All 15 Projects
All 15 Projects
All 15 Projects
January, 2019
1
INDEX
2
National Highways Authority of India (NHAI)
(Ministry of Road Transport and Highways)
Government of India
Yours sincerely,
(Arun Jagga)
National Highways Authority of India
G-5 & 6, Sector-10
Dwarka, New Delhi-110075
Tel: 91-011-25074100/4200
Fax:91-011-25093507/3514
Email:- arunjagga@nhai.org
Website: www.nhai.org
3
Letter of Invitation (LOI)
Dear Sir,
Introduction
The National Highways Authority of India (NHAI) has been constituted through an Act
of Parliament for faster, economical and quality Road Construction work throughout
India. The National Highways Authority of India (NHAI) has been entrusted with the
assignment of Request for engagement of DPR consultant for Upgradation of of
Highways (6 packages) in the state of UP.. NHAI now invites proposal from Technical
consultants for carrying out detailed project report as per details given in Annexure-
1.
1.1 A brief description of the assignment and its objectives are given in the
Appendix-1, “Terms of Reference”.
1.2 The NHAI invites Proposals (the “Proposals”) through e-tender (on-line bid
submission) for selection of Technical Consultant (the “Consultant”) who shall
prepare detailed p r o j e c t report (DPR). The consultant should have expertise in
carrying out the similar kind of job, in similar geographical location (particularly
for hill road projects). Consultants are here by invited to submit proposal in the
manner as prescribed in the RFP document. A Consultant with “a Particular Team”
may submit proposals for more than one package. However, a Consultant is not
allowed to bid for a package with more than one team. For the sake of clarity, it
is mentioned that one consultant cannot submit two proposals/ bids for the same
package. A consultant (either as sole or as in JV/Association) can be awarded only
upto 2 packages. A Consultant with “a Particular Team” may submit only one “proof
of eligibility (Part 1)” and “Technical Proposal (Part II)” for any number of packages
applied for by them. However, the packages for which a Consultant with “a
Particular Team” applies should be clearly mentioned. Financial proposal for each
package are to be submitted separately. Financial proposal are only to be
submitted online and no hard copy of the financial proposal should be submitted.
The most preferred bidder (H-1) for each package would be determined on the
basis of Quality and Cost as mentioned in the RFP. Award of work to a Consultant
with “a Particular Team” either as sole or as in JV/Association shall be limited to
one package only. Joint venture shall not have more than two firms In case, a
Consultant with “a Particular Team” turns out to be the most preferred bidder (H-
1) in more than one package, the package which is to be awarded to this
Consultant with “a Particular Team” shall be determined on the basis of least
cost to NHAI considering the financial quote of H-1 bidder and H-2 bidder limited
4
to those packages, which shall be worked out as per the procedure given in the
RFP. The consultants are hereby invited to submit proposals in the manner
prescribed in the RFP.
1.4 To obtain first hand information on the assignment and on the local conditions,
the consultants are encouraged to pay a visit to the client, local State PWDs and
the project site before submitting a proposal and attend a pre-proposal
conference. They must fully inform themselves of local and site conditions and
take them into account in preparing the proposal.
1.5 Financial Proposals will be opened only for the firms found to be eligible and
scoring qualifying marks in accordance with Para 5 hereof. The consultancy
services will be awarded to the highest ranking consultant on the basis of Quality
and Cost.
1.6 Please note that (i) costs of preparing the proposal and of negotiating the
contract, including visits to the Client, etc., are not reimbursable as a direct cost
of the assignment; and (ii) Client is not bound to accept any of the proposals
submitted and reserve the right to reject any or all proposals without assigning any
reasons.
1.8.3 In case of Joint venture, one of the firms which preferably have relatively higher
experience, will act as the lead firm representing the Joint Venture. The duties,
responsibilities and powers of such lead firm shall be specifically included in the
MOU /agreement. It is expected that the lead partner would be authorized to
incur liabilities and to receive instructions and payments for and on behalf of the
Joint Venture. Payment to be made to the JV can also be made to the account of
the JV. For a JV to be eligible for bidding, the experience of lead partner and
other partner should be as indicated in data sheet.
1.8.4 A firm can bid for a project either as a sole consultant or in the form of joint
venture with other consultant or in association with any other consultant.
However, alternative proposals i.e. one as sole or in JV with other consultant and
another in association / JV with any other consultant for the same package will be
summarily rejected. In such cases, all the involved proposals shall be rejected.
1.9 Pre-proposal conference shall be held on the date, time and venue given in Data
Sheet.
1.10.1 The applicant shall furnish as part of its Proposal, a Bid Security of Rs.5,00,000
(Rupees Five lakhs only) in the form of a Bank Guarantee in the
prescribed format given at instruction to Consultants (Form IC-I) issued by one
of the Nationalized/Scheduled Banks in India in favour of the Chairman, National
Highway Authority of India payable at New Delhi (the “Bid Security”) valid for a
minimum period of 150 days (i.e. 30 days beyond the validity of the bid) from the
last date of submission of proposals. Demand Draft of Rs.5,00,000/- (Rupees Five
lakhs only) can also be deposited as bid security. This Bid Security is returnable not
later than 30 (thirty) days from the date of Opening of the Financial proposals
except in case of the two highest ranked Applicants. Bid Security of the Selected
Applicant and the Second ranked Team shall be returned, upon the Selected
Applicant signing the Agreement.
1.10.2 Any Bid not accompanied by the Bid Security of the required value and minimum
required validity shall be rejected by the Authority as non-responsive.
1.10.3 The NHAI shall not be liable to pay any interest on the Bid Security and the same
shall be interest free.
6
1.10.4 The Applicant, by submitting its Application pursuant to this RFP, shall be
deemed to have acknowledged that without prejudice to the NHAI's any other
right or remedy hereunder or in law or otherwise, the Bid Security shall be
forfeited and appropriated by the Authority as the mutually agreed pre-estimated
compensation and damage payable to the Authority for, inter alia the time,
cost and effort of the NHAI in regard to RFP including the consideration and
evaluation of the Proposal under the following conditions:
(a) If an Applicant withdraws its Proposal during the period of its
validity as specified in this RFP and as extended by the Applicant from time
to time.
(b) In the case of a Selected Applicant, if the Applicant fails to sign the
Agreement.
2 Documents
2.1 To enable you to prepare a proposal, please find and use the attached documents
listed in the Data Sheet.
2.2 Consultants requiring a clarification of the documents must notify the Client, in
writing, by 15:00 HRS, 30.01.2019. Any request for clarification in writing or by
telefax/e- mail must be sent to the Client’s address indicated in the Data Sheet.
The Client will upload replies to pre-bid queries on its website.
2.3 At any time before the submission of proposals, the Client may, for any reason,
whether at its own initiative or in response to a clarification requested by a
Consulting firm, modify the Documents by amendment or corrigendum. The
amendment will be uploaded on NHAI website. The Client may at its discretion
extend the deadline for the submission of proposals and the same shall also be
uploaded on NHAI website.
3. Preparation of Proposal
3.1.1 The minimum essential requirement in respect of eligibility has been indicated
in the Data Sheet. The proposal found deficient in any respect of these
requirements will not be considered for further evaluation. The following
documents must be furnished in support of proof of eligibility as per Formats given
in Appendix-II:
7
(ii) Firm’s relevant experience and performance for the last 7 years:
Project sheets in support of relevant experience as per Form-E2/T3
supported by the experience certificates from clients in support of
experience as specified in data sheet for the project size preferably in
terrain of similar nature as that of proposed project shall be submitted on
Infracon portal in input data sheet. Certificate should indicate clearly the
firms Design/DPR experience, in 2/4-/6- laning of highway, structures like
bridges, Viaducts, tunnels, hill slope stabilization, rock bolting, ground
improvement, etc. Scope of services rendered by the firm should be
clearly indicated in the certificate obtained from the client. The
information given in Form E2/T3 shall also be considered as part of
Technical Proposal and shall be evaluated accordingly. The Consultants are
therefore advised to see carefully the evaluation criteria for Technical
Proposal and submit the Project Sheets accordingly.
(iii) Firm’s turnover for the last 5 years: A tabular statement as in Form E3
showing the turnover of the applicant firm(s) for the last five years
beginning with the last financial year certified by the Chartered Account
along with certified copies of the audit reports shall be submitted in
support of the turnover shall be submitted on Infracon Portal in input data
sheet.
(iv) Document fee: The fee for the document amounting to Rs.5,000 (Rupees
Five Thousand only) in the form of Demand Draft favoring 'National
Highways Authority of India' payable at New Delhi must be furnished in a
separate envelope while submitting the proposal.
(v) Bid Security: Bank Guarantee in support of bid security for an amount
specified in Data Sheet and having validity for a minimum period of 150
days (i.e. 30 days beyond the validity of the bid), from the last date of
submission of proposals in the Form E4.
3.1.2 The minimum essential requirement in respect of eligibility has been indicated in
the data sheet, the proposal found deficient in any respect of these requirements
will not be considered for further evaluation.
3.2.1 You are expected to examine all terms and instructions included in the
Documents. Failure to provide all requested information will be at your own risk
and may result in rejection of your proposal.
8
3.2.2 During preparation of the technical proposal, you must give particular attention
to the following:
3.2.3 The technical proposal shall be submitted strictly in the Formats given in
Appendix- III And shall comprise of following documents:
ii) Details of projects for which Technical and Financial Proposals have been
submitted by a Consultant with a particular Team as in Form-T-2
iii) Firm’s references - Relevant Services carried out in the last seven years as
per Form- E2/T-3. This information submitted as part of Proof of Eligibility
shall be evaluated and need not be submitted again as a part of the
Technical proposal
iv) Site Appreciation: limited to four A4 size pages in 1.5 space and 12 font
including photographs, if any (Form-T-4).
vi) Proposed methodology for the execution of the services illustrated with bar
charts of activities, including any change proposed in the methodology of
services indicated in the TOR, and procedure for quality assurance: The
proposed methodology should be accompanied by the consultants initial
view, key challenges they foresee and potential solutions suggested
regarding: a) proposed alignment and bypass required, b) land acquisition
requirements, c)access control, rehabilitaton of existing road, drainage and
utilities, d) adoption of superior technology along with proof: limited to six
A4 size pages in 1.5 space and 12 font including photographs, if any for
items a to c, (Form-T-6) and information in Form-T-8 (as covered in para
viii below) for item d
vii) The proposal should clearly identify and mention the details of Material
Testing lab facilities to be used by the Consultants for the project (Form-T-
7). In this connection, the proposals of the Consultants to use in-house lab
facilities up to a distance of maximum 400 km from the project site being
feasible would be accepted. For all other cases suitable nearby material
Testing Laboratory shall be proposed before Contract Agreement is
9
executed.
viii) The proposal shall indicate as to whether the firm is having the facilities for
carrying out the following field activities or these are proposed to be
outsourced to specialized agencies in the Form- T-8.
a) Pavement Investigation
b) Geo-technical Investigation
In case the consultant envisages outsourcing any or all of the above services
to the expert agencies, the details of the same indicating the arrangement
made with the agencies need to be furnished. These agencies would
however, be subject to approval of the client to ensure quality input by
such agencies before award of the work. For out-sourced services, proposed
firms/consultants should have such experience on similar projects
ix) Details of office equipment and software owned by the firm in Form-T9
i) The CVs of the four key personnel (Team leader cum Senior Highway
Engineer, Senior Bridge Engineer, Highway cum Pavement Engineer & Traffic
/ Road Signage / Marking and Safety expert) in the format as per Form T-10
is to be furnished on Infracon portal. It may please be ensured that the
format is strictly followed and the information furnished therein is true and
correct. The CV must indicate the work in hand and the duration till which
the person will be required to be engaged in that assignment. If any
information is found incorrect, at any stage, action including termination
and debarment from future NHAI projects for a minimum period of 2 years
may be taken by NHAI on the personnel and the Firm.
iii. Team Leader, Highway cum Pavement Engineer, Bridge Engineer, Geo-
technical cum material engineer and Senior Survey Engineer should be
available from beginning of the project. 3 Key Personnel namely
Environmental Specialist, Quantity Surveyor/Documentation expert and
Traffic/ Road Signage/Marking and safety Expert are allowed to be
deployed/proposed in 2 teams at a time. If same CV is submitted by two
or more firms, zero marks shall be given for such CV for all thefirms.
iv. The availability of key personnel must be ensured for the duration of the
project as per proposed work programme. If a firm claims that a key
personnel proposed by them is a permanent employee of the firm (the
personnel should have worked in the firm continuously for a period of at
least 1 year), a certificate to the effect be furnished by the firm.
v. The age limit for key personnel is 65 years as on the date of bid submission.
The proof of age and qualification of the key personnel must be furnished
in the technical proposal.
vi. An undertaking from the key personnel must be furnished that he/she
will be available for entire duration of the project assignment and will not
engage himself/herself in any other assignment during the period of his/her
assignment on the project. After the award of work, in case of non-
availability of key personnel in spite of his/her declaration, he/she shall
be debarred for a period of two years for all projects of NHAI and MoRTH.
vii. Age limit for supporting staff to be deployed on project is 65 years as on
the date of bid submission.
11
xi. It may please be noted that in case the requirement of the ‘Experience’ of
the firm/consortium as mentioned in the “Proof of Eligibility’ is met by any
foreign company, their real involvement for the intended project shall be
mandatory. This can be achieved either by including certain man-months
input of key experts belonging to the parent foreign company, or by
submitting at least the draft feasibility report and draft DPR duly reviewed
by the parent firm and their paying visit to the site and interacting with
NHAI. In case of key personnel proposed by the foreign company, they
should be on its pay roll for at least last six months (from the date of
submission).
xii. In case a firm is proposing key personnel from educational/research
institutions, a ‘No Objection Certificate’ from the concerned institution
should be enclosed with the CV of the proposed key personnel committing
his services for the instant project.
3.2.5 The technical proposal must not include any financial information.
3.3.1 The Financial proposal should include the costs associated with the assignment.
These shall normally cover: remuneration for staff (foreign and local, in the field,
office etc.), accommodation, transportation, equipment, printing of documents,
surveys, geotechnical investigations etc. This cost should be broken down into
foreign and local costs. Your financial proposal should be prepared strictly using,
the formats attached in Appendix – IV. Your financial proposal should clearly
indicate the amount asked for by you without any assumptions of conditions
attached to such amounts. Conditional offer or the proposal not furnished in the
format attached in Appendix-IV shall be considered non- responsive and is liable to
be rejected.
3.3.2 The financial proposal shall take into account all types of the tax liabilities and
cost of insurance specified in the Data Sheet.
3.3.3 Costs shall be expressed in Indian Rupees in case of domestic as well as for
foreign Consultant. The payments shall be made in Indian Rupees by the
National Highways Authority of India and the Consultant themselves would be
required to obtain foreign currency to the extent quoted and accepted by NHAI.
Rate for foreign exchange for payment shall be at the rate established by RBI
applicable at the time of making each payment installment on items involving
actual transaction in foreign currency. No compensation done to fluctuation of
currency exchange rate shall be made.
12
3.3.4 Consultants are required to charge only rental of equipments / software(s) use
so as to economize in their financial bid.
4 Submission of Proposals
4.1 The Applicants shall submit the proposal (Proof of Eligibility and Technical
Proposal) in hard bound form with all pages numbered serially and by giving and
index of submissions. Applications submitted in other forms like spiral bound form;
loose form etc shall be rejected. Copies of Applications shall not be submitted and
considered. A Consultant with “a Particular Team” may submit only one hard copy
(in original) of “proof of eligibility (Part 1)” and “Technical Proposal (Part II)” to
NHAI for all the packages applied by them with a particular team on or before
the deadline of submission of bids. A consultant can apply for a particular package
with one team only. The packages for which a Consultant with “a Particular
Team” applies should be clearly mentioned in their proposal. However,
Consultants are required to submit a copy of Proof of Eligibility and Technical
Proposal online separately for each package. Financial proposal for each package
are to be submitted separately. Financial proposal are only to be submitted online
and no hard copy of the financial proposal should be submitted.
4.2 You must submit original proposal as indicated in the Data Sheet. “Proof
of Eligibility” in original and hard bound should be enclosed in an envelope which
should be marked as “Part-I – Proof of Eligibility”. Similarly, “Technical Proposal”
in original and hard bound should be enclosed in an envelope which should be
marked as “Part-II – Technical Proposal” The proposal will be sealed in an
outer envelope which will bear the address and information indicated in the
Data Sheet and shall be submitted to NHAI on or before the deadline for
submission of bids. The envelope must be clearly marked:
4.2.1 This outer envelope will contain three separate envelopes. The first envelope
containing “Proof of Eligibility” (which should be clearly marked), the second
envelope containing “Technical Proposal” (which should be clearly marked) and the
third envelope containing a demand draft of Rs.5,000/- (cost of RFP), Bid Security
of required amount and validity as mentioned in the RFP. Only one bid security and
one DD of Rs.5,000/ (as cost of Document) may be submitted by a consultant
applying with a particular team for a number of packages. However for consultants
applying with 2 teams, 2 nos. of Bid Security of Rs 5 lakhs each and 2 no’s of DD of
Rs.5,000/ each as mentioned in RFP have to be submitted.
4.2.2 The proposal must be prepared in indelible ink and must be signed by the
authorized representative of the consultants. The letter of authorization must be
confirmed by a written power of attorney accompanying the proposals. All pages
of the Proof of Eligibility and Technical Proposal must be initialed by the person
or persons signing the proposal.
13
4.3 The proposal must contain no interlineations or overwriting except as necessary to
correct errors made by the Consultants themselves, in which cases such corrections
must be initialed by the person or persons signing the proposal.
4.4 Your completed Proof of eligibility and Technical proposal (in hard copy) must
be delivered on or before the scheduled time and date at the address stated in
Data Sheet. Proof of Eligibility, Technical Proposal and Financial Proposal for each
package shall have to be submitted online also on or before the time and date at
the address stated in Data Sheet
4.5 Your proposal must be valid for the number of days stated in the Data Sheet
from the closing date of submission of proposal.
5 Proposal Evaluation
In case answers to any of the above items is ‘No’ the bid shall be declared as non-
responsive and shall not be evaluated further.
14
considered to have failed in the evaluation of Technical Proposals and shall not
be considered for opening of Financial Proposals.
5.3.1 In case for a particular package, only one firm is eligible for opening of
Financial Proposals, the Financial Proposal shall not be opened, the bids for that
package shall be cancelled and NHAI shall invite fresh bids for this package. For
financial evaluation, total cost of financial proposal excluding Goods & Service Tax
shall be considered. Goods & Service Tax shall be payable extra.
5.3.2 The evaluation committee will determine whether the financial proposals
are complete (i.e. whether they have included cost of all items of the
corresponding proposals; if not, then their cost will be considered as NIL but the
consultant shall however be required to carry out such obligations without any
compensation. In case, if client feels that the work cannot be carried out within
overall cost of financial proposal, the proposal can be rejected. The client shall
correct any computational errors and correct prices in various currencies to the
single currency specified in Data Sheet. The evaluation shall exclude those taxes,
duties, fees, levies and other charges imposed under the applicable law & applied
to foreign components/ resident consultants.
5.3.3 For a package, the procedure as mentioned at Clauses 5.3.4, 5.4 and, 5.5 as
mentioned below shall be followed for determining the “most preferred bidder (H-
1 bidder)” for this package.
5.3.4 The lowest financial proposal (FM) will be given a financial score (SF) of 100 points.
The financial scores of other proposals will be computed as follows:
SF = 100xFM/F
(SF = Financial Score, FM= Amount of lowest bid, F= Amount of financial
proposal converted in the common currency)
S= STxT + SFxf
Where,
S= Combined Score,
ST= Technical Score out of 100
SF= Financial Score out of 100
15
5.6 In case work has to be awarded for multiple packages, award of work to a
Consultant with “a Particular Team” either as sole or as in JV/Association shall
be limited to one package only. At first, Consultants who become H-1 in one
package each shall be assigned the respective package. Then packages in which a
Consultant with “a Particular Team” turns out to be the most preferred bidder (H-
1) in more than one package shall be considered. In case, a Consultant with “a
Particular Team” turns out to be the most preferred bidder (H-1) in more than
one package, the package which is to be awarded to this team of a consultant shall
be determined on the basis of least cost to NHAI considering the Financial Quote
of H-1 bidder and H-2 Bidder limited to those packages. Procedure to be followed
for awarding work based on QCBS including assessment of least cost to NHAI under
special circumstances i.e. When a Consultant with “a Particular Team” turns out
to be the most preferred bidder (H-1) in more than one package is given at given
at Annex-II.
6 Performance Security
6.1 The consultant will furnish within 15 days of the issue of Letter of Acceptance
(LOA), an unconditional Bank Guarantee equivalent to 10% of the total contract
value from a Nationalized Bank, IDBI or ICICI/ ICICI Bank/ Foreign Bank/ EXIM Bank
/ Any Scheduled Commercial Bank approved by RBI having a net worth of not less
than Rs.500 crore as per latest Annual Report of the Bank. In the case of a Foreign
Bank (issued by a Branch in India) the net worth in respect of Indian operations
shall only be taken into account. In case of Foreign Bank, the BG issued by
Foreign Bank should be counter guaranteed by any Nationalized Bank in India. In
case of JV, the BG shall be furnished on behalf of the JV or by the lead member
of the JVs for an amount equivalent to 10% of the total contract value to be
received by him towards Performance Security valid for a period of three years
beyond the date of completion of services, or end of civil works contract,
whichever earlier. The Bank Guarantee will be released by NHAI upon expiry of
3 years beyond the date of completion of services, or end of civil works
contract, whichever earlier, provided rectification of errors if any, found
during implementation of the contract for civil work and satisfactory report by
NHAI in this regard is issued. However, if contract is foreclosed / terminated by
NHAI at Inception Stage, with no fault of Consultant, Performance Security shall
be released within three months from date of forecloser / termination. If a
Consultant fails to submit the Performance Security (as specified above), it shall
attract penalty –encashment of Bid Security submitted by the Consultant.
6.2 As an alternative to the contents of Para 1.10 and Para 6.1 above, a single Bank
Guarantee to cover for the performance of all projects under NHAI may also be
deposited as tabulated below, at the discretion of the consultant, instead of
depositing separately again and again. The Consultant may initially provide the
Performance Security for a period of two years provided that it shall procure the
extension of the validity of the Performance Security at least one month prior to
the date of expiry thereof. Once the appropriate single Bank Guarantee for
Performance Security has been submitted by the Consultant, the existing BGs shall
be returned. The Bank Guarantee be submitted in prescribed Performa.
16
Performance Security
Remaining cumulative Value of Consultancy Fee as per BG Value (in Rs. Crores.)
Contracts under a Agency (NHAI) (Cr)
0-20 0.5
20-40 1
40-100 2.50
100-200 4.0
Beyond 200 5.0
7. Penalty
The consultant will indemnify for any direct loss or damage that accrue due to
deficiency in services in carrying out Detailed Project Report. Penalty shall be
imposed on the consultants for poor performance/ deficiency in service as
expected from the consultant and as stated in General Conditions of Contract.
8. Award of Contract
The Client shall issue letter of award to selected Consultant and ask the Consultant
to provide Performance Security as in Para 6 above. If the selected Consultant fail
to provide performance security within the prescribed time or the Consultant
fail to sign the Contract Agreement within prescribed time the Client may invite
the 2nd highest ranking bidder Consultant and follow the procedure outlined in
Para 8 and 9 of this Letter of Invitation.
After having received the performance security and verified it, the Client shall
invite the selected bidder for signing of Contract Agreement on a date and time
convenient to both parties within 15 days of receipt of valid Performance Security.
10. The Client shall keep the bidders informed during the entire bidding process
and shall host the following information on its website:
17
11. Confirmation
Thanking you.
Encl. as above
18
Annex-1
Tentative
S. Package No. Name of Project Length (in
No. km)
1 2 3 4
(i) Package 1 (i) Unnao-Bangarmau-Bilgram-Shahjahanpur-Bisalpur-Pilibhit (i)124.00
(ii) Balrampur-Utraula-Bewa charwaha road (Pilibhit basti (ii) 49.00
road)
(ii) Package 2 (i) Badaun Bijnor road (SH-51) (i) 66.00
(ii) Meerut Badaun Road (SH-18) (ii) 65.00
(iii) Bijnor Mandawar Madawali Road (iii) 39.00
(iii) Package 3 (i) Aligarh –Ramghat Road (i) 51.00
(ii) Bulandsahar-Shyana-Garh Road (SH-65) (ii)50.00
(iii) Ghajuranla-Chandpur-Noorpur-dhampur road (iii)74.00
(iv) Kotwali-Nethaur-Noorpur-Amroha Joya road (iv)74.00
9iv) Package 4 (i) Etawah –Mainpuri-Kurawali Road (SH), (i) 73.00
(ii) EairchGursarai Mauranipur (MDR-31) (ii)71.00
(iii) Mathura-Gowardhan Deeng-Bharatpur road to Agra (iii)26.00
Jaipur Road (NH road)
(iv) Mathura-Gowardhan-Sonkh-Gunsara Road to Bharatpur- (iv)33.00
Agra Jaipur road
(v) Package 5 (i)Bilraya-Panwari road (SH-21) 320.00
19
Annex-II
Procedure of Awarding Work based on QCBS including Assessment of Least Cost
to NHAI under Special Circumstances i.e. When a Consultant with a particular
team becomes H-1 bidder in more than one package
A Consultant with a particular Team can apply for any number of packages with one
team. However, Award of work to a Consultant with “a Particular Team” either as sole
or as in JV/Association shall be limited to one package only. Following procedure shall
be followed for the selection of the most preferred bidder for the consultancy
assignment:
1. At first, Consultants who become H-1 in one package each shall be assigned
the respective package. Then packages in which a Consultant with “a Particular
Team” turns out to be the most preferred bidder (H-1) in more than one package
shall be considered. In case, a Consultant with “a Particular Team” turns out to
be the most preferred bidder (H-1) in more than one package, the package which
is to be awarded to this team of a consultant shall be determined on the basis of
least cost to NHAI considering the Financial Quote of H-1 bidder and H-2 Bidder
limited to those packages which shall be worked out as per procedure illustrated
with an example as mentioned below.
2. Suppose there are 8 packages namely Package-1, Package-2, Package -3,
Package-4, Package -5, package -6,Package-7,Package-8 respectively. It is also
assumed that 10 consultants namely P, Q, R, S, T, U, V, W, X and Y has applied
for these packages. It is also assumed that three Consultants namely P, R and U
has applied with two Teams and the remaining Consultants have applied with
only one team. It is also assumed that the following is the position of various
firms after opening of the Financial proposals (and after arithmetic corrections if
any of the Financial bids) of the packages and after applying QCBS
H-1 H-2 H-3 H-4 H-5 H-6
Package no. Name of Consultants and Financial Quotes (Rs in lakhs)
Package-1 P (team-1) Q W X T Y
230 lakhs 200 lakhs 240 lakhs 220 lakhs 200 lakhs 230 lakhs
Package-2 V U(team-1) X P (team-2) T Y
240 lakhs 210 lakhs 240 lakhs 220 lakhs 200 lakhs 230 lakhs
Package-3 V P(team-1) U(team-1) R (team-2) X Y
200 lakhs 230 lakhs 250 lakhs 230 lakhs 220 lakhs 200 lakhs
Package-4 R (team-1) T U (team-2) P (team-2) Y X
250 lakhs 220 lakhs 250 lakhs 260 lakhs 220 lakhs 245 lakhs
Package-5 R (team-1) V S U(team-2) W T
220 lakhs 240 lakhs 260 lakhs 250 lakhs 220 lakhs 240 lakhs
Package-6 Q T S P (team-2) W U (team-2)
210 lakhs 240 lakhs 250 lakhs 220 lakhs 200 lakhs 230 lakhs
Package-7 R (team-1) U (team-1) Q S W Y
200 lakhs 220 lakhs 240 lakhs 255 lakhs 230 lakhs 240 lakhs
Package-8 V R(team-1) W S P (team-1) Y
190 lakhs 250 lakhs 220 lakhs 240 lakhs 255 lakhs 240 lakhs
20
The different packages shall be awarded to consultants as mentioned below:
2.1 Step-1:
In this case, Consultants P (team-1) and Q are the H-1 in only one package each
namely package-1 and package-6 respectively. Consultant V is H-1 in 3 packages
namely Package-2, Package-3 and Package-8 respectively. Consultant R (team-1) is
H-1 in 3 packages namely Package-4, Package-5 and Package-7 respectively. Since
Consultant P (team-1) is H-1 in Package-1 only and Consultant Qis H-1 in Package-
6 only, Consultant P (team-1) shall be awarded Package-1 and Consultant Q
shall be awarded Package-6.
2.2 Step-2:
Consultant V shall be awarded only one package out of the 3 packages for which it is H-1
namely Package-2, Package-3 and Package-8 respectively. Similarly Consultant R (team-1)
shall be awarded only one package out of the 3 packages for which it is H-1 namelyPackage-
4, Package-5 and Package-7 respectively. The determination of package to be awarded to
Consultant V and Consultant R (team-1) shall be worked out in a single step (i.e. one at a
time) .New H-1 for the remaining packages (4 packages) shall be worked out only after
determination of packages to be awarded to the H-1 bidders at this stage [i.e. Consultant V
and R (Team-1) in the instant case] in one step . Determination of Package to be awarded
to each of Consultant V and Consultant R (team-1) shall be worked out as follows
21
(i) After the award of Package-1 to Consultant –P (team-1) and Package -6 to
Consultant –Q and also considering that a Consultant with a particular team can be
awarded only one work, the details of H-1 and H-2 / New H-2 in the remaining
6 packages are as mentioned below .Since V is H-1 in more than one package
and shall be awarded one of these packages, V has been deleted from all other
packages .Similarly, since R(Team-1) in more than one package and shall be
awarded one of these packages, R (Team-1) has been deleted from all other
packages
H-1 H-2 / New Remarks
H-2
Package-2 V U(team-1)
240 lakhs 210 lakhs
Package-3 V U(team-1) Since Consultant P (Team-1) is awarded
200 lakhs 250 lakhs Package-1, Consultant U (team-1) becomes the new H-
2
Package-4 R (team-1) T
250 lakhs 220 lakhs
Package-5 R (team-1) S
220 lakhs 260 lakhs
Package-7 R (team-1) U (team-1)
200 lakhs 220 lakhs
Package-8 V W Consultant-R(team-1) has not been considered as H-2
190 lakhs 220 lakhs since Consultant –C (team-1) is to be awarded one
package out of the packages 4,5 and 7 in which it is H-1.
Hence Consultant – W is the new H-2
22
In a similar way, Package to be awarded to Consultant – R (team-1) who is H-1 in three
packages namely Package -4, 5 and 7 respectively shall be determined as illustrated
below:
2.3 Step-3
(i) After the award of the above mentioned 4 packages namely, Package-1 to
Consultant–P (team-1), Package -6 to Consultant –Q, Package -3 to Consultant –
V, Package -5 to Consultant –R (team-1) and also considering that a Consultant
with a particular team can be awarded only one work, the details of new H-1 and
New H-2 in the remaining 4 packages are as mentioned below
(ii) Consultant T is the new H-1 for only one package namely Package-4.
Similarly Consultant W is the new H-1 for only one package namely Package-8.
Accordingly Package- 8 shall be awarded to Consultant–W and Package -4 shall
be awarded to Consultant–T.
23
2.4 Step-4:
Consultant U (team-1) is the new H-1 for package- 2 and Package-7 respectively and
Consultant U (team-1) shall be awarded only one package out of this 2 packages. Package
to be awarded to Consultant –U (team-1) shall be determined as illustrated below
H-1 H-2 / New Financial Bid of H-2/ Remarks
H-2 New H-2 minus
Financial Bid of H-1
Package-2 U(team-1) X 240-210 = (+)
210 lakhs 240 lakhs 30
lakhs
Package-7 U (team-1) S 255 – 220 = (+) 35 H-2 minus H-1 is Maximum.
220 lakhs 255 lakhs lakhs Hence Consultant – U (team- 1)
shall be awarded Package- 7
2.5 Step-5 :
(i) After the award of the above mentioned 7 packages namely, Package-1 to
Consultant–P (team-1) , Package -6 to Consultant –Q, Package -3 to Consultant
–V, Package -5 to Consultant –R (team-1), Package-4 to Consultant -T, Package -8
to Consultant-W, package-7 to Consultant –U (team-1) team and also considering
that a Consultant with a particular team can be awarded only one work , the
details of new H-1 and / New H-2 in the remaining package i.e. package -2 is
as mentioned below
(ii) Consultant X is the new H-1 for only one package namely Package-2.
Accordingly, Package -2 shall be awarded to Consultant –X.
3. Thus as per the above mentioned procedure the 8 packages are awarded
to the following Consultant at the Financial Quoted (after arithmetic
Corrections) by them for the respective packages
Package-3 Consultant- V
24
Package-4 Consultant- T
Package-5 Consultant- R (team-1)
Package-6 Consultant- Q
Package-7 Consultant- U (team-1)
Package-8 Consultant- W
25
DATA SHEET
(The Name of project and Package No. should be indicated in the format given
in the technical proposal)
Date: 31.01.2019
Time: 15:00 Hrs
Venue: National Highways Authority of India
G5&6, Sector-10
Dwarka-New Delhi-110075, India (Ref. Para 1.9)
(i). The Consultants and their personnel shall pay all taxes (including G o o d s
& service tax), custom duties, fees, levies and other impositions levied
under the laws prevailing seven days before the last date of submission of
the bids. The effects of any increase / decrease of any type of taxes
levied by the Government shall be borne by the Client / Consultant, as
appropriate.
(ii). Limitations of the Consultant’s Liability towards the Client shall be as per
Clause 3.4 of Draft Contract Agreement
26
(iii). The risk and coverage shall be as per Clause 3.5 of Draft Contract Agreement.
8. The number of copies of the proposal required to be submitted: 1 no. (ref. para
4.1)
i. Original Proposal;
ii. Documents in proof of eligibility and technical proposal as appropriate; and,
iii. Do not open, except in presence of the evaluation committee on the
outer envelope.
iv. Consultancy Package No. :----------
v. Project Name: ------------
vi. Name and Address of Consultant
11. Proposal Validity period (Number of days): 120 days (Ref. Para 4.5)
12.1 First stage evaluation – eligibility requirement. (Ref. Para 3.1 & 5.1)
27
Table-1: Minimum Eligibility Requirements
i) The sole applicant shall fulfill all the requirements given in Table-1.
(ii) In case of JV, the Lead Partner should fulfill at least 75% of all eligibility
requirements and the other partner shall fulfill at least 50% of
all eligibility requirements.
(iii) If the applicant firm has / have prepared the DPR/FS projects solely on
its own, 100% weightage shall be given. If the applicant firm has prepared
the DPR/FS projects as a lead partner in a JV, 75% weightage shall be given.
If the applicant firm have prepared the DPR projects as the other partner
(not lead partner) in a JV 50% weightage shall be given. If the applicant
firm have prepared the DPR/FS projects as an associate, 25%
weightage shall be given.
(iv) Similar project means 2/4/6 lane as applicable for the project for which RFP
is invited. For 2-lane projects experience of 4/6 lane also to be considered
with a multiplication factor of 1.5. Experience of 4/6 lane shall be
considered interchangeably for 4/6 laning projects. For 4/6 laning projects,
experience of 2 lane will be considered with a multiplication factor of 0.4,
but only for those 2 lane projects whose cost of consultancy services was
more than Rs.1.0 crore
28
12.2 Second stage technical evaluation (Refer 5.2)
29
Further break-up of each criteria has been detailed out below:
30
For special projects such as special bridges, tunnels and expressways that
require specialized capabilities and skill sets, the following is the break-up:
31
S. No. Description Maximum Sub-Points
Points
4.2.1 Upto 50 km 2
4.2.2 50km to 100 km 3
4.2.3 100km to 150 km 4
4.2.4 More than 150 Km 5
Note: In case feasibility study is a part of DPR services the experience shall be counted in
DPR only. In case bridge is included as part of DPR of highway the experience will be (1)
and (2)
S. No Description Points
1 Site appreciation 1
2 Team composition and task assignment 1
3 Methodology* 3
Approach and initial view on project plan including key
3.1
challenges envisaged and potential solutions for
Proposed alignment and bypasses required and land acquisition
3.1.1 1
requirements
3.1.2 Access control, rehabilitation of existing road, drainage and utilities 1
Adoption of superior technology along with proof of past use
3.1.3 1
vendor association
Total 5
*Higher marks for adoption of superior technology in data collection, processing and report
may be given. Documents for association with vendors supplying LiDAR or better technology
and GPR/ Induction Locator or better technology shall be furnished.
32
S. No. Description Maximum Sub-Points
Points
2.2 Outsourced
(a) Through NABL accredited labs / IIT / NIT labs 1
(b) Other than (a) 0
3 Office Equipment and Software 3
3.1 High Level (More than 75% as per ToR requirement) 3
3.2 Medium Level (Between 75%-50% as per ToR requirement) 2
3.3 Low Level (Less than 50% as per ToR requirement) 1
4 Experience in LiDAR or better technology for topographic 5
survey (Infrastructure sector)
4.1 1-2 projects 1
4.2 3-5 projects 2
4.3 6-10 projects 3
4.4 >10 projects 5
5 Experience in using GPR and Induction Locator or better 4
technologies for detection of sub-surface utilities
(Infrastructure sector)
5.1 1-2 projects 1
5.2 3-5 projects 2
5.3 >5 projects 4
6 Experience in digitization of cadastral maps for land surveys 3
6.1 Project of area upto 100 ha 1
6.2 Project of area between 100-500 ha 2
6.3 Project of area between 500 ha 3
Note: The experience of firm in LiDar or equivalent technology, GPR and Induction Locator
or equivalent technologies and Experience in digitization of cadastral maps for land
acquisition shall be supported by experience certificate. The experience of a firm in LiDar
or equivalent technology, GPR and Induction Locator or equivalent technologies and
Experience in digitization of cadastral maps for land acquisition for a private
concessionaire/contractor shall be considered only if the experience certificate is
authenticated by the concerned competent Government department/authority.
33
D. Qualification and relevant experience of the proposed key personnel (50)
The number of points assigned during the evaluation of qualification and competence of
key staff are as given below:
34
12.3 Detailed evaluation criteria which is to be used for evaluation of technical
bids is as indicated at Appendix-V.
Financial Proposals of all Qualified Consultants in accordance with clause 5.2 and
5.3 of Letter of Invitation shall be opened.
The consultancy services will be awarded to the consultant scoring highest marks
in combined evaluation of Technical and Financial proposals in accordance with
clause 1.3 and 5.4 hereof.
The Factors are:
The weight given to Technical Proposal (T) = 0.80
The weight given to Financial Proposal (f) = 0.20
Consultant have to quote in Rupees both for domestic Consultant as well as Foreign
Consultants
35
APPENDIX-I
1. General
NHAI has been assigned the work of Request for engagement of DPR consultant for
Upgradation (i) Etawah-Mainpur-Kurawali Road (SH) (ii) Aligarh-Ramghat Road (iii) Bulandshahar to
Badaun in the State of Uttar Pradesh. NHAI now invites proposal from Technical
consultants for carrying out detailed project report as per details given in
Annexure-1.
1.1 NHAI w i l l be the employer and executing agency for the consultancy services
and the standards of output required from the appointed consultants are of
international level both in terms of quality and adherence to the agreed time
schedule. The consultancy firm will solely be responsible for submission of quality
work in stipulated period.
1.2 Ministry has recently awarded works of consultancy services for construction of
ROBs for replacing level crossings in various states. In case a level crossing exists
in a project reach, consultant is required to co-ordinate with those consultants and
finalize the alignment & configuration of road accordingly. However, if the same
is not covered in the above assignment of DPR/feasibility study awarded by
Ministry, the consultant under this assignment shall be responsible for preparing
DPR for such level crossings.
2. Objective
2.1 The main objective of the consultancy service is to establish the technical,
economical, and financial viability of the project and prepare detailed project
reports for rehabilitation and upgrading of the existing road to 4-lane
configuration.
2.2 The viability of the project shall be established taking into account the
requirements with regard to rehabilitation, upgrading and improvement based on
highway design, pavement design, provision of service roads wherever
necessary, type of intersections, rehabilitation and widening of existing and/or
construction of new bridges and structures, road safety features, quantities of
various items of works and cost estimates and economic analysis within the
given time frame.
2.3 The Detailed Project Report (DPR) would inter-alia include detailed highway
design, design of pavement and overlay with options for flexible or rigid
pavements, design of bridges and cross drainage structures and grade
36
separated structures, design of service roads, quantities of various items,
detailed working drawings, detailed cost estimates, economic and financial
viability analyses, environmental and social feasibility, social and environmental
action plans as appropriate and documents required for tendering the project on
commercial basis for international / local competitive bidding.
2.4 The DPR consultant should ensure detailed project preparation incorporating
aspects of value engineering, quality audit and safety audit requirement in design
and implementation. The Consultant shall ensure to carry out Road Safety Audit at
various stages as per supplement-III (Additional Requirement for Safety Audit) of
TOR.
2.5 The consultant should, along with Feasibility Report, clearly bring out through
financial analysis the preferred mode of implementation on which the Civil Works
for the stretches are to be taken up. The consultant should also give cost estimates
along with feasibility report/ detailed Project Report.
3. Scope of Services
The general scope of services is given in the sections that follow. However, the
entire scope of services would, inter-alia, include the items mentioned in the Letter
of Invitation, terms of reference, general contract and any supplements and
appendices to these documents.
3.1.1 The land for any Expressway will be acquired with a RoW of 100 mtrs.
3.1.2 As for the four-lane / six-lane Highway Road Projects, experience shows that all the
existing two-lane Roads requiring upgradation to 4/6-lane involve acquisition of
land, shifting of utilities, felling of trees and other statutory clearances etc. As
such, keeping in view a futuristic approach, it has been decided that the land for
any 4/6 lane Highway Road will be acquired with a RoW of 60 mtrs irrespective of
the width of the carriageway. Further, efforts shall be made to design the road for
upgradation from 2 lane to 4 lane in such a way that the existing 2 lane shall be
retained for one way traffic and separate one way 2 lane greenfield shall be
provided at an appropriate distance from existing 2 lane road with interlinking in
between, to avoid higher LA cost, avoiding shifting of utilities and felling of trees
depending upon specific site conditions and economic considerations.
3.1.3 All efforts shall be made to avoid any road alignment through National Parks and
Wildlife Sanctuaries, even if it requires taking a longer route / bypass. However,
where it becomes absolutely unavoidable and necessary to keep the alignment
through such reserve forest / restricted areas, land would be acquired with RoW of
not more than 30 mtrs. The cross-section in such areas may be kept as 3.25m,
(shoulder / Utility Corridor) + 10.5m (three-lane one side carriageway) + 2.5m
(Median) + 10.5m (2nd three-lane carriageway) + 3.25m (shoulder / Utility Corridor).
37
3.1.4 Similarly, though it may be difficult, while determining the alignment for any
bypass, efforts be made to see if these could be along the revenue boundaries of
two revenue estates thereby minimizing the compulsions of land owners / farmers
for cross-overs to the other side. In case such an alignment is not found feasible, it
should be ensured that access to common facilities for the local people (e.g.
schools, Healthcare facilities etc.) is maintained only on one side of the alignment,
thereby minimizing the need for cross-over for day-to-day life.
3.1.5 Protection of the acquired RoW against any possible encroachments is extremely
important. Boundary stones be provided at the end of the RoW as per Clause 9.8 of
IRC:SP:84-2014 and also supplemented as per Circular dated 08.12.2015 issued by
NHAI. The boundary pillars alone, which are subject to removal with passage of
time, may not be enough to save against encroachments. As such, the typical cross-
section of a Highway Road is being re-visited separately with the intention of
providing permanent features in this behalf. For a typical RoW of 60 mtrs, starting
from one end, these will require the following:
(a) Use barricading of the RoW with plantation of hedge-like species (Ficus /
Poplars) within a 3m wide strip area, dug up to 0.6 to 0.9 mtrs, of which 2.0
mtrs to serve as a Utility Corridor.
(b) Provision of a Service Road (along the inhabited area) with its drainage slope
towards the drain / area reserved for Strip Plantation, for a width of 9.0
mtrs.
(d) Three lane with paved shoulders: Main carriageway – 10.5 mtrs, paved
shoulder – 1.5 mtr and earthen shoulder – 2.0 mtr (Total – 14 mtr).
38
3.3.1 Support in land Acquisition process till the receipt of land possession certificate
from CALA
i. The Consultant shall identify all land parcels needing to be acquired as part
of project RoW and shall furnish land acquisition details as per revenue
records/maps for further processing of land acquisition.
ii. Assist CALA in preparation and verification of draft 3A/3D/3G/3H
notifications, collecting information/documents, claims hearing etc.
iii. Liaison with state departments like land revenue department and registrar's
office for collection and verification of revenue records, surveys, sale deeds,
circle rates and for valuation of land related assets.
iv. Conduct all required surveys/valuation including joint measurement survey
and valuation of land assets.
v. Support CALA by providing technical manpower (like Amins) clerical
manpower and other resources (like vehicles, printers)
vi. Assist PIU in verification of 3A/3D/3G/3H drafts from CALA , drafting of
documents (to be forwarded to RO/HQ), receipt of land possession
certificate and in related activities till award of civil work
vi. Assist PIU in all official communications with CALA and other State
department
3.4.3 Wherever the alignment of 4-lane Highway road project is retained in-situ while
passing through inhabited areas (e.g. villages), it should be ensured that Service
Roads are provided on both sides of the carriageway, connected underneath with
a cross-over structure (VUP/PUP/CUP). Thus each habitation should preferably
have crossing facility at the highways with a vertical clearance of 4 mtrs.
3.4.4 To ensure that bypass once constructed serves the intended purpose during its life,
all the bypasses shall be well designed and access controlled. The entry / exit from
/ to side roads shall be controlled such that they are grade separated at major
roads or at spacing not less than 5 kms. Side roads at closer spacing shall be
connected to the service roads on either side and taken to major roads for provision
of grade separated interchange.
3.5 The provision of embankments shall be kept minimum so as to save land as well as
earth which are scarce resources. This can be decided on case to case basis with
due deliberations. However, economic considerations may also be given due
weightage before deciding the issue.
3 . 6 The Consultant shall study the possible locations and design of toll plaza if
applicable to the project. Wayside amenities Land (minimum 5 acres, length and
depth preferably in the ratio of 3:2) shall also be acquired for establishment of
Way-side amenities at suitable locations at distances varying between 30 to 50 kms
on both sides of the Highway. The local and slow traffic may need segregation
from the main traffic and provision of service roads and fencing may be considered,
wherever necessary to improve efficiency and safety.
3.7 The Consultant will also make suitable proposals for widening/improvement of the
existing road and strengthening of the carriageways, as required at the
appropriate time to maintain the level of service over the design period. The
Consultants shall prepare documents for EPC/PPP contracts for each DPR
assignment.
3.8 All ready to implement ‘good for construction’ drawings shall be prepared
incorporating all the details.
3.9 Environmental Impact Assessment, Environmental Management Plan and
Rehabilitation and Resettlement Studies shall be carried out by the Consultant
meeting the requirements of the lending agencies like ADB/ World Bank/JICA, etc.
3.10 Wherever required, consultant will liaise with concerned authorities and
arrange all clarifications. Approval of all drawings including GAD and detail
engineering drawings will be got done by the consultant from the Railways.
However, if Railways require proof checking of the drawings prepared by the
consultants, the same will be got done by NHAI and payment to the proof consultant
shall be made by NHAI directly. Consultant will also obtain final approval from
Ministry of Environment and Forest for all applicable clearances. Consultant will
40
also obtain approval for estimates for shifting of utilities of all types from the
concerned authorities and NHAI. Consultant is also required to prepare all Land
Acquisition papers (i.e. all necessary schedule and draft 3a, 3A, and 3D, 3G
notification as per L.A. act) for acquisition of land either under NH Act or State
Act.
3.11 The DPR consultant may be required to prepare the Bid Documents, based
on the feasibility report, due to exigency of the project for execution if desired by
NHAI.
3.12 Consultant shall obtain all types of necessary clearances required for
implementation of the project on the ground from the concerned agencies. The
client shall provide the necessary supporting letters and any official fees as per
the demand note issued by such concerned agencies from whom the clearances
are being sought to enable implementation.
3.13 The consultant shall prepare separate documents for BoT as well as EPC
contracts at Feasibility stage / DPR stage. The studies for financing options like
BoT, Annuity, EPC will be undertaken in feasibility study stage.
3.14 The consultant shall be guided in its assignment by the Model Concession/ Contract
Agreements for PPP/ EPC projects, as applicable and the Manual of Specifications
and Standards for two/ four/ six laning of highways published by IRC (IRC:SP:73 or
IRC:SP:84 or IRC:SP:87, as applicable) along with relevant IRC codes for design of
long bridges.
3.15 The consultant shall prepare the bid documents including required schedules (as
mentioned above) as per EPC/ PPP documents. For that it is suggested that
consultant should also go through the EPC/PPP documents of ministry before
bidding the project. The Consultant shall assist the NHAI and the Legal Adviser by
furnishing clarifications as required for the financial appraisal and legal scrutiny of
the Project Highway and Bid Documents.
3.16 Consultant shall be responsible for sharing the findings from the preparation stages
during the bid process. During the bid process for a project, the consultant shall
support the authority in responding to all technical queries, and shall ensure
participation of senior team members of the consultant during all interaction with
potential bidders including pre-bid conference, meetings, site visits etc. In
addition, the consultant shall also support preparation of detailed responses to the
written queries raised by the bidders.
4. General
4.1 Primary Tasks
General Scope of Services shall cover but be not limited to the following major
tasks (additional requirements for Preparation of Detailed Project Report for Hill
Roads and Major Bridges are given in Supplement I and II respectively):
41
cultural properties, natural habitats, involuntary resettlement etc.
v. traffic studies including traffic surveys and Axle load survey and
demand forecasting for next thirty years;
xii. Detailed design of road, its x-sections, horizontal and vertical alignment
and design of embankment of height more than 6m and also in poor soil
conditions and where density consideration require, even lesser height
embankment. Detailed design of structures preparation of GAD and
construction drawings and cross-drainage structures and underpasses etc.
xiv. Design of complete drainage system and disposal point for storm water
42
xv. Value analysis / value engineering and project costing;
xviii Strip plan indicating the scheme for carriageway widening, location
of all existing utility services (both over- and underground) and the scheme
for their relocation, trees to be felled, transplanted and planted and land
acquisition requirements including schedule for LA: reports documents and
drawings arrangement of estimates for cutting/ transplanting of trees
and shifting of utilities from the concerned department;
xx To find out financial viability of project for implementation and suggest the
preferred mode on which the project is to be taken up.
xxii. Design of toll plaza and identification of their numbers and location and
office cum residential complex including working drawings
xxvi. Preparation of social plans for the project affected people as per policy
of the lending agencies/ Govt. of India R&RPolicy.
4.2 While carrying out the field studies, investigations and design, the development
plans being implemented or proposed for future implementation by the local
bodies, should be taken into account. Such aspect should be clearly brought out in
the reports and drawings.
4.3 The consultant shall study the possible locations and design of toll plaza,
wayside amenities required and arboriculture along the highway shall also be
planned.
4.4 The local and slow traffic may need segregation from the main traffic and
provision of service roads and physical barrier including fencing may be
considered, wherever necessary to improve efficiency and safety.
43
1. All activities related to field studies, design and documentation shall be
done as per the latest guidelines/ circulars of MoRT&H and relevant
publications of the Indian Roads Congress (IRC) and Bureau of Indian
Standards (BIS). For aspects not covered by IRC and BIS, international
standards practices, may be adopted. The Consultants, upon award of the
Contract, may finalize this in consultation with NHAI and reflect the same
in the inception report.
1.(i) The Consultants should have detailed Quality Assurance Plan (QAP) for all
field studies including topographic surveys, traffic surveys, engineering
surveys and investigations, design and documentation activities. The
quality assurance plans/procedures for different field studies, engineering
surveys and investigation, design and documentation activities should be
presented as separate sections like engineering surveys and investigations,
traffic surveys, material geo-technical and sub-soil investigations, road
and pavement investigations, investigation and design of bridges &
structures, environment and R&R assessment, economic & financial
analysis, drawings and documentation, preparation, checking, approval
and filing of calculations, identification and tractability of project
documents etc. Further, additional information as per format shall be
furnished regarding the details of personal who shall be responsible for
carrying out/preparing and checking/verifying various activities forming
part of feasibility study and project preparation, since inception to the
completion of work. The detailed Draft QAP Document must be discussed
and finalised with the concerned NHAI officers immediately upon the award
of the Contract and submitted as part of the inception report.
(ii) It is imperative that the QAP is approved by NHAI before the Consultants
start the field work.
i. Required data formats for some reports, investigations and documents are
discussed in Enclosure IV: Formats for submission of Reports and Documents.
ii. The consultants will need to propose data formats for use in all other field
studies and investigations not covered in enclosure IV.
iii. The proposed data forms will need to be submitted for the approval of NHAI
after the commencement of services.
44
i. Climate;
ii. Road inventory
iii Road condition, year of original construction, year and type of major
maintenance/rehabilitation works;
iv. Condition of bridges and cross-drainage structures;
v. sub-surface and geo-technical data for existing bridges;
vi. Hydrological data, drawings and details of existing bridges;
vii Existing geological maps, catchment area maps, contour plans etc. for the
project area
viii Condition of existing river bank / protection works, if any.
ix. Details of sanctioned / on-going works on the stretch sanctioned by
MoRT&H/other agencies for Tie-in purposes
x. Survey and evaluation of locally available construction materials;
xi. Historical data on classified traffic volume (preferably for 5 years or
more);
xii. Origin-destination and commodity movement characteristics; if available
xiii. Speed and delay characteristics; if available;
xiv. Commodity-wise traffic volume; if available;
xv. Accident statistics; and,
xvi. Vehicle loading behavior (axle load spectrum), if available.
xvii Type and location of existing utility services (e.g. Fibre Optical Cable,
O/H and U/G Electric, Telephone line, Water mains, Sewer, Trees etc.)
xviii Environmental setting and social baseline of the project.
1. The type of traffic surveys and the minimum number of survey stations
shall normally be as under, unless otherwise specifically mentioned.
Number of Survey
Sl.NR. Description Stations
45
4. Intersection Volume Count All Major Intersections
5. Speed-Delay Characteristics Project Road Section
6. Pedestrian/animal cross traffic count All major inhabitations along the
highway
7. Turning movement surveys For all major intersections
2. The number of survey locations indicated in the table above are indicative
only for each road stretch under a package. The Consultants shall,
immediately upon award of the work, submit to NHAI, proposals regarding
the total number as well as the locations of the traffic survey stations as of
inception report. Suitable maps and charts should accompany the
proposals clearly indicating the rationale for selecting the location of
survey Station.
2. Consultant shall use ATCC systems that can meet the following accuracy
levels after validation/ calibration:
Before validation and calibration, the ATCC system shall meet the following
accuracy levels:
For verification of above accuracy levels, audit of raw ATCC shall be done
by the consultant on a sampling basis and should submit a certificate in this
regard.
46
4. The classified traffic volume count surveys shall be carried out for
7 days (continuous, direction-wise) at the selected survey stations. The
vehicle classification system as given in relevant IRC code may be
followed. However, the following generalized classification system is
suggested in view of the requirements of traffic demand estimates and
economic analysis:
5. All results shall be presented in tabular and graphical form. The survey data
shall be analyzed to bring out the hourly and daily variations. The traffic
volume count per day shall be averaged to show a weekly average daily
traffic (ADT) by vehicle type. The annual average daily traffic (AADT) shall
be worked out by applying seasonal factors.
6. The consultant shall compile the relevant traffic volume data from
secondary sources also. The salient features of traffic volume
characteristics shall be brought out and variations if any, from the traffic
census carried out by the State PWD shall be suitably explained.
1. The consultants shall carry out 1-day (24 hour, both directions) O-D and
commodity movement surveys at locations finalized in consultation with
NHAI. These will be essentially required around congested towns to
delineate through traffic. The road side interviews shall be carried out on
random sample basis and cover all four-wheeled vehicles. The location of
the O-D survey and commodity movement surveys shall normally be same
as for the classified traffic count.
47
3. The trip matrices shall be worked out for each vehicle type information on
weight for trucks should be summed up by commodity type and the results
tabulated, giving total weight and average weight per truck for the various
commodity types. The sample size for each vehicle type shall be indicated
on the table and also in the graphical representations.
4. The data derived from surveys shall also be analyzed to bring out the
lead and load characteristics and desire line diagrams. The data analysis
should also bring out the requirement for the construction of bypasses.
5. The distribution of lead and load obtained from the surveys should be
compared. The axle load surveys shall normally be done using axle load
pads or other sophisticated instruments. The location(s) of count
station(s) and the survey with those derived from the axle load studies.
1. The turning movement surveys for estimation of peak hour traffic for the
design of major and minor intersections shall be carried out for the
Study. The details regarding composition and directional movement of
traffic shall be furnished by the Consultant.
2. The methodology for the surveys shall be as per IRC: SP: 41-1994. The details
including location and duration of surveys shall be finalized in consultation
with NHAI officials. The proposal in response to this TOR shall clearly
indicate the number of locations that the Consultants wish to conduct
turning movement surveys and the rationale for the same.
48
2. Axle load surveys shall normally be done using axle load pads or other
sophisticated instruments. The location(s) of count station(s) and the survey
methodology including the data formats and the instrument type to be used
shall be finalized before taking up the axle load surveys
3. The axle load data should be collected axle configuration-wise. The number
of equivalent standard axles per truck shall be calculated on the basis of
results obtained. The results of the survey should bring out the VDF for each
truck type (axle configuration, if the calculated VDF is found to be below
the national average, then national average shall be used. Furthermore, the
data from axle load surveys should be analyzed to bring out the Gross
Vehicle Weight (GVW) and Single Axle Load (SAL) Distributions by truck type
(axle configuration).
The Consultants shall carry out appropriate field studies such as moving car
survey to determine running speed and journey speed. The data should be
analyzed to identify sections with typical traffic flow problems and congestion.
The objective of the survey would be to recommend suitable measures for
segregation of local traffic, smooth flow of through traffic and traffic safety.
These measures would include the provision of bypasses, under-passes, fly-overs,
interchanges, grade-separated intersections and service roads.
The data derived from the O-D, speed-delay, other surveys and also
supplementary surveys should be analyzed to assess requirements for present and
future development of truck terminals at suitable locations en route.
3. It is envisaged that the project road sections covered under this TOR would
be completed and opened to traffic after 3 years. The traffic demand
estimates shall be done for a further period of 30 years from completion of
two/four lane. The demand estimates shall be done assuming three
scenarios, namely, optimistic, pessimistic and most likely traffic growth.
The growth factors shall be worked out for five-yearly intervals.
6. The traffic forecasts shall also be made for both diverted and generated
traffic.
7. Overall traffic forecast thus made shall form the basis for the design of
each pavement type and other facilities/ancillary works.
51
4.11.2. Topographic Surveys
2. The carrying out of topographic surveys will be one of the most important
and crucial field tasks under the project. Technologies which can meet the
following accuracy levels shall be adopted. For land based surveys (a)
Fundamental horizontal accuracy of 5cm or better (b) Fundamental vertical
accuracy of 5cm or better (c) More than 50 points shall be measured per sq.
m and for aerial based surveys (a) Fundamental horizontal accuracy of 5 cm
or better (b) Fundamental vertical accuracy of 5 cm or better (c) More than
10 points shall be measured per sq. m. To establish accuracy, a check point
survey using DGPS (for horizontal accuracy) and Auto Level (for vertical
accuracy) shall be carried out to establish the fundamental horizontal and
vertical accuracy. A minimum of 25 check points, or check points once every
4 km should be established, and these should be strictly different from any
geo-referencing or control network points.
3. The following are the set of deliverables which should be submitted after
completion of survey:
(a) Raw DGPS data for the entire highway length and adjoining areas of
interest
(b) Point cloud data or equivalent for the entire highway length and
adjoining areas of interest in a format/ platform as per industry good
practice which shall be amenable to operations by NHAI/ Consultant. NHAI
may decide about format/ platform of point cloud data
(c) Topographic map of scale 1:1000 of the entire highway length and
adjoining areas of interest
4. For land based surveys, Mobile LiDAR (Light Detection and Ranging) or
better technology that can meet above requirements shall be adopted. For
aerial based surveys, Aerial Mobile LiDAR (Light Detection and Ranging) or
better technology that can meet above requirements shall be adopted.
52
Where possible, mobile/terrestrial LiDAR and total station or better studies
should be used to supplement aerial LiDAR for the final alignment chosen.
Aerial based surveys shall be used as the primary source of topographical
data only in cases where a new/green field alignment is being planned
and/or major junctions are being planned where it is necessary to
significantly increase the survey corridor beyond the capabilities of mobile
LiDAR. In shadow areas such as invert levels below culverts, terrestrial
LiDAR shall be used where LiDAR or better technologies cannot survey
accurately, traditional methods of Total Station/ Auto Level shall be used
to complete the study.
6. The detailed field surveys would essentially include the following activities:
i. Topographic Surveys along the Existing Right of Way (ROW): Carrying out
topographic survey using LiDAR or better technology along the existing road
and realignments, wherever required and properly referencing the same
with reference pillars fixed on either side of the centre-line at safe places
within the ROW
ii. The detailed field surveys would essentially include the topographic surveys
along the proposed location of bridge and alignment of approach road.
iii. The detailed topographic surveys should be carried out along the approach
roads alignment and location of bridge approved by NHAI.
iv. Collection/ Extraction of details for all features such as structures (bridges,
culverts etc.) utilities, existing roads, electric and telephone
installations (both O/H as well as underground), huts, buildings, fencing
and trees (with girth greater than 0.3metre) oil and gas lines etc. falling
within the extent of survey.
i. The width of the survey corridor should take into account the layout of the
existing alignment including the extent of embankment and cut slopes and
the general ground profile. While carrying out the field surveys, the
widening scheme (i.e. right, left or symmetrical to the centre line of the
existing carriageway) should be taken into consideration so that the
topographic surveys cover sufficient width beyond the centre line of the
proposed divided carriageway. Normally the surveys should extend a
minimum of 30 m beyond either side of the centre line of the proposed
divided carriageway or land boundary whichever is more
ii. In case the reconnaissance survey reveals the need for bypassing the
congested locations, the traverse lines would be run along the possible
alignments in order to identify and select the most suitable alignment for
53
the bypass. The detailed topographic surveys should be carried out along
the bypass alignment approved by NHAI. At locations where grade separated
intersections could be the obvious choice, the survey area will be suitably
increased. Field notes of the survey should be maintained which would
also provide information about traffic, soil, drainage etc.
iii. The width of the surveyed corridor will be widened appropriately where
developments and / or encroachments have resulted in a requirement for
adjustment in the alignment, or where it is felt that the existing alignment
can be improved upon through minor adjustments.
iv Where existing roads cross the alignments, the survey will extend a
minimum of100 m either side of the road centre line and will be of sufficient
width to allow improvements, including at grade intersection to be
designed.
iii. Boundary Pillars- Wherever the proposed alignment follows the existing
alignment, the boundary pillars shall be fixed by the DPR consultant at an
interval of 200m on either side of proposed Right of Way. Wherever there
is a proposal of realignment of the existing Highway and/or construction of
New Bypasses, Consultant shall fix boundary pillars along the proposed
alignment on the extreme boundary on either side of the project Highway
at 50 m interval. Boundary pillars shall be strictly provided as per
IRC:25:1967.
i. Longitudinal section levels along final centre line shall be taken at every 10
m interval. The levels shall be taken at closer intervals at the curve points,
small streams, and intersections and at the locations of change in elevation.
The interval shall also be modified as per IRC:SP-19 for rolling, mountainous
& steep terrain.
ii. Cross sections at every 50 m interval in full extent of survey covering
sufficient number of spot levels on existing carriageway and adjacent
54
ground for profile correction course and earth work calculations. Cross
sections shall be taken at closer interval at curves. The interval shall be
modified as per IRC SP 19 for rolling, mountainous & steep terrain.
iii. Longitudinal section for cross roads for length adequate for design and
quantity estimation purposes.
iv. Longitudinal and cross sections for major and minor streams shall cover
Cross section of the channel at the site of proposed crossing and few cross
sections at suitable distance both upstream and downstream, bed level upto
top of banks and ground levels to a sufficient distance beyond the edges of
channel, nature of existing surface soil in bed, banks & approaches,
longitudinal section of channel showing site of bridge etc. These shall be as
per recommendations contained in IRC Special Publication No. 13
(Guidelines for the Design of Small Bridges and Culverts) and provisions of
IRC:5 (“Standard Specifications & Code of Practice for Road Bridges, Section
1 – General Features of Design”).
ii. Earth surface, road layers, utilities, buildings and trees with feature data
extracted and mapped in layers, marked on the map and tabulated data
provided separately.
iii. All road, surface, sub surface inventory, pavement investigation and soil
survey data to be super-imposed as layers using geo-referencing data
2. Consultant shall also map out sub-surface utilities. Accurate mapping and
resolution of all sub-surface utilities up to a depth of 4 m shall be carried
out. Differentiation between sub-surface utilities such as live electric
cables, metallic utilities and other utilities shall be indicated and sub-
surface utilities radargrams further processed into utility maps in formats
such as PDF, JPEG and AutoCAD shall be furnished. To meet the accuracy
levels, consultant shall use Ground Penetrating Radar, Induction Locatoror
better technologies.
55
3. The information collected during reconnaissance and field surveys shall be
shown on a strip plan so that the proposed improvements can be
appreciated and the extent of land acquisition with LA schedule, utility
removals of each type etc. assessed and suitable actions can be initiated.
Separate strip plan for each of the services involved shall be prepared for
submission to the concerned agency.
The Consultants shall carry out detailed field studies in respect of road and
pavement. The data collected through road inventory and pavement investigations
should be sufficient to meet the input requirements of HDM-IV.
iii. Carriageway width, surfacing type @ every 500m and every change of
feature whichever is earlier;
iv. Shoulder surfacing type and width @ every 500m and every change of
feature whichever is earlier;
xii. Culverts, bridges and other structures (type, size, span arrangement and
location)
56
xiv. Existing utility services on either side within ROW. There shall be a provision
of utility corridor for appropriate categories / combination of utilities in the
construction of new 4/6 laning of National Highways. Such structures shall
be located at appropriate location preferably as close to the extreme edge
of Right of Way (RoW). In this connection, guidelines contained in IRC:98
shall be followed.
1. Pavement Composition
ii. For each test pit, the following information shall be recorded:
57
2. Road and Pavement Condition Surveys
i. Detailed field studies shall be carried out to collect road and pavement
surface conditions. The data should generally cover:
Pavement Condition
Shoulder Condition
Paved: Same as for pavement
Unpaved: material loss, rut depth and corrugation,
Edge drop, mm.
Embankment Condition
ii. The objective of the road and pavement condition surveys shall be to
identify defects and sections with similar characteristics. All defects shall
be systematically referenced, recorded and quantified for the purpose of
determining the mode of rehabilitation.
iii. In addition to visual means, the pavement condition surveys shall be carried
out using Network Survey vehicles mounted with equipments such as high
resolution cameras, digital laser profilometer, transverse profiler- the data
from which should be geo-referenced using a DGPS receiver and in vehicle
data processing software or equivalent technology to accurately measure
the pavement surface properties covered earlier. This pavement condition
survey shall also be used as a repository for civil work and shall be carried
out as per the directions of NHAI.
vii. Middle 200m could be considered as representative sample for each one km.
of road and incase all other things are considered similar.
Drainage Condition
General condition
Connectivity of drainage turnouts into the natural topography
Condition in cut sections
Condition at high embankments
The data obtained from the condition surveys should be analyzed and the road
segments of more or less equal performance may be identified using the criteria
given in IRC: 81-1997.
3. Pavement Roughness
i. The roughness surveys shall be carried out using a network survey vehicle
mounted laser profilometer or better technology with specifications as
described in para 2 above
i(a) In addition, the following criteria should be met by the process of defect
detection:
Roughness measurement with outputs of both raw longitudinal
profiles and IRI calculation shall be reported at 100m referenced to
the preceding LRP. The roughness must meet ASTM-E950 (equivalent
to Class I road profiler).
The IRI shall be determined for both wheelpaths over a minimum
length of 250m for a minimum of 6 calibration sites with a roughness
range between 2m/km and 8m/km. Calibration shall be made for
speeds of 20, 30, 40, 50, 60 km/h.
ii. The surveys shall be carried out along the outer wheel paths. The surveys
shall cover a minimum of two runs along the wheel paths for each direction.
iii. The results of the survey shall be expressed in terms of BI and IRI and shall
be presented in tabular and graphical forms. The processed data shall be
analyzed using the cumulative difference approach to identify road
segments homogenous with respect to surface roughness.
1 The Consultants shall carry out structural strength surveys for existing
pavements using Falling Weight Deflectometer metre (FWD) in accordance
with IRC 115 or IRC 117 as the case may be.
i. It is suggested that the deflection surveys may be carried out as per the
59
scheme given below:
iv. Falling weight deflectometre surveys may not be carried out for severely
distressed sections of the road warranting reconstruction. The Consultants,
immediately upon the award of the contract, shall submit to NHAI the
scheme describing the testing schedule including the interval. The testing
scheme shall be supported by data from detailed reconnaissance surveys.
i. For the widening (2-Laning) of existing road within the ROW, the
Consultants shall test at least three sub-grade soil samples for each
homogenous road segment or three samples for each soil type encountered,
whichever is more.
60
ii. For the roads along new alignments, the test pits for sub grade soil shall
be @5km or for each soil type, whichever is more. A minimum of three
samples should be tested corresponding to each homogenous segment.
iii. Characterization (grain size and Atterberg limits) at each test pit and,
v. Laboratory CBR (unsoaked and 4-day soak compacted at three energy levels)
and swell.
5. The laboratory for testing of material should be got approved from NHAI
before start of work.
61
4.11.4 Investigations for Bridges and Structure
The Consultants shall make an inventory of all the structures (bridges, viaducts,
ROBs/RUB and other grade separated structures, culverts, etc.) along the road
under the project. The inventory for the bridges, viaducts and ROBs shall include
the parametres required as per the guidelines of IRC-SP:35. The inventory of
culverts shall be presented in a tabular form covering relevant physical and
hydraulic parametres.
62
6. Conducting Model studies for bridges is not covered in the scope of
consultancy services. If Model study is envisaged for any bridge,
requirement of the same shall be spelt out in the RPF documents
separately indicating scope and time frame of such study. Salient features
of the scope of services to be included for model study are given in the
supplement- II Terms of Reference.
1. The Consultants shall thoroughly inspect the existing structures and shall
prepare a report about their condition including all the parametres given
in the Inspection pro-forma of IRC-SP:35. The condition and structural
assessment survey of the bridges / culverts / structures shall be carried
out by senior experts of the Consultants.
i. when the design live load is less than that of the statutory commercial
vehicle plying or likely to ply on bridge;
ii. if during the condition assessment survey and supplementary testing the
bridge is found to indicate distress of serious nature leading to doubt
about structural and / or functional adequacy, and
iii. Design live load is not known nor are the records and drawings available
4. The evaluation of the load carrying capacity of the bridge shall be carried
out as per IRC-SP:37 (“Guidelines for Evaluation of Load Carrying Capacity
of Bridges”). The analytical and correlation method shall be used for the
evaluation of the load carrying capacity as far as possible. When it is not
possible to determine the load carrying capacity of the bridge using
analytical and correlation method, the same shall be carried out
using load testing. The consultant has to exhaust all other methods of
evaluation of strength of bridges before recommending to take up load
testing of bridges. Road closure for testing if unavoidable shall be
arranged by NHAI for limited duration say 12 hours or so.
63
4.11.4.4 Geo-technical Investigations and Sub-Soil Exploration
5. The scheme for the borings locations and the depth of boring shall be
prepared by the Consultants and submitted to NHAI for approval. These
may be finalized in consultation with NHAI.
64
7. For the approach road pavement, bore holes at each major change in
pavement condition or in deflection readings or at 2 km intervals
whichever is less shall be carried out to a depth of at least 2 m below
embankment base or to rock level and are to be fully logged. Appropriate
tests to be carried out on samples collected from these bore holes to
determine the suitability of various materials for use in widening of
embankments or in parts of new pavement structure.
65
4.12 Detailed Design of Road and Pavements, Bridges, Structures
4.12.1. General
ii. Design of pavement for the additional lanes and overlay for the existing
road, paved shoulders, medians, verges;
v. ROB for railway crossings as per the requirement and the standards of
the Indian Railways; and,
vii. Designs for road furniture and road safety/traffic control features;
ix.. Toll plazas and office-cum-residential complex for PIU (one for each civil
contract package)
xii. Bridges and structures rehabilitation plan with design and drawings
xiii. Traffic amenities (Parking Areas, Weighing Station and Rest Areas, etc.).
66
4.12.2. Design Standards
2. The Design Standards evolved for the project shall cover all aspects of
detailed design including the design of geometric elements, pavement
design, bridges and structures, traffic safety and materials.
1. The design of geometric elements shall, therefore, take into account the
essential requirements of such facilities.
4. The detailed design for geometric elements shall cover, but not be limited
to the following major aspects:
i. horizontal alignment;
v. bypasses; and,
67
6. The consultants shall make detailed analysis of traffic flow and level of
service for the existing road and workout the traffic flow capacity for
the improved project road. The analysis should clearly establish the
widening requirements with respect to the different horizon periods taking
into account special problems such as road segments with isolated steep
gradients.
7. In the case of closely spaced cross roads the Consultant shall examine
different options such as, providing grade separated structure for some of
them with a view to reduce number of at-grade crossings, services roads
connecting the cross-roads and closing access from some of the
intersections and prepare and furnish appropriate proposals for this purpose
keeping in view the cost of improvement, impact on traffic movement and
accessibility to cross roads. The detailed drawings and cost estimate should
include the provisions for realignments of the existing cross roads to allow
such arrangements.
9. The Consultant shall also prepare details for at-grade junctions, which
may be adopted as alternative to the grade separated structures. The
geometric design of interchanges shall take into account the site conditions,
turning movement characteristics, level of service, overall economy and
operational safety.
10. The Consultants shall prepare design and other details in respect of the
parallel service roads in urbanized locations and other locations to
cater to the local traffic, their effect of the viability of the project on
commercial basis if service roads are constructed as part of the project
and the implications of not providing the service roads.
11. The consultant shall prepare complete road and pavement design including
drainage for new bypass option identified around congested town en-route.
68
2. The design of pavement shall primarily be based on IRC publications.
3. The design of pavement shall be rigorous and shall make use of the latest
Indian and International practices. The design alternatives shall include
both rigid and flexible design options. The most appropriate design,
option shall be established on life-cycle costing and techno-economic
consideration.
4. For the design of pavement, each set of design input shall be decided on
the basis of rigorous testing and evaluation of its suitability and relevance
in respect of in-service performance of the pavement. The design
methodology shall accompany the design proposals and shall clearly bring
out the basic assumptions, values of the various design inputs, rationale
behind the selection of the design inputs and the criteria for checking and
control during the implementation of works. In other words, the design of
pavement structure should take due account of the type, characteristics of
materials used in the respective courses, variability of their properties and
also the reliability of traffic predictions. Furthermore, the methodology
adopted for the design of pavement shall be complete with
flowcharts indicating the various steps in the design process, their
interaction with one another and the input parametre required at each
step.
5. For the design of overlays for the existing 2-lane pavement, the
strengthening requirement shall duly take into account the strength of the
existing pavement vis-à-vis the remaining life. The overlay thickness
requirements shall be worked out for each road segment homogenous with
respect to condition, strength and sub- grade characteristics. The
rehabilitation provisions should also include the provision of regulating
layer. For existing pavement with acceptable levels of cracking, provision
of a crack inhibiting layer should also be included.
8. The pavement design task shall also cover working out the maintenance
and strengthening requirements and periodicity and timing of such
treatments.
2. The Consultants shall carry out detailed analysis and design for all
embankments of height greater than 6 m based on relevant IRC publications.
i. HFL
ii. LWL
iii. LBL
iv. Erodibility of bed/scour level
v. Design discharge
vi. Linear waterway and effective linear waterway
vii. Likely foundation depth
viii. Safe bearing capacity
ix. Engineering properties of sub soil
x. Artesian conditions
70
xi. Settlement characteristics
xii. Vertical clearance
xiii. Horizontal clearance
xiv. Free board for approach road
xv. Severity of environment with reference to corrosion
xvi. Data pertaining to seismic and wind load
xvii. Requirement of model study etc.
71
8. Suitable repair / rehabilitation measures shall be suggested in respect
of the existing structures as per IRC-SP:40 along with their specifications,
drawings and cost estimate in the form of a report. The rehabilitation or
reconstruction of the structures shall be suggested based on broad
guidelines for rehabilitation and strengthening of existing bridges contained
in IRC-SP:35 and IRC-SP:40.
9. Subsequent to the approval of the GAD and the alignment plan by NHAI,
detailed design shall also be carried out for the proposed underpasses,
overpasses and interchanges.
10. The Consultants shall also carry out the design and make
suitable recommendations for protection works for bridges and drainage
structures.
11. In case land available is not adequate for embankment slope, suitable
design for RCC retaining wall shall be furnished. However, RES wall may
also be considered depending upon techno-economic suitability to be
approved by NHAI.
12. All the bridge structures having a length of 100 m or less can be used for
tapping of water for serving dual purpose i.e., to cross the water body or to
store water, if technically feasible. Therefore, such structures shall be
designed as bridge cum barrage structures (bridge cum bandhara). Ministry’s
guidelines in this regard issued vide letter no. RW/NH-34066/89/2015-
S&R(B) dated 18.04.2017 may be referred.
72
shall be provided with proper gradient and connected to the existing outlets
for final disposal.
5. The rain water harvesting requirements be assessed taking into
consideration the Ministry of Environment & Forest Notification Dt.
14.01.1997 (as amended on 13.01.1998, 05.01.1999 & 06.11.2000). The
construction of rainwater harvesting structure is mandatory in and around
water scarce / crisis areas notified by the Central Ground Water Board. The
provisions for rainwater harvesting be executed as per the requirements of
IRC:SP:42-2014 (Guidelines for Road Drainage) and IRC:SP:50-2013
(Guidelines on Urban Drainage).
6. All the bridge structures having a length of 100m or less can be used for
tapping of water for serving dual purpose i.e. to cross the water body and
to store water, if technically feasible. Therefore, such structures should be
designed as bridge cum barrage structures (bridge cum bandhara). Ministry’s
guidelines in this regard issued vide letter no. RW/NH-34066/59/2015-
S&R(B) dated 18.04.2017 may be referred.
7. The locations of the culverts should be planned in such a way that the
proposed culvert covers optimum catchment area & the location shall be
decided on the basis of topographical survey, local rainfall data, gradient of
natural ground and enquiry from the local habitants. All culverts should
preferably be box culverts as pipe culverts get filled up with silt, which is
rarely cleared.
1. The Consultants shall design suitable traffic safety features and road
furniture including traffic signals, signs, markings, overhead sign boards,
crash barriers, delineators etc. The locations of these features shall be
given in the reports and also shown in the drawings.
2. The Consultant should make the provisions for “the overhead (gantry-
mounted) signs on roads with two or more lanes in the same direction” as
per provisions of IRC-67. The minimum height of gantry mounted sign be 5.5
m above the highest point at the carriageway.
3. Road safety shall be the focus of design. The roads shall be forgiving, having
self-explaining alignment, safe designed intersections / interchanges
segregation and safe crossing facilities for VRUs with crash barriers at
hazardous locations. The details of traffic signs and pavement markings with
their locations, types and configuration shall be shown on the plan so that
they are correctly provided.
4. DPR shall undergo the exercise of Road Safety Audit through the Road Safety
Auditor (separate from design team) and recommendations mentioned be
incorporated.
6. Advanced Traffic Management System (ATMS) shall be in place for all 4/6
lane roads of NHAI being put to tolling. This would provide real time
information, guidance and emergency assistance to users. ATMS would
include outdoor equipment including emergency call boxes, variable
message sign systems, meteorological data system, close circuit TV camera
(CCTV) system in addition to any other equipment required to meet the
objective. Indoor equipment would include large display board, central
computer with Network Management System, CCTV monitor system and
management of call boxes system with uninterrupted power supply, all
housed in a central control centre. In this connection, NHAI’s policy circular
no.11041/218/2007-Admn dated 15.09.2016 may be referred.
1. The Consultants shall identify the possible toll plaza location(s) based on
the data and information derived from the traffic studies and a study of
the existing physical features including the availability of land. The location
of the plaza should keep in view that the project road is to be developed
as a partially access controlled highway facility and it is required to collect
toll on rational basis from as much of the vehicular traffic as possible
consistent with economy of collection and operations. The location of the
toll plaza should be finalized in consultation with NHAI.
2. The minimum number of toll lanes at the toll plazas should be carefully
designed taking into consideration the projected peak hour tollable traffic,
permissible service time, adopted toll collection system and the capacity of
service lanes. The number of lanes at any toll plaza would, however, be not
less than four times the number of lanes for which the highway has been
designed. Eventually, all the lanes have to be designed / equipped with
Electronic Toll Collection (ETC) systems and one lane at the extreme outer
side for Over Dimensioned Vehicles (ODV) should be earmarked in each
74
direction.
3. Car lanes and lanes for commercial vehicles shall be earmarked at the toll
plaza with outer lanes earmarked for the commercial vehicles. At least 50%
of the total lanes on each side shall be equipped with weigh-in-motion
facility for dedicated use by commercial vehicles followed by a static weigh
bridge on either side. Number of lanes with weigh-in-motion facility may be
suitably increased depending on proportion of commercial vehicles in total
traffic. Provision should be kept for acquisition and earmarking of about
one acre area for parking of the overloaded vehicles.
1. The consultant shall select suitable sites for weighing stations, parking
areas and rest areas and prepare suitable separate designs in this regard.
The common facilities like petrol pump, first-aid medical facilities, police
office, restaurant, vehicle parking etc. should be included in the general
layout for planning. For petrol pump, the guidelines issued by OISD of
Ministry of Petroleum shall be followed. The facilities should be planned to
be at approximately 50 km interval. At least each facility (1 no.) is foreseen
to be provided for this project stretch. Weighing stations can be located
near toll plazas so that overloaded vehicles can be easily identified and
suitably penalized and unloaded before being allowed to proceed further.
The type of weighing system suitable for the project shall be brought out
in the report giving merits of each type of the state-of-the art and basis
of recommendations for the chosen system.
2. The Consultant should take into consideration the provisions for persons
with disabilities (PwD) in way side amenity centres / rest areas and provide
ramp facilities, exit / entrance door with minimum clear opening of 900 mm
and special toilet facilities for use of handicapped persons. The consultant
shall also take into consideration, the provisions for Pedestrians facilities as
per IRC-103.
1. The Consultants shall make suitable designs and layout for miscellaneous
works including rest areas, bus bays, vehicle parking areas,
telecommunication facilities etc. wherever appropriate.
2. The Consultants shall prepare the detailed scheme and lay out plan for
the works mentioned in Para 1.
3. The Consultants shall prepare detailed plan for the traffic management
and safety during the construction period.
75
4.13 Environment and Social Impact Assessment
The consultant shall under take the detailed environmental and social impact
assessment in accordance with the standard set by the Government of India for
projects proposed to be funded by MORT&H/NHAI. In respect of projects
proposed to be funded by ADB loan assistance, Environmental Assessment
Requirements, Environmental Guidelines for selected infrastructure projects, 1993
of Asian Development Bank shall be followed. Similarly, for projects proposed to
be funded by World Bank loan assistance, World Bank Guidelines shall be
followed.
3. The consultant shall assess the potential significant impacts and identify
the mitigation measures to address these impacts adequately.
8. The consultant shall provide the cost of mitigation measures and ensure
that environmental related staffing, training and institutional
requirements are budgeted in project cost.
10. The consultant shall identify and plan for plantation and Transplantation
of the suitable trees along the existing highway in accordance with IRC
guidelines.
77
4.13.2 Social Assessment
2 The consultant shall prepare Land Acquisition Plan and assist NHAI in
acquisition of land under various Acts.
4.13.3 The consultant would prepare Resettlement and Rehabilitation Plan and
assess feasibility and effectiveness of income restoration strategies and
suitability and availability to relocation sites. The resettlement plan which
accounts for land acquisition and resettlement impacts would be based on
a 25% socio-economic survey and 100 % census survey of project affected
people which provides the complete assessment of the number of affected
households and persons, including common property resources. All
untitled occupants are recorded at the initial stages and identify cards
will be issued to ensure there is no further influx of people in to the project
area. All consultations with affected persons (to include list of
participants) should be fully documented and records made available to
NHAI.
Executive summary
Description of project
Objectives of the project.
The need for Resettlement in the Project and evaluation of measures to
minimize resettlement.
79
Description and results of public consultation and plans for
continued participation of PAPs.
Definition of PAPs and the eligibility criteria.
Census and survey results-number affected, how are they affected
and what impacts will they experience.
Legal and entitlement policy framework-support principles for
different categories of impact.
Arrangements for monitoring and evaluation (internal and external)
Implementation schedule for resettlement which is linked to the civil works
contract
A matrix of scheduled activities linked to land acquisition procedures to
indicate clearly what steps and actions will be taken at different stages and
the time frame
The payment of compensation and resettlement during the acquisition
process
An itemized budget (replacement value for all assets) and unit costs for
different assets
81
8. Assist PIU in preparing 3A notification (English & Hindi version) and
corresponding check-list documents in format prescribed to be sent for
approval to NHAI HQ
5.1.7 Assist CALA and NHAI (PIU) in the publishing of 3D notification
1. Provide copy of 3A Gazette notification to CALA
2. Support CALA staff to draft 3C notification and 3A notification to be
published in 2 newspapers : 1 Vernacular + 1 other
3. Co-ordinate with NHAI/CALA on publishing of 3C and 3A notifications in 2
local newspapers - 1 vernacular and 1 other
4. Provide copies of newspaper publication of 3C and 3A notification to the
CALA
5. Assist CALA staff in receiving and compiling of public objections
6. Co-ordinate with CALA for scheduling public hearings
7. Assist CALA staff for sending notices to petitioners on respective hearing
dates
8. Assist CALA during objection hearings, recording of hearings , ensuring
compliance of corresponding orders and notification of final CALA order to
petitioners
9. Plant boundary stones/peg-marking along the alignment
10. Conduct Joint measurement survey in conjunction with CALA, NHAI and Land
revenue department to verify land records. Prepare and submit Joint
Measurement Survey Report along with updated alignment sketches of each
survey and village to PIU
11. Co-ordinate collection of all relevant land records including but not limited
to Khatiyaan, Jamabandi, Chakbandi and other relevant records required for
preparation of 3D draft
12. Prepare draft 3D based on JMS report and collected records
13. Co-ordinate submission of draft 3D to CALA office through PIU
14. Assist CALA staff in verification of draft 3D and preparation of draft 3D
declared
15. Assist CALA staff in preparation of draft 3D notification, preamble and
forwarding letter to be forwarded to PIU
16. Co-ordinate delivery of 3D notification (declared by CALA) along with
preamble and forwarding letter to PIU
17. Assist PIU in verification of 3D notification (declared by CALA)
18. Assist PIU in preparing Draft 3D (English & Hindi version) and corresponding
check-list documents in format prescribed to be sent for approval to NHAI
HQ
5.1.8 Assist the CALA in the declaration of award (3G)
1. Provide copy of 3D Gazette notification to CALA.
2. Assist CALA in drafting public notice inviting claims (under sub-section 3 of
section 3G) from all persons interested in the land to be acquired and 3D
notification to be published in 2 local newspaper - 1 vernacular and 1 other.
3. Co-ordinate with NHAI/CALA on publishing of 3D and claim invitation
notification in 2 local newspapers - 1 vernacular and 1 other.
4. Provide 1 copy of newspaper notification of 3D and claim invitation to CALA,
Ward, Panchayat, Circle office, police station and Collector office.
82
5. Assist CALA during claim hearings, record hearings and compliance of
corresponding orders.
6. Conduct valuation of land related assets (Structures, trees, crops etc.) and
liaison with respective State authority for authentication of the valuation.
7. Co-ordinate collection of documents including but not limited to sale deeds,
circle rate and other information required by CALA to prepare 3G award
8. Assist CALA in 3G award preparation and in drafting 3G award documents
9. Deliver 3G award to PIU for approval along with valuation details
10. Assist CALA staff in preparation of field book which contains award by each
beneficiary after 3G award is declared based on 3A, 3D and 3G notification
5.1.9 Assist NHAI in obtaining possession of land
1. Co-ordinate delivery of confirmation letter of deposit from PIU to CALA
2. Assist CALA staff in drafting notification for beneficiaries for award
collection and vacating the land within 60 days (under section 3E)
3. Co-ordinate serving of notice to all beneficiaries for collection of award and
to vacate the land within 60 days (under section 3E)
4. Co-ordinate collection of certificate of possession from CALA
5.1.10 Publication of Gazette Notifications relating to Land Acquisition
Cost for publication of Gazette Notifications relating to land acquisition in
Newspapers shall be borne by the NHAI.
5.2 Utility shifting proposal and estimates
5.2.1 Identify type and location of all existing utilities within the
proposed ROW
1. Consultant will review information available with all utilities agencies in the
region, consult maps/plans available with NHAI, MoRTH and state road
agencies, consult with locals and municipal bodies to ascertain the presence
and location of utilities , including but not limited to water-mains, gas,
telephone, electricity and fiber-optic installations in and around the project
road
2. Deploy ground penetrating radar, inductor locators or better technology to
accurately map the location, type and size of utilities in the ROW of the
project road as required in the section of this TOR
3. Develop a detailed strip plan and digitized maps showing:
i. type, size and current location of all the utilities identified
ii. relative offset from the centerline
iii. existing right of way
5.2.2 Plan for utilities in future road design
1. Consultants need to identify utilities that will require shifting to enable
construction of the proposed project road
2. Incorporate space required for elevated and under-ground utilities corridors
and utilities crossings as required for existing and future utilities in
consultation with user departments
5.2.3 Develop a utilities relocation plan
1. Consultants need to develop and submit a utilities relocation plan in
consultation with NHAI and user departments clearly identifying current
utilities and suggested relocations along with crossings as required
83
2. Plan and conduct discussions, consultations and joint site visits required for
the planning of utilities shifting and the development of required drawings
and proposals
3. Prepare necessary details, documents and suggested relocation plan to be
submitted to user department
4. Develop initial cost estimates based on suggested relocation plan and the
latest available schedule of rates for inclusion in the cost of the project at
the time of approval
5.2.4 Estimates and approvals
1. Consultants need to obtain draft utilities shifting proposal from user
departments for all utilities identified for shifting along project road
2. Prepare utility shifting cost estimates using latest schedule of rates and
obtain approval from user departments
3. Review final designs submitted, cost estimates, complete checklist, obtain
required declarations and submit to PIU for approval
4. Work with user department, PIU and RO as required to incorporate any
changes requested in shifting proposal and cost estimate by RO and NHAI
HQ
5. Obtain all required utilities shifting proposal estimates and required
approvals from both user departments and NHAI within the time stipulated
in DPR contract
2. The Consultants shall make detailed analysis for computing the unit rates
for the different items of works. The unit rate analysis shall duly take
into account the various inputs and their basic rates, suggested location
of plants and respective lead distances for mechanized construction. The
unit rate for each item of works shall be worked out in terms of manpower,
machinery and materials.
4. The Consultant should work out the quantity of Bitumen, Steel and Cement
likely to be used in the project and indicate in the summary sheet.
2. The values of input parametres and the rationale for their selection for
the economic and commercial analyses shall be clearly brought out and got approved by
NHAI.
4. The economic and commercial analyses should bring out the priority
of the different homogenous links in terms of project implementation.
2. The economic analysis shall cover but be not limited to be following aspects:
i. assess the capacity of existing roads and the effects of capacity constraints
on vehicle operating costs (VOC);
ii. calculate VOCs for the existing road situation and those for the project;
iii. quantify all economic benefits, including those from reduced congestion,
travel distance, road maintenance cost savings and reduced incidence of
road accidents; and,
iv. estimate the economic internal rate of return (EIRR) for the project over a
30-year period. In calculating the EIRRs, identify the tradable and non-
tradable components of projects costs and the border price value of the
tradable components.
v. Saving in time value.
The sensitivity scenarios given above are only indicative. The Consultants shall
select the sensitivity scenarios taking into account possible construction delays,
construction costs overrun, traffic volume, revenue shortfalls, operating costs,
85
exchange rate variations, convertibility of foreign exchange, interest rate
volatility, non-compliance or default by contractors, political risks and force
majeure.
4. The economic analysis shall take into account all on-going and future
road and transport infrastructure projects and future development plans in
the project area.
6.3.1 Consultant shall assist the authority in preparing the required bid documents
and support the authority through the bidding process
6.3.2 Preparation of documents
86
1. The consultant shall prepare all required bid documents and technical schedules
required for the bidding of the project
2. The Consultants shall prepare separate documents for each type of contract
(EPC/PPP) for each package of the DPR assignment
3. The consultant shall assist authority in reviewing bid documents and in making
any changes required basis their findings or the and finalising bid documents
4. The consultant shall assist the authority in collecting and providing all required
supporting documents for initiating bid as defined by the SOP for contracting
5. The DPR consultant may be required to prepare the Bid Documents, based
on the feasibility report, due to exigency of the project for execution if desired
by NHAI.
a. To enable this, consultant should study the financial viability and
financial options for the project for modes such as BOT Toll/ Annuity
during the feasibility stage.
6. Provide any and all clarifications required by the authority or other functionaries
such as the financial consultant and legal advisor as required for the financial
appraisal and legal scrutiny of the Project Highway and Bid Documents.
7. The consultant shall be guided in its assignment by the Model Concession/
Contract Agreements for PPP/ EPC projects, as applicable and the Manual of
Specifications and Standards for two/ four/ six laning of highways published by
IRC (IRC:SP:73 or IRC:SP:84 or IRC:SP:87, as applicable) along with relevant IRC
codes for design of long bridges.
a. It is suggested that consultant should go through the EPC/ PPP
documents of ministry before bidding the project.
6.3.3 Support during the bidding process
1. Consultant shall support NHAI through the entire bid process and shall be
responsible for sharing the findings from the preparation stages during the bid
process
2. The consultant shall ensure participation of senior team members of the
consultant during all interaction with potential bidders including pre-bid
conference, meetings, site visits etc.
3. During the bid process for a project, the consultant shall support the authority
in:
a. Responding to all pre-bid technical queries
b. Preparation of detailed responses to the written queries raised by the
bidders
4. The consultant shall assist NHAI and its functionaries as needed in the evaluation
of technical bids
1. Time period envisaged for the study of the project is indicated in LOI.
The final reports, drawings and documentation shall be completed within
this time schedule.
87
8. Project Team and Project Office of the Consultant
5. All key personnel and sub professional staff of the DPR consultants shall
use the fingerprint based (biometric) attendance system for marking their
daily attendance. Attendance shall be marked at least once a day and
anytime during the day. Biometric Attendance system shall be installed by
the DPR Consultants at its own cost at the site office and design office in
order to facilitate the attendance marking. A copy of attendance records
shall be attached at the time of submission of their bills to the NHAI from
time to time. Proposer justification shall be provided for cases of absence
of key personnel/sub-professional staff which do not have prior approval
from Project Director of Concerned Stretch. If NHAI so desires, it shall
facilitate electronic linking of the attendance system with the Central
Monitoring System of NHAI.
88
9. Reports to be submitted by the Consultant to NHAI
9.1 All reports, documents and drawings are to be submitted separately for each of
the traffic homogenous link of the Project Road. The analysis of data and the design
proposals shall be based on the data derived from the primary surveys and
investigations carried out during the period of assignment. The sources of data and
model relationships used in the reports shall be indicated with complete details for
easy reference.
89
9.2 Project preparation activities will be split into eight stages as brought out
below.
No Stage Key activities Report/deliverable submitted
1 Inception Project planning and mobilization Inception Report and QAP
2 Feasibility Alignment finalization, preliminary Alignment Options Report and
surveys Feasibility Report
3 LA and Clearances I LA, utilities identification; creation ofStrip Plan, LA Report (3a, 3A),
draft notifications and proposals Clearances and Utility Shifting
proposals
4 DPR Detailed design of highway, Draft DPR Report, Final DPR Report,
preparation of detailed project report documents and drawings
with drawings
5 Technical Schedules Preparation of bid documents and Civil Works Contract Agreement and
technical schedules Schedules
6 (i) LA II Land acquisition process, obtaining JMS and 3D Report, Final Project
(ii) Project final utilities estimates and required Clearances and Utilities Report
Clearances clearances
7 LA III- Award Land acquisition award determination 3G Report
Determination
8 LA IV- Possession Obtaining possession of land Land Possession Report
Preliminary design work should commence without waiting for feasibility study to be
completed. Stage 3, 5 and 6 shall run in parallel with Stage 2 and 4
For stages 7 and 8 consultant will be required to submit a report at the completion of 90%
of the activities for that stage. In addition, an updated report will need to be submitted at
the completion of all land acquisition activities covering receipt of 100% of the land
possession certificates for the land parcels pertaining to the project road.
Consultant shall be required to complete, to the satisfaction of the client, all the
different stages of study within the time frame indicated in the schedule of
submission in para 10 pertaining to Reports and Documents for becoming eligible
for payment for any part of the next stage.
1. The Consultant shall submit to the client the reports and documents in
bound volumes (and not spiral binding form) after completion of each stage
of work as per the schedule and in the number of copies as given in
Enclosure-III. Further, the reports shall also be submitted in floppy
diskettes / CD’s in addition to the hardcopies as mentioned in Enclosure-
III. Consultant shall submit all other reports mentioned specifically in the
preceding paras of the TOR.
2. The time schedule for various submissions prescribed at Sl. No.1 above shall
be strictly adhered to. No time overrun in respect of these submissions will
90
normally be permitted. Consultant is advised to go through the entire terms
of reference carefully and plan his work method in such a manner that
various activities followed by respective submissions as brought out at
Sl.No.1 above are completed as stipulated. Consultant is, therefore, advised
to deploy sufficient number of supporting personnel, both technical and
administrative, to undertake the project preparation activities in
construction package (Section) simultaneously. As far as possible, the
proposal should include complete information such as number of such
persons, name, position, period of engagement, remuneration rate etc. The
Consultant is also advised to start necessary survey works from the
beginning so as to gain time in respect of various other activities in that
stage.
STAGE 1
10.1 Quality Assurance Plan (QAP) Document
1. Immediately upon the award, the Consultants shall submit four copies
of the QAP document covering all aspects of field studies, investigations
design and economic financial analysis. The quality assurance
plans/procedures for different field studies, engineering surveys and
investigation, design and documentation activities should be presented as
separate sections like engineering surveys and investigations, traffic
surveys, material geo-technical and sub-soil investigations, road and
pavement investigations, investigation and design of bridges
&structures, environment and R&R assessment, economic & financial
analysis, drawings and documentation; preparation, checking, approval and
filing of calculations, identification and traceability of project documents
etc. Further, additional information as per format shall be furnished
regarding the details of personnel who shall be responsible for carrying
out/preparing and checking/verifying various activities forming part of
feasibility study and project preparation, since inception to the completion
of work. The field and design activities shall start after the QAP is approved
by NHAI.
91
ii. The consultants will need to propose data formats for use in all other field
studies and investigations not covered in enclosure IV.
iii. The proposed data forms will need to be submitted for the approval of NHAI
after the commencement of services.
i. Project appreciation;
ii. Detailed methodology to meet the requirements of the TOR finalized in
consultation with the NHAI officers; including scheduling of various sub
activities to be carried out for completion of various stages of the work;
stating out clearly their approach & methodology for project preparation
after due inspection of the entire project stretch and collection/
collation of necessary information;
iii. Task Assignment and Manning Schedule;
iv. Work programme;
v. Proforma for data collection;
vi. Design standards and proposed cross-sections;
vii. Key plan and Linear Plan;
viii. Development plans being implemented and / or proposed for
implementation in the near future by the local bodies and the possible
impact of such development plans on the overall scheme for field work and
design for the study;
ix. Quality Assurance Plan (QAP) finalized in consultation with NHAI;
x. Draft design standards; and
92
STAGE 2: Feasibility Report
1. Basis review of the existing project road, local traffic patterns and initial
reconnaissance surveys, the consultant shall present possible alignment
alternatives for the project road
2. Alignment options should include but not be limited to:
(i) Greenfield sections of the road
(ii) New alignments due to lack of RoW, opportunity to shorten road etc.
(iii) New/Re-alignment to cater to local traffic and o-d points
(iv) Re-alignment due to changes in local network and/or surrounding road
network
(v) Bypasses as suggested and approved in alignment report
(vi) Re-alignment due to need to improve road geometry
(vii) Provision of ROBs, flyovers and other structures
3. The alignment report shall contain:
i. Drivers for re-alignment of road and re-alignment needed as discussed in
para 2 above
ii. Alignment alternatives for each section where re-alignment of road is
needed
iii. Analysis of alignment alternatives bringing out the pros and cons of each
alternative including, but not limited to: new construction required, land
acquisition requirements, environmental impact, utilities and structures
affected, cost of construction, road geometry and road safety aspects, input
from local consultation, NHAI views
iv. Recommendations from among the alignment options presented for the
authority to consider
a. Consultant will enable authority to visualize and compare alignment options
by providing alignment options in a GIS environment that should include, but
not be limited to:
i. Road alignment alternative centerlines
ii. Digital elevation model of the region
iii. Land use / land cover information
iv. Hydrology information
v. Surrounding road network including key NH, SH, MDR and ODRs
vi. Key O/D points and urban settlements
vii. High resolution satellite/airborne imagery of the region
i. Executive summary
ii. Overview of NHAI organization and activities, and project financing and
cost recovery mechanisms
iii. Project description including possible alternative alignments/bypasses
and technical/engineering alternatives
iv. Methodology adopted for the feasibility study
93
v. Socioeconomic profile of the project areas
vi. Indicative design standards, methodologies and specifications
vii. Traffic surveys and analysis
viii. Environmental screening and preliminary environmental assessment
ix. Initial social assessment and preliminary land acquisition/resettlement plan
x. Cost estimates based on preliminary rate analysis and bill of quantities,
xi. Cost analysis of all alternate identified alignments
xii. Economic and financial analysis
xiii. Conclusions and recommendations
3. The basic data obtained from the field studies and investigations
shall be submitted in a separate volume as an Appendix to Feasibility
Report.
STAGE 3:
2. The strip plans and land acquisition plan shall be prepared on the basis
of data from reconnaissance and detailed topographic surveys.
3. The Report accompanying the strip plans should cover the essential
aspects as given under:
4. The strip plans shall clearly indicate the scheme for widening. The
views and suggestions of the concerned State PWDs should be duly taken
into account while working out the widening scheme (left, right or
symmetrical). The widening scheme shall be finalized in consultation with
NHAI.
1. Consultant shall submit a detailed land acquisition plan that provides details
on kilometre-wise land acquisition requirements, all required details and
draft notifications made.
95
2. The Land acquisition plan and report shall be prepared and submitted for
each section (package). Details shall also be submitted in land acquisition
proforma to be supplied by NHAI, in both Hind and English languages.
3. The Land Acquisition Plan shall be prepared after digitization of
cadastral/land revenue maps as per clause 5.1.2 Digitization of cadastral
maps of this TOR
i. Land parcels identification should be verified by superimposing the proposed
road corridor RoW on the geo-located cadastral map to ensure all affected
land parcels have been accounted for and land area to be acquired is
accurately determined
4. The land acquisition plan shall present details concerning the land area to
be acquired in conjunction with the strip plan:
i. Kilometer-wise existing and proposed RoW on either side of the proposed
centreline
ii. Detail schedules of additional land to be acquired, land ownership and other
required details as per revenue records
iii. Details of properties, such as buildings and structures falling within the
right-of way
iv. Costs of acquisition as per revenue authorities and also based on realistic
market derived rates
v. Detail schedules for acquisition of additional land and additional properties
in consultation with the revenue authorities;
5. The land acquisition plan shall report the progress of the land acquisition
process under the NH Land Acquisition act
i. All required details on land parcels to be acquired
ii. Copies draft 3a and 3A notifications and approvals from NHAI
iii. Copies of published notifications, communication with CALAs and current
status land acquisition process
iv. Village, district and CALA wise summary of land to be acquired, current
status of process and notifications published
6. The land acquisition report should be prepared in consultation with affected
persons, non-governmental organisations and concerned government
agencies and should cover land acquisition and resettlement plan and
estimated costs of resettlement and rehabilitation of affected persons.
96
v. Details of consultations made with local people and user agencies
vi. Preliminary scheme for shifting and cost estimates for shifting as per the
concerned authorities
vii. Separate strip plan showing shifting/relocation of each utility services
prepared in consultation with the concerned local authorities
viii. Draft map and plans showing road centerline, existing right of way, proposed
right of way, pertinent topographic details and existing and proposed
location of utilities
1. The consultant shall prepare a report regarding all other clearances required
to enable the construction of the project road such as environment, forest,
tree cutting and railways clearances
2. The clearances report shall include kilometre-wise requirement of all
clearances required presented along with the strip plan including, but not
limited to:
i. Requirements for environmental clearances along the project corridor
ii. Requirements for forest clearances including type of forest affected, extent
of land area needing diversion
iii. Account of required felling of trees of different type and girth and value
estimate of such trees based on realistic rates obtainable from concerned
District forest office
iv. Plan of compensating afforestation, its land requirement with specific
locations and cost involved for undertaking all activities in this regard.
v. ROB/RUBs along the project corridor to be constructed, widened or modified
in any form requiring clearances from the railways
3. The clearances report shall also include:
i. Details of proposals made to concerned agencies and departments
ii. Date of submission of clearances proposals, Environmental impact
assessment report to the competent authority
iii. Copies of all actual clearance proposals made or drafts of proposals yet to
be submitted
iv. Information regarding points of contact, current status of proposals made,
key issues raised and clear next steps to obtaining clearances
STAGE: 4
97
3. The Documents and Drawings shall be submitted for the Package and shall
be in the following format:
Reports
i. Volume-I, Main Report: This report will present the project background,
social analysis of the project, details of surveys and investigations carried
out, analysis and interpretation of survey and investigation data, traffic
studies and demand forecasts designs, cost estimation, environmental
aspects, economic and commercial analyses and conclusions. The report
shall include Executive Summary giving brief accounts of the findings of the
study and recommendations. A sample executive summary has been
enclosed in Appendix VIII.
The Report shall also include maps, charts and diagrams showing locations
and details of existing features and the essential features of improvement
and upgrading. The Environmental Impact Assessment (EIA) Report for
contract package shall be submitted as a part of the main report.
The basic data obtained from the field studies and investigations and input
data used for the preliminary design shall be submitted in a separate volume
as an Appendix to Main Report.
ii. Volume - II, Design Report: This volume shall contain design calculations,
supported by computer printout of calculations wherever applicable. The
Report shall clearly bring out the various features of design standards
adopted for the study. The design report will be in two parts. Part-I shall
primarily deal with the design of road features and pavement composition
while Part-II shall deal with the design of bridges, tunnels and cross-
drainage structures. The sub-soil exploration report including the complete
details of boring done, analyses and interpretation of data and the selection
of design parametres shall be included as an Appendix to the Design Report.
The detailed design for all features should be carried out as per the
requirements of the Design Standards for the project. However, there may
be situations wherein it has not been possible to strictly adhere to the
design standards due to the existing site conditions, restrictions and other
considerations. The report should clearly bring out the details of these
aspect and the standards adopted.
iii. Volume - III, Materials Report: The Materials Report shall contain details
concerning the proposed borrow areas and quarries for construction
materials and possible sources of water for construction purposes. The
report shall include details on locations of borrow areas and quarries shown
on maps and charts and also the estimated quantities with mass haul
diagram including possible end use with leads involved, the details of
sampling and testing carried out and results in the form of important index
values with possible end use thereof.
The materials Report shall also include details of sampling, testing and test
results obtained in respect physical properties of subgrade soils. The
98
information shall be presented in tabular as well as in graphical
representations and schematic diagrams. The Report shall present soil
profiles along the alignment.
The material Report should also clearly indicate the locations of areas with
problematic soils. Recommendations concerning the improvement of such
soils for use in the proposed construction works, such as stabilization
(cement, lime, mechanical) should be included in the Report.
vi. Volume - VI, Rate Analysis: This volume will present the analysis of rates
for all items of works. The details of unit rate of materials at source,
carriage charges, any other applicable charges, labour rates, machine
charges as considered in arriving at unit rates will be included in this
volume.
vii. Volume - VII, Cost Estimates: This volume will present the contract package
wise cost of each item of work as well as a summary of total cost.
viii. Volume - VIII, Bill of Quantities: This volume shall contain the package-
wise detailed Bill of Quantities for all items of works.
ix. Volume - IX, Drawing Volume: All drawings forming part of this volume
shall be ‘good for construction’ drawings. All plan and profile drawings will
be prepared in scale 1:250V and 1:2500H scale to cover one km in one sheet.
In addition this volume will contain ‘good for construction’ drawings for the
following:
Horizontal Alignment and Longitudinal Profile.
Cross-section @ 50m interval along the alignment within ROW
Typical Cross-Sections with details of pavement structure.
Detailed Working Drawings for individual Culverts and Cross Drainage
Structures.
Detailed Working Drawings for individual Bridges, tunnels and
Structures.
Detailed Drawings for Improvement of At-Grade and Grade-Separated
Intersections and Interchanges.
Drawings for Road Sign, Markings, Toll Plazas, and other Facilities.
99
Schematic Diagrams (linear chart) indicating but be not limited to be
following:
o Widening scheme;
o Locations of median openings, intersections, interchanges, underpasses,
overpasses, bypasses;
o Locations of service roads;
o Location of traffic signals, traffic signs, road markings, safety features; and,
o Locations of toll plaza, parking areas, weighing stations, bus bays, rest
areas, if any.
Drawings for toll plaza, Bus Bays, Parking areas, Rest areas, weighing
stations etc. All drawings will be prepared in A2 size sheets. The format for
plan, cross section and profile drawings shall be finalized in consultation
with the concerned NHAI officers. The drawings shall also include details of
all BM and reference pillars, HIP and VIP. The co-ordinates of all points
should be referenced to a common datum, preferably GTS referencing
system. The drawings shall also include the locations of all traffic safety
features including traffic signals, signs, markings, crash barriers,
delineators and rest areas, busbays, parking areas etc.
The typical cross-section drawings should indicate the scheme for future
widening of the carriageway. The proposed cross-sections of road segment
passing through urban areas should indicate the provisions for pedestrian
movements and suitable measures for surface and sub-surface drainage and
lighting, as required.
Digital drawings of proposed highway and features
a. The consultant shall deliver the final road alignment geometry, proposed
road way model and all proposed structures in a 3D engineered model with
all the required features as proposed in Enclosure IV
b. The consultant shall also provide digital versions of all drawings stated in
para 1 above in the format proposed in Enclosure IV
100
STAGE: 5
10.11 Bid documents and Technical Schedules
1. Bid documents
a. The consultant shall prepare bid documents for EPC, PPP or other modes of
contracting as suggested by NHAI
b. Individual bid documents will be submitted for each mode suggested and for
each individual package or section identified for execution
c. Consultant shall assemble and provide all supporting documents from the
DPR assignment that will be required for the bid, in the format required by
the contracting SOP in force at the time of bidding or as maybe required by
the authority
2. Technical Schedules
a. The consultant shall submit a Draft Contract/Concession Agreement derived
from the Master Contract/Concession Agreement maintained by the
authority with all required modifications and inclusions made with reference
to the
b. The agreement submitted shall contain all required technical schedules
updated with the pertinent project details and data required
c. Draft agreement and schedules shall be finalised in consultation with the
authority and submitted for further processing and use with the
contractor/concessionaire awarded the bid packages
STAGE: 6
10.12 LA & Clearances II Report
102
Stage 7: Award Determination
10.13 Submission of Award Determination Report
a. Consultant shall submit a a report on status of award upon approval by NHAI
of award declared for 90% of area as per LA plan or as per the timeline as
given in Enclosure III, whichever is earlier
b. The Consultant shall also submit an updated report containing all required
details upon approval of award by NHAI of 100% of land required to be
acquired
c. The Land award report shall contain details of:
i. Summary of compensation award status by village including:
1. total private and public land being acquired for the project (sq. m) - by
village
2. date of 3A& 3D, final award by CALA, approval by NHAI by village
3. variation of land area and nature of land use against that notified in 3D with
reasons
4. Total award declared by village, claims made by beneficiaries and status of
disbursement
ii. In detail for each village:
1. Updated land acquisition tracker containing parcel-wise status of each
notification, award and disbursement
2. Method used by CALA for arrival on market value
3. Valuation report and details of Award calculation
4. Claims report (received under sub-section 3 of 3G)
5. Copies of notifications published, certificates received
6. Deviations in area according to CALA from provisions under sec. 26-30
iii. Key issues being faced in completing land acquisition and tentative timeline
for completion
iv. A GIS map containing digitised details of land parcels shall be updated with
all relevant land possession details and supplied in the agreed digital format
103
iv. Updated land acquisition tracker containing parcel-wise status of each
notification and disbursement status
v. A GIS map containing digitised details of land parcels shall be updated with
all relevant land possession details and supplied in the agreed digital format
2. The NHAI officers and other Government officers may visit the site at any
time, individually or collectively to acquaint/ supervise the field
investigation and survey works. NHAI may also appoint a Proof Consultant
to supervise the work of the DPR consultant including inter-alia field
investigation, survey work, Design work and preconstruction activities
4. All equipment, software and books etc. required for satisfactory services
for this project shall be obtained by the Consultant at their own cost and
shall be their property.
a. Consultants shall also deliver to NHAI all basic as well as the processed data
from all field studies and investigations, report, appendices, annexure,
documents and drawings in a digital format as described in Enclosure IV over
the course of this assignment and at the submission of the final report in the
form of a removable storage device (CD or USB pen drive) and hosted in a
secure online file hosting platform
b. If required by NHAI the consultant shall arrange at their own cost
necessary software for viewing and measurement of imagery/ point cloud
data.
104
Condition, Roughness, Test Pit (Pavement composition), Falling Weight
Deflectometer (FWD) Material Investigation including test results for
subgrade soils, Traffic Studies(traffic surveys), axle load surveys, Sub-soil
Exploration, Drainage Inventory, Inventory data for bridge and culverts
indicating rehabilitation, new construction requirement etc. in MS EXCEL or
any other format which could be imported to widely used utility packages.
ii. Topographic Surveys and Drawings: All topographic data would be supplied
in (x, y, z) format along with complete reference so that the data could be
imported into any standard highway design software. The drawing files
would be submitted in dxf or dwg format.
iii. Rate Analysis: The Consultant shall submit the rate analysis for various
works items including the data developed on computer in this relation so
that it could be used by the Authority later for the purpose of updating the
cost of the project.
4. Consultant shall include editable soft copies of the final versions of all
documents, including but not limited to the strip plan, plan & profile
drawings, cross sections of right of way and details of structures as well as
any cost workings.
105
SUPPLEMENT I
106
6. 4.7 Review of data and documents pertaining to
a) Terrain and soil condition
b) Condition of tunnels, if required.
c) Sub-surface and geo-technical data for existing tunnels, if required.
d) Drawing and details of existing tunnels, if required.
e) Existing protective works, erosion control and land slide control/protection works,
slope stabilization measures, snow drift control measures, avalanche protection
measures
f) Existing land slide and snow clearance facilities
g) Geological details of rock strata in the area in case of tunnels
7. 4.11.1(1) The Consultant should make an in depth study of available geological and
Meteorological maps of the area.
8. 4.11.1(2) The primary tasks to be accomplished during the reconnaissance survey shall also
include:
a) details of terrain (steep or mountainous), cliffs and gorges, general elevation of
the road including maximum heights negotiated by main ascents and descents,
total number of ascents and descents, hair pin bends, vegetation etc.
b) Climatic conditions i.e. temperature, rainfall data, snowfall data, fog conditions,
unusual weather conditions etc.
c) Realignment requirements including provision of tunnels, if required.
d) Inventory of tunnels and geologically sensitive areas like slip prone areas, areas
subject to landslides, rockfall, snow drifts, erosion, avalanche activity etc.
9. 4.11.2.1 (3.ii) Cross sections shall be taken at every 25 m. in case of hill roads and at points of
appreciable changes in soil conditions. While taking cross sections, soil conditions
shall also be recorded.
10. 4.11.3.1 (1) The inventory data shall also include:
a) General elevation of road indicating maximum & minimum heights negotiated
by main ascents & descents and total no. of ascents & descents.
b) Details of road gradients, lengths of gentle & steep slopes, lengths & location
of stretches in unstable areas, areas with cliffs, areas with loose rocks, land slide
prone areas, snow drift prone areas, no. & location of hairpin bends etc.
c) Details of tunnels
d) Details & types of protective structures, erosion & land slide control/protection
measures, snow drift control measures, avalanche protection/control measures
etc.
11. 4.11.3.2 (2) Pavement:
a) Location of crust failures along with their causes
107
12. -- Condition Surveys & Investigation for Slope Stabilization, Erosion Control,
Landslide Correction/Protection & Avalanche Protection Measures:
108
15. 4.12.2 (1) The Consultant shall evolve Design Standards and material specifications for the
Study primarily based on IRC publications, MORT&H Circulars and relevant
recommendations of the international standards for hill roads for approval by NHAI.
4.12.2 (2) The Design Standards evolved for the project shall cover all aspects of detailed
design including the design of geometric elements, pavement design, bridges and
structures, tunnels if required, traffic safety and materials.
16. 4.12.3 Wherever practicable/feasible hairpin bends and steep gradients shall be
avoided by realignments, provision of structures or any other suitable
provisions.
17. 4.12.4 While designing pavement for hill roads specific aspects relevant to hill regions
like terrain & topographic conditions, weather conditions, altitude effects etc. shall
be duly considered and suitably incorporated in design so that pavement is able to
perform well for the design traffic and service life. Effects of factors like heavy
rainfall, frost action, intensive snow and avalanche activity, thermal stresses due
to temperature difference in day and night, damage by tracked vehicles during
snow clearance operations etc. must also be considered along with traffic
intensity, its growth, axle loads and design life.
18. 4.12.5(3) The design of embankments should include the requirements for protection works
and traffic safety features including features specific to hill roads.
19. 4.12.6 Design and Drawing of Tunnels:
The Consultant shall prepare design and drawings for tunnels, if required as per
the results of feasibility study, as per the relevant specifications of
IRC:SP:91/MORT&H and other international specifications.
20. 4.12.7 a) Topography of hills generates numerous water courses and this coupled with
continuous gradients of roads in hills and high intensity of rainfall calls for effective
drainage of roads. The drainage system shall be designed to ensure that the water
flowing towards the road surface may be diverted and guided to follow a definite
path by suitable provision of road side drains, catch water drains, interceptors etc.
and flow on valley side is controlled so that stability is not affected.
109
23. 10.9.3 Volume II: Design Report :
110
SUPPLEMENT II
2. Methodology
Physical/Mathematical Model study shall be carried out at a reputed/recognized
institution. The consultant will be responsible for identifying the institution,
supplying Information /Documents /Data required for modal studies as indicated
in para 4 below and coordinating the model study with the institution concerned
3. Scope of Work
3.1 Physical Model study
Physical modeling with appropriate model scale for Hydraulic and Hydrologic
Investigations to:
i) Finalize span arrangement causing uniformity in flow distribution, and work
out the alignment and orientation of river training works and bridge axis.
ii) Provide information on estimated/observed maximum depth of scour.
iii) Provide information on required river training works for proposed bridge
iv) Provide hydraulic design for the bridge and the required river training works.
v) Quantify the general direction of river course through bridge, afflux, extent
and magnitude of flood, effect of backwater, if any, aggradation/degradation
of bed, evidence of scour etc. shall be used to augment the available
hydrological data. The presence of flood control/irrigation structures, if affecting
the hydraulic characteristics like causing obliquity, concentration of flow,
scour, silting of bed, change in flow levels, bed levels etc. shall be studied and
considered in Hydraulic design of proposed bridge. The details of any planned
work in the immediate future that may affect the river hydraulics shall be studied
and considered
111
design of proposed bridge. The details of any planned work in the immediate
future that may affect the river hydraulics shall be studied and considered.
i) Plan layouts showing the locations of the proposed bridge as well as the
existing bridges /barrages etc., in the vicinity of the proposed bridge with the
chainages with respect to a standard reference marked on it.
ii) High flood discharges and corresponding flood levels at the locations of the
existing bridges in the vicinity of the proposed bridge.
iii) General arrangement drawing (GAD) of the existing bridges showing
number of spans, pier and well dimensions, founding levels, maximum scour
level, the design discharge and the HFL, guide bund details. On this, the plan
form of the river course with the bridge alignment may also be shown as far
as possible.
iv) General arrangement drawing (GAD) of the proposed new bridge showing
number of spans, pier and foundation dimensions. On this, the plan form of the
river course with the bridge alignment may also be shown as for aspossible.
112
v) River cross sections at 500m longitudinal spacing (maximum) up to a
distance of 2 times the bridge total length on the upstream side and up to a
distance equal to the bridge total length on the downstream with right bank
and left bank clearly marked on it. At least one cross section to be provided at
the location of the proposed bridge. At each cross section, the bed levels to be
taken at a maximum lateral distance of 8 m in flow section and at 25 m in non-
flow section respectively. The abrupt variations in the bed levels to be captured
by taking measurements at closer locations both in longitudinal as
well as lateral directions.
vi) The cross sections, as for as possible, from high bank to high bank.
vii) The longitudinal profile of the river along the length of the proposed
alignment.
viii) Size distribution of the river bed material and the bore log data at different
locations at the site of the proposed bridge.
ix) The series of annual peak flood of the river for at least 15 years period
113
SUPPLEMENT-III
The use of checklists is highly recommended as they provide a useful “aide memoire”
for the audit team to check that no important safety aspects are being overlooked. They
also give to the project manager and the design engineer a sense of understanding of the
place of safety audit in the design process. The following lists have been drawn up based
on the experience of undertaking systematic safety audit procedures overseas. This
experience indicates that extensive lists of technical details has encouraged their use as
“tick” sheets without sufficient thought being given to the processes behind the actions.
Accordingly, the checklists provide guidelines on the principal issues that need to be
examined during the course of the safety audits.
1. The audit team should review the proposed design from a road safety perspective
and heck the following aspects
CONTENTS ITEMS
Aspects to be checked A. Safety and operational implications of proposed alignment and
junction strategy with particular references to expected road
users and vehicle types likely to use the road.
B. Width options considered for various sections.
C. Departures from standards and action taken.
D. Provision of pedestrians, cyclists and intermediate transport
E. Safety implications of the scheme beyond its physical limits
i.e. how the scheme fits into its environs and road Hierarchy
114
A2 : Local Alignment Visibility
New/Existing road interface
Safety Aids on steep hills
1. The audit team should review the proposed check the following aspects design from a road safety
perspective and check the following aspects
CONTENTS ITEMS
Aspects to be checked A. Safety and operational implications of proposed alignment and
junction strategy with particular references to expected road
users and vehicle types likely to use the road.
B. Width options considered for various sections.
C. Departures from standards and action taken.
D. Provision of pedestrians, cyclists and intermediate transport
E. Safety implications of the scheme beyond its physical limits i.e.
how the scheme fits into its environs and road hierarchy
115
B1 : General Departures from standards
Cross-sectional variation
Drainage
Climatic conditions
Landscaping
Services apparatus
Lay-byes
Footpaths
Pedestrian crossings
Access (minimize number of private accesses)
Emergency vehicles
Public Transport
Future widening
Staging of contracts
Adjacent development
B2 : Local Alignment Visibility
New/Existing road interface
Safety Aids on steep hills
B3 : Junctions Minimise potential conflicts
Layout
Visibility
B4 : Non-Motorised road Adjacent land
users Provision Pedestrians
Cyclists
Non-motorised vehicles
B5 : Signs and Lighting Lighting
Signs/Markings
116
Stage 2 – Completion of Detailed Design
1. The audit team should satisfy itself that all issues raised at Stage 1 have been resolved. Items may require
further consideration where significant design changes have occurred.
2. If a scheme has not been subject to a stage 1 audit, the items listed in Checklists B1 to B6 should be considered
together with the items listed below.
CONTENTS ITEMS
Aspects to be checked A. Any design changes since Stage 1.
B. The detailed design from a road safety viewpoint, including the road
safety implications of future maintenance (speed limits; road signs
and markings; visibility; maintenance of street lighting and central
reserves).
C1 : General Departures from standards
Drainage
Climatic conditions
Landscaping
Services apparatus
Lay-byes
Access
Skid-resistance
Agriculture
Safety Fences
Adjacent development
C2 : Local Alignment Visibility
New/Existing road interface
C3 : Junctions Layout
Visibility
Signing
Lighting
Road Marking
T,X,Y-junctions
All roundabouts
Traffic signals
C4 : Non-Motorised road users Adjacent land
Provision Pedestrians
Cyclists
117
Non-motorised vehicles
C5 : Signs and Lighting Advanced direction signs
Local traffic signs
Variable message signs
Other traffic signs
Lighting
118
Enclosure-I
MANNING SCHEDULE
7 Environmental Specialist 2 1 3
In case Tunnels are to be constructed, necessary input of Tunnel Experts shall be provided
in addition to above mentioned Manpower requirement.
Tunnel expert, if required, the remuneration may be provided equivalent to Team Leader
remuneration and time period shall be decided by Regional Officer, concerned, NHAI.
3. The Consultant shall provide one Land Acquisition Expert along with allied team and
supporting logistic as envisaged in Clause 5.1.5.1 of TOR for each 100 km stretches proposed
for DPR preparation or part thereof
If delay in LA process occurs beyond the reasonable control of consultant, the extension of
LA team staff/s along with logistic support/transportation shall be granted by Nodal Project
119
Director and beyond further 6 months, Regional Officer, NHAI is empowered to grant
extension to LA team staff/s.
120
Enclosure-II
i) Educational Qualification
Essential Graduate in Civil Engineering or equivalent as approved by
AICTE
121
Enclosure-II (contd.)
i) Educational Qualification
Essential Graduate in Civil Engineering or equivalent
Desirable Masters in Bridge Engineering / Structural
Engineering
ii) Essential Experience
a)Total Professional Experience Min. 10 years
122
Enclosure-II (contd.)
i) Educational Qualification
Essential Degree in Civil Engineering
Desirable Masters in highway engineering/Transportation
Engineering
ii) Experience
a)Total Professional Experience Min. 08 years
123
Enclosure-II (contd.)
i) Educational Qualification
124
Enclosure-II (contd.)
i) Educational Qualification
Essential Graduate or equivalent in Civil Engineering or Diploma in
Civil Engg or Diploma in Surveying
125
Enclosure-II (contd.)
QUALIFICATION AND EXPERIENCE REQUIREMENT OF KEY PERSONNEL
i) Educational Qualification
126
Enclosure-II (contd.)
Environmental Specialist
i) Educational Qualification
127
Enclosure-II (contd.)
i) Educational Qualification
Desirable
ii) Essential Experience
a) Total Professional Experience Min. 10 years
b) Experience in Highway Projects Min. 8 years in Preparation of Bill of Quantities,
Contract documents and documentation for major
highway projects involving two/ four laning
128
Enclosure-II (contd.)
i) Educational Qualification
Essential Graduate or equivalent
129
Enclosure-II (contd.)
Utilities expert
i) Educational Qualification
130
Enclosure-III
2 Inception Report
(i) Draft Inception Report including 3 21
QAP document
131
6 Technical Schedules
The checklist for different stages of submission of report has been enclosed as under
and the same shall be appended with proper references and page numbering. The
checklist/s shall be appended with the report without which no payment shall be made.
132
Schedule for approval of Reports and Documents by PD after
submission by Consultant.
5 Technical Schedules
The checklist for different stages of submission of report has been enclosed as under
and the same shall be appended with proper references and page numbering. The
checklist/s shall be appended with the report without which no payment shall be made.
133
Enclosure IV: Formats for submission of Reports and Documents
134
2. Consultants are encouraged to keep commonly available software and data
packages, and typical uses for data while deciding final formats of data within the
constraints of this document or where a format has not been defined
3. As required in clause Error! Reference source not found. Error! Reference source
not found., consultants are required to agree with NHAI all actual data formats
proposed to be used for the project
4. In order to standardise data formats and simplify hand over and re-use of data,
some requirements for minimum content and format are laid down below.
Sr Data product Contents required (definition) Data format
No
0 Formats to be List of data, drawing and design outputs, reporting CSV or ODF sheet, .xlsx
used format, digital format suggested, key data to be optional
included (column headers), units and system to be used
1 Traffic surveys
1.1 List of traffic Point no, location coordinates (lat, long), location of CSV or ODF sheet, .xlsx
survey points survey point, chainage, no lanes/type of junction, type optional
of survey, date of survey, length of survey, any
commentary, equipment/technique used, link to survey
output
1.2 Classified traffic Survey point, survey location, location id (ihmcl), no of Raw data: IHMCL Traffic
volume count lanes, chainage, location coordinates (lat, long), date, survey data format
survey time and period of survey Processed, corrected
with AADT: CSV or ODF
sheet, .xlsx optional
1.3 O-D, turning Survey point, survey location, location lat, long, CSV or ODF sheet, .xlsx
movement, axle chainage, date, time, period of survey, optional
load and other technique/equipment used in addition to the survey
surveys data itself
2 Engineering surveys and investigations
2.1 Raw DGPS data Notes must contain Date, time of survey, equipment CSV or ODF, Receiver
used, corrections applied is any. Data: Survey Independent Exchange
benchmarks, benchmark points, location data points Format (RINEX)
2.2 LiDAR point cloud Notes must contain Date, time of survey, equipment, LASer file format for
summary post processing applied. Data: Survey exchange
benchmarks, data points, point cloud of entire project CSV sheet, .xlsx
corridor as defined in optional
2.3 Images 360 Deg/ ortho images of entire project road way Geographic Tagged
Image File Format
(GeoTIFF)
2.4 Video Traverse video of entire project length Audio video interleave
(.avi) or MPEG-4 file
(.mp4)
135
Sr Data product Contents required (definition) Data format
No
2.5 Topographic map 1:1000 scale map with 50 cm contours with roadway Contours: geo-
+ contours marked on maps referenced shape files
(.shp) or .dxf files,
.dwg/.dgn files options
2.6 Digital elevation Digital terrain modeled from aerial and ground surveys Digital elevation model
model in USGS Spatial Data
transfer standard
(SDTS) format
2.7 Longitudinal and Location of cross section - existing, design chainage, .dxf files, .dwg/.dgn files
cross sections lat, long, Cross section drawing options
2.8 As-is road map 3D digital map of as-is project highway containing earth Digital terrain model and
surface, road layers, utilities, buildings and trees with maps in LandXML/.dxf
feature data extracted and mapped in layers, marked format, .dwg/.dgn files
on the map and tabulated data provided separately. All options
road, surface, sub surface inventory, pavement Separate CSV or ODF
investigation and soil survey data to be super-imposed sheet, .xlsx optional of
as layers feature data in addition
to map
2.9 Details of utility type of utility, no, class and category of utility installation CSV or ODF sheet, .xlsx
(e.g. 66 kV xlpe), location, distance from centerline, optional
user agency
2.10 Utility maps geo-referenced schematic map, existing and design georeferenced shape
road centerline, type of utility, size, no, class and files (.shp) and drawings
category in .dxf format
2.11 Road inventory All data as required in clause 4.11.3.1, geo-referencing CSV or ODF sheet
surveys for each row of data in lat, long form
2.12 Pavement Test pit reference id, location, chainage, geo-reference CSV or ODF sheet
investigation (lat, long), pavemet composition - layer no, material
type, thickness, sub grade type, and condition
2.13 Pavement Data as required in clause 4.11.3.2, along with CSV or ODF sheet
condition survey location/chainage and geo-reference for all data
2.14 Pavement FWD results as per IRC guidelines, geo-referencing for CSV or ODF sheet
structural strength test points
2.15 Sub-grade and In the format of the testing lab, summary details must Summary in CSV or
soil strength be tabulated and must include: test pit no, location, ODF sheet
chianage, lat/long, date, time of test, tester/lab details,
in-situ density, moisture content, field CBR,
characterization, in-lab moisture and density, lab CBR
3 Proposed roadway designs
136
Sr Data product Contents required (definition) Data format
No
3.1 Proposed Georeferenced centerline horizontal and vertical Geometry or shape files
alignment alignment for the road : .shp/.dxf, .dwg/.dgn
geometry To be presented superimposed on surface map, files options
satellite imagery and digital elevation model of region
3.2 Final alignment Georeferenced centerline horizontal and vertical Geometry or shape files
geometry alignment for the road. Additional detail on lanes, super : .shp/.dxf, .dwg/.dgn
elevation, junctions, structures, under/overpasses, files options
PUP/CUP, wayside amenities etc
3.3 Proposed Proposed digital roadway model and design data- .dxf/.dtm
roadway model including embankment, road way, road layers, roadside
amenities, signals, road furniture, markings and other
construction elements in 3D
3.4 Proposed Geo referenced location and alignment, 3D model of .dxf/.dtm
structures structure and appurtenances, cross section, plan and
profile drawings for construction as per IRC
3.5 Proposed highway Roadway cross sections for homogenous sections .dxf files
cross sections Digital surface model in
.dxf format
4 Other deliverables
4.1 Digitized cadastral Digitized revenue map overlaid with key landmarks, Geometry or shape files
maps land size, survey number and ownership data. min : .shp/.dxf, .dwg/.dgn
1:1000 scale map with >1mm accuracy files options
4.2 Financial analysis Spreadsheet model with instructions, index and ODF sheets, MS office
containing all inputs and assumptions, time series .xlsx optional
construction and operating costs, revenues, financing
and equity cash flows, NPV/IRR, sensitivity scenarios
and results
137
3.2 Deliverables to be hosted
i. Data and deliverables to be hosted in an online accessible format shall include but
not be limited to:
ii. All draft and final deliverables in the digital formats prescribed in this TOR and in
file formats in wide use where formats are not specified
iii. Data, images and videos from all surveys and investigations conducted of this
enclosure
iv. All correspondence to and from NHAI including clients’ comments on submitted
reports
v. Any communication, letters and approvals to and from other government local
agencies and any other relevant body
vi. The platform shall also contain an index and table of contents of information being
hosted for ease of access and use
3.3 Time period and costs
i. Access to above mentioned files will be provided till the end of construction (final
commercial operations date of contractor/ concessionaire) of all packages that
form a part of this assignment at the cost of the consultant
ii. Access to additional users shall also be at no additional cost to the authority
138
APPENDIX-II
Proof of Eligibility
Form-E1
Sub: Appointment of Consultant for preparation of Detailed Project Report for ……………...
Dear Sir,
With reference to your RFP Document dated ………, I/we i.e M/s-------------------------------
-------------------------------------------- (Name of Bidder) h a v i n g examined all relevant
documents and understood their contents, hereby submit our Proposal for selection as
Consultant. The proposal is unconditional and unqualified.
2. All information provided in the Proposal and in the Appendices is true and correct
and all documents accompanying such Proposal are true copies of their respective
originals.
3. This statement is made for the express purpose of appointment as the Consultant
for the aforesaid Project.
5. I/We acknowledge the right of the authority to reject our application without
assigning any reason or otherwise and hereby waive our right to challenge the same on
any account whatsoever.
6. I/We certify that in the last three years, we or any of our Associates have neither
failed to perform on any contract, as evidenced by imposition of a penalty by an arbitral
or judicial authority or a judicial pronouncement or arbitration award against the
Applicant, nor been expelled from any project or contract by any public authority nor
have had any contract terminated by any public authority for breach on our part.
7. I/We understand that you may cancel the Selection Process at any time and that
you are neither bound to accept any Proposal that you may receive nor to select the
Consultant, without incurring any liability to the Applicants in accordance with Clause 1.7
of the RFP document.
139
8. I/We declare that we/any member of the consortium, are/is not a Member of
any other Consortium applying for Selection as a Consultant.
9. I/We certify that in regard to matters other that security and integrity of the
country, we or any of our Associates have not been convicted by a Court of Law or
indicted or adverse orders passed by a regulatory authority which would cast a
doubt on our ability to undertake the Consultancy for the Project or which relates to a
grave offence that outrages the moral sense of the community.
10. I/We further certify that in regard to matters relating to security and integrity
of the country, we have not been charge-sheeted by any agency of the Government or
convicted by a Court of Law for any offence committed by us or by any of our Associates.
11. I/We further certify that no investigation by a regulatory authority is pending either
against us or against our Associates or against our CEO or any
of our Directors/Managers/employees.
12. I/We hereby irrevocably waive any right or remedy which we may have at any stage
at law or howsoever otherwise arising to challenge or question any decision taken
by the Authority [and/ or the Government of India] in connection with the selection of
Consultant or in connection with the Selection Process itself in respect of the above
mentioned Project.
13. The Bid Security of Rs. ***** (Rupees *****) in the form of a Bank Guarantee is
attached, in accordance with the RFP document.
14. I/We agree and understand that the proposal is subject to the provisions of
the RFP document. In no case, shall I/we have any claim or right of whatsoever nature if
the Consultancy for the Project is not awarded to me/us or our proposal is not opened or
rejected.
15. I/We agree to keep this valid for 120 (One hundred and twenty) days from the
Proposal Due Date specified in the RFP.
16. A Power of Attorney in favor of the authorized signatory to sign and submit this
Proposal and documents is attached herewith.
17. In the event of my/our firm/consortium being selected as the Consultant, I/we
agree to enter into any Agreement in accordance with the form Appendix V of the RFP.
We agree not to seek any changes in the aforesaid form and agree to abide by the same.
18. I/We have studied RFP and all other documents carefully and also surveyed the
Project site. We understand that except to the extent as expressly set forth in the
Agreement, we shall have no claim, right or title arising out of and documents or
information provided to us by the Authority or in respect of any matter arising out of or
concerning or relating to the Selection Process including the award of Consultancy.
19. The Proof of Eligibility and Technical proposal are being submitted in separate
covers in hard copy and they are being submitted online also. Financial Proposal is being
submitted online only. This Proof of Eligibility read with Technical Proposal and Financial
140
Proposal shall constitute the Application which shall be binding on us.
20. I/We agree and undertake to abide by all the terms and conditions of the RFP
Document. In witness thereof, I/we submit this Proposal under and in accordance with the
terms of the RFP Document.
Yours faithfully,
(Signature, name and designation of the authorized signatory)
(Name and seal of the Applicant/Lead Member)
141
Appendix- II
Form-E2/T3
FIRM’S REFERENCES
Relevant Services Carried out in the Last Seven Years (2011-12 onwards) Which
Best Illustrate Qualifications
The following information should be provided in the format below for each reference
assignment for which your firm, either individually as a corporate entity or as one of the
major companies within a consortium, was legally contracted by the client:
142
APPENDIX-II
Form- E3
Name of Applicant:
1 2017-18
2 2016-17
3 2015-16
4 2014-15
5 2013-14
Certificate from the Statutory Auditor$
This is to certify that -------------- (name of the Applicant) has received the payments shown above against
the respective years on account of Consultancy Services.
$In case he Applicant does not have a statutory auditor, it shall provide the certificate from
its chartered accountant that ordinarily audits the annual account of the Applicant.
Note:
143
APPENDIX-II
Form- E4
(To be stamped in accordance with Stamp Act if any, of the country of issuing bank)
1. If the Bidder withdraws his Bid during the period of bid validity specified in the Bid
document; or
2. If the Bidder does not accept the correction of arithmetical errors of his Bid Price in
accordance with the Instructions to Bidder; or
3. If the Bidder having been notified of the acceptance of his Bid by the Employer during
the period of bid validity,
a. fails or refuses to execute the Form of Agreement in accordance with the Instructions
to Bidders, if required; or
b. fails or refuses to furnish the Performance Security, in accordance with the letter of
invitation, we undertake to pay the Employer up to the above amount upon receipt
of his first written demand, without the Employer having to substantiate his demand,
provided that in his demand the Employer will note that the amount claimed by him
is due to him owing to the occurrence of one or any of the conditions, specifying the
occurred condition or conditions.
This Guarantee will remain in force up to and including the date 150 (one hundred and fifty)
days after the deadline for submission of bids as such deadline is stated in the Instructions
to Bidders or as it may be extended by the Employer, notice of which extension(s) to the
Bank is hereby waived. Any demand in respect of this Guarantee should reach the Bank not
later than the above date.
Notwithstanding anything contained herein before, our liability under this guarantee is
restricted to Rs. (Rs. ) and the guarantee shall remain
valid till . Unless a claim or a demand in writing is made upon us on or before
144
all our liability under this guarantee shall cease
DATE
SIGNATURE OF THE BANK
SEAL OF THE BANK
SIGNATURE OF THE WITNESS
Name and Address of the Witness
The bank guarantee shall be issued by a bank (Nationalized/Scheduled) located in India
145
Appendix III
(Form-T1)
TECHNICAL PROPOSAL
FROM: TO:
Sir:
Yours faithfully,
Signature
Full Name
Designation
Address
(Authorized Representative)
146
(Form-T-2)
Details of projects for which Technical and Financial Proposals have been
submitted
Sl. No. Name of Project Consultancy Package No. Names of Proposed Key
Personnel
1
2
3
4
147
Form-E2/T3
FIRM’S REFERENCES
Relevant Services Carried out in the Last Seven Years Which Best Illustrate
Qualifications
The following information should be provided in the format below for each reference
assignment for which your firm, either individually as a corporate entity or as one of
the major companies within a consortium, was legally contracted by the client:
148
Form- T4
SITE APPRECIATION
Shall give details of site as per actual site visit and data provided in RFP and
collected from site supported by photographs to demonstrate that responsible
personnel of the Consultant have actually visited the site and familiarized with
the salient details/complexities and scope of services.
149
Form- T5
Composition of the Team Personnel and the task Which would be assigned to
each Team Member
I. Technical/Managerial Staff
1.
2.
3.
4.
….
….
….
1.
2.
3.
4.
….
….
….
150
Form- T6
APPROACH PAPER ON METHODOLOGY PROPOSED FOR PERFORMING THE
ASSIGNMENT
The approach and methodology will be detailed precisely under the following topics.
1) Methodology for services, surveying, data collection [not more than 2 pages]
and analysis
2) Quality Assurance system for consultancy assignment [not more than 1 page]
3) The key challenges foreseen and proposed solutions will be detailed precisely under
the following topics
Replies to items 3) a) to c) should be limited to six A4 size pages in 1.5 space and 12 font
including photographs, if any
151
Form- T7
1. State whether the Applicant has in-house Material Testing Facility Available /
Outsourced / Not Available
2. In case answer to 1 is Available, attach a list of Lab equipment and facility for
testing of materials and location of laboratory
3. In case laboratory is located at a distance of more than 400 km from the project site,
state arrangements made / proposed to be made for testing of materials
152
Form- T8
Facility for Field investigation and Testing
4. For experience in LiDAR or better technology for topographic survey, GPR and
Induction Locator or better technologies for detection of sub-surface utilities and
digitization of cadastral maps for land acquisition, references need to be provided in
following format:
REFERENCES
The following information should be provided in the format below for each reference
assignment for which your firm, either individually as a corporate entity or as one of
the major companies within a consortium, was legally contracted by the client:
153
Form- T9
Office Equipment and software
154
Form- T10
155
UNDERTAKING FROM THE PROFESSIONAL
I, …………………. (Name and Address) have not left any assignment with the consultants
engaged by MORT&H/ NHAI for any continuing works of MORT&H/NHAI without completing
my assignment. I will be available for the entire duration of the current project
(named…………..). If I leave this assignment in the middle of the completion of the work,
I may be debarred for an appropriate period to be decided by NHAI. I have also no
objection if my services are extended by NHAI for this work in future.
156
Appendix IV
(Form-I)
FINANCIAL PROPOSALS
FROM: TO:
Sir:
Yours faithfully,
Signature
Full Name
Designation
Address
(Authorized Representative)
*The Financial proposal is to be filled strictly as per the format given in RFP.
157
(Form-II)
I Local Consultants
Remuneration for Local Staff (inclusive of per diem allowance)
II Support Staff (inclusive of per diem allowance)
III Transportation
IV Duty Travel to Site
V Office Rent
VI Office Supplies, Utilities and Communication
VII Office Furniture and Equipment (Rental)
VIII Reports and Document Printing
IX Surveys & Investigations
A Topographical Survey
B Investigations
C Net Work Survey and GPR
X Cost of supply and fixing Boundary Pillars
XI Land Acquisition Team including support staff and
logistics/transportation
Subtotal Local Consultants :
Foreign Consultants
F-I Remuneration for Expatriate Staff
F-II Mobilization and Demobilization
Total Cost Net of Tax :
Taxes I. Income Tax (Expatriate)
and ll. Other Taxes/ Duties (if any) Specify clearly
Duties
158
(Form-III)
Professional Staff
1 Team Leader cum Senior 9
Highway Engineer
2 Senior Bridge Engineer 5
3 Highway cum Pavement 5
Engineer
4 Material-cum-Geotechnical 6
Engineer- Geologist
5 Senior Survey Engineer 7
6 Traffic and Safety Expert 4
7 Environmental Specialist 3
8 Quantity Surveyor/ 6
Documentation Expert
9 Land Acquisition Expert 10
10 Utility Expert 4
Sub-Total:
Sub-Professional Staff (To be assessed by Consultant as per requirement
of assignment and one sub-professional be a fresh graduate)
1
2
3
4
5
6
7
Sub-Total:
TOTAL
159
II. Support Staff
2 Typist
3 Office Boy
4 Night Watchman
Total :
Total
160
VI. Office Supplies, Utilities and Communication (Fixed Costs)
No. Item Months Monthly Amount
Rate (INR) In INR.
2 Supplies Computer
3 Running Costs
TOTAL:---------------------------
161
12 Draft Bidding Documents 4
13 Final Detailed Project Report with Bill of 6
Quantities, Cost Estimates, Updated Drawings
etc. Final EMP
14 Final Bidding Documents 6
15 Draft 3(a) ,3(A) and 3(D) notification for land 9
acquisition ( 3 copies each)
16 LA & Clearances II Report 6
Total
Note: * Quantities of borings shall be taken from Financial Proposal Form No. V. For
financial evaluation, these quantities and rates quoted by the consultant will be
considered. However, Payment shall be made on the actual quantity of boring at rates
quoted above by the Consultant, which may be substantially more or less than the estimated
quantities.
Amount
Item (INR.)
163
XI Land Acquisition Team including support staff and logistics/transportation
S. No. Position Name Number Rate (INR) Man Months Amount (INR)
1 Ex-Land Revenue TBN 1 8
Inspector/Officer or
equivalent
2 Ex-Kanoogo/Girdwar or TBN 1 8
equivalent
3 Ex-Patwari or TBN 1 8
equivalent
4 Typist TBN 2 8
5 Peon TBN 1 8
Total
Number of Land acquisition Teams
Grand Total for All Land acquisition Teams (A)
164
(Form-IV)
Total :
Total
3. Other Miscellaneous expenses (like DA, internal travel expenses other incidentals)
(fixed cost)
Lump Sum …….
165
TENTATIVE QUANTITIES FOR SUB-SOIL INVESTIGATIONS
2 For projects of length > 110 km As per As per List As per As per 2000 300
- <Details of List at at Annex-1 List at List at
packages> Annex- Annex-1 Annex-
1 1
166
Appendix-V
The sole applicant firm shall satisfy the following 3 (Three) Nos. of criteria.
(a) & (b) Firm should have experience of preparation of DPR/Feasibility of 4/6 lane of
aggregate length as given below. The firm should have also prepared DPR/Feasibility of at
least one project of 4/6 laning of minimum length as indicated below in the last 7 years
(i.e. from 2011-12 onwards)
Note: Similar project means 2/4/6 lane as applicable for the project for which RFP is
invited. For 2-lane projects experience of 4/6 lane also to be considered with a
multiplication factor of 1.5. Experience of 4/6 lane shall be considered interchangeably
for 4/6 laning projects. For 4/6 laning projects, experience of 2 lane will be considered
with a multiplication factor of 0.4, but only for those 2 lane projects whose cost of
consultancy services was more than Rs.1.0 crore
(c) Annual Average Turn Over for the last 5 years {In cases where, Audited/Certified copy
of Balance Sheet for the FY 2017-18 is available, last five years shall be counted from
2013-14 to 2017-18. However, where audited/certified copy of the Balance Sheet for
the FY 2016-17 is not available (as certified by the Statutory auditor) then in such cases
last five years shall be considered from 2012-13 to 2016-17} of the firm from Consultancy
services should be equal to more than Rs.5 crore.
In case of JV, the Lead Partner should fulfill at least 75% of all eligibility requirements and
the other partner shall fulfill at least 50% of all eligibility requirements as given at 1.1
above. Thus a Firm applying as Lead Partner/Other Partner in case of JV/Associate should
satisfy the following
(a) & (b) Firm should have experience of preparation of DPR/Feasibility of 4/6 lane
of aggregate length as given below. The firm should have also prepared DPR/Feasibility of
at least one project of 4/6 laning of minimum length as indicated below in the last 7
years (i.e. from 2011-12 onwards)
167
S. Package No. Minimum Aggregate Minimum length of a Eligible Project (4/ 6 lane)
No. Length required of
DPR/ Feasibility km)
DPR Feasibility
c ) Minimum Annual Average Turn Over for the last 5 years { In cases where,
Audited/Certified copy of Balance Sheet for the FY 2017-18 is available, last five years
shall be counted from 2013-14 to 2017-18. However, where audited/certified copy of the
Balance Sheet for the FY 2017-18 is not available (as certified by the Statutory auditor)
then in such cases last five years shall be considered from 2012-13 to 2016-17} of a
firm applying as Lead Partner/Other Partner in case of JV from Consultancy services
should be as given below:
No. Mode of Submission by a firm Annual Average Turn Over for the last 5 years
No. Status of the firm in carrying out DPR/ Feasibility Study Weightage for experience
168
2. Second Stage Evaluation -Technical Evaluation(Para 12.2 of Data Sheet)
169
For special projects such as special bridges, tunnels and expressways that require
specialized capabilities and skill sets, the following is the break-up:
1.1.3 More than 3 times the indicative length of the package applied for 7
1.2 DPR for 2/4/6 laning projects each equal to or more than 40 % 7
of indicative length of a package applied for (or Feasibility
Study for 2/4/6 laning projects each equal to or more than 60
% of indicative length of a package applied for)
1.2.1 1 project 4
1.2.2 2 projects 6
1.2.3 3 or more projects 7
2 DPR of Bridge having length more than 200 m 3
2.1 1 bridge 1
2.2 2 bridges 2
2.3 3 or more bridges 3
3 Specific experience of firms in terms of turnover 3
3.1 Firm’s Average Turnover of last 5 years > 50 crore 3
3.2 Firm Average Turnover of last 5 years, –20-50 crore 2.5
3.3 Firm Average Turnover of last 5 years, 5 – 20 crore 2
4 DPR for special category projects (Special bridges/ tunnels or
expressways, whichever applicable). It is to be noted that
either 4.1 or 4.2 shall be applicable, and not both.
4.1 DPR of number of special bridges/ tunnels (if applicable) 5
4.1.1 1 project 1
4.1.2 2 projects 2
4.1.3 3 projects 3
4.1.4 4 projects 4
4.1.5 5 or more projects 5
4.2 Aggregate length of DPR/ Feasibility study for expressways 5
170
S. Description Maximum Sub-Points
No. Points
4.2.1 Upto 50km 2
4.2.2 50km to 100km 3
4.2.3 100km to 150km 4
4.2.4 More than 150 km 5
Note:
A. In case feasibility study is a part of DPR services the experience shall be counted in
DPR only. In case bridge is included as part of DPR of highway the experience will be (1)
and (2)
B. Similar project means 2/4/6 lane as applicable for the project for which RFP is
invited. For 2-lane projects experience of 4/6 lane also to be considered with a
multiplication factor of 1.5. Experience of 4/6 lane shall be considered interchangeably
for 4/6 laning projects. For 4/6 laning projects, experience of 2 lane will be considered
with a multiplication factor of 0.4, but only for those 2 lane projects whose cost of
consultancy services was more than Rs.1.0 crore
Note: (i) Weightage to be given when experience by a Firm as Sole Firm/Lead Partner
in a JV/Other Partner in a JV/As Associate
3 Other partner in a JV 50 %
4 As Associate 25%
S. No Description Points
1 Site appreciation 1
2 Team composition and task assignment 1
171
3 Methodology 3
Approach and initial view on project plan including key
3.1
challenges envisaged and potential solutions for
Proposed alignment and bypasses required and land acquisition
3.1.1 1
requirements
3.1.2 Access control, rehabilitation of existing road, drainage and utilities 1
Adoption of superior technology along with proof of past use
3.2 1
vendor association
Total 5
C Material testing, survey and investigation, equipment and software
proposed to be used (20)
172
S. Description Maximum Sub-Points
No. Points
5.3 >5 projects 4
6 Experience in digitization of cadastral maps for land surveys 3
6.1 Project of area upto 100 ha 1
6.2 Project of area between 100-500 ha 2
6.3 Project of area between 500 ha 3
Note: The experience of firm in LiDar or equivalent technology, GPR and Induction Locator
or equivalent technologies and Experience in digitization of cadastral maps for land
acquisition shall be supported by experience certificate. The experience of a firm in LiDar
or equivalent technology, GPR and Induction Locator or equivalent technologies and
Experience in digitization of cadastral maps for land acquisition for a private
concessionaire/contractor shall be considered only if the experience certificate is
authenticated by the concerned competent Government department/authority
2.4. Qualification and Competence of the Key Staff for adequacy of the
Assignment. (Para 12.2 of Data Sheet and Enclosure II of TOR)
< 12 years 0
12-15 years 18
15-18 years 22
>18 years 25
c) Experience in Similar Capacity 30
173
(i) In Feasibility of 2/4/6 laning works or DPR/IC/Construction Supervision 20
of major highway projects i.e. 2/4/6 laning of NH/SH/Expressways in
Similar Capacity ( Minimum Aggregate length of 80 km )
< 80km 0
80 km-150km 14
150km-250km 17
> 250km 20
(ii) In Feasibility of 2/4/6 laning works or DPR/IC/Construction Supervision 10
of major highway projects i.e. 2/4/6 laning of NH/SH/Expressways in
Similar Capacity- Number of Projects
< 2 projects 0
2 projects 8
3- 5 projects 9
More than 5 projects 10
III Employment with Firm 5
174
2.4.2 HIGHWAY cum PAVEMENT ENGINEER
175
2.4.3 SENIOR BRIDGE ENGINEER
176
2.4.4 Traffic / Road Signage / Marking and Safety Expert
177
2.4.5 MATERIAL ENGINEER cum GEOTECHNICAL ENGINEER cum GEOLOGIST
I General Qualification 25
i) Degree in Civil Engineering /M. Sc. in Geology[AICTE Approved] 20
ii) Post graduation in Foundation Engineering / Soil Mechanics / Geo Tech 5
Engineering
II Relevant Experience & Adequacy for the Project 70
a) Total Professional Experience 15
<10 years 0
10-12 years 11
12-15 years 13
>15 years 15
b) Experience in Highway Projects – In Similar Projects (2/4/6 laning 25
of NH/SH/Expressways) in design and or Construction/ Construction
Supervision
<7 years 0
7-10 years 18
10 -12 years 22
>12years 25
c) Experience as Material cum Geo-technical Engineer or in Similar 30
capacity on Highway Projects (2/4/6 laning of NH/SH/Expressways) (Minimum
aggregate length 80 km)
<80km 0
80km-150km 24
150km – 250km 27
>250km 30
III Employment with Firm 5
178
1.4.6 SENIOR SURVEY ENGINEER
<80km 0
80km-150km 24
150km-250km 27
>250km 30
III Employment with Firm 5
179
2.4.7 ENVIRONMENTAL SPECIALIST
<5 years 0
5 -7 years 18
7-10 years 22
>10 years 25
c) Experience as Environmental Specialist or in Similar Capacity in Highway 30
Projects(2/4/6 laning of NH/SH/Expressways)
<2 projects 0
2- 4 projects 24
5-7 projects 27
>7 projects 30
III Employment with Firm 5
180
2.4.8 QUANTITY SURVEYOR/DOCUMENTATION EXPERT
181
2.4.9 LAND ACQUISITION EXPERT
Nil project 0
1 project 18
2 projects 22
3 projects 25
d) Retired Revenue officer at the level of ADM/SDM / Tehsildar 10
III Employment with Firm 5
Less than 1 Year 0
1-2 years 2.5
more than 2 years 5
Total 100
182
2.4.10 UTILITY EXPERT
<10 years 0
10-12 years 12
12-15 years 13
>15 years 15
b) Experience in Utility estimation and its laying/ erection 30
<8 years 0
8 -10 years 22
10-12 years 26
>12 years 30
c) Experience in Utility shifting estimation and its laying/ erection along Highway/ roads 25
Nil project 0
1 project 15
2 projects 20
3 projects 25
III Employment with Firm 5
183
Assumptions to be made regarding Similar Capacity for various
positions
184
5. Traffic and Safety Expert
7. Environmental Specialist
Note: While carrying out evaluation of key personnel, the experience in similar capacity
is also a criteria of evaluation and assumptions to be made regarding similar capacity have
been mentioned above. However, if a key personnel has worked in next lower category to
the similar capacity, the marks allotted to key personnel in the category ‘experience in
similar capacity’ shall be reduced to two thirds of marks in this category. This shall be
applicable for evaluation of all key personnel.
186
Appendix VI
Between
And
For
<Project Discription>
187
CONTENTS
1. General Provisions
1.1 Definitions
1.2 Relation between the Parties
1.3 Law Governing the Contract
1.4 Language
1.5 Headings
1.6 Notices
1.7 Location
1.8 Authority of Member in Charge
1.9 Authorized Representatives
1.10 Taxes and Duties
4. Consultants’ Personnel
4.1 General
4.2 Description of Personnel
4.3 Approval of Personnel
4.4 Working Hours, Overtime, Leave etc.
4.5 Removal and/or Replacement of Personnel
4.6 Resident Project Manager
9. SETTLEMENT OF DISPUTES
9.1 Amicable Settlement
9.2 Dispute Settlement
189
III. SPECIAL CONDITIONS OF CONTRACT
IV. APPENDICES
Appendix A: Terms of reference containing, inter-alia, the Description of the
Services and Reporting Requirements
190
DRAFT CONTRACT FOR CONSULTANT’S SERVICES
191
CONTRACT FOR CONSULTANTS’ SERVICES
Consultancy Services for Request for engagement of DPR consultant for 4-laning of
Palwal-Tappal-Aligarh section of NH-334D in the state of Uttar Pradesh.
This CONTRACT (hereinafter called the “Contract”) is made on the ----------- day of the
month of----------------- 2015 , between, on the one hand, National Highways Authority of
India (NHAI), New Delhi (hereinafter called the “Client”) and,
on the other hand,M/s ------------------------------------------ in JV with ---------------------
------------- and in Association with ................................... (hereinafter called the
“Consultants”).
WHEREAS
(A) the Client has requested the Consultants to provide certain consulting services as
defined in the General Conditions attached to this Contract (hereinafter called the
“Services”);
(B) the Consultants, having represented to the Client that they have the required
professional skills, personnel and technical resources, have agreed to provide
the Services on the terms and conditions set forth in this Contract;
1 The following documents attached hereto shall be deemed to form an integral part
of this Contract:
Appendix A: Terms of reference containing, inter-alia, the Description of the Services and
Reporting Requirements
Appendix B: Consultants’ Sub consultants, Key Personnel and Sub Professional Personnel,
Task assignment, work programme, manning schedule, qualification
requirements of key personnel, and schedule for submission of various
report.
192
Appendix H: Copy of Bank Guarantee for Performance Security
2. The mutual rights and obligations of the Client and the Consultants shall be as set
forth in the Contract; in particular:
(a) The Consultants shall carry out the Services in accordance with the provisions of
the Contract; and
(b) Client shall make payments to the Consultants in accordance with the provisions
of the Contract.
IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed in their
respective names as of the day and year first above written.
1. Signature Name
Address
By
Authorized Representative 2. Signature Name
Address
1. Signature
Name
Address
By
Authorized Representative 2. Signature Name
Address
193
GENERAL CONDITIONS OF CONTRACT
194
GENERAL CONDITIONS OF CONTRACT
1. GENERAL PROVISIONS
1.1 Definitions
Unless the context otherwise requires, the following terms whenever used in this
Contract have the following meanings:
(a) “Applicable Law means the laws and any other instruments having the force of
lawin the Government’s country as they may be issued and in force from time to
time;
(b) “Contract” means the Contract signed by the Parties, to which these
General Conditions of Contract are attached, together with all the documents
listed in Clause 1 of such signed Contract;
(c) “Effective Date” means the date on which this Contract comes into force and effect
pursuant to Clause GC 2.1;
(d) “foreign currency” means any currency other than the currency of the
Government;
(i) “Personnel” means persons hired by the Consultants or by any Sub consultant as
employees and assigned to the performance of the Services or any part thereof;
“foreign Personnel” means such persons who at the time of being so hired had their
domicile outside India; and “local Personnel” means such persons who at the time
of being so hired had their domicile inside India;
(j) “Party” means the Client or the Consultants, as the case may be, and Parties means
both of them;
(k) “Services” means the work to be performed by the Consultants pursuant to this
Contract for the purposes of the Project, as described in Appendix A hereto;
(l) “SC” means the Special Conditions of Contract by which these General Conditions
of Contract may be amended or supplemented;
195
(m) “Sub consultant” means any entity to which the Consultants subcontract any part
of the Services in accordance with the provisions of Clause GC 3.7; and
(n) “Third Party” means any person or entity other than the Government, the Client,
the Consultants or a Sub consultant.
1.4 Language
This Contract has been executed in the language specified in the SC, which shall be the
binding and controlling language for all matters relating to the meaning or interpretation
of this Contract.
1.6 Notices
1.6.1 Any notice, request or consent required or permitted to be given or made pursuant
to this Contract shall be in writing. Any such notice, request or consent shall be deemed
to have been given or made when delivered in person to an authorized representative of
the Party to whom the communication is addressed, or when sent by registered mail,
facsimile or e-mail to such Party at the address specified in the SC.
1.6.3 A party may change its address for notice hereunder by giving the other Party
notice of such change pursuant to the provisions listed in the SC with respect to Clause GC
1.6.2.
1.7 Location
The Services shall be performed at such locations as are specified in Letter of Acceptance
(Appendix-I) hereto and, where the location of a particular task is not so specified, at such
locations, whether in India or elsewhere, as the Client may approve.
2.6 Modification
Modification of the terms and conditions of this Contract, including any modification of the
scope of the Services, may only be made by written agreement between the Parties.
Pursuant to Clause GC 8.2 hereof, however, each party shall give due consideration to any
proposals for modification made by the other Party.
197
2.7 Force Majeure
2.7.1 Definition
(a) For the purposes of this Contract, “Force Majeure” means an event which is beyond
the reasonable control of a Party, and which makes a Party’s performance of its
obligations hereunder impossible or so impractical as reasonably to be considered
impossible in the circumstances, and includes, but is not limited to, war, riots, civil
disorder, earthquake, fire, explosion, storm, flood or other adverse weather
conditions, strikes, lockouts or other industrial action (except where such strikes,
lockouts or other industrial action are within the power of the Party invoking Force
Majeure to prevent), confiscation or any other action by government agencies.
(b) Force Majeure shall not include (i) any event which is caused by the negligence or
intentional action of a Party or such Party’s Sub consultants or agents or employees,
nor (ii) any event which a diligent Party could reasonably have been expected to
both (A) take into account at the time of the conclusion of this Contract and (B)
avoid or overcome in the carrying out of its obligations hereunder.
(c) Force Majeure shall not include insufficiency of funds or failure to make any
payment required hereunder.
(b) A party affected by an event of Force Majuere shall notify the other Party of such
event as soon as possible, and in any event not later than fourteen (14) days
following the occurrence of such event, providing evidence of the nature and
cause of such event, and shall similarly give notice of the restoration of normal
conditions as soon as possible.
(c) The Parties shall take all reasonable measures to minimize the consequences of any
event of Force Majeure.
2.7.5 Payments
During the period of their inability to perform the Services as a result of an event of Force
Majeure, the Consultants shall be entitled to be reimbursed for additional costs reasonably
and necessarily incurred by them during such period for the purposes of the Services and
in reactivating the Services after the end of such period.
198
2.7.6 Consultation
Not later than thirty (30) days after the Consultants, as the result of an event of Force
Majeure, have become unable to perform a material portion of the Services, the Parties
shall consult with each other with a view to agreeing on appropriate measures to be taken
in the circumstances.
2.8 Suspension
The Client may, by written notice of suspension to the Consultants, suspend all payments
to the Consultants hereunder if the Consultants fail to perform any of their obligations
under this Contract, including the carrying out of the Services, provided that such notice
of suspension (i) shall specify the nature of the failure, and (ii) shall request the Consultants
to remedy such failure within a period not exceeding thirty (30) days after receipt by the
Consultants of such notice of suspension.
2.9 Termination
2.9.1 By the Client
The Client may, by not less than thirty (30) days’ written notice of termination to the
Consultants (except in the event listed in paragraph (f) below, for which there shall be a
written notice of not less than sixty (60) days), such notice to be given after
the occurrence of any of the events specified in paragraphs (a) through (f) of this
Clause2.9.1, terminate this Contract:
(a) if the Consultants fail to remedy a failure in the performance of their obligations
are under, as specified in a notice of suspension pursuant to Clause 2.8 hereinabove,
within thirty (30) days of receipt of such notice of suspension or within such further
period as the Client may have subsequently approved in writing;
(b) if the Consultants become (or, if the Consultants consist of more than one entity, if
any of their Members becomes) insolvent or bankrupt or enter into any agreements
with their creditors for relief of debt or take advantage of any law for the benefit
of debtors or go into liquidation or receivership whether compulsory or voluntary;
(c) if the Consultants fail to comply with any final decision reached as a result of
arbitration proceedings pursuant to Clause 8 hereof;
(d) if the Consultants submit to the Client a statement which has a material effect on
the rights, obligations or interests of the Client and which the Consultants know to
be false;
(e) if, as the result of Force Majeure, the Consultants are unable to perform
a material portion of the Services for a period of not less than sixty (60) days; or
(f) if the Client, in its sole discretion and for any reason whatsoever, decides
to terminate this Contract.
200
3. OBLIGATIONS OF THE CONSULTANTS
3.1 General
(a) during the term of this Contract, any business or professional activities in the
Government's country which would conflict with the activities assigned to them under this
Contract; or
201
(b) after the termination of this Contract, such other activities as may be specified in the
SC.
3.3 Confidentiality
The Consultants, their Sub consultants and the Personnel of either of them shall not,
either during the term or within two (2) years after the expiration of this
Contract, disclose any proprietary or confidential information relation to the Project, the
Services, this Contract or the Client's business or operations without the prior written
consent of the Client.
202
3.9 Documents prepared by the Consultants to be the Property of the Client
All plans, drawings, specifications, designs, reports and other documents prepared by the
Consultants in performing the Services shall become and remain the property of the Client,
and the Consultants shall, not later than upon termination or expiration of this Contract,
deliver all such documents to the Client, together with a detailed inventory thereof. The
Consultants may retain a copy of such documents. Restrictions about the future use of
these documents, shall be as specified in the SC.
4. CONSULTANTS' PERSONNEL
4.1 General
The Consultants shall employ and provide such qualified and experienced Personnel as are
required to carry out the Services.
(b) If required to comply with the provisions of Clause 3.1.1 of this Contract, adjustments
with respect to the estimated periods of engagement of Key Professional / Sub Professional
Personnel set forth in Appendix B may be made by the Consultants by written notice to
the Client, provided
(i) that such adjustments shall not alter the originally estimated period of engagement of
any individual by more than 10% or one week, whichever is larger, and
(ii) that the aggregate of such adjustments shall not cause payments under this Contract
to exceed the ceilings set forth in Clause 6.1 (b) of this Contract. Any other such
adjustments shall only be made with the Client's written approval.
(c) If additional work is required beyond the scope of the Services specified in Appendix
A, the estimated periods of engagement of Key Personnel set forth in Appendix B may be
increased by agreement in writing between the Client and the Consultants.
(b) The Key Professional / Sub Professional Personnel shall not be entitled to be paid for
overtime nor to take paid sick leave or vacation leave except as specified in Appendix C
hereto, and except as specified in such Appendix, the Consultants' remuneration shall
be deemed to cover these items. All leave to be allowed to the Personnel is included in
the staff- months of service set for in Appendix B. Any taking of leave by Personnel shall
be subject to the prior approval of the Client by the Consultants, who shall ensure
that absence for leave purposes will not delay the progress and adequate supervision of
the Services.
4.5.1 In case notice to commence services pursuant to Clause 2.1 of this Contract is not
ordered by Client within 120 days of signing of contract the key personnel can excuse
themselves on valid grounds, e.g., selection on some other assignment, health problem
developed after signing of contract, etc. In such a case no penalty shall be levied on the
Firm or on the person concerned. The firm shall however be asked to give a replacement
by an equal or better scoring person, whenever mobilization is ordered.
4.5.2 In case notice to commence services is given within 120 days of signing
of contract the replacement shall be as below:
204
4.5.4 If the Employer (i) finds that any of the Personnel has committed serious
misconduct or has been charged with having committed a criminal action or (ii) has
reasonable ground to be dissatisfied with the performance of any of the Personnel, then
the consultant shall, at the Employer’s written request specifying the grounds
therefore, forthwith provide a replacement with qualifications and experience acceptable
to him.
4.5.5 If the team leader or any other key personnel/ specialist considered pivotal to
the project is replaced, the substitute may be interviewed by NHAI to assess their merit
and suitability.
4.5.6 If any member of the approved team of a consultant engaged by NHAI leaves
that consultant before completion of the job, he shall be barred for a period of 6 months
to 24 months from being engaged as a team member of any other consultant working
(or to be appointed) for any other NHAI/ MoRTH projects.
i) The new proposed personnel as a replacement has to be evaluated as per the criteria
fixed at the time of evaluation of original proposal and marks/rating and then:
-If the original personnel (included in the original proposal based on which the contract
was awarded) is to be replaced at the instruction of NHAI and the new proposed personnel
is having less qualification/ experience i.e marks/rating (but fulfilling the minimum
requirement as per TOR), his remuneration would be reduced by 15% over and above the
stipulated conditions in the contract because of less qualified personnel
It will be ensured that the new proposed personnel should score at least 75% of the marks
of the originally approved key personnel. Both the Consulting firm and the proposed
personnel should give the undertaking in the format available in Form VII of Appendix II
along with the replacement CV.
ii) The CV should be signed by personnel and the consulting firm in every page. If the CV
is found incorrect at later date, the personnel accepted would be removed from the
assignment and debarred from further NHAI/ MoRTH works for an appropriate period to
be decided by NHAI and the new proposed personnel in place of removed personnel would
be paid 15% less salary than the original personnel. 15% reduction in the salary will be
imposed as penalty for submitting the incorrect information. This penalty will be imposed
only once. If the same consulting firm submits incorrect information again second time,
necessary action will be taken by NHAI to blacklist the firm.
205
4.6 Resident Project Manager
If required by the SC, the Consultants shall ensure that at all times during the Consultants'
performance of the Services in the Government's country a resident project manager,
acceptable to the Client, shall take charge of the performance of such Services.
(b) assist for the Personnel and, if appropriate, their eligible dependents to be provided
promptly with all supporting papers for necessary entry and exit visas, residence permits,
exchange permits and any other documents required for their stay in India;
(c) facilitate prompt clearance through customs of any property required for the Services;
(d) issue to officials, agents and representatives of the Government all such instructions
as may be necessary or appropriate for the prompt and effective implementation of the
Services;
206
5.5 Payment
In consideration of the Services performed by the Consultants under this Contract, the Client
shall make to the Consultants such payments and in such manner as is provided by Clause 6 of
this Contract.
(a) An abstract of the cost of the Services payable in local currency (Indian Rupees) is set forth
in Appendix E.
(b) Except as may be otherwise agreed under Clause 2.6 and subject to Clause 6.1(c), the
payments under this Contract shall not exceed the ceiling specified in the SC. The Consultants
shall notify the Client as soon as cumulative charges incurred for the Services have reached
80% of the ceiling.
(c) Notwithstanding Clause 6.1(b) hereof, if pursuant to Clauses 5.4 hereof, the Parties shall
agree that additional payments shall be made to the Consultants in order to cover any
necessary additional expenditures not envisaged in the cost estimates referred to in Clause
6.1(a) above, the ceiling set forth in Clause 6.1(b) above shall be increased by the amount or
amounts, as the case may be, of any such additional payments.
(a) The Client shall cause to be paid to the Consultants an advance payment as specified in the
SC, and as otherwise set forth below. The advance payment will be due after provision by the
Consultants to the Client of a bank guarantee by a bank acceptable to the Client in an amount
(or amounts) and in a currency (or currencies) specified in the SC, such bank guarantee (i) to
remain effective until the advance payment has been fully set off as provided in the SC, and
ii) in such form as the Client shall have approved in writing.
207
(b) Payment Schedule
The Consultant will be paid stage-wise as a percentage of the contract value as per the
schedule given below:
S. No Item Payment %
1 Submission of final QAP and Inception Report 10%
2 Approval of final Alignment Report 5%
3 Submission of final feasibility Report 5%
4 Submission Of 3a Notification, Draft 3 A And Approval Of Final Land 5%
Acquisition Report containing details of 3a, 3A
5 Submission of all utilities shifting proposals to user agencies and 2.5%
submission of utilities relocation plan to NHAI
6 Submission of all stage I clearance proposals and submission of 5%
clearances repot to NHAI
7 Approval of final DPR report, documents and drawings 10%
8 Approval of bid documents and draft civil works contract agreement along 5%
with technical schedules.
9 3D publication for all land parcels identified in item 4 above and submission 10%
of Land Acquisition II report
10 Stage II clearance approval and submission of final clearances II report 5%
11 Final approval of utilities shifting estimates and submission of Utilities II 2.5%
report
12 Completion of award declaration (3G) for 90% of land parcels identified in 10%
item 9 and submission of Land Award report
13 Earlier of award of package to contractor/concessionaire or 6 months from 10%
launch of tender process
14 Receipt of land possession certificates (3E) for 90% of all land parcels 10%
identified in LA II report and submission of Land Possession report
15 Amount to be released at earlier of projects COD or 3 years from start of 5%
civil work
Total : 100%
16 Bonus on submission of draft 3A within 15 days of alignment finalization 1 % bonus
17 Bonus on submission of draft 3D within 60 days of draft 3 A. 2.5% bonus
18 Bonus on receipt of possession certificate (3E) for more than 90% of land 5% bonus
identified in item 9 above within 165 days of draft 3 A.
19 Bonus on submission of utility shifting proposal including clearance within 1% bonus
60 days of alignment finalization.
Note: Consultants have to provide a certificate that all key personnel as envisaged in the
Contract Agreement has been actually deployed in the project. They have to submit this
certificate at the time of submission of bills to NHAI from time to time.
* The Concerned Project Director or his authorized representative shall ensure and
certify at least 5% test check of all the data collected by the Consultant before releasing
the payment to the Consultant.
208
(c) No payment shall become eligible for the next stage till the consultant completes to
the satisfaction of the client the work pertaining to the preceding stage. The payment
for the work of sub-soil investigation (Boring)will be as per plan approved by the client
and will be paid as per actual at the rates quoted by the consultants .The payment for
the quantity given by the client for boring will be deemed to be included in the above
mentioned payment schedule. Any adjustment in the payment to the consultants will be
made in the final payment only.
(d) The Client shall cause the payment of the Consultants in Para 6.4 (b) above as
given in schedule of payment within thirty (30) days after the receipt by the Client of
bills. Interests at the rate specified in the SC shall become payable as from the above due
date on any amount due by, but not paid on, such due date.
(e) The final payment under this Clause shall be made only after the final report and a
final statement, identified as such, shall have been submitted by the Consultants and
approved as satisfactory by the Client. The Services shall be deemed completed and
finally accepted by the Client and the final report and final statement shall be deemed
approved by the Client as satisfactory one hundred and eighty (180) calendar days after
receipt of the final report and final statement by the Client unless the Client, within
ninety(90) day period, gives written notice to the Consultants specifying in detailed
deficiencies in the Services, the final report or final statement. The Consultants shall
t h e r e u p o n p r o m p t l y make a n y necessary corrections, and upon completion of
such corrections, the foregoing process shall be repeated. Any amount which the Client
has paid or caused to be paid in accordance with this Clause in excess of the amounts
actually payable in accordance with the provisions of this Contract shall be reimbursed by
the Consultants to the Client within thirty (30) days after receipt by the Consultants of
notice thereof. Any such c l a i m by t h e C l i e n t f o r reimbursement must be made
within twelve (12) calendar months after receipt by the Client of a final report and a
final statement approved by the Client in accordance with the above.
(f) All payments under this Contract shall be made to the account of the Consultants
specified in the SC.
(g) Efforts need to be made by the Consultant to submit the schedule reports of each road
stretch / s of a package. However, due to reasons beyond the reasonable control of
Consultant, if the schedule submission of reports / documents of each road stretch /s of
a package is not done, the payment shall be made on pro-rata basis.
7.1 General
7.1.1 The Consultant shall be responsible for accuracy of the data collected, by him
directly or procured from other agencies/authorities, the designs, drawings, estimates
and all other details prepared by him as part of these services. He shall indemnify the
Authority against any inaccuracy in the work which might surface during implementation
of the project. The Consultant will also be responsible for correcting, at his own cost
and risk, the drawings including any re-survey / investigations and correcting layout
etc. if required during the execution of the Services.
209
7.1.2 The Consultant shall be fully responsible for the accuracy of design and drawings
of the bridges and structures. All the designs and drawings for bridges and structures
including all their components shall be fully checked by a Senior Engineer after completion
of the designs. All drawings for bridges and structures shall be duly signed by the (a)
Designer, (b) Senior Checking Engineer, and (c) Senior Bridge / Structure Expert. The
designs and drawings not signed by the three persons mentioned above shall not be
accepted. The Consultant shall indemnify the Client against any inaccuracy / deficiency
in the designs and drawings of the bridges and structures noticed during the construction
and even thereafter and the Client shall bear no responsibility for the accuracy of the
designs and drawings submitted by the Consultants.
7.1.3 The survey control points established by the Consultant shall be protected bythe
Consultants till the completion of the Consultancy Services.
7.3. Penalty
ii. If there is a discrepancy in land to be acquired during the execution of the project
upto an extent of +/- 5% of the area of land, a penalty equivalent to 3% of the contract
value shall be imposed. For this purpose retention money equivalent to 3% of the contract
value will be forfeited. This shall exclude any additional/deletion of items/works ordered
by the client during the execution
iii. If there is a variation in utilities shifting payments to be made during the execution
of the project upto an extent of +/- 10% of the value estimated by the design consultant,
a penalty equivalent to 3% of the contract value shall be imposed. For this purpose
retention money equivalent to 3% of the contract value will be forfeited. This shall exclude
any additional/deletion of items/works ordered by the client during the execution
210
Sr. Item Penalty (%age of
No. contract value)
Topographic Surveys 0.5 to 1.0
a) The horizontal alignment does not match with ground condition.
7.3.3 Total amount of recovery from all penalties shall be limited to 15% of the
Consultancy Fee.
7.3.4 NHAI is in process of evolving performance based rating system for DPR
Consultants. Performance of Consultants shall be monitored by NHAI and will be taken into
account in technical evaluation of future DPR projects. For this purpose, performance of
Consultant in the current project shall also be taken into account to create rating of
Consultant.
9. SETTLEMENT OF DISPUTES
ii) The Consultancy fee shall be revised on account of change of scope as below:
212
- In case the total length of project increase/ decrease up to 10% of
indicative length given in the RFP: No change in Consultancy Fees.
- In case the increase/ decrease in total length of project is more than 10
% of the indicative length as given in the RFP: The consultancy fee shall be
increased/ decreased in the same proportion in which the length of the
project road is increased/ decreased beyond 10% .
10.1 The Consultancy fee shall be increased on account of change of scope as below:
a) In case of Lanes increase in the project after the submission of Final Report: 10%
of the original consultancy charges
b) In case of change of mode of delivery is involved after submission of Final Report /
due to revision of specifications / IRC Codes etc.
(i) Revision of DPR after submission due to changes in IRC 2.5% of the original Consultancy
codes / specification etc. charges.
(ii) Revision of DPR due to changes in mode EPC / BOT / HAM 2.5% of the original Consultancy
etc charges.
213
SPECIAL CONDITIONS OF CONTRACT
Number of GC Clause
1.1(a) The words “in the Government’s country” are amended to read “in INDIA”
E-mail: arunjagga@nhai.org
Attention: Name
Designation
Address
Tel: Fax: E-mail address
1.8 Entity to Act as Member in charge (In case of Joint Venture of Consultants) with
or without an Associate: - ………………………..
1.10 The Consultants and the personnel shall pay the taxes, duties, fees, levies and
other impositions levied under the existing, amended or enacted laws (prevailing 7 days
before the last date of submission of bids) during life of this contract and the Client shall
perform such duties in regard to the deduction of such tax as may be lawfully imposed.
214
2.1 The effectiveness conditions are the following:
2.2 The time period shall be“four months” or such other time period as the parties
may agree in writing.
2.3 The time period shall be “fifteen days” or such other time period as the Parties
may agree in writing.
2.4 The time period shall be -------months or such other time period as the parties
may agree in writing.
(a) Except in case of negligence or willful misconduct on the part of the Consultants or
on the part of any person or firm acting on behalf of the Consultants in carrying out the
Services, the Consultants, with respect to damage caused by the Consultants to the
Client’s property, shall not be liable to the Client:
(b) This limitation of liability shall not affect the Consultants’ liability, if
any, for damage to Third Parties caused by the Consultants or any person or firm acting
on behalf of the Consultants in carrying out the Services.
215
(c) (i) The Consultant shall provide to NHAI Professional Liability Insurance (PLI) for
a period of Five years beyond completion of Consultancy services or as per Applicable
Law, whichever is higher.
(ii) The Consultant will maintain at its expense PLI including coverage for errors and
omissions caused by Consultant’s negligence in the performance of its duties under this
agreement, (A) For the amount not exceeding total payments for Professional Fees and
Reimbursable Expenditures made or expected to be made to the Consultants
hereunder OR (B) the proceeds, the Consultants may be entitled to receive from any
insurance maintained by the Consultants to cover such a liability, whichever of (A) or
(B) is higher.
iii) The policy should be issued only from an Insurance Company operating in India.
iv) The policy must clearly indicate the limit of indemnity in terms of “Any One
Accident” (AOA) and “Aggregate limit on the policy” (AOP) and in no case should be for
an amount less than stated in the contract.
v) If the Consultant enters into an agreement with NHAI in a joint venture or ‘in
association’, the policy must be procured and provided to NHAI by the joint venture/in
association entity and not by the individual partners of the joint venture/ association.
vi) The contract may include a provision thereby the Consultant does not cancel the
policy midterm without the consent of NHAI. The insurance company may provide an
undertaking in this regard.
3.9 The Consultants shall not use these documents for purposes unrelated to this
Contract without the prior written approval of the Client.
4.6 The person designated as Team Leader cum Senior Highway Engineer in
Appendix B shall serve in that capacity, as specified in Clause 4.6.
6.1 (b) The ceiling amount in local currency is Rs……… Excluding Goods & Service Tax)
9.2 Disputes shall be settled by arbitration in accordance with the following provisions:
216
9.2.1 Selection of Arbitrators
9.2.5 Miscellaneous
In any arbitration proceeding hereunder:
(a) Proceedings shall, unless otherwise agreed by the parties be held in Delhi.
(b) The English language shall be the official language for all purposes;
(c) The decision of sole arbitrator shall be final and binding and shall be
enforceable in any court of competent jurisdiction, and the Parties hereby
waive any objections to or claims of immunity in respect of such
enforcement; and
Or
Or
3. Secretarial Rs.20,000/-
Assistance and
Incidental Charges
(telephone, fax,
postage etc.)
218
7. Extra charges for Rs.5,000/- per day for outstation Arbitrator
days other than
hearing / meeting
days (maximum for
2 days)
Note: 1. Lodging, boarding and travelling expenses shall be allowed only for
those members who are residing 100 kms. away from place of
meeting.
219
Appendix A
Terms of reference containing, inter-alia, the Description of the Services and Reporting
Requirements
220
Appendix B
Consultants’ Sub consultants, Key Personnel and Sub Professional Personnel
221
Appendix C
The Consultant’s personnel shall normally work for 8 hours in a day and six days a week.
Normally Sundays shall be closed for working. In addition they shall also be allowed to
avail holidays as observed by the Client’s office in the relevant state without deduction
of remunerations. In case any person is required to work on Sunday or Holiday due to
exigency of work, he/she shall be given compensatory leave within the next 15 days.
222
Appendix D
223
Appendix E
Cost Estimate
224
Appendix F: Copy of letter of invitation
225
Appendix G: Copy of letter of acceptance
226
Appendix – H (I)
Format for Bank Guarantee for Performance Security (For individual work)
BANK GUARANTEE FOR PERFORMANCE SECURITY
To,
Chairman
National Highways Authority of India,
G-5&6, Sector-10,
Dwarka, New Delhi-110075
The Client shall have the fullest liberty without affecting in any way the liability of
the Bank under this Guarantee, from time to time to vary or to extend the time for
performance of the contract by the Consultant. The Client shall have the fullest liberty
without affecting this guarantee, to postpone from time to time the exercise of any
powers vested in them or of any right which they might have against the consultant and
to exercise the same at any time in any manner, and either to enforce or to forbear to
enforce any covenants, contained or implied, in the Contract between the Client and the
Consultant any other course or remedy or security available to the Client. The bank shall
not be relieved of its obligations under these presents by any exercise by the Client
of its liberty with reference to the matters aforesaid or any of them or by reason of any
227
other act or forbearance or other acts of omission or commission on the part of the Client
or any other indulgence shown by the Client or by any other matter or thing whatsoever
which under law would but for this provision have the effect of relieving the Bank.
The Bank also agrees that the Client at its option shall be entitled to enforce this
Guarantee against the Bank as a principal debtor, in the first instance without proceeding
against the Consultant and notwithstanding any security or other guarantee that the Client
may have in relation to the Consultant’s liabilities.
c) We are liable to pay the guaranteed amount or any part thereof under this Bank
Guarantee only and only if you serve upon us a written claim or demand on or before
……………(date of expiry of Guarantee).
NOTE:
(i) The bank guarantee(s) contains the name, designation and code number of the officer(s)
signing the guarantee(s).
(ii) The address, telephone no. and other details of the Head Office of the Bank as well as
of issuing branch should be mentioned on the covering letter of issuing Branch.
(iii) The bank guarantee for Rs 10,000 and above is signed by at least two officials (or as
per the norms prescribed by the RBI in this regard).
228
Appendix H (2):
The Employer shall have the fullest liberty without affecting in any way the liability of the
Bank under this Guarantee, from time to time to vary or to extend the time for performance
of the contracts by the Consultancy firm. The Employer shall have the fullest liberty
without affecting this guarantee, to postpone from time to time the exercise of any powers
vested in them or of any right which they might have against the consultant and to exercise
the same at any time in any manner, and either to enforce or to forbear to enforce any
covenants, contained or implied, in the Contract between the Employer and the
Consultancy any other course or remedy or security available to the Employer. The bank
shall not be relieved of its obligations under these presents by any exercise by the Employer
of its liberty with reference to the matters aforesaid or any of them or by reason of any
other act or forbearance or other acts of omission or commission on the part of the
Employer or any other indulgence shown by the Employer or by any other matter or thing
229
whatsoever which under law would but for this provision have the effect of relieving the
Bank The Bank also agrees that the Employer at its option shall be entitled to enforce this
Guarantee against the Bank as a principal debtor, in the first instance without proceeding
against the Consultant and notwithstanding any security or other security or other
guarantee that the Employer may have in relation to the Consultant’s liabilities.
1. Our liability under this Omnibus Guarantee shall not exceed Rs…………….
(Rupees… ......... );
2. This Bank Guarantee shall be valid upto (Date (Month) Year); and (24 months).
3. We are liable to pay the guaranteed amount or any part thereof under this Bank
Guarantee if you serve upon us a written claim or demand on or before…” (24 months).
Thereafter, all your rights under this guarantee shall be forfeited and we shall be released
from all our liabilities hereunder irrespective of whether the guarantee in original is
returned to us or not.
*4. This guarantee shall also be operatable at our… branch at New Delhi, from whom,
confirmation regarding the issue of this guarantee or extension/renewal thereof shall be
made available on demand. In the contingency of this guarantee being invoked and
payment thereunder claimed, the said branch shall accept such invocation letter and make
payment of amount so demanded under the said invocation.
Address……………………… 2. ………………….
Date
*This clause shall be kept for Bank Guarantees being issued outside Delhi.
230
Appendix I: Minutes of Pre-bid meeting
231
APPENDIX-VII
General Details
Project Name
Consultant's Name
Date of Review
Details /
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
2 Project Appreciation Yes ☐ No ☐ NA ☐ NA
2.1 Location of site office Yes ☐ No ☐ NA ☐
Review of scope of ToR and gap
2.2 Yes ☐ No ☐ NA ☐ NA
identification
Key departments identified for various
2.3 documents Yes ☐ No ☐ NA ☐
Start and end location of project verified with
2.4 Yes ☐ No ☐ NA ☐
client (Mention details)
Project description
2.5 Start and End Chainage Yes ☐ No ☐ NA ☐
Village/District
Project location map
2.6 On State Map Yes ☐ No ☐ NA ☐ NA
On District Map
2.7 Site photos and data of project alignment Yes ☐ No ☐ NA ☐ NA
2.8 Overview of land use plans Yes ☐ No ☐ NA ☐ NA
Overview of existing pavement conditions
Number of Lanes
2.9 Yes ☐ No ☐ NA ☐
Type of Pavement
(Flexible/Rigid/Surfaced/ Unsurfaced)
2.10 Existing right of way details Yes ☐ No ☐ NA ☐
Number/ Location of major and minor
2.11
bridges Yes ☐ No ☐ NA ☐
Number/ Location of level crossings
2.12 Yes ☐ No ☐ NA ☐
2.13 Number/ Location of ROB and RUB Yes ☐ No ☐ NA ☐
2.14 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
3 Approach Methodology Yes ☐ No ☐ NA ☐ NA
3.1 Engineering survey and investigations Yes ☐ No ☐ NA ☐ NA
3.2 Design of road, pavements and structures Yes ☐ No ☐ NA ☐ NA
3.3 Environment and social impact assessment Yes ☐ No ☐ NA ☐ NA
Estimation of project cost, viability and
3.4 Yes ☐ No ☐ NA ☐ NA
financing options
232
Details /
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
3.5 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
4 Task Assignment and Manning Schedule Yes ☐ No ☐ NA ☐ NA
4.1 Number of key personnel provided Yes ☐ No ☐ NA ☐
Specific tasks assigned to each key
4.2 Yes ☐ No ☐ NA ☐ NA
personnel
4.3 Manning schedule for key personnel Yes ☐ No ☐ NA ☐ NA
4.4 Number of key personnel deployed at site Yes ☐ No ☐ NA ☐
5 Performa for data collection Yes ☐ No ☐ NA ☐ NA
Indicative design standards and cross
6
sections Yes ☐ No ☐ NA ☐ NA
7 Development plans Yes ☐ No ☐ NA ☐ NA
Overview of development plans being
7.1
implemented/ proposed by local bodies Yes ☐ No ☐ NA ☐ NA
Overview of impact of such development
7.2
plans Yes ☐ No ☐ NA ☐ NA
8 Quality Assurance Plan Yes ☐ No ☐ NA ☐ NA
8.1 Engineering surveys and investigation Yes ☐ No ☐ NA ☐ NA
8.2 Traffic surveys Yes ☐ No ☐ NA ☐ NA
Material geo-technical and sub-soil
8.3
investigations Yes ☐ No ☐ NA ☐ NA
8.4 Road and pavement investigations Yes ☐ No ☐ NA ☐ NA
Investigation and design of bridges and
8.5
structures Yes ☐ No ☐ NA ☐ NA
8.6 Environment and R&R assessment Yes ☐ No ☐ NA ☐ NA
8.7 Economic and financial analysis Yes ☐ No ☐ NA ☐ NA
8.8 Drawing and documentation Yes ☐ No ☐ NA ☐ NA
8.9 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Discussion of draft QAP document with
8.10 Yes ☐ No ☐ NA ☐ NA
client
8.11 Approval of final QAP document by client Yes ☐ No ☐ NA ☐ NA
9 Draft design Standards Yes ☐ No ☐ NA ☐ NA
Geometric design standards of highway
9.1 Yes ☐ No ☐ NA ☐ NA
(Plain)
Geometric design standards of highway
9.2
(Hilly) Yes ☐ No ☐ NA ☐ NA
10 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
10.1 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
Report fulfils project objectives and scope
10.2 Yes ☐ No ☐ NA ☐ NA
as per RFP
10.3 Report reviewed for errors and omissions Yes ☐ No ☐ NA ☐ NA
Compliance report prepared on client
10.4 Yes ☐ No ☐ NA ☐ NA
observations
233
DPR Checklist – Stage 2 – Feasibility Report (Pavements)
General Details
Project Name
Consultant's Name
Date of Review
Details /
S.No SECTION OF THE REPORT YES/ NO/ NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
Overview of client organization /
2
activities Yes ☐ No ☐ NA ☐ NA
Methodology adopted for feasibility
3 study Yes ☐ No ☐ NA ☐ NA
Socioeconomic profile of the project
4 Yes ☐ No ☐ NA ☐ NA
areas
Regional economic profile basis last 10
4.1 Yes ☐ No ☐ NA ☐ NA
years data as per IRC
Economic profile of project influence
4.2 Yes ☐ No ☐ NA ☐ NA
area basis last 10 years data as per IRC
Socio Economic status of project
4.3 influence area Yes ☐ No ☐ NA ☐ NA
Indicative design standards,
5 Yes ☐ No ☐ NA ☐ NA
methodologies, and specifications
6 Traffic surveys and analysis Yes ☐ No ☐ NA ☐ NA
Classified traffic volume counts using
6.1 Yes ☐ No ☐ NA ☐ NA
IHMCL data (7 day data)
Traffic projection methodology as per
6.2 Yes ☐ No ☐ NA ☐ NA
IRC:108
6.3 Projected Traffic data for 20 years Yes ☐ No ☐ NA ☐ NA
6.4 Current and Projected PCU Yes ☐ No ☐ NA ☐
6.5 Current and Projected TVU Yes ☐ No ☐ NA ☐
Origin destination surveys as per IRC:
6.6 Yes ☐ No ☐ NA ☐ NA
102
6.7 Speed and delay studies as per IRC:102 Yes ☐ No ☐ NA ☐ NA
Traffic surveys for the design of road
6.8
junctions as per data in IRC: SP:41 Yes ☐ No ☐ NA ☐ NA
Analysis for replacing railway level
6.9
crossings with over bridges/ subways Yes ☐ No ☐ NA ☐ NA
6.10 Axle load survey as per IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
6.11 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Traffic surveys monitored and reviewed
6.12 Yes ☐ No ☐ NA ☐ NA
by the client
7 Reconnaissance survey Yes ☐ No ☐ NA ☐ NA
7.1 Road Inventory Survey as per IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
Review of Road Inventory survey by
7.2 Yes ☐ No ☐ NA ☐ NA
client
234
Details /
S.No SECTION OF THE REPORT YES/ NO/ NA Remarks
Specifications
Chainage wise details of pavement
7.3
composition survey Yes ☐ No ☐ NA ☐ NA
Geological Survey
7.4 Geological Map of the Area Yes ☐ No ☐ NA ☐ NA
Seismicity
Climatic Conditions
Temperature
7.5 Yes ☐ No ☐ NA ☐ NA
Rainfall
Wind
Pavement composition and condition
7.6
survey as per IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
Review of pavement composition and
7.7 condition survey by client Yes ☐ No ☐ NA ☐ NA
Pavement roughness survey as per
7.8 Yes ☐ No ☐ NA ☐ NA
IRC:SP:16
Review of pavement roughness survey
7.9 by client Yes ☐ No ☐ NA ☐ NA
Pavement structural strength survey as
7.10
per IRC:81 Yes ☐ No ☐ NA ☐ NA
Review of pavement structural strength
7.11 survey by client Yes ☐ No ☐ NA ☐ NA
7.12 Sub grade characteristics and strengths Yes ☐ No ☐ NA ☐ NA
Topographical survey as per IRC:SP:19
using LiDAR
7.13 Yes ☐ No ☐ NA ☐ NA
Gradient
Terrain
7.14 Review of topographical survey by client Yes ☐ No ☐ NA ☐ NA
Inventory of bridges, culverts and
7.15 Yes ☐ No ☐ NA ☐ NA
structures
Condition survey for bridges, culverts
7.16 Yes ☐ No ☐ NA ☐ NA
and structures
Review of condition survey for bridges,
7.17 Yes ☐ No ☐ NA ☐ NA
culverts and structures by client
7.18 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
8 Geotechnical Survey Yes ☐ No ☐ NA ☐ NA
Geo-technical and sub-soil explorations
8.1
as per IRC:78 Yes ☐ No ☐ NA ☐ NA
Bore holes dug for every pier and
8.2 Yes ☐ No ☐ NA ☐ NA
abutment
Review of geo-technical and sub-soil
8.3 explorations by client Yes ☐ No ☐ NA ☐ NA
Field testing, soil sampling, laboratory
8.4 testing in accordance with BIS/ Yes ☐ No ☐ NA ☐ NA
AASHTO/ BS
Recommendation of Foundation Type
8.5
and Depth Yes ☐ No ☐ NA ☐ NA
8.6 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
235
Details /
S.No SECTION OF THE REPORT YES/ NO/ NA Remarks
Specifications
9 Hydraulic and Hydrological Survey Yes ☐ No ☐ NA ☐ NA
Hydraulic and hydrological investigations
9.1
as per IRC:SP:13 and IRC:5 Yes ☐ No ☐ NA ☐ NA
9.2 High Flood Level specified Yes ☐ No ☐ NA ☐ NA
9.3 Depth of Water Table specified Yes ☐ No ☐ NA ☐ NA
9.4 Ponded Water Level specified Yes ☐ No ☐ NA ☐ NA
9.5 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Review of hydrological investigations by
9.6
client Yes ☐ No ☐ NA ☐ NA
10 Materials Survey Yes ☐ No ☐ NA ☐ NA
Materials Survey conducted as per
10.1 Yes ☐ No ☐ NA ☐ NA
IRC:SP:19
Sources of Naturally Occurring
Aggregates specified
10.2 Details of Borrow Pits with Yes ☐ No ☐ NA ☐
Distance from Project Site
Cost of Material/ Transportation
Sources of Manufactured Items specified
Details of suppliers with
10.3 Yes ☐ No ☐ NA ☐ NA
distance from project site
Cost of material/ transportation
Sources of water for construction
10.4 Yes ☐ No ☐ NA ☐ NA
specified as per IS: 456
10.5 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Environmental screening/ preliminary
11 Yes ☐ No ☐ NA ☐ NA
environmental assessment
Analysis basis Initial Environment
11.1 Yes ☐ No ☐ NA ☐ NA
Examination in IRC: SP: 19
Recommended feasible mitigation
11.2 measures Yes ☐ No ☐ NA ☐ NA
Initial social assessment/ preliminary
12
LA resettlement plan Yes ☐ No ☐ NA ☐ NA
Analysis basis Initial Environment
12.1 Examination in IRC: SP: 19 Yes ☐ No ☐ NA ☐ NA
Details of consultation with potentially
12.2
affected persons Yes ☐ No ☐ NA ☐ NA
Names/ Details of consultation with local
12.3
NGOs Yes ☐ No ☐ NA ☐
Names/ Details of consultation with
12.4 Yes ☐ No ☐ NA ☐
municipal authorities
12.5 Preliminary resettlement plan Yes ☐ No ☐ NA ☐ NA
12.6 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
13 Cost estimates Yes ☐ No ☐ NA ☐ NA
13.1 Item rates and rate analysis Yes ☐ No ☐ NA ☐ NA
13.2 Escalation Yes ☐ No ☐ NA ☐ NA
14 Economic and financial analysis Yes ☐ No ☐ NA ☐ NA
236
Details /
S.No SECTION OF THE REPORT YES/ NO/ NA Remarks
Specifications
14.1 Estimated cost details Yes ☐ No ☐ NA ☐ NA
14.2 Projected revenues details Yes ☐ No ☐ NA ☐ NA
14.3 Assumptions stated Yes ☐ No ☐ NA ☐ NA
Analysis and results (IRR, Sensitivity
14.4 Yes ☐ No ☐ NA ☐ NA
Analysis, Financial Viability)
15 Strip plan and Alignment Yes ☐ No ☐ NA ☐ NA
Details of center line of proposed
15.1
highway Yes ☐ No ☐ NA ☐ NA
15.2 Details of existing RoW Yes ☐ No ☐ NA ☐ NA
15.3 Details of proposed RoW Yes ☐ No ☐ NA ☐ NA
Details about ownership of land to be
15.4 Yes ☐ No ☐ NA ☐ NA
acquired
Strip plan basis reconnaissance and
15.5 topographic surveys Yes ☐ No ☐ NA ☐ NA
Strip plan reviewed and approved by the
15.6 Yes ☐ No ☐ NA ☐ NA
client
16 Alignment Options Study Yes ☐ No ☐ NA ☐ NA
At least two alignments proposed
16.1
Details of Alignments on Map Yes ☐ No ☐ NA ☐ NA
16.2 Review of options with client Yes ☐ No ☐ NA ☐ NA
16.2.1 Review of options with local authority Yes ☐ No ☐ NA ☐ NA
Length of the project along proposed
16.3 Yes ☐ No ☐ NA ☐
alignment options
Land Acquisition required along
16.4 Yes ☐ No ☐ NA ☐
alignment options
16.4.1 Environmental impact of each option Yes ☐ No ☐ NA ☐
Review of road geometry and safety for
16.4.2
each option Yes ☐ No ☐ NA ☐
16.5 Cost Estimates of alternatives Yes ☐ No ☐ NA ☐
Recommended Alignment with
16.6
Justification Yes ☐ No ☐ NA ☐ NA
16.7 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
17 Technical Specifications Yes ☐ No ☐ NA ☐ NA
MoRTH technical specifications for
17.1
Roads and Bridge works followed Yes ☐ No ☐ NA ☐ NA
17.2 Details of technical specifications Yes ☐ No ☐ NA ☐ NA
18 Rate Analysis Yes ☐ No ☐ NA ☐ NA
Rate analysis for all relevant items as per
18.1
latest SoR Yes ☐ No ☐ NA ☐ NA
19 Cost Estimates Yes ☐ No ☐ NA ☐ NA
Cost estimates for all relevant items as
19.1
per latest SoR Yes ☐ No ☐ NA ☐ NA
20 Bill of quantities Yes ☐ No ☐ NA ☐ NA
21 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
21.1 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
237
Details /
S.No SECTION OF THE REPORT YES/ NO/ NA Remarks
Specifications
Report fulfils project objectives and
21.2
scope as per RFP Yes ☐ No ☐ NA ☐ NA
21.3 Report reviewed for errors and omissions Yes ☐ No ☐ NA ☐ NA
Compliance report prepared on client
21.4
observations Yes ☐ No ☐ NA ☐ NA
238
DPR Checklist – Stage 3 – LA and Clearances I Report (Pavements)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
2 Strip plan- additional details added Yes ☐ No ☐ NA ☐ NA
Details of centreline, existing structures,
2.1 Yes ☐ No ☐ NA ☐ NA
road furniture and other features
2.2 Widening scheme Yes ☐ No ☐ NA ☐ NA
New construction/ reconstruction of
2.3
structures and amenities Yes ☐ No ☐ NA ☐ NA
2.4 Existing and proposed right of way Yes ☐ No ☐ NA ☐ NA
2.5 Clearances impacting each chainage Yes ☐ No ☐ NA ☐ NA
3 Forest Clearance Yes ☐ No ☐ NA ☐ NA
3.1 Requirement for forest clearance identified Yes ☐ No ☐ NA ☐ NA
Date/ Details of initial consultation with
3.2 Yes ☐ No ☐ NA ☐
competent authority
Details/cost of trees being felled basis
3.3 Yes ☐ No ☐ NA ☐
concerned District Forest Office
Date of submission of proposal for forest
3.4 clearance Yes ☐ No ☐ NA ☐ NA
3.5 Review of proposal by client Yes ☐ No ☐ NA ☐ NA
4 Wildlife Clearance Yes ☐ No ☐ NA ☐ NA
4.1 Requirement for wildlife clearance identified Yes ☐ No ☐ NA ☐ NA
Date/ Details of initial consultation with
4.2 Yes ☐ No ☐ NA ☐
competent authority
Details/cost of trees being felled basis
4.3 concerned District Forest Office Yes ☐ No ☐ NA ☐
Date of submission of proposal for wildlife
4.4 Yes ☐ No ☐ NA ☐
clearance
4.5 Review of proposal by client Yes ☐ No ☐ NA ☐ NA
5 Utility Clearances (Electricity) Yes ☐ No ☐ NA ☐ NA
5.1 Identification of overground utilities Yes ☐ No ☐ NA ☐ NA
Identification of underground utilities using
5.2 GPR, Induction Locator or equivalent Yes ☐ No ☐ NA ☐ NA
technologies
Name/ Details of consultation with local
5.3
authority/ people Yes ☐ No ☐ NA ☐
Utility relocation plan with existing /
5.4 proposed location showing existing RoW Yes ☐ No ☐ NA ☐ NA
and topographic details
5.5 Cost for relocation as per authority Yes ☐ No ☐ NA ☐
239
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Date of proposal submission to competent
5.6
authority Yes ☐ No ☐ NA ☐
Review of utility relocation plan/ proposal
5.7 Yes ☐ No ☐ NA ☐ NA
by client
6 Utility Clearances (Water) Yes ☐ No ☐ NA ☐ NA
6.1 Identification of overground utilities in RoW Yes ☐ No ☐ NA ☐ NA
Identification of underground utilities using
6.2 GPR, Induction Locator or equivalent Yes ☐ No ☐ NA ☐ NA
technologies
Name/ Details of consultation with local
6.3 Yes ☐ No ☐ NA ☐
authority/ people
Utility relocation plan with existing /
6.4 proposed location showing existing RoW Yes ☐ No ☐ NA ☐ NA
and topographic details
6.5 Cost for relocation as per authority Yes ☐ No ☐ NA ☐
Date of proposal submission to competent
6.6 Yes ☐ No ☐ NA ☐ NA
authority
Review of utility relocation plan/ proposal
6.7 Yes ☐ No ☐ NA ☐ NA
by client
7 Utility Clearances (Others) Yes ☐ No ☐ NA ☐ NA
7.1 Identification of overground utilities in RoW Yes ☐ No ☐ NA ☐ NA
Identification of underground utilities using
7.2 GPR, Induction Locator or equivalent Yes ☐ No ☐ NA ☐ NA
technologies
Name/ Details of consultation with local
7.3
authority/ people Yes ☐ No ☐ NA ☐
Utility relocation plan with existing /
7.4 proposed location showing existing RoW Yes ☐ No ☐ NA ☐ NA
and topographic details
7.5 Cost for relocation as per authority Yes ☐ No ☐ NA ☐
Date of proposal submission to competent
7.6 Yes ☐ No ☐ NA ☐
authority
Review of utility relocation plan/ proposal
7.7 by client Yes ☐ No ☐ NA ☐ NA
8 Railway Clearances Yes ☐ No ☐ NA ☐ NA
Identification of ROB/ RUB on project
8.1 Yes ☐ No ☐ NA ☐ NA
corridor
8.2 Initial consultation with competent authority Yes ☐ No ☐ NA ☐ NA
Date of proposal submission to competent
8.3 Yes ☐ No ☐ NA ☐
authority
8.4 Review of GAD/ proposal by client Yes ☐ No ☐ NA ☐ NA
9 Other Clearances Yes ☐ No ☐ NA ☐ NA
9.1 Requirement for other clearances identified Yes ☐ No ☐ NA ☐ NA
Date of proposal submission to competent
9.2 Yes ☐ No ☐ NA ☐
authority
9.3 Review of proposal by client Yes ☐ No ☐ NA ☐ NA
240
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
10 Land Acquisition Yes ☐ No ☐ NA ☐ NA
Detailed schedule about acquisition of
10.1
landholdings as per land records Yes ☐ No ☐ NA ☐ NA
10.2 Consultation with affected persons Yes ☐ No ☐ NA ☐ NA
10.3 Name/ Details of consultation with NGOs Yes ☐ No ☐ NA ☐
Name/ Details of consultation with
10.4
concerned government agencies Yes ☐ No ☐ NA ☐
Total land required, land area already
10.5 Yes ☐ No ☐ NA ☐
available , land to be acquired identified
Review of land acquisition using digital
10.6 Yes ☐ No ☐ NA ☐ NA
cadastral map by client
10.7 Draft 3a notification submitted Yes ☐ No ☐ NA ☐ NA
10.8 Review of 3a notification by client Yes ☐ No ☐ NA ☐ NA
10.9 Date of 3a gazette notification Yes ☐ No ☐ NA ☐
10.10 Draft 3a notification submitted Yes ☐ No ☐ NA ☐ NA
10.11 Review of 3A notification by client Yes ☐ No ☐ NA ☐ NA
10.12 Date of 3A gazette notification Yes ☐ No ☐ NA ☐
11 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
11.1 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
Report fulfils project objectives and scope
11.2
as per RFP Yes ☐ No ☐ NA ☐ NA
11.3 Report reviewed for errors and omissions Yes ☐ No ☐ NA ☐ NA
Compliance report prepared on client
11.4
observations Yes ☐ No ☐ NA ☐ NA
241
DPR Checklist – Stage 4 – Detailed Project Report (Pavements)
General Details
Project Name
Consultant's Name
Date of Review
Details /
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Main Report Yes ☐ No ☐ NA ☐ NA
2 Introduction and project background Yes ☐ No ☐ NA ☐ NA
Overview of project location, project
2.1 Yes ☐ No ☐ NA ☐ NA
objectives etc.
Overview of report structure, deliverables
2.2 Yes ☐ No ☐ NA ☐ NA
etc.
3 Social analysis of the project Yes ☐ No ☐ NA ☐ NA
Project impact on stakeholders such as
3.1 Yes ☐ No ☐ NA ☐ NA
local people
Project impact on residential, commercial
3.2 and public properties Yes ☐ No ☐ NA ☐ NA
3.3 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
4 Reconnaissance survey Yes ☐ No ☐ NA ☐ NA
Geometric Features of the Existing Road
Design Speed
Sight distance details
4.1 Yes ☐ No ☐ NA ☐
Horizontal Alignment Details
Vertical Alignment Details
Height of Embankment
Topographical Survey using LiDAR (or
equivalent technology) as per IRC:SP:19
4.2 Yes ☐ No ☐ NA ☐ NA
Gradient
Terrain
Pavement composition and condition
4.3 Yes ☐ No ☐ NA ☐ NA
survey as per IRC:SP:19
Pavement roughness survey as per
4.4
IRC:SP:16 Yes ☐ No ☐ NA ☐ Na
Pavement structural strength survey as
4.5
per IRC:81 Yes ☐ No ☐ NA ☐ NA
Geological Survey
4.6 Geological Map of the Area Yes ☐ No ☐ NA ☐ NA
Seismicity
Climatic Conditions
Temperature
4.7 Yes ☐ No ☐ NA ☐ NA
Rainfall
Wind
Land Use along the existing alignment
4.8 Map of the Project Area depicting Yes ☐ No ☐ NA ☐ NA
Agricultural/Habitation/Forest Area
242
Details /
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Details of Existing Structures
Map of the Project Area depicting
4.9 Yes ☐ No ☐ NA ☐ NA
Hutments/Buildings/Temples/Public
Building/Any Other Significant Structure
4.10 Inventory and condition survey of culverts Yes ☐ No ☐ NA ☐ NA
Geo-technical and sub-soil explorations as
4.11 Yes ☐ No ☐ NA ☐ NA
per IRC:78
Number of Bore holes dug (holes for every
4.12 Yes ☐ No ☐ NA ☐
pier and abutment)
Field testing, soil sampling, laboratory
4.13 Yes ☐ No ☐ NA ☐ NA
testing as per IRC: 78
Recommendation of Foundation Type and
4.14 Yes ☐ No ☐ NA ☐
Depth
4.15 Hydrological investigations as per IRC:5 Yes ☐ No ☐ NA ☐ NA
4.16 High Flood Level specified Yes ☐ No ☐ NA ☐ NA
4.17 Depth of Water Table specified Yes ☐ No ☐ NA ☐ NA
4.18 Ponded Water Level specified Yes ☐ No ☐ NA ☐ NA
Materials Survey conducted as per
4.19
IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
Sources of Naturally Occurring
Aggregates specified
4.20 Details of Borrow Pits with Yes ☐ No ☐ NA ☐
Distance from Project Site
Cost of Material/Transportation
Sources of environmentally friendly
4.20.1 construction materials identified as per Yes ☐ No ☐ NA ☐ NA
MoRT&H circular
Sources of Manufactured Items specified
Details of Suppliers with Distance
4.21 Yes ☐ No ☐ NA ☐ NA
from Project Site
Cost of Material/Transportation
Source of Water for construction specified
4.22
as per IS:456 Yes ☐ No ☐ NA ☐ NA
4.23 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Traffic studies and demand forecast
5 Yes ☐ No ☐ NA ☐ NA
designs
Classified traffic volume counts using
5.1
IHMCL data (7 day data) Yes ☐ No ☐ NA ☐ NA
Traffic projection methodology as per
5.2
IRC:108 Yes ☐ No ☐ NA ☐ NA
5.3 Projected Traffic data for 20 years Yes ☐ No ☐ NA ☐ NA
5.4 Current and Projected PCU Yes ☐ No ☐ NA ☐
5.5 Current and Projected TVU Yes ☐ No ☐ NA ☐
5.6 Origin destination surveys as per IRC: 102 Yes ☐ No ☐ NA ☐ NA
5.7 Speed and delay studies as per IRC:102 Yes ☐ No ☐ NA ☐ NA
243
Details /
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Traffic surveys for the design of road
5.8
junctions as per data in IRC: SP:41 Yes ☐ No ☐ NA ☐ NA
Analysis for replacing railway level
5.9 Yes ☐ No ☐ NA ☐ NA
crossings with over bridges/ subways
5.10 Axle load survey as per IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
5.11 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Traffic surveys monitored and reviewed by
5.12 Yes ☐ No ☐ NA ☐ NA
the client
6 Cost estimates Yes ☐ No ☐ NA ☐ NA
6.1 Project costing as per latest SoR Yes ☐ No ☐ NA ☐ NA
7 Environmental aspects Yes ☐ No ☐ NA ☐ NA
7.1 Environment profile of the project region Yes ☐ No ☐ NA ☐ NA
Details of Public consultation at residential
7.2 Yes ☐ No ☐ NA ☐ NA
and commercial settlements affected
7.3 Impact analysis and mitigation measures Yes ☐ No ☐ NA ☐ NA
8 Economic and commercial analysis Yes ☐ No ☐ NA ☐ NA
8.1 Estimated cost details Yes ☐ No ☐ NA ☐ NA
8.2 Projected revenues details Yes ☐ No ☐ NA ☐ NA
8.3 Assumptions stated Yes ☐ No ☐ NA ☐ NA
Analysis and results (IRR, Sensitivity
8.4
Analysis, Financial Viability) Yes ☐ No ☐ NA ☐ NA
8.5 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
Financial model shared with client and
8.6 Yes ☐ No ☐ NA ☐ NA
reviewed
9 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
Report fulfils project objectives and scope
9.1 Yes ☐ No ☐ NA ☐ NA
as per RFP
9.2 Report reviewed for errors and omissions Yes ☐ No ☐ NA ☐ NA
Compliance report prepared on client
9.3
observations Yes ☐ No ☐ NA ☐ NA
10 Design Report Yes ☐ No ☐ NA ☐ NA
10.1 Highway improvement proposals Yes ☐ No ☐ NA ☐ NA
10.2 Highway geometric designs Yes ☐ No ☐ NA ☐ NA
10.3 Roadside drainage Yes ☐ No ☐ NA ☐ NA
10.4 Intersections Yes ☐ No ☐ NA ☐ NA
10.5 Urban service roads Yes ☐ No ☐ NA ☐ NA
10.6 Bus-stops Yes ☐ No ☐ NA ☐ NA
10.7 Toll plazas Yes ☐ No ☐ NA ☐ NA
10.8 Pedestrian crossings Yes ☐ No ☐ NA ☐ NA
10.9 Utility relocation Yes ☐ No ☐ NA ☐ NA
10.10 Pavement Yes ☐ No ☐ NA ☐ NA
10.11 Structures Yes ☐ No ☐ NA ☐ NA
10.12 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
244
Details /
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Pavement deflection survey as per IRC
10.13
81-1997 Yes ☐ No ☐ NA ☐ NA
10.14 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
11 Materials Report Yes ☐ No ☐ NA ☐ NA
11.1 Material investigations as per IRC:10 Yes ☐ No ☐ NA ☐ NA
11.2 Review of material investigations by client Yes ☐ No ☐ NA ☐ NA
11.3 Multiple borrow areas identified Yes ☐ No ☐ NA ☐ NA
11.4 Material survey as per IRC: SP: 19 Yes ☐ No ☐ NA ☐ NA
11.5 Review of material survey by client Yes ☐ No ☐ NA ☐ NA
Geo-technical and sub-soil explorations as
11.6 Yes ☐ No ☐ NA ☐ NA
per IRC:78
Review of geo-technical and sub-soil
11.7
explorations by client Yes ☐ No ☐ NA ☐ NA
Field testing, soil sampling, laboratory
11.8 testing in accordance with BIS/ AASHTO/ Yes ☐ No ☐ NA ☐ NA
BS
Pavement composition and condition
11.9 survey as per IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
Review of pavement composition and
11.10 Yes ☐ No ☐ NA ☐ NA
condition survey by client
Pavement roughness survey as per
11.11 IRC:SP:16 Yes ☐ No ☐ NA ☐ NA
Review of pavement roughness survey by
11.12 Yes ☐ No ☐ NA ☐ NA
client
Pavement structural strength survey as
11.13 per IRC:81 Yes ☐ No ☐ NA ☐ NA
Review of pavement structural strength
11.14 Yes ☐ No ☐ NA ☐ NA
survey by client
Water sample tests as per MoRTH
11.15
specifications Yes ☐ No ☐ NA ☐ NA
11.16 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Environmental Assessment Report/
12
Resettlement and Rehabilitation Plan Yes ☐ No ☐ NA ☐ NA
Option for alignment alternatives
12.1
considered and conclusions Yes ☐ No ☐ NA ☐ NA
Land environment data collection and
12.2 details/ impact/ mitigation measures Yes ☐ No ☐ NA ☐ NA
Air environment data collection and
12.3
details/ impact/ mitigation measures Yes ☐ No ☐ NA ☐ NA
Water resources details/ impact/ mitigation
12.4
measures Yes ☐ No ☐ NA ☐ NA
Noise environment details/ impact/
12.5
mitigation measures Yes ☐ No ☐ NA ☐ NA
Biological environment details/ impact/
12.6 mitigation measures Yes ☐ No ☐ NA ☐ NA
12.7 Details of public consultation Yes ☐ No ☐ NA ☐ NA
245
Details /
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Environment monitoring and management
12.8
plan Yes ☐ No ☐ NA ☐ NA
12.9 Details of social impact assessment Yes ☐ No ☐ NA ☐ NA
Details of resettlement and rehabilitation
12.10
action plan Yes ☐ No ☐ NA ☐ NA
12.11 Measures to minimize resettlement Yes ☐ No ☐ NA ☐ NA
Details of public consultation with
12.12 Yes ☐ No ☐ NA ☐ NA
stakeholders
Details of implementation arrangement /
12.13 Yes ☐ No ☐ NA ☐ NA
budget
12.14 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
13 Technical Specifications Yes ☐ No ☐ NA ☐ NA
MoRTH technical specifications for Roads
13.1 Yes ☐ No ☐ NA ☐ NA
and Bridge works followed
13.2 Details of technical specifications Yes ☐ No ☐ NA ☐ NA
14 Rate Analysis Yes ☐ No ☐ NA ☐ NA
Rate analysis for all relevant items as per
14.1 Yes ☐ No ☐ NA ☐ NA
latest SoR
15 Cost Estimates Yes ☐ No ☐ NA ☐ NA
Cost estimates for all relevant items as per
15.1
latest SoR Yes ☐ No ☐ NA ☐ NA
16 Bill of quantities Yes ☐ No ☐ NA ☐ NA
17 Drawing Volume Yes ☐ No ☐ NA ☐ NA
18 Digital drawings of road
18.1 Highway cross sections Yes ☐ No ☐ NA ☐
3D engineered models of:
Road alignment geometry
18.2 Yes ☐ No ☐ NA ☐
Proposed highway
Proposed structures
246
DPR Checklist – Stage 5 – Technical Schedules (Pavements)
General Details
Project Name
Consultant's Name
Date of Review
Details /
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Bid documents- EPC Yes ☐ No ☐ NA ☐ NA
2 Bid documents- BOT/PPP Yes ☐ No ☐ NA ☐ NA
3 Bid documents- other, if any Yes ☐ No ☐ NA ☐ NA
4 Draft concession agreement Yes ☐ No ☐ NA ☐ NA
Schedule D - Specifications and Yes ☐ No ☐ NA
4 NA
standards ☐
Yes ☐ No ☐ NA
5 NA
Any other relevant details ☐
247
DPR Checklist – Stage 6 – LA and Clearances II Report (Pavements)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
2 Environment Clearance Yes ☐ No ☐ NA ☐ NA
2.1 Details of public hearings completed Yes ☐ No ☐ NA ☐
Date of final environment clearance by
2.2 Yes ☐ No ☐ NA ☐
competent authority
3 Forest Clearance Yes ☐ No ☐ NA ☐ NA
Date/ Details of Joint site inspection with
3.1
DFO/ competent authority Yes ☐ No ☐ NA ☐
Date of Stage I forest clearance approval
3.2
by competent authority Yes ☐ No ☐ NA ☐
Date of final forest clearance approval by
3.3 competent authority Yes ☐ No ☐ NA ☐
4 Wildlife Clearance Yes ☐ No ☐ NA ☐ NA
Date/ Details of joint site inspection with
4.1
DFO/ competent authority Yes ☐ No ☐ NA ☐
Date of final wildlife clearance approval by
4.2
competent authority Yes ☐ No ☐ NA ☐
5 Utility Clearances (Electricity) Yes ☐ No ☐ NA ☐ NA
Date/ Details of Joint site inspection with
5.1 Yes ☐ No ☐ NA ☐
competent authority
Date of estimate submission by competent
5.2 Yes ☐ No ☐ NA ☐
authority
Date of estimate approval by competent
5.3 authority Yes ☐ No ☐ NA ☐
Approved utility shifting proposal including
5.4 Yes ☐ No ☐ NA ☐
strip plan
Details of approved contractors, SoR and
5.5 deposit details for user agency Yes ☐ No ☐ NA ☐ NA
Utilities checklist, no upgradation certificate
5.6 Yes ☐ No ☐ NA ☐
attached
Date of estimate submission by competent
6.2
authority Yes ☐ No ☐ NA ☐
Date of estimate approval by competent
6.3
authority Yes ☐ No ☐ NA ☐
Approved utility shifting proposal including
6.4 strip plan Yes ☐ No ☐ NA ☐
Details of approved contractors, SoR and
6.5 Yes ☐ No ☐ NA ☐ NA
deposit details for user agency
Utilities checklist, no upgradation certificate
6.6 attached Yes ☐ No ☐ NA ☐
248
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Date of estimate submission by competent
7.2
authority Yes ☐ No ☐ NA ☐
Date of estimate approval by competent
7.3 Yes ☐ No ☐ NA ☐
authority
Approved utility shifting proposal including
7.4 strip plan Yes ☐ No ☐ NA ☐
Details of approved contractors, SoR and
7.5
deposit details for user agency Yes ☐ No ☐ NA ☐ NA
Utilities checklist, no upgradation certificate
7.6 attached Yes ☐ No ☐ NA ☐
Date of final approval of GAD by competent
8.2 Yes ☐ No ☐ NA ☐
authority
9 Other Clearances Yes ☐ No ☐ NA ☐ NA
Date of final approval by competent
9.1 Yes ☐ No ☐ NA ☐
authority
10 Land Acquisition Yes ☐ No ☐ NA ☐ NA
10.1 Draft 3a notification submitted Yes ☐ No ☐ NA ☐
10.2 Review of 3a notification by client Yes ☐ No ☐ NA ☐
10.3 Date of 3a gazette notification Yes ☐ No ☐ NA ☐
10.4 Draft 3a notification submitted Yes ☐ No ☐ NA ☐
10.5 Review of 3A notification by client Yes ☐ No ☐ NA ☐
10.6 Date of 3A gazette notification Yes ☐ No ☐ NA ☐
Date of Joint Measurement Survey with
10.7 Yes ☐ No ☐ NA ☐
competent authority
10.7.1 Date of survey - village wise Yes ☐ No ☐ NA ☐ NA
10.7.2 Land type –by survey number Yes ☐ No ☐ NA ☐ NA
10.7.3 Nature of Land –by survey number Yes ☐ No ☐ NA ☐ NA
10.7.4 Ownership status of plots- by survey
Yes ☐ No ☐ NA ☐ NA
number
10.7.5 Verification of area to be acquired – by
Yes ☐ No ☐ NA ☐ NA
survey number
10.7.6 List of structures on each plot Yes ☐ No ☐ NA ☐ NA
10.7.7 Sketches of updated alignment by village Yes ☐ No ☐ NA ☐ NA
10.7.8 Verification from Land revenue department Yes ☐ No ☐ NA ☐ NA
10.7.9 Verification by CALA office Yes ☐ No ☐ NA ☐ NA
249
1.1.1 DPR Checklist – Stage 7 – Award determination (Pavements)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
2 Village level summary Yes ☐ No ☐ NA ☐ NA
Total private and public land being
2.1 Yes ☐ No ☐ NA ☐ NA
acquired
Variation in area and nature of land against
2.2 Yes ☐ No ☐ NA ☐ NA
3D with justification
2.3 Method used by CALA to arrive at award Yes ☐ No ☐ NA ☐ NA
Date of award by CALA and approval by
2.4
NHAI along with valuation report
Total award calculated and deviation from
2.5 RFCTLARR act Yes ☐ No ☐ NA ☐ NA
3 In detail for each Village Yes ☐ No ☐ NA ☐ NA
Updated land acquisition tracker with
status of:
3.1 Notifications Yes ☐ No ☐ NA ☐ NA
Award
Disbursement
Valuation report and details of award
3.2 calculation- verification by state authority to Yes ☐ No ☐ NA ☐ NA
be included
3.3 Claims report Yes ☐ No ☐ NA ☐ NA
3.4 Copies of notifications published Yes ☐ No ☐ NA ☐ NA
Copies of land possession certificates
3.5 Yes ☐ No ☐ NA ☐ NA
received
4 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
4.1 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
Report fulfils project objectives and scope
4.2 Yes ☐ No ☐ NA ☐ NA
as per RFP
4.3 Report reviewed for errors and omissions Yes ☐ No ☐ NA ☐ NA
Compliance report prepared on client
4.4 Yes ☐ No ☐ NA ☐ NA
observations
250
1.1.2 DPR Checklist – Stage 8 – Land possession report (Pavements)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
2 Village level summary Yes ☐ No ☐ NA ☐ NA
Total private and public land being
2.1
acquired Yes ☐ No ☐ NA ☐ NA
Date of final award by CALA and approval
2.2
by NHAI
Status of disbursement on date of receipt
2.3
of Land possession certificate Yes ☐ No ☐ NA ☐ NA
Key issues being faced in completing land
2.4 acquisition, if any Yes ☐ No ☐ NA ☐ NA
3 In detail for each Village Yes ☐ No ☐ NA ☐ NA
Updated land acquisition tracker with
status of:
3.1 Notifications Yes ☐ No ☐ NA ☐ NA
Award
Disbursement
3.2 Final award and claims report Yes ☐ No ☐ NA ☐ NA
Copies of notifications published, land
3.3 Yes ☐ No ☐ NA ☐ NA
possession certificates received
4 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
4.1 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
Report fulfils project objectives and scope
4.2 Yes ☐ No ☐ NA ☐ NA
as per RFP
4.3 Report reviewed for errors and omissions Yes ☐ No ☐ NA ☐ NA
Compliance report prepared on client
4.4
observations Yes ☐ No ☐ NA ☐ NA
GIS Map containing digitsed details of
5 land parcels acquired with all relevant Yes ☐ No ☐ NA ☐ NA
details
251
Annexure III: Checklists for Structures such as ROB/ RUB
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
2 Project Appreciation Yes ☐ No ☐ NA ☐ NA
2.1 Location of site office Yes ☐ No ☐ NA ☐
Review of scope of ToR and gap
2.2 Yes ☐ No ☐ NA ☐ NA
identification
2.3 Details of key departments for documents Yes ☐ No ☐ NA ☐
Project description
Existing LC number
2.4 Yes ☐ No ☐ NA ☐
Start and End Chainage
Village/District
Project location map
On State Map
2.5 On District Map Yes ☐ No ☐ NA ☐
Latitude & Longitude
Coordinates of the LC
Details of Existing Level Crossing
Number of Railway Tracks
2.6 Type of Railway Tracks Yes ☐ No ☐ NA ☐
(Broad/Metre/Narrow)
No. of trains per day
Justification for need of an ROB/RUB (on
2.7
basis of TVU count) Yes ☐ No ☐ NA ☐ NA
2.8 Overview of land use plans Yes ☐ No ☐ NA ☐ NA
Overview of existing pavement conditions
Number of Lanes
2.9 Yes ☐ No ☐ NA ☐
Type of Pavement
(Flexible/Rigid/Surfaced/Unsurfaced)
2.10 Existing right of way details Yes ☐ No ☐ NA ☐
2.11 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
3 Approach Methodology Yes ☐ No ☐ NA ☐ NA
3.1 Engineering survey and investigations Yes ☐ No ☐ NA ☐ NA
3.2 Design of road, pavements and structures Yes ☐ No ☐ NA ☐ NA
Environment and social impact
3.3 Yes ☐ No ☐ NA ☐ NA
assessment
Estimation of project cost, viability and
3.4 Yes ☐ No ☐ NA ☐ NA
financing options
252
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
3.5 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Task Assignment and Manning
4
Schedule Yes ☐ No ☐ NA ☐ NA
4.1 Number of key personnel provided Yes ☐ No ☐ NA ☐
Specific tasks assigned to each key
4.2 Yes ☐ No ☐ NA ☐ NA
personnel
4.3 Manning schedule for key personnel Yes ☐ No ☐ NA ☐ NA
4.4 Number of key personnel deployed at site Yes ☐ No ☐ NA ☐
5 Performa for data collection Yes ☐ No ☐ NA ☐ NA
Indicative Design standards and cross
6 Yes ☐ No ☐ NA ☐ NA
sections
7 Development plans Yes ☐ No ☐ NA ☐ NA
Overview of development plans being
7.1
implemented/ proposed by local bodies Yes ☐ No ☐ NA ☐ NA
Overview of impact of such development
7.2 Yes ☐ No ☐ NA ☐ NA
plans
8 Quality Assurance Plan Yes ☐ No ☐ NA ☐ NA
8.1 Engineering surveys and investigation Yes ☐ No ☐ NA ☐ NA
8.2 Traffic surveys Yes ☐ No ☐ NA ☐ NA
Material geo-technical and sub-soil
8.3 Yes ☐ No ☐ NA ☐ NA
investigations
8.4 Road and pavement investigations Yes ☐ No ☐ NA ☐ NA
Investigation and design of bridges and
8.5 Yes ☐ No ☐ NA ☐ NA
structures
8.6 Environment and R&R assessment Yes ☐ No ☐ NA ☐ NA
8.7 Economic and financial analysis Yes ☐ No ☐ NA ☐ NA
8.8 Drawing and documentation Yes ☐ No ☐ NA ☐ NA
Discussion of draft QAP document with
8.9 Yes ☐ No ☐ NA ☐ NA
client
8.10 Approval of final QAP document by client Yes ☐ No ☐ NA ☐ NA
8.11 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
9 Draft design standards Yes ☐ No ☐ NA ☐ NA
Geometric design standards of bridges
9.1 Yes ☐ No ☐ NA ☐ NA
(Plain)
Geometric design standards of bridges
9.2 Yes ☐ No ☐ NA ☐ NA
(Hilly)
9.3 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
10 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
10.1 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
Report fulfils project objectives and scope
10.2
as per RFP Yes ☐ No ☐ NA ☐ NA
10.3 Report reviewed for errors and omissions Yes ☐ No ☐ NA ☐ NA
Compliance report prepared on client
10.4 Yes ☐ No ☐ NA ☐ NA
observations
253
DPR Checklist – Stage 2 – Feasibility Report (Structures)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
Overview of client organization /
2
activities Yes ☐ No ☐ NA ☐ NA
Methodology adopted for feasibility
3 study Yes ☐ No ☐ NA ☐ NA
Socioeconomic profile of the project
4 Yes ☐ No ☐ NA ☐ NA
areas
Regional economic profile basis last 10
4.1 Yes ☐ No ☐ NA ☐ NA
years data as per IRC
Economic profile of project influence area
4.2 Yes ☐ No ☐ NA ☐ NA
basis last 10 years data as per IRC
Socio Economic status of project influence
4.3 area Yes ☐ No ☐ NA ☐ NA
Indicative design standards,
5 Yes ☐ No ☐ NA ☐ NA
methodologies, and specifications
6 Traffic surveys and analysis Yes ☐ No ☐ NA ☐ NA
Classified traffic volume counts using
6.1 Yes ☐ No ☐ NA ☐ NA
IHMCL data (7 day)
Traffic projection methodology as per
6.2 Yes ☐ No ☐ NA ☐ NA
IRC:108
6.3 Projected Traffic data for 20 years Yes ☐ No ☐ NA ☐ NA
6.4 Current and Projected PCU Yes ☐ No ☐ NA ☐
6.5 Current and Projected TVU Yes ☐ No ☐ NA ☐
6.6 Axle load survey as per IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
6.7 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Traffic surveys monitored and reviewed by
6.8 Yes ☐ No ☐ NA ☐ NA
the client
7 Reconnaissance survey Yes ☐ No ☐ NA ☐ NA
7.1 Road Inventory as per IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
7.2 Review of Road Inventory Survey by client Yes ☐ No ☐ NA ☐ NA
Geometric Features of the Existing Road
Design Speed
Sight distance elements
7.3 Yes ☐ No ☐ NA ☐ NA
Horizontal Alignment Details
Vertical Alignment Details
Height of Embankment
254
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Topographical Survey as per IRC:SP:19
using LiDAR or equivalent technology
7.4
Gradient Yes ☐ No ☐ NA ☐ NA
Terrain
7.5 Review of topographical survey by client Yes ☐ No ☐ NA ☐ NA
Pavement composition and condition survey
7.6
as per IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
Geological Survey
7.7 Geological Map of the Area Yes ☐ No ☐ NA ☐ NA
Seismicity
Climatic Conditions
Temperature
7.8 Yes ☐ No ☐ NA ☐ NA
Rainfall
Wind
Land Use along the existing alignment
7.9 Map of the Project Area depicting Yes ☐ No ☐ NA ☐ NA
Agricultural/Habitation/Forest Area
Details of Existing Structures
Map of the Project Area depicting
7.10 Yes ☐ No ☐ NA ☐ NA
Hutments/Buildings/Temples/Public
Building/Any Other Significant Structure
7.11 Inventory and condition survey of culverts Yes ☐ No ☐ NA ☐ NA
7.12 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
8 Geotechnical Survey Yes ☐ No ☐ NA ☐ NA
Geo-technical and sub-soil explorations as
8.1
per IRC:78 Yes ☐ No ☐ NA ☐ NA
Number of Bore holes dug (holds for every
8.2 Yes ☐ No ☐ NA ☐
pier and abutment)
Review of geo-technical and sub-soil
8.3 Yes ☐ No ☐ NA ☐ NA
explorations by client
Field testing, soil sampling, laboratory
8.4 testing as per IRC:78 Yes ☐ No ☐ NA ☐ NA
Recommendation of Foundation Type and
8.5 Yes ☐ No ☐ NA ☐
Depth
8.6 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
9 Hydraulic & Hydrological Survey Yes ☐ No ☐ NA ☐ NA
Hydrological investigations as per IRC:5 and
9.1 Yes ☐ No ☐ NA ☐ NA
IRC: 13
9.2 High Flood Level specified Yes ☐ No ☐ NA ☐ NA
9.3 Depth of Water Table specified Yes ☐ No ☐ NA ☐ NA
9.4 Ponded Water Level specified Yes ☐ No ☐ NA ☐ NA
9.5 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
9.6 Review of Hydrological Survey by the client Yes ☐ No ☐ NA ☐ NA
10 Materials Survey Yes ☐ No ☐ NA ☐ NA
Materials Survey conducted as per
10.1 Yes ☐ No ☐ NA ☐ NA
IRC:SP:19
255
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Sources of Naturally Occurring Aggregates
specified
10.2 Details of Borrow Pits with Yes ☐ No ☐ NA ☐
Distance from Project Site
Cost of Material/Transportation
Sources of Manufactured Items specified
Details of Suppliers with Distance
10.3 Yes ☐ No ☐ NA ☐ NA
from Project Site
Cost of Material/Transportation
Source of Water for construction specified
10.4
as per IS:456 Yes ☐ No ☐ NA ☐ NA
10.5 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Determination of whether ROB or RUB is
11 Yes ☐ No ☐ NA ☐ NA
appropriate
Justification of whether ROB or RUB should
11.1
be built Yes ☐ No ☐ NA ☐ NA
11.2 Review of justification by client Yes ☐ No ☐ NA ☐ NA
12 Alignment Options Study Yes ☐ No ☐ NA ☐ NA
At least two alignments proposed
12.1 Details of Alignments on Map Yes ☐ No ☐ NA ☐ NA
256
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Details of consultation with potentially
14.2
affected persons Yes ☐ No ☐ NA ☐ NA
14.3 Details of consultation with local NGOs Yes ☐ No ☐ NA ☐ NA
Details of consultation with municipal
14.4
authorities Yes ☐ No ☐ NA ☐ NA
14.5 Preliminary resettlement plan Yes ☐ No ☐ NA ☐ NA
14.6 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
15 Cost estimates Yes ☐ No ☐ NA ☐ NA
15.1 Item rates and rate analysis Yes ☐ No ☐ NA ☐ NA
15.2 Escalation Yes ☐ No ☐ NA ☐ NA
16 Economic and financial analysis Yes ☐ No ☐ NA ☐ NA
16.1 Estimated cost details Yes ☐ No ☐ NA ☐ NA
16.2 Projected revenues details Yes ☐ No ☐ NA ☐ NA
16.3 Assumptions stated Yes ☐ No ☐ NA ☐ NA
Analysis and results
IRR
16.4 Yes ☐ No ☐ NA ☐ NA
Sensitivity Analysis
Financial Viability
16.5 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
17 Strip Plan NA
17.1 Details of center line of proposed structure Yes ☐ No ☐ NA ☐ NA
17.2 Details of existing RoW Yes ☐ No ☐ NA ☐
17.3 Details of proposed RoW Yes ☐ No ☐ NA ☐
Details about ownership of land to be
17.4
acquired Yes ☐ No ☐ NA ☐ NA
Strip plan basis reconnaissance and
17.5 Yes ☐ No ☐ NA ☐ NA
topographic surveys
Strip plan reviewed and approved by the
17.6 Yes ☐ No ☐ NA ☐ NA
client
17.7 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
11 Strip plan- additional details added Yes ☐ No ☐ NA ☐ NA
Details of centreline, existing structures,
11.1 Yes ☐ No ☐ NA ☐ NA
road furniture and other features
11.2 Widening scheme Yes ☐ No ☐ NA ☐ NA
New construction/ reconstruction of
11.3 Yes ☐ No ☐ NA ☐ NA
structures and amenities
11.4 Existing and proposed right of way Yes ☐ No ☐ NA ☐ NA
11.5 Clearances impacting each chainage Yes ☐ No ☐ NA ☐ NA
257
DPR Checklist – Stage 3 – LA and Clearances I Report (Structures)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
2 Environment Clearance Yes ☐ No ☐ NA ☐ NA
Requirement for environment clearance
2.1 Yes ☐ No ☐ NA ☐ NA
identified
Date/ Details of Initial consultation with
2.2 Yes ☐ No ☐ NA ☐
competent authority
Date of submission of draft EIA report/
2.3 Yes ☐ No ☐ NA ☐ NA
proposal for clearance
2.4 Review of proposal/ EIA report by client Yes ☐ No ☐ NA ☐ NA
3 Forest Clearance Yes ☐ No ☐ NA ☐ NA
3.1 Requirement for forest clearance identified Yes ☐ No ☐ NA ☐ NA
Date/ Details of initial consultation with
3.2
competent authority Yes ☐ No ☐ NA ☐
Details/cost of trees being felled basis
3.3 Yes ☐ No ☐ NA ☐
concerned District Forest Office
Date of submission of proposal for forest
3.4
clearance Yes ☐ No ☐ NA ☐ NA
3.5 Review of proposal by client Yes ☐ No ☐ NA ☐ NA
4 Wildlife Clearance Yes ☐ No ☐ NA ☐ NA
4.1 Requirement for wildlife clearance identified Yes ☐ No ☐ NA ☐ NA
Date/ Details of initial consultation with
4.2
competent authority Yes ☐ No ☐ NA ☐
Details/cost of trees being felled basis
4.3
concerned District Forest Office Yes ☐ No ☐ NA ☐
Date of submission of proposal for wildlife
4.4 clearance Yes ☐ No ☐ NA ☐
4.5 Review of proposal by client Yes ☐ No ☐ NA ☐ NA
5 Utility Clearances (Electricity) Yes ☐ No ☐ NA ☐ NA
5.1 Identification of overground utilities Yes ☐ No ☐ NA ☐ NA
Identification of underground utilities using
5.2 GPR, Induction Locator or equivalent Yes ☐ No ☐ NA ☐ NA
technologies
Name/ Details of consultation with local
5.3
authority/ people Yes ☐ No ☐ NA ☐
Utility relocation plan with existing /
5.4 proposed location showing existing RoW Yes ☐ No ☐ NA ☐ NA
and topographic details
5.5 Cost for relocation as per authority Yes ☐ No ☐ NA ☐
258
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Date of proposal submission to competent
5.6
authority Yes ☐ No ☐ NA ☐
Review of utility relocation plan/ proposal by
5.7 Yes ☐ No ☐ NA ☐ NA
client
6 Utility Clearances (Water) Yes ☐ No ☐ NA ☐ NA
6.1 Identification of overground utilities in RoW Yes ☐ No ☐ NA ☐ NA
Identification of underground utilities using
6.2 GPR, Induction Locator or equivalent Yes ☐ No ☐ NA ☐ NA
technologies
Name/ Details of consultation with local
6.3 Yes ☐ No ☐ NA ☐
authority/ people
Utility relocation plan with existing /
6.4 proposed location showing existing RoW Yes ☐ No ☐ NA ☐ NA
and topographic details
6.5 Cost for relocation as per authority Yes ☐ No ☐ NA ☐
Date of proposal submission to competent
6.6 Yes ☐ No ☐ NA ☐ NA
authority
Review of utility relocation plan/ proposal by
6.7 Yes ☐ No ☐ NA ☐ NA
client
7 Utility Clearances (Others) Yes ☐ No ☐ NA ☐ NA
7.1 Identification of over ground utilities in RoW Yes ☐ No ☐ NA ☐ NA
Identification of underground utilities using
7.2 GPR, Induction Locator or equivalent Yes ☐ No ☐ NA ☐ NA
technologies
Name/ Details of consultation with local
7.3
authority/ people Yes ☐ No ☐ NA ☐
Utility relocation plan with existing /
7.4 proposed location showing existing RoW Yes ☐ No ☐ NA ☐ NA
and topographic details
7.5 Cost for relocation as per authority Yes ☐ No ☐ NA ☐
Date of proposal submission to competent
7.6 Yes ☐ No ☐ NA ☐
authority
Review of utility relocation plan/ proposal by
7.7 client Yes ☐ No ☐ NA ☐ NA
8 Railway Clearances Yes ☐ No ☐ NA ☐ NA
Identification of ROB/ RUB on project
8.1 Yes ☐ No ☐ NA ☐ NA
corridor
8.2 Initial consultation with competent authority Yes ☐ No ☐ NA ☐ NA
Date of proposal submission to competent
8.3 Yes ☐ No ☐ NA ☐
authority
8.4 Review of GAD/ proposal by client Yes ☐ No ☐ NA ☐ NA
9 Other Clearances Yes ☐ No ☐ NA ☐ NA
9.1 Requirement for other clearances identified Yes ☐ No ☐ NA ☐ NA
Date of proposal submission to competent
9.2 Yes ☐ No ☐ NA ☐
authority
9.3 Review of proposal by client Yes ☐ No ☐ NA ☐ NA
259
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
10 Land Acquisition Yes ☐ No ☐ NA ☐ NA
Detailed schedule about acquisition of
10.1
landholdings as per land records Yes ☐ No ☐ NA ☐ NA
10.2 Consultation with affected persons Yes ☐ No ☐ NA ☐ NA
10.3 Name/ Details of consultation with NGOs Yes ☐ No ☐ NA ☐
Name/ Details of consultation with
10.4
concerned government agencies Yes ☐ No ☐ NA ☐
Total land required, land area already
10.5 Yes ☐ No ☐ NA ☐
available , land to be acquired identified
Review of land acquisition using digital
10.6 Yes ☐ No ☐ NA ☐ NA
cadastral map by client
11 Strip plan- additional details added Yes ☐ No ☐ NA ☐ NA 11
260
DPR Checklist – Stage 4 – Detailed Project Report (Structures)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Project background Yes ☐ No ☐ NA ☐ NA
Project description
Existing LC number
1.1 Yes ☐ No ☐ NA ☐
Start and End Chainage
Village/District
Project location map
On State Map
1.2 On District Map Yes ☐ No ☐ NA ☐
Latitude & Longitude Coordinates
of the LC
Details of Existing Level Crossing
Number of Railway Tracks
1.3 Type of Railway Tracks Yes ☐ No ☐ NA ☐
(Broad/Metre/Narrow)
No. of trains per day
Justification for need of an ROB/RUB (on
1.4 Yes ☐ No ☐ NA ☐ NA
basis of TVU count)
1.5 Overview of land use plans Yes ☐ No ☐ NA ☐ NA
Overview of existing pavement conditions
Number of Lanes
1.6 Yes ☐ No ☐ NA ☐
Type of Pavement
(Flexible/Rigid/Surfaced/Unsurfaced)
1.7 Existing right of way details Yes ☐ No ☐ NA ☐
1.8 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
2 Social analysis of the project Yes ☐ No ☐ NA ☐ NA
Project impact on stakeholders such as
2.1
local people Yes ☐ No ☐ NA ☐ NA
Project impact on residential, commercial
2.2 Yes ☐ No ☐ NA ☐ NA
and public properties
2.3 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
3 Reconnaissance survey Yes ☐ No ☐ NA ☐ NA
Geometric Features of the Existing Road
Design Speed
Sight distance details
3.1 Yes ☐ No ☐ NA ☐
Horizontal Alignment Details
Vertical Alignment Details
Height of Embankment
261
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Topographical Survey using LiDAR or
equivalent technology as per IRC:SP:19
3.2
Gradient Yes ☐ No ☐ NA ☐ NA
Terrain
Pavement composition and condition
3.3
survey as per IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
Geological Survey
3.4 Geological Map of the Area Yes ☐ No ☐ NA ☐ NA
Seismicity
Climatic Conditions
Temperature
3.5 Yes ☐ No ☐ NA ☐ NA
Rainfall
Wind
Land Use along the existing alignment
3.6 Map of the Project Area depicting Yes ☐ No ☐ NA ☐ NA
Agricultural/Habitation/Forest Area
Details of Existing Structures
Map of the Project Area depicting
3.7 Yes ☐ No ☐ NA ☐ NA
Hutments/Buildings/Temples/Public
Building/Any Other Significant Structure
3.8 Inventory and condition survey of culverts Yes ☐ No ☐ NA ☐ NA
Geo-technical and sub-soil explorations as
3.9
per IRC:78 Yes ☐ No ☐ NA ☐ NA
Number of Bore holes dug (holds for every
3.10 Yes ☐ No ☐ NA ☐
pier and abutment)
Field testing, soil sampling, laboratory
3.11
testing as per IRC: 78 Yes ☐ No ☐ NA ☐ NA
Recommendation of Foundation Type and
3.12 Yes ☐ No ☐ NA ☐
Depth
Hydraulic and Hydrological investigations
3.13 Yes ☐ No ☐ NA ☐ NA
as per IRC:5
3.14 High Flood Level specified Yes ☐ No ☐ NA ☐ NA
3.15 Depth of Water Table specified Yes ☐ No ☐ NA ☐ NA
3.16 Ponded Water Level specified Yes ☐ No ☐ NA ☐ NA
Materials Survey conducted as per
3.17 Yes ☐ No ☐ NA ☐ NA
IRC:SP:19
Sources of Naturally Occurring Aggregates
specified
3.18 Details of Borrow Pits with Yes ☐ No ☐ NA ☐
Distance from Project Site
Cost of Material/Transportation
Sources of Manufactured Items specified
Details of Suppliers with Distance
3.19 Yes ☐ No ☐ NA ☐ NA
from Project Site
Cost of Material/Transportation
262
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Sources of environmentally friendly
3.19.1 construction materials identified as per Yes ☐ No ☐ NA ☐ NA
MoRT&H circular
Source of Water for construction specified
3.20 Yes ☐ No ☐ NA ☐ NA
as per IS:456
3.21 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
4 Traffic surveys and analysis Yes ☐ No ☐ NA ☐ NA
Classified traffic volume counts using
4.1 Yes ☐ No ☐ NA ☐ NA
IHMCL data (7 day)
4.2 Traffic projection as per IRC:108 Yes ☐ No ☐ NA ☐ NA
4.3 Projected Traffic data for 20 years Yes ☐ No ☐ NA ☐ NA
4.4 Current and Projected PCU Yes ☐ No ☐ NA ☐
4.5 Current and Projected TVU Yes ☐ No ☐ NA ☐
4.6 Axle load survey as per IRC:SP:19 Yes ☐ No ☐ NA ☐ NA
4.7 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
Determination of whether ROB or RUB is
5 Yes ☐ No ☐ NA ☐ NA
appropriate
Justification of whether ROB or RUB should
5.1 be built Yes ☐ No ☐ NA ☐ NA
6 Alignment Options Study Yes ☐ No ☐ NA ☐ NA
At least two alignments proposed
6.1 Details of Alignments on Map Yes ☐ No ☐ NA ☐ NA
Length of the project along proposed
6.2 Yes ☐ No ☐ NA ☐ NA
alignment options
Land Acquisition required along alignment
6.3
options Yes ☐ No ☐ NA ☐ NA
6.4 Cost Estimates of alternatives Yes ☐ No ☐ NA ☐ NA
6.5 Recommended Alignment with Justification Yes ☐ No ☐ NA ☐
Skew Angle of Proposed Alignment
6.6 Yes ☐ No ☐ NA ☐
Specified
6.7 Traffic Diversion Route Specified Yes ☐ No ☐ NA ☐ NA
6.8 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
7 Design Specifications Yes ☐ No ☐ NA ☐ NA
7.1 Number of Lanes Yes ☐ No ☐ NA ☐
Width of ROB
Width of Carriageway
7.2 Width of Safety Kerbs Yes ☐ No ☐ NA ☐
Width of Footpath
Any other
Proposed Number of Lanes on ROB in line
7.3 Yes ☐ No ☐ NA ☐ NA
with PCU as per latest MoRTH guidelines
263
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Proposed Length of the Project
Length of ROB
Length of Viaduct
7.4 Yes ☐ No ☐ NA ☐
Length of RE Wall
Length of Approach Road
Length of Service Road
Span Arrangement
7.5 Span Length Yes ☐ No ☐ NA ☐
Number of Spans
Are all spans of standardised length as per
Railways standards
7.6 (https://ircep.gov.in/RCApproval/) Yes ☐ No ☐ NA ☐ NA
If non-standardised, suitable
justification provided
Details of Proposed Superstructure Design
Type
7.7 Yes ☐ No ☐ NA ☐ NA
Details of Material Use Proposed
Drawings of Cross-Sections
Details of Proposed Substructure Design
Type
7.8 Yes ☐ No ☐ NA ☐ NA
Details of Material Use Proposed
Drawings of Cross-Sections
Details of Proposed Pavement Design
Type
Details of Material Use Proposed
7.9 Yes ☐ No ☐ NA ☐ NA
Thickness
Design MSA
Drawings of Cross-Sections
7.10 Details of Drainage Structures Proposed Yes ☐ No ☐ NA ☐ NA
7.11 Any other details relevant to the project Yes ☐ No ☐ NA ☐ NA
8 Cost estimates Yes ☐ No ☐ NA ☐ NA
Summary of Cost Estimates (Refer
8.1
following subsection) Yes ☐ No ☐ NA ☐
8.2 Detailed Abstract of Cost Yes ☐ No ☐ NA ☐ NA
8.3 Detailed Bills of Quantity Yes ☐ No ☐ NA ☐ NA
8.4 Detailed Rate Analysis Yes ☐ No ☐ NA ☐ NA
9 Financial Viability Yes ☐ No ☐ NA ☐ NA
9.1 Estimated cost details Yes ☐ No ☐ NA ☐ NA
9.2 Projected revenues details Yes ☐ No ☐ NA ☐ NA
9.3 Assumptions stated Yes ☐ No ☐ NA ☐ NA
Analysis and results
IRR
9.4 Yes ☐ No ☐ NA ☐
Sensitivity Analysis
Financial Viability
10 Land Acquisition Study Yes ☐ No ☐ NA ☐ NA
264
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Land Acquisition Details
Total Land Required
10.1 Yes ☐ No ☐ NA ☐
Land Area already available
Area of Land to be Acquired
10.3 Details of LA Cost Yes ☐ No ☐ NA ☐
11 Utility Shifting Study Yes ☐ No ☐ NA ☐ NA
11.1 Results of GPR investigation Yes ☐ No ☐ NA ☐ NA
Utility relocation plan with existing /
11.2 proposed location showing existing RoW Yes ☐ No ☐ NA ☐ NA
and topographic details
11.3 Cost for relocation as per authority Yes ☐ No ☐ NA ☐
12 General Arrangement Drawing Yes ☐ No ☐ NA ☐ NA
12.1 Elevation of Railway Portion Yes ☐ No ☐ NA ☐ NA
12.2 Plan of Railway Portion Yes ☐ No ☐ NA ☐ NA
12.3 General Elevation Yes ☐ No ☐ NA ☐ NA
General Plan (showing complete ROB/RUB
12.4
along with diversion) Yes ☐ No ☐ NA ☐ NA
12.5 Key Plan Yes ☐ No ☐ NA ☐ NA
12.6 Cross-Section of Railway Portion Yes ☐ No ☐ NA ☐ NA
3D engineered models of:
Existing structure, if any
12.7 Yes ☐ No ☐ NA ☐
Proposed structure
Utilities and other features in RoW
2 Cost of Viaduct
Foundation
Substructure
Superstructure
Total-Viaduct
4 Cost of RE Wall
265
S.No. Particulars Cost Estimate(in '000)
6 Miscellaneous Costs
Cost of Subway
Cost of Toll Plaza
Cost of Culverts
Any Other Costs
266
DPR Checklist – Stage 5 – Technical Schedules (Structures)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Bid documents- EPC Yes ☐ No ☐ NA ☐ NA
2 Bid documents- Other, if any Yes ☐ No ☐ NA ☐ NA
3 Draft concession agreement Yes ☐ No ☐ NA ☐ NA
3 Schedule C - Project facilities Yes ☐ No ☐ NA ☐ NA
4 Schedule D - Specifications and standards Yes ☐ No ☐ NA ☐ NA
5 Any other relevant details Yes ☐ No ☐ NA ☐ NA
267
DPR Checklist – Stage 6 – LA and Clearances II Report (Structures)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
2 Environment Clearance Yes ☐ No ☐ NA ☐ NA
2.1 Details of public hearings completed Yes ☐ No ☐ NA ☐
Date of final environment clearance by
2.2 Yes ☐ No ☐ NA ☐
competent authority
3 Forest Clearance Yes ☐ No ☐ NA ☐ NA
Date/ Details of Joint site inspection with
3.1
DFO/ competent authority Yes ☐ No ☐ NA ☐
Date of Stage I forest clearance approval
3.2
by competent authority Yes ☐ No ☐ NA ☐
Date of final forest clearance approval by
3.3 competent authority Yes ☐ No ☐ NA ☐
4 Wildlife Clearance Yes ☐ No ☐ NA ☐ NA
Date/ Details of joint site inspection with
4.1
DFO/ competent authority Yes ☐ No ☐ NA ☐
Date of final wildlife clearance approval by
4.2
competent authority Yes ☐ No ☐ NA ☐
5 Utility Clearances (Electricity) Yes ☐ No ☐ NA ☐ NA
Date/ Details of Joint site inspection with
5.1 Yes ☐ No ☐ NA ☐
competent authority
Date of estimate submission by competent
5.2 Yes ☐ No ☐ NA ☐
authority
Date of estimate approval by competent
5.3 authority Yes ☐ No ☐ NA ☐
5.4 Approved utility shifting proposal Yes ☐ No ☐ NA ☐
Details of approved contractors, SoR and
5.5 Yes ☐ No ☐ NA ☐ NA
deposit details for user agency
Utilities checklist, no upgradation certificate
5.6 attached Yes ☐ No ☐ NA ☐
Date of estimate submission by competent
6.2
authority Yes ☐ No ☐ NA ☐
Date of estimate approval by competent
6.3
authority Yes ☐ No ☐ NA ☐
6.4 Approved utility shifting proposal Yes ☐ No ☐ NA ☐
Details of approved contractors, SoR and
6.5 Yes ☐ No ☐ NA ☐ NA
deposit details for user agency
Utilities checklist, no upgradation certificate
6.6
attached Yes ☐ No ☐ NA ☐
268
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
Date of estimate submission by competent
7.2
authority Yes ☐ No ☐ NA ☐
Date of estimate approval by competent
7.3 Yes ☐ No ☐ NA ☐
authority
7.4 Approved utility shifting proposal Yes ☐ No ☐ NA ☐
Details of approved contractors, SoR and
7.5
deposit details for user agency Yes ☐ No ☐ NA ☐ NA
Utilities checklist, no upgradation certificate
7.6 Yes ☐ No ☐ NA ☐
attached
Date of final approval of GAD by competent
8.2 Yes ☐ No ☐ NA ☐
authority
9 Other Clearances Yes ☐ No ☐ NA ☐ NA
Date of final approval by competent
9.1 Yes ☐ No ☐ NA ☐
authority
10 Land Acquisition Yes ☐ No ☐ NA ☐ NA
10.1 Draft 3a notification submitted Yes ☐ No ☐ NA ☐ NA
10.2 Review of 3a notification by client Yes ☐ No ☐ NA ☐ NA
10.3 Date of 3a gazette notification Yes ☐ No ☐ NA ☐
10.4 Draft 3a notification submitted Yes ☐ No ☐ NA ☐ NA
10.5 Review of 3A notification by client Yes ☐ No ☐ NA ☐ NA
10.6 Date of 3A gazette notification Yes ☐ No ☐ NA ☐
Date of Joint Measurement Survey with
10.7
competent authority Yes ☐ No ☐ NA ☐
10.7.1 Date of survey Yes ☐ No ☐ NA ☐ NA
10.7.2 Land type –by survey number Yes ☐ No ☐ NA ☐ NA
10.7.3 Nature of Land –by survey number Yes ☐ No ☐ NA ☐ NA
10.7.4 Ownership status of plots- by survey
number Yes ☐ No ☐ NA ☐ NA
10.7.5 Verification of area to be acquired – by
Yes ☐ No ☐ NA ☐ NA
survey number
10.7.6 List of structures on each plot Yes ☐ No ☐ NA ☐ NA
10.7.7 Sketches of updated alignment Yes ☐ No ☐ NA ☐ NA
10.7.8 Verification from Land revenue department Yes ☐ No ☐ NA ☐ NA
10.7.9 Verification by CALA office Yes ☐ No ☐ NA ☐ NA
269
1.1.3 DPR Checklist – Stage 7 – Award determination (Structures)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Remarks
Specifications
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
2 Village level summary Yes ☐ No ☐ NA ☐ NA
Total private and public land being
2.1
acquired Yes ☐ No ☐ NA ☐ NA
270
1.1.4 DPR Checklist – Stage 8 – Land possession report (Structures)
General Details
Project Name
Consultant's Name
Date of Review
Details/
S.No SECTION OF THE REPORT YES/NO/NA Specification Remarks
s
1 Executive Summary Yes ☐ No ☐ NA ☐ NA
2 Village level summary Yes ☐ No ☐ NA ☐ NA
2.1 Total private and public land being acquired Yes ☐ No ☐ NA ☐ NA
Date of final award by CALA and approval
2.2
by NHAI
Status of disbursement on date of receipt of
2.3 Yes ☐ No ☐ NA ☐ NA
Land possession certificate
Key issues being faced in completing land
2.4 acquisition, if any Yes ☐ No ☐ NA ☐ NA
3 In detail Yes ☐ No ☐ NA ☐ NA
Updated land acquisition tracker with status
of:
3.1 Notifications Yes ☐ No ☐ NA ☐ NA
Award
Disbursement
3.2 Final award and claims report Yes ☐ No ☐ NA ☐ NA
Copies of notifications published, land
3.3
possession certificates received Yes ☐ No ☐ NA ☐ NA
4 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
4.1 Conclusions and recommendations Yes ☐ No ☐ NA ☐ NA
Report fulfils project objectives and scope as
4.2
per RFP Yes ☐ No ☐ NA ☐ NA
4.3 Report reviewed for errors and omissions Yes ☐ No ☐ NA ☐ NA
Compliance report prepared on client
4.4
observations Yes ☐ No ☐ NA ☐ NA
GIS Map containing digitised details of
5 land parcels acquired with all relevant Yes ☐ No ☐ NA ☐ NA
details
271
National Highways Authority of India
(Ministry of Road Transport & Highways)
Government of India
272
Table of Contents
1 Introduction 275
2 Project overview 276
2.1 Key features of project 276
2.2 Key plan of existing project stretch 278
3 Traffic demands on project road 279
3.1 Traffic volume surveys 279
3.2 Axle load survey 280
3.3 Traffic volume forecast 280
3.4 Turning movement surveys 281
4 Pavement and corridor surveys 282
4.1 Pavement condition and distress seen 282
4.2 Pavement composition 282
4.3 Pavement strength 283
4.4 Sub-grade soil survey 283
5 Improvement proposals 284
5.1 Proposed alignment 284
5.2 Bypasses proposed 284
5.3 Road geometry 285
5.4 Widening scheme 285
5.5 Pavement design 285
5.6 Design of structures 287
5.7 Intersections and grade separators 287
5.8 Toll plazas 288
5.9 Wayside amenities proposed 288
6 Environmental impact assessment 289
6.1 Impact and clearances needed 289
6.2 Cost of environmental mitigation 289
7 Social impact assessment and Land acquisition 290
7.1 Social impact assessment 290
7.2 Land acquisition requirements 290
7.3 Key risks envisaged in land acquisition 290
8 Utilities shifting and clearances 291
8.1 Utilities shifting estimates 291
8.2 Total cost of utilities shifting 291
9 Project cost estimates 292
273
10 Material investigation 293
10.1 Borrow pits for soil 293
10.2 Sand 293
10.3 Gravel 293
10.4 Fly ash 293
10.5 Bitumen 293
10.6 Cement 293
10.7 Other local material available 294
10.8 Key risks 294
10.9 Location of material sources 295
11 Potential for value engineering and innovative technologies 296
12 Economic and financial analysis 297
12.1 Economic analysis of the project 297
12.2 Financial analysis 297
13 Execution plan 299
13.1 Packaging 299
13.2 Bidding mode and timelines 299
13.3 Construction time and planning 299
14 Conclusions and recommendation 300
274
1. Introduction
The National Highways Authority of India proposes to implement the <re> the
development, maintenance and management of the <NH-xx> stretch from <Origin> to
<Destination> from chainage <aa km> to <bb km> into <proposed improvement, xx lane
road/ expressway etc.> under the NHDP Phase V programme. The proposed project road
has been selected to <primary reason for project- e.g. to improve connectivity and ease
congestion between aa bb>
<Consultant> was appointed in <mm/yyyy> to prepare the detailed project report for
the project road, and this executive summary covers is submitted along with the
<draft/final> detailed project report to cover the key aspects of the project.
<Any special circumstances or requests made by the Authority for the project that
affect the consultancy assignment e.g.: NHAI desired to restructure project into two
packages, bifurcating the project road at Betulnagar, this report has been revised and
resubmitted providing improvement proposals and bid documents separately for the two
stretches>
275
2. Project overview
As described earlier the project road lies on NH xx (previously NH yy) and connects
<orgin> with <destination>, passing through the states of <state 1, state 2>. The proposed
project alignment passess through <towns/junctions a, b, c, d> for a total length of <xx
km>.
Attributes Details
NH No Xx (old)
Yy (new)
Service lanes and slip roads Service lanes of 2-4m width for 16 km, largely in urban
areas
276
Right of way Typically 45 m along entire stretch
Land use along project road Predominant land use in the area is agricultural (60%
on LHS, 50% on RHS), with the rest being urban and
forest area (20% on LHS, RHS)
Traffic on the stretch Largely commercial, with trucks accounting for 80% of
vehicle volume
User amenities along stretch 32 bus shelters, 7 truck lay-byes, and 1 rest area
Key utilities in the proposed RoW 4 km 66 kV UG line with 3 crossings, 30in water main
for 7.3 km
Forest Stretches along RoW Xx km of road from <point a> to <point b> crosses
<type of forest> <forest name>
Other clearance related aspects <please describe any other clearances that will be
required for the project>
277
2.2. Key plan of existing project stretch
<lat/long> <lat/long>
<lat/long>
278
3. Traffic demands on project road
3.1. Traffic volume surveys
For the purposes of traffic projections and lane design, <xx> individual sections of
road were considered:
Table 2: Traffic survey locations
Length Volume Count
Section Chainages Remarks
(Kms) Locations
Kasia/Tonta mines near
1 Km 163.0 - 192.0 29.0 Km 177.0, 45.0
192.000
End point of proposed Koida
2 Km 192.0 - 219.0 27.0 Km 201.50
bypass at km 218.250
Traffic volume surveys for the project road were < available from IHMCL for x
locations> and were carried out at <x> additional locations along the project road in the
month of <mm/yyyy>. The results are as follows:
Table 3: Results of traffic surveys conducted
Homogenous section 1 1 2
Chainage 45.00 177.00 201.50
Source of data IHMCL Consultant Consultant
Bicycle 47 75 61
2 Wheeler 3320 3288 2630
3 Wheeler 32 47 30
Tractor 24 18 22
Tractor with Trailer 389 385 341
2 Axle SCV 436 386 388
LMV 2 axle 3561 3545 3327
LCV 2 Axle 577 603 563
2 Axle Truck or Bus 908 987 1014
3 Axle Truck or Bus 1142 1062 1086
Multi Axle Vehicles MAV 2033 1962 1994
Oversized Vehicle OSV 2 1 3
Cycle 0 0 0
Earth Moving Equipment 0 0 0
279
AADT (in PCUs) 34000 xx xx
280
3.4. Turning movement surveys
17:00 - 3 arm No
1 0.300 xxx 30988 1915
18:00
09:00 - 4 arm No
2 6.200 xxx 28077 1962
10:00
15:00 - 5 arm Yes
3 10.200 xxx 53333 3599
16:00
10:00 - 4 arm Yes
4 28.000 xxx 64315 3884
11:00
281
4. Pavement and corridor surveys
282
4.3. Pavement strength
<xxx FWD/BBD> was carried out to test the strength of the existing pavement, and
the characteristic deflection values have been calculated for each homogeneous section of
road to enable design of an overlay for the road.
Table 9: Strength of existing pavement
Characteristic
Chainage Distance
Section deflection
Start End Km Mm
1 0.400 2.400 2.000 1.6
2 2.400 10.000 7.600 1.3
X
283
5. Improvement proposals
Bypass plan
Urban area to be
Start End Length Key driver for by-pass
bypassed
chainage chainage proposed
Nagar 1 45.000 52.000 21.000 Heavy local traffic of ~10,000 PCUs in
town limits
Xxxx
284
5.3. Road geometry
The project road has been re-designed to accommodate speeds of <xx>, adopted as
per <standard or consultation with NHAI>. Enabling this higher speed will require re-design
and re-alignemnt of the road in certain sections given their <description of poor geometry>.
Chainage Traffic
forecast Service
Section Start End Lane config. Comments
k PCUs in lanes
20xx
1 0.00 2.400 43.5 6 Yes High urban traffic influx
2 2.400 60.400 16.4 4 No
3
xx
Basis availability of RoW and land acquisition constraints, a widening scheme has
been proposed that makes optimum use of existing ROW and minimizes need for land
acquisition in urban areas, a summary of which is given below:
Table 14: Summary of widening type proposed
285
5.5.2. Design sub-grade strength
Considering the soil investigations conducted in the prject road area, and the
availability of suitable soil in the region, the following sub-grade strength has been assumed
to vary from <xx%> to <yy%> for various sections of the highway
Sub-grade Pavement
Design Chainage Layer thickness (mm)
Section strength loading
Start End Min % CBR MSA GSB WMM DBM BC xx
1 0.400 2.400 10% 40 200 250 95-125 40
2 2.400 10.000 8%
X
286
5.5.5. Pavement design for service lanes
Pavement for service lanes is designed for MSA of xx-yy with a design CBR of ~xx%.
The composition for the <flexible/rigid> service lane pavement along the project corridor
is as follows:
Sl Construct New
Structure Existing Dismantle Widen Reconstruct Total
No in parallel construction
1 Major bridge 4 1 - 1 2 3 7
2 Minor bridge
3 Flyover
4 Vehicle
overpass
5 Vehicle
underpass
6 Passenger
under pass
7 Culverts
8 xxx
Grade separator
2 28.000 xxx 64315 3884
287
SL. Existing Est total vol (k Est Peak Hour
Location Improvement proposed
No. Chainage PCU) Vol (k PCU)
288
6. Environmental impact assessment
The Environmental Mitigation and Management Costs were developed based on the
estimation of resources required to implement the mitigation measures proposed and also
number of places where intervention is required. Environmental mitigation cost for the
proposed project is Rs. <xx> cr.
289
7. Social impact assessment and Land acquisition
The existing RoW (x-y m) is <adequate/ in adequate> for the proposed widening and
RoW requirements as required by <NHAI/Authority>. This will lead to the additional
acquisition of <xx>Ha across the states of <states1, 2>, affecting a total of <yy> villages in
<zz> districts. In addition to structures found to be encroaching the current Row, the
required acquisition is poised to affect <xx> residential and <yy> other structures.
Preliminary interactions have been held with locals to understand their issues and
concerns and help communicate the project plan and its impact on them. The key concerns
of title and non-title holders centered around:
<Key issues expressed over and above land being acquired, and
compensation norms>
7.2. Land acquisition requirements
The state and district wise details and status of land acquisition as on the date of
publishing of this report is as follows:
Table 23: Districtwise land acquisition requirements and status
Private land
Total land 3A done,
Village and to be 3A pending 3D
State required 3D pending
Chainage acquired (Ha) completed
(Ha) (Ha)
(Ha)
Thane
Maharashtra 137 90 10 70 10
(xx to yy)
Gujarat <aaa> 454 400 20 300 80
Gujarat <bbb> 588 588 60 500 28
Gujarat <ccc> 688 320 80 160 80
A total of <xx cr> is expected to be awarded for the acquisition of land required for
this project. The land acquisition process is underway with a total of <xx> CALAs appointed,
and 90% of land is expected to be in possession by <xx, 20xx>.
Utilities belonging to <x> user agencies have been identified that fall within the
project road ROW and will need to be shifted to enable road construction. Shifting
proposals have been submitted to the user agencies and initial estimates have been
received from the concerned agencies. The process of site inspection, review and revision
of the proposals for utilities shifting is in process.
<To enable better management of utilities and installation going forward, all utilities
are being shifted underground/into a utilitiy corridor/out of the road RoW/ utilities trench
is being planned as part of construction>
8.1. Utilities shifting estimates
Table 24: Key utilities shifting requirements
The total cost of utilities shifting for all the utilities identified in the road RoW is
estimated to be <xx cr> with supervision charges of <yy cr> being paid as supervision
charges to the <z> concerned agencies.
291
9. Project cost estimates
The cost estimates for the project has been carried out based on detailed design, bill
of quantitities, and the schedule of rates for <state/district/authority> of year <xx-yy>.
Table 25: Summary of project cost
292
10. Material investigation
Material investigations were carried out to explore the availability and identify
sources of suitable material for the construction of the road.
<retain only relevant sections>
10.2. Sand
Sand is available in <close proximity> of the project site. Test results show that xx
of yy sand sources satisfy the minimum requirement for use in the project.
<Include details of additional potential for sources such as pond bed desilting, other
excavation happening>
10.3. Gravel
Several quarries were identified for sourcing aggregates in the project zone. Xx of yy
quarries were found to be suitable for use in the construction of the road. <further details
on gravel available and suitability for construction>
10.5. Bitumen
Bulk bitumen of the <required grades> is available <closest sources> with an average
lead of <xx km>. For the project road <grade> of bitumen has been proposed for <yy layer>
due to <reason> and <grade of bitumen> has been proposed for <zz layer> due to <reason>.
10.6. Cement
Bulk bitumen of the <required grades> is available <closest sources> with an average
lead of <xx km>. For the project road <grade> of bitumen has been proposed for <yy layer>
due to <reason> and <grade of bitumen> has been proposed for <zz layer> due to <reason>.
293
10.7. Other local material available
Details of other local material available for construction
Table 26: Localy available and alternative materials
Sl No Material Source
1 Hume pipes Local hume pipe factory in xx yy
2 xx xxxx
294
10.9. Location of material sources
295
11. Potential for value engineering and innovative technologies
Throughout the detailed design of the project, several opportunities for value
engineering and introduction of new technology were explored that will help in reducing
the cost of the project or increase quality and longevity of project road. Approval of these
elements as part of the construction design and suitable instructions to all stakeholders of
the project can help significantly lower the projected cost of construction.
A summary of these opportunities is provided here.
Table 28: Key value engineering opportunities identified
Sl
Value engineering opportunity Potential impact
No
1 Use of inverted pavement with a cement stabilized based and 40% reduction in layer thickness and
granular material in the base layer ~15% reduction in TPC
296
12. Economic and financial analysis
RUCS HDM 4
Option Sensitivity Case NPV (in NPV (in
EIRR (in %) EIRR (in %)
million Rs.) million Rs.)
Base Case 0 19199 30.31 2788.5 14.1
Sensitivity 1 18041 27.51 1362.6 12.9
With time
Sensitivity 2 15147 27.1 943.3 12.8
Sensitivity 3 13989 24.56 -ve 11.7
Base Case 0 19199 30.31 2788.5 14.1
Sensitivity 1 18041 27.51 1362.6 12.9
Without time
Sensitivity 2 15147 27.1 943.3 12.8
Sensitivity 3 13989 24.56 -ve 11.7
297
3 Axle Truck or Bus 1142 1062
Multi Axle Vehicles MAV 2033 1962
Oversized Vehicle OSV 2 1
Earth Moving Equipment 0 0
Figure 5: Equity IRR with increasing concession period for project road
298
13. Execution plan
13.1. Packaging
Given the length of the project, the entire project is planned to be bid out in <xx>
packages with <yy> packages.
<include table of package details if more than 1 package>
299
14. Conclusions and recommendation
The project as envisaged is economically viable with an estimated EIRR >12%. The
project with a 30 year concession period is expected to return an equity IRR of <xx%> with
<yy%> <grant/premium> and is hence recommended for implementation in the
<BOT/EPC/HAM> mode.
Table 31: Salient features and key financial aspects of the project road a
Project road
Project road length Xx km
Connecting <origin>- <destination>
On national highway NH No
Proposed features Current road Proposed
Lanes 2 4
Bypasses proposed - 5
Major junctions 5 5
Minor Junctions 18 18
Grade separated interchanges 1 4
Major Bridges 4 6
Minor Bridges 19 21
ROBs 1 3
Culverts 120 200
Vehicle/Pedestrian under/overpasses 16 25
Service roads (kms) 14 32
Slip roads (kms) 8 9
Toll plazas (no) - 2
Bus bays (no) 4 15
Truck lay-byes (no) 2 8
Rest areas (no) 2 6
Financial implications INR Cr/%
Total capital cost 1595
Total project cost 1486
300
Civil construction cost (incl. contingency) 1249
Preconstruction expenses 110
Land acquisition 40
Utilities shifting 30
Rehabilitiation and resettlement costs 20
Other pre-construction expenses 20
Implementation mode proposed BOT (Toll)
Total project cost 1486
Concession period 18 years
<Authority> support (Grant/Premium) 18%
Estimated NPV 50
Project IRR 12%
Equity IRR 15%
301
302