
TUTORIAL MANUAL