MSPDCL Tariff Order Fy 2019-20
MSPDCL Tariff Order Fy 2019-20
MSPDCL Tariff Order Fy 2019-20
``
TARIFF ORDER
AND
FOR
ABBREVIATIONS
Abbreviation Description
A&G Administrative and General
AAD Advance Against Depreciation
ARR Aggregate Revenue Requirement
CAG Controller and Auditor General of India
CEA Central Electricity Authority
CERC Central Electricity Regulatory Commission
CWIP Capital Work in Progress
DG Diesel Generation
DPS Delayed Payment Surcharge
EA, 2003 Electricity Act, 2003
EDM Electricity Department, Manipur
EHT Extra High Tension
FSA Fuel Surcharge Adjustment
FY Financial Year
GFA Gross Fixed Assets
GOI Government of India
HT High Tension
IEGC Indian Electricity Grid Code
ISGS Inter State Generating Station
IR Inter Regional
Joint Electricity Regulatory Commission for Manipur and
JERC
Mizoram
kV Kilovolt
kVA Kilovolt-ampere
kW kilowatt
kWh kilowatt-hour
LT Low Tension
MAT Minimum Alternate Tax
MDI Maximum Demand Indicators
MSPCL Manipur State Power Company Limited
MSPDCL Manipur State Power Distribution Company Limited
MUs Million Units
MYT Multi Year Tariff
NLDC National Load Despatch Centre
NTI Non-Tariff Income
O&M Operation and Maintenance
PGCIL Power Grid Corporation of India Ltd
PLF Plant Load Factor
PLR Prime Lending Rate
POSOCO Power System Operation Corporation Ltd.
PPA Power Purchase Agreement
PWW Public Water Works
R&M Repair and Maintenance
RoE Return on Equity
RGGVY Rajiv Gandhi Gramina Vidyutikaran Yojana
True up for FY 2017-18, Annual Performance Review for FY 2018-19 and determination of
Aggregate Revenue Requirement (ARR) and retail Tariff for FY 2019-20 for sale of electricity
by the Manipur State Power Distribution Company Limited (MSPDCL) in the State of
Manipur
AND
Present
Mr. Lalchharliana Pachuau
Chairperson
ORDER
2. JERC (M&M) (MYT) Regulations, 2014 specify that the distribution licensee shall file ARR
and Tariff Petition in all aspects along with requisite fee as specified in Commission’s
fees, fines and charges regulations, on or before 30 th November of the preceding year.
MSPDCL has filed petition for determination of ARR and retail tariffs for FY 2019-20
along with true up petition for FY 2017-18 on 24.12 2018. However, the petition for
Annual Performance Review (APR) for FY 2018-19 was submitted on 27.02.2019.
considering the bare figures of revenue realised from LT & HT consumers within state
and from surplus energy sales. No break-up details were provided by the MSPDCL in
support of their submission and hence, the Commission could not finalise the True-up
pending availability of the basic audited accounts figures. Fundamentally, the true-up
would be processed on due verification of the audited actuals which are missing in this
case and hence, there is no question of making any true-up for FY 2017-18 and it cannot
be entertained at this juncture under these constraints.
Accordingly, MSPDCL has published the Tariff Petition in an abridged form as public
notice in the following newspapers and the Tariff petition was also placed on the
website of MSPDCL. The last date for submission of suggestions/objections was fixed as
7th February 2019.
SI. No. Name of the Newspaper Language Date of Publication
1 Imphal Free Press English 26th & 27th January 2019
31st January 2019 &
2 Poknapham Manipuri
1st February 2019
The Commission received one objection / suggestion from all Manipur Power
Consumers’ Association on the petition filed by the MSPDCL. The Commission passed
on the objection received to MSPDCL for communicating their response on the
objections raised.
The Commission, to ensure transparency in the process of Tariff determination and for
providing proper opportunity to all stake holders and general public for making
suggestions/objections on the Tariff petition and for convenience of the consumers and
general public across the state, has decided to hold a public hearing at the
headquarters of the state.
8. Notice for Public Hearing
Accordingly, the Commission published a notice in the following leading newspapers
giving due intimation to the general public, interested parties, objectors and the
consumers about the public hearing to be held at Imphal on 7.03.2019.
Sl.
Name of the news paper Language Date of Publication
No
1 Poknapham Manipuri 19th & 20th February 2019
2 Imphal Free Press English 26th & 27th February 2019
9. Public Hearing
The Public hearing was held as scheduled on 7.03.2019 at Hotel Classic Grande, Imperial
Hall, Imphal from 11 AM to 12:30 PM. During the public hearing, each objector was
provided a time slot for presenting before the Commission his/her views on the petition
of the MSPDCL. The main issues raised by the objectors during the public hearing and
corresponding response of the MSDPCL are briefly narrated in Chapter - 4.
10. The proposal of MSPDCL was also placed before the State Advisory Committee in its
meeting held on 5th March 2019 at Hotel Classic Grande, Regency Hall, Imphal from
11.00 AM and various aspects of the Petition were discussed by the Committee.
11. The Commission took into consideration the facts presented by the MSPDCL in its
Petition and subsequent filings, the suggestions/objections received from stakeholders,
consumer organizations, general public and State Advisory Committee and response of
the MSPDCL to those suggestions/objections for approval of the ARR and tariff petition
for FY 2019-20.
12. The Commission has reviewed the directives issued earlier in the Tariff orders for FY
2010-11 to FY 2018-19 and noted that some of the directives are compiled and some
are partially attended. The Commission has dropped the directives which are complied
fully and the remaining directives are consolidated and fresh directives are added.
13. In exercise of the powers vested under section 62 read with section 64 of the Electricity
Act 2003 and Regulation 16 JERC for M&M (Multi Year Tariff) Regulations, 2014
(hereinafter referred to as Tariff Regulations) and other enabling provisions in this
behalf the Commission issues this order approving of the ARR and tariffs for supply of
electricity in the state of Manipur.
15. The MSPDCL should ensure implementation of the order from the effective date after
issuance of a public notice, in such a font size which is clearly visible in two daily
newspapers having wide circulation in the state within a week and compliance of the
same shall be submitted to the Commission by the MSPDCL.
16. This order shall be effective from 1st April, 2019 and shall remain in force till the next
Tariff Order of the Commission.
Place : Aizawl
Date: 26.03.2019
1. Introduction
1.1 JERC for Manipur and Mizoram (JERC, M&M)
In exercise of the powers conferred by the Electricity Act 2003, (hereinafter referred
to as Act) the Government of India constituted Electricity Regulatory Commission for
the States of Manipur and Mizoram to be known as “Joint Electricity Regulatory
Commission for Manipur and Mizoram” vide GOI. Gazette (Extra Ordinary)
Notification No. 23/3/2002 R&R dated 18/01/2005, (hereinafter referred to as
Commission) as per the authorization given by the Government of Manipur and the
Government of Mizoram vide Memorandum of Agreement dated 23/07/2004. The
Commission is constituted with a two-member body designated to function as an
autonomous authority responsible for regulation of the power sector in States of
Manipur and Mizoram. The powers and functions of the Commission are as
prescribed in the Act. The head office of the Commission is presently located at
Aizawl, the capital town of Mizoram. The Commission became functional w.e.f
January 24th, 2008.
a) In accordance with the Act, the Commission discharges the following functions:
i. Determine the tariff for generation, transmission, distribution and wheeling
of electricity, wholesale, bulk or retail, as the case may be, within the State:
Provided that where open access has been permitted to a category of
consumers under Section 42 of the Act, the State Commission shall determine
only the wheeling charges and surcharge thereon, if any, for the said category
of consumers;
ii. Regulate electricity purchase and procurement process of distribution
licensees including the price at which electricity shall be procured from the
generating companies or licensees or from other sources through agreements
for purchase of power for distribution and supply within the State;
iii. Facilitate intra-State transmission and wheeling of electricity
iv. Issue licenses to persons seeking to act as transmission licensees, distribution
licensees and electricity traders with respect to their operations within the
State;
b) Further, the Commission also advises the State Government on all or any of the
following matters namely:
i. Promotion of competition, efficiency and economy in activities of the
electricity industry;
ii. Promotion of investment in electricity industry;
iii. Reorganization and restructuring of electricity industry in the State;
iv. Matters concerning generation, transmission, distribution and trading of
electricity or any other matter referred to the State Commission by the State
Government.
c) The State Commission ensures transparency while exercising its powers and in
discharging its functions.
d) In discharge of its functions, the State Commission is guided by the national
Tariff Policy (NTP) as brought out by GOI in compliance to Section 3 of the Act.
The objectives of the NTP are to:
Ensure availability of electricity to consumers at reasonable and competitive
rates;
Ensure financial viability of the power sector and attract investments;
Promote transparency, consistency and predictability in regulatory
approaches across jurisdictions and minimize perceptions of regulatory risks;
Promote competition, efficiency in operations and improvement in quality of
supply.
Prayer
MSPDCL requests the Hon’ble Commission to:
a. Admit the Petition for Limited Provisional True-up for FY 2017-18 and Tariff
Determination for FY 2019-20, as submitted herewith;
b. Approve the amounts claimed in the Limited Provisional True-up for FY 2017-18;
Petitioner to add/ change/ modify/ alter this filing and make further submissions
as may be required at a future date;
e. Permit submission of any additional information required by the Commission
during the processing of this Petition;
f. Pass such other and further orders as are deemed fit and proper in the facts and
circumstances of the case.
b) Power Purchase
The MSPDCL is mostly dependent on Central Generating Stations (CGS) located in
different parts of the North Eastern Region for meeting its energy requirement.
The total firm share from own generation and the Central Sector Generating
Stations of NEEPCO and NHPC and Tripura is 174.30 MW as shown in the Table
below. The actual peak and off-peak availabilities are however always less
because of low plant load factors.
The energy drawls from various central generating stations and Tripura during 2017-
18 are given Table below:
Table3. 3: Energy Drawls from Central Generating Stations & Tripura
(MU)
Station FY 2017-18
NEEPCO (Hydro)
Kopili I HEP 76.31
Kopili II HEP 7.66
Khandong HEP 16.52
Station FY 2017-18
Ranganadi HEP 116.98
Doyang HEP 20.47
Sub total 237.94
NEEPCO (Gas Based)
Assam Gas based Power Project 117.62
Agartala Gas Turbine Power Project 53.84
Agartala Gas Extension
Sub total 171.46
NHPC (Loktak HEP)
Purchased (20.02MW) 247.02
Free Power (12.60 MW) 97.16
Sub total 344.18
TRIPURA
Baramura (Gas Based)- (Unit IV and V) 41.49
OTPC-Pallatana (Unit I) 222.55
OTPC-Pallatana (Unit II)
Sub Total 264.04
NTPC Bongaigaon (Unit I) 29.78
NTPC Bongaigaon (Unit II & III)
Sub total 29.78
Total 1047.40
UI Purchases/IEX 8.97
Gross Power Purchase 1056.37
(Transmission and Distribution)
For the purpose of drawing power from the Central Sector generating stations and
other sources in the North Eastern Region, the MSPDCL has utilized 1 no. of 400 kV
D/C line presently charged at 132 kV and 4 No’s single circuit 132kV interstate
transmission lines, 3 (three) being owned by PGCIL and two by MSPCL, as detailed
below.
Owned by MSPCL
Leimatak-Ningthoukhong-Karong-Kohima-132 kV line.
Leimatak-Jiribam-132 kV line
Owned by PGCIL
Silchar – Imphal – 400 kV D/C line charged at 132 kV
Leimatak – Imphal - Dimapur – 132 kV line.
Leimatak - Jiribam – 132 kV line.
Manipur, being a hilly state with its population unevenly dispersed and spread over
remote corners, it is having large network of Sub-Transmission and Distribution
system. The details of Distribution network, owned & operated by MSPDCL as on
SI. FY 2017-18
Consumer Category
No No. of Consumers Connected Load
(Nos) (KW)
A LT Category 365661 541372.34
1 Kutir Jyoti 69639 10491
2 Domestic 278049 472683.3
3 Commercial 15161 37902.04
4 Public lighting 441 1144
5 Public waterworks LT 15 190
6 Agriculture & Irrigation LT 39 117
7 Small and cottage industry 2317 18845
HT Category 1047 50380.21
Commercial 35 1097
9 PWS HT 169 14845
10 Agriculture HT 25 625
8 Medium industry 73 1095
11 Large industry 27 3992.7
12 Bulk supply 718 28725.51
13 Grant Total 366708 591752.55
3.5 Demand
The energy demand of the MSPDCL is met by supply of power from own generation,
central generating stations of North Eastern Region and Baramura Gas Based Plants
in Tripura State. The annual energy requirement during the FY 2017-18 is 691.15 MU.
As per Load Generation Balance Report (LGBR) of NERPC for FY 2017-18 the
Maximum Demand during FY 2017-18 is 202 MW.
One written objection is received, received from all Manipur Power Consumers
Association, Imphal.
4.2 Public Hearing
In order to ensure transparency in the process of determination of tariff as envisaged
in the Electricity Act, 2003, Public Hearing was held at Hotel Classic Grande, Regency
Hall, Imphal on 7th March 2019 from 11 A.M. to 12:30 P.M. During the Public Hearing
the participants from general public were given an opportunity to offer their views in
respect of the ARR and Tariff Petition for FY 2019-20 of MSPDCL. The list of
stakeholders who attended the Public Hearing is given in Annexure-II. The Officers of
MSPDCL who attended the Public Hearing responded on the issues raised by the
objectors.
4.3 Proceedings of Public Hearing
The Objector, the Secretary, All Manipur Power Consumers’ Association has raised
the following objections from the said association and the item wise replies as
furnished by the Licensee MSPCL are placed below:
OBEJECTION-1
All India average per capita consumption of energy for the year(2017-18) was 1149 kwh,
whereas per capita consumption for some NE States for the year 2015-16, 2016-17 and
2017-18 were given below(in kwh):
From the figures, it is evident that Manipur is Lowest in Power Consumption till (2017-18),
after depriving Interior Remote Areas and Industries of Manipur by Power Companies of
Manipur particularly MSPDCL but they still claimed as one of the best in India instead of
claiming lowest per capita consumption of the country(India), even may be lowest in the
World.
Today Per capita consumption of Energy for Manipur is 286 Units (2017-18) and 459 Units
(2017-18) as that of Mizoram, far below all India level of 1149 Units (2017-18). It is therefore
requested that JERC(M&M) kindly consider not to increase the existing Retail tariff Rates of
(2018-19) with the backwardness of the area in mind and Manipur already Levied more
during (2018-19) for enable to bring per capita consumption in the national level in the
coming years.
MSPDCL Submission-It is pertinent to mention that the per capita consumption comes out
to be 299.13 units for the FY 2017-18 where actual energy available at the state is taken for
FY 2017-18 as submitted to Hon'ble Commission in limited provisional true-up petition and
population in the state of Manipur taken as of census 2011.
It is pertinent to mention that Manipur state has very limited number of Industrial
Consumer and that is the main reason for low per-capita consumption in the state of
Manipur, although the state is having
surplus power.
However, MSPDCL is taking every initiative to improve the per-capita by implementing the
central government schemes like Saubhagya in which every house will be electrified in the
state after completion of the scheme. In this way the per capita consumption of the state
will increase.
OBEJECTION-2
On the other hand, as per LGBR, CEA (2018-19) indicates Manipur has maximum energy
shortage in the NE Region at 5.2% and next to Jammu and Kashmir in the National Level,
whereas our State Planners particularly MSPCL and MSPDCL tried to reduce the energy
consumption of Manipur at their best level on the following counts while filling Retail Tariff
Petition for FY-2019-20:
It is pertinent to mention that Manipur state is a power surplus state in totality. According
to the limited provisional true-up petition filled by MSPDCL, there is a surplus power of 207
.74 MUs in the FY 2017-18 and for the FY 2018-19, there is surplus power estimated and
submitted to the Hon'ble commission in the APR filling for the FY 2018-19.
OBJECTION-3
No provision for Kutri Jyothi program. Please restore the programme for the poor.
No Provision for Kutir Jvoti- As per Kutir Jyoti Scheme, a consumer consuming more that 45
units of electricity in consecutive 3 months will be treated and charged as per domestic
category tariff. It is pertinent to mention that as per data available from April 2018-
September 2018, no consumer has been booked in the category of Kutir Jyoti (However, the
numbers may vary from the actual figure once accounts get finalized).
OBJECTION-4
Reduced the initial ceiling limit of energy at 0-30 Units (2019-20) from 0-100 Units (2018-19)
for Normal Domestic Consumers and increased the fixed Charges at Rs. 70/- per kW (2019-
20) for the connected load from Rs.60/- per Kw(2018-19) connected load, the highest rate
chargeable in any NE Region.
Please increase the initial ceiling limit of energy at 0-120 Units for FY-(2019-20) and reduce
the fixed Charges at par with the other NE States.
OBJECTION-5
In brief Under the same Joint Electricity regulatory Commission i.e. JERC (M&M), there are
2(two) different retail Tariff rates, that too entirely different angels.
Mizoram can look after better for their public than that of Manipur but their performance
for the FY-(2018-19) is also sleeping from the preceding FY (2017-18).
Please arrange similar retail Tariff rates for Manipur and Mizoram.
OBJECTION-6
While preparing the Tariff Rates, the Power Companies of Manipur, i.e. MSPCL and MSPDCL,
have forgotten, Manipur belongs to SPECIAL CATEGORY STATE and comparing with the
other advance & bigger states of India for misleading the JERC (M&M) and general public.
Manipur has improved drastically and in doing so the fixed expenses i.e. power purchase
cost, employee cost etc has been increasing simultaneously. It is important to mention that
Manipur State Government has informed MSPDCL through letter, that State is in financial
crisis and cannot increase the revenue subsidy for the FY 2019-20.
MSPDCL has been left with no other option to meet its Approved ARR other than proposal of
increase in tariff to Hon'ble Commission.
OBJECTION-7
The Power Companies of Manipur, i.e MSPCL and MSPDCL, never encourage the program of
MNRE target installed capacity of Renewable Energy of 175GW by 2022, as the tariff also
coming down to a very affordable rate(now below Rs.2.50 per Unit as per SECI) as per MNRE
for bigger projects(both Wind and Solar).
Reply of MSPDCL :
MSPDCL and MSPCL never encourage the program of MNRE target installed capacity of
Renewable energy of 175 GW by 2022:
It is to submit that the Nodal Agency for the Renewable Energy for Manipur State is
MANIREDA. Policies formulation and primary approval of the project is done by MANIREDA.
5.1.1 Background
The Commission had approved the ARR and tariff for FY 2017-18 vide Tariff Order
dated 28.02.2017 based on projected data by MSPDCL. The Commission had carried
out annual performance review for FY 2017-18 in its Tariff Order dated 12.03.2018
based on revised estimates furnished by MSPDCL. Now the MSPDCL has filed petition
for Provisional True up for FY 2017-18 based on actuals without audited accounts. As
per Regulation 10.6(ii) of JERC(MYT) Regulations 2014 the Commission has to
undertake true up based on audited accounts and pass an order recording approved
aggregate gain or loss on account of controllable factors and the amount of such gain
or loss may be shared in accordance with Regulation 13 of JERC for M&M (MYT)
Regulations 2014 and the components of approved cost pertaining to uncontrollable
factors which were not recovered during previous years shall pass through as per
Regulations 12 of JERC M&M (MYT) Regulations 2014. As per Regulation 12 read
with regulation 13 of JERC M&M (MYT) Regulations 2014 one third of gains or losses
on account of uncontrollable factors shall be passed through as an adjustment in the
tariff of the distribution licensee for such period as may be specified in the order of
the Commission passed under these regulations.
The balance amount which will amounts to two-third of such gain may be utilized at
the discretion of the distribution licensee.
As the MSPDCL has not filed audited accounts, the Commission has carried out
provisional true up as requested by MSPDCL without passing on profit/ loss.
The category wise actual number of consumers and connected load as compared to
the earlier estimates for FY 2017-18 as mentioned in the tariff order for dated 28
February 2017 are as given below.
The actual category wise energy sales as compared with the energy sales as
approved by the Commission for FY 2017-18 in its tariff Order dt.28.02.2017 and now
approved by the commission are given below:
Table 5.2: Category wise Energy sales approved by the commission after true up for FY 2017-18
(MU)
Approved in Actuals Energy Sales Now
Sl.
Category T.O Dated furnished by approved by the
No
28.02.2017 MSPDCL Commission
1 Kutir Jyoti 7 18.17 18.17
2 Domestic 372 336.57 336.57
3 LT Commercial 42 47.33 47.33
4 HT Commercial 6 - -
5 Public Lighting 5 3.67 3.67
6 LT Public Water-works 4 1.24 1.24
7 HT Public Water-works 15 19.83 19.83
8 LT Agri. &Irrigation 1 1.29 1.29
9 HT Agri. &Irrigation 1 0.83 0.83
10 Cottage & Small Industries 18 19.25 19.25
11 Bulk 95 106.63 106.63
12 Medium Industries (HT) 4 3.73 3.73
13 Large Industries (HT) 6 5.31 5.31
14 Temporary - 0.14 0.14
The actual surplus energy available and sold by MSPDCL in the Indian Energy Exchange
(IEX) in FY 2017-18 was 207.73 MU as compared to the surplus quantum of 297.02 MU
approved by the Hon’ble Commission in the Tariff Order for FY 2017-18.
The actual Distribution Loss of 22.98% achieved by MSPDCL in FY 2017-18 is higher than
the normative Distribution Loss of 18.40% approved by the Hon’ble Commission in the
Tariff Order for FY 2017-18, as shown in the Table above.
MSPDCL respectfully submits that the actual Distribution Loss are slightly higher than
the approved figures, on account of Manipur having a hilly terrain and characterized
by population spread throughout the State. The distribution system network in the
State consists of long length of distribution and LT lines. In recent years, majority of
the new connections through various schemes are in the LT category, which inherently
incurs higher Distribution Loss.
MSPDCL wishes to bring to the attention of the Hon’ble Commission that in the above-
said Order, the Distribution Loss have been calculated with reference to the energy
injected at the State Periphery, as the Distribution Loss for FY 2017-18 have been
considered as equal to the arithmetical difference between T&D Loss and
Transmission Loss of 3.6% approved by the Hon’ble Commission (i.e., 22% - 3.6% =
18.40%). Hence, for the purpose of Limited True-up for FY 2017-18, MSPDCL has also
calculated the Distribution Loss with reference to the energy injected at State
periphery, which works out to 20.68%. The corresponding Distribution Loss with
reference to the energy injected into the distribution system works out to 22.98%.
The inter-State Transmission loss has been considered as 2.62%, based on the
Interstate transmission loss in North-Eastern Region for FY 2017-18, and has been
deducted from the total Power Purchase quantum. Further MSPDCL has added the UI
Over drawal and subtracted UI Under drawal and Surplus sales from the Net Power
Purchase to compute the Net Power available at State Periphery for sale within the
State of Manipur.
MSPDCL has considered the intra-State Transmission (MSPCL) loss of 10% for
computing the power available at the DISCOM periphery. The Hon’ble Commission has
been allowing intra-State Transmission loss of only 3.6%. MSPDCL respectfully submits
that in other States, 33 kV system is part of the distribution network, whereas, in
Manipur, the 33 kV system is part of MSPCL network, and the distribution network is
from 11 kV and below voltages. Thus, when other SERCs have approved intra-State
Transmission Losses of around 3 to 4%, the 33 kV loss has also been separately
approved as around 5-6%, which works out to total loss of around 10% upto 33 kV
level. The relevant data from some selected States, based on data available in the
public domain, is given in the Table below:
Hence, the intra-State Transmission (MSPCL) loss of 10% considered by MSPDCL for
computing the Energy Balance is appropriate and needs to be allowed.
Further, MSPDCL respectfully submits that the Distribution Loss approved by the other
SERCs are generally higher than the Distribution Loss approved by the Hon’ble
Commission, as shown in the Table below:
Table 5.5: Distribution Loss and AT&C loss approved by Different SERCs
Approved by
State Particulars Utility/Department Order Reference
Commission
Department of
Petition No. TP 01 of
AT&C Loss for Power, Government
Arunachal Pradesh 2018, dated 31May, 44%
FY 2016-17 of Arunachal
2018
Pradesh
Distribution Meghalaya Power
Case No. 1/2018, dated
Meghalaya Loss for FY Distribution 21%
25September, 2018
2017-18 Corporation
Distribution
Bihar Losses for FY NBPDCL Case No. 40 of 2017 24%
2017-18
Source: Latest Tariff Orders of respective SERCs
It is further submitted that MSPDCL has been incorporated in recent years and it has
taken significant steps over the years to reduce the Distribution Loss. Hence, in view of
all the above, MSPDCL requests the Hon’ble Commission to approve the actual
Distribution Loss of 20.68% for FY 2017-18.
Commission’s Analysis
The distribution loss calculation done by MSPDCL is not in order.
The pool losses in NER adopted by MSPDCL are in correct. As per actual average
weekly loss from 03.04.2017 to 01.04.2018 the pool loss in NER system is 2.61%. Intra
state transmission loss are however adopted at 7.97%. IEX purchases of 8.97MU and
UI over drawls of 15.73 MU are considered. Surplus energy sales are 270.34 MU
excluding UI under drawal of 13.34 MU, but not 207.74MU as furnished by MSPDCL.
Distribution loss should be at distribution periphery but not at state periphery. So the
distribution loss during FY 2017-18 is recalculated as detailed in the table below.
Table 5.6: Calculation of distribution loss during FY 2017-18 approved by the Commission
Sl. Actual FY
Particulars Unit
No 2017-18
A Own Generation MU -
B Power purchase from CGS in NER MU 1047.40
C Pool loss % 2.61
D Pool loss MU 27.34
E ADD: UI purchases & IEX MU 24.70
F Less: UI sales (Surplus Power) MU 270.34
G Energy available (A+B+E)-(D+F) MU 774.42
H Less: Intra state transmission loss at 7.97% MU 83.27
I Net energy available for sale MU 691.15
J Energy sales within the state MU 563.98
K Distribution Loss MU 127.17
L Distribution Loss% % 18.40%
Thus the distribution loss works out to 18.40% as against 22.98% furnished by
MSPDCL.
The MSPDCL shall conduct system studies and energy audit after proper metering
systems are put into operation. Further, segregation of technical and commercial
loss has to be completed by Sept-2019.
Commission’s Analysis
The reasons for NIL generation is not furnished by MSPDCL. The Commission
however provisionally approves own generation at NIL MU for FY 2017-18 after
true up.
Table 5.9: Power purchase approved by the Commission for FY 2017-18 after True up
(MU)
Now
Commission Actuals
SI. Approved
Particulars Approved in T. O furnished
NO by the
dated 28.02.2017 by MSPDCL
Commission
A NEEPCO
Kopili I
1 64.04 76.31 76.31
2 Kopili II 6.77 7.66 7.66
3 Khandong 10.75 16.52 16.52
4 Ranganadi 106.45 116.98 116.98
5 Doyang 18.12 20.47 20.47
6 Kamang stage I 18.40 - -
7 Pare - - -
8 Sub total 224.53 237.94 237.94
B NEEPCO (GB )
9 AGBPP 132.99 117.62 117.62
10 AGTPP 73.75 53.84 53.84
11 AGTPP ext - - -
12 Monarchank Gas based P.P. - - -
13 Sub Total 206-74 - 171.46
C NHPC
14 Loktak
14(i) Purchased 180.08 247.02 247.02
14(ii) Free Power 70.83 97.16 97.16
15 Sub total 250.91 344.18 344.18
D TRIPURA
16 Baramura IV& V 81.84 41.49 41.49
E O T PC
17 Pallatana I & II 220.23 222.55 222.55
18 Sub total 307.07 264.04 264.04
F NTPC
19 Bongaigaon I 83.70 29.78 29.78
20 Sub total 83.70 29.78 29.78
21 UI Over drawl - - 15.73
22 IEX - 8.97 8.97
23 Total 1067.95 1056.37 1072.10
Commission’s Analysis
The MSPDCL has not considered UI Over drawal of 6.02 MU. After considering this
quantity, the total power purchase works out to 1062.39 as follows:
Power Purchase from Generating Stations 1047.40
UI Over drawal 15.73
24.70
IEX Purchase 8.97
Total 1072.10
Table 5.10: Energy Balance approved by the Commission for FY 2017-18 after true up
Approved by
Now
the Actuals
Sl. Approved
Particulars Unit commission Furnished by
No by the
in T.O dated MSPDCL
Commission
28.02.2017
A Energy Requirement
1 Energy Sales MU 576 563.98 563.98
2 Distribution loss % 18.40 22.98 18.40
3 Distribution loss MU 129.88 168.29 127.17
4 Energy Requirement MU 705.88 732.27 691.15
B Energy Availability
5 Own Generation (Net) MU 0.68 - -
6 Power Purchase MU 1067.95 1056.36 1047.40
7 Less: External Losses % 2.65 2.62 2.61
8 Less: External Losses MU 28.30 27.68 27.34
Net energy available at
9
state periphery (6-8) MU 1039.68 1028.68 1020.06
10 UI Purchase -7.32 24.70
11 Total (5+9+10) 1040.36 1021.36 1044.76
Transmission Loss (T.L) @ 81.36 83.27
12
3.6% MU 37.45 (@7.97%) (@ 7,97%)
Energy Available for
13
Distribution MU 1002.91 940.00 961.50
14 Surplus (13-4) MU 297.02 207.73 270.34
Surplus grossed up by T.L
15 % for sale outside the 308.12 225.71 293.76
state MU (@3.60%) (@ 7.97%) (@ 7.97%)
(Source Table 7 and 9 of Petition)
Commission’s Analysis
As seen from the data furnished by MSPDCL it is observed that the petitioner has
erred in calculation of energy requirement with distribution loss of 20.68%. Had the
distribution loss is taken as 22.98%, it is worked out as under.
The MSPDCL has not furnished further data to energy balance. As such the energy
balance is worked out with the available data which resulted in surplus power of
293.76 MU. UI under drawal of 13.34 MU is not considered as it comes under UI
sales.
Thus the Energy balance resulted in surplus power of 293.76 MU which was sold
under UI Sales.
5.7 Power Purchase Cost
Petitioner’s submission
The MSPDCL has furnished actual power purchase cost of Rs.337.26 Crore during FY
2017-18 as detailed in Table below:
Table 5.11: Power Purchase cost actuals furnished by MSPDCL for FY 2017-18
Average Total
SI. Quantity
Particulars Rate adopted cost
No (MU)
MSPDCL (Rs./kWh) (Rs. Cr)
1 NEEPCO (Hydro )
2 Koppilil I 76.31 1.17 8.91
3 Koppilil II 7.66 1.25 0.96
4 Khandong 16.52 1.76 2.91
5 Ranganadi 116.98 2.21 25.81
6 Doyang 20.47 4.90 10.03
7 Kamang stage I
8 Sub Total 237.94 11.29 48.62
9 NEEPCO(G
10 AGBPP 117.62 3.37 39.69
11 AGTPP 53.84 2.88 15.50
12 Sub Total 171.46 6.25 55.19
13 NHPC
14 Loktak
15 Power Purchases 247.02 2.68 66.29
16 Free Power 97.16 - -
17 Sub Total 344.18 2.68 66.29
18 TRIPURA
19 BARAMURA IV & V 41.49 3.00 12.43
20 OTPC
21 Pallatana I& II 222.55 3.25 72.29
22 Sub Total 264.04 6.25 84.72
23 NTPC
24 Bangaigaon 29.78 16.61 49.46
Average Total
SI. Quantity
Particulars Rate adopted cost
No (MU)
MSPDCL (Rs./kWh) (Rs. Cr)
25 UI/over drawal 1.574
26 UI Under drawal (-)2.304
27 Solar
0
28 Non solar
29 U I Purchases/IEX 8.97 3.39 3.04
30 NERLDC charges 0.64
31 Arrears/Supplementary charges 25.37
32 Reimbursement 4.68
33 Total 1056.37 337.26
Commission’s Analysis
Commission in its order dated 29.02.2017 had approved power purchase cost of Rs.
317.33 Crore for purchase of 1067.95 MU including free power of 70.83 MU from
Loktak and renewable energy certificates cost for solar at Rs.1.02 Crore and non
solar at Rs.11.06 Crore at an average cost of Rs.2.97/kwh.
As seen from the actuals furnished by MSPDCL, it is observed that the following item
which will not come under power purchase cost are included as detailed below:
Sl.
Particulars MU Amount Remarks
No
1 UI Under drawal 13.34 2.304 To be accounted for under sale
of surplus power
2 NERLDC Charges - 0.64 To be accounted for in
transmission charges.
As such the above items are deleted from power purchase cost. There by the power
purchase cost works out to Rs.338.92 Crore for purchase of 1072.10 MU including
UI/IEX purchase of 24.70 MU (15.73+8.97) and free power of 97.16 MU from Loktak
at an average cost of Rs.2.91/kWh excluding arrears payment etc of Rs.30.05 Crore
and Rs.3.19/kWh including arrear payment etc of Rs. 30.05 Crore as detailed in table
below:
Table 5.12: Power Purchase cost considered by the commission for FY 2017-18
Average
Total
SI. Quantity Rate adopted
Particulars cost
No (MU) MSPDCL
(Rs. Cr)
(Rs./kWh)
1 NEEPCO (Hydro )
2 Koppilil I 76.31 1.17 8.91
3 Koppilil II 7.66 1.25 0.96
4 Khandong 16.52 1.76 2.91
5 Ranganadi 116.98 2.21 25.81
6 Doyang 20.47 4.90 10.03
7 Kamang stage I
8 Sub Total 237.94 2.043 48.62
9 NEEPCO(G
10 AGBPP 117.62 3.37 39.69
11 AGTPP 53.84 2.88 15.50
12 Sub Total 171.46 3.22 55.19
13 NHPC
14 Loktak
15 Power Purchases 247.02 2.68 66.29
16 Free Power 97.16 - -
17 Sub Total 344.18 1.93 66.29
18 TRIPURA
19 BARAMURA IV & V 41.49 3.00 12.43
20 OTPC
21 Pallatana I& II 222.55 3.25 72.29
22 Sub Total 264.04 3.21 84.72
23 NTPC
24 Bangaigaon 29.78 16.61 49.46
25 Subtotal 29.78 16.61 49.46
25 UI/over& under drawal 15.73 1.00 -0.73
26 Solar
1.65
27 Non solar
28 U I Purchases/IEX 8.97 3.38 3.04
39 Subtotal 24.70 6.264
30 Total 1072.10 2.54 308.87
Arrears/Supplementary
31 25.37
charges
32 Reimbursement 4.68
33 Total 1072.10 3.19 338.28
The Commission provisionally considers power purchase cost of Rs. 338.28 Crore
for purchase of 1072.10 MU including UI purchase of 24.70 MU and free power of
97.16 MU for FY 2017-18 and payment of supplementary bills of Rs. 25.37 Crore
and reimbursement of Rs.4.68 Crore but excluding NERLDC charges of Rs.0.64 crs
for the purpose of true up. However, the true-up would be finalised on assessing
a. Employee Expenses, which includes the Basic Pay, Dearness Pay, Dearness
allowances, house rent allowances, and other allowances, new pension scheme
paid to the staff;
b. Repair and Maintenance (R&M) Expenses, which includes all expenditure
incurred on the maintenance and upkeep of distribution assets; and
29.02.2016 and actuals furnished by the MSPDCL and now approved by the
Commission are furnished in Table below:
Table 5.14:Employee Cost approved by the Commission for FY 2017-18 after true-up
(Rs. Cr)
Approved
in Tariff
Sl. Actuals furnished Now approved by
Particulars Order
No. by MSPDCL the Commission
dated
28.02.2017
1 Employees Cost 83.98 74.20 74.20
MSPDCL requests the Hon’ble Commission to approve the actual R&M expenses of
Rs. 8.91 Crore for FY 2017-18.
The actual A&G expenses in FY 2017-18 are significantly lower than the actual A&G
expenses in FY 2016-17 (Rs. 10.98 crore), as approved by the Hon’ble Commission in
the Limited Provisional true-up for FY 2016-17. MSPDCL requests the Hon’ble
Commission to approve the actual A&G expenses of Rs. 7.31 Crore for FY 2017-18.
The Commission provisionally considers Rs 7.31 Crore towards Administration and General
Expenses as per the actuals furnished by MSPDCL for FY 2017-18 after true up.
Commission’s Analysis
The MSPDCL has not submitted audited annual accounts from 2015-16 to 2017-18.
However, MSPDCL has furnished unaudited annual accounts for FY 2015-16 & FY
2016-17. Based on closing CWIP to end of 31.03.2015 the year-wise CWIP is arrived
as follows, which are inconformity with the annual accounts for FY 2015-16 and FY
2016-17.
Sl. FY FY FY
Particulars
No 2015-16 2016-17 2017-18
1 Opening CWIP 506.26 845.51 1068.93
2 Investment during the year 423.58 326.66 Not furnished
Sl. FY FY FY
Particulars
No 2015-16 2016-17 2017-18
3 Capitalisation during the year 84.34 103.24 20.05
4 Closing CWIP (1+2-3) 845.51 1068.93
While so, the capital investment furnished by MSPDCL in the petition and capital
investment as per annual accounts are furnished here under:
Sl. As per Annual
Year As per petition
No Accounts
1 2015-16 - 423.58
2 2016-17 55.00 326.66
3 2017-18 55.00 Not furnished
Commission’s analysis
In the ARR petition for FY 2017-18 MSPDCL has stated that the loans before
Petitioner’s Submission
The major part of capital expenditure undertaken by MSPDCL is funded by the State
Government’s grants and consumer contribution. However, in addition to these
sources of funds, MSPDCL has also taken a significant amount of loan from REC for
RAPDRP-B Project and RGGVY project, and a Vehicle loan from SBI. The Hon’ble
Commission had approved Interest expenses of Rs. 0.19 crore in the Tariff Order for
FY 2017-18, including interest on Consumer Security Deposit of Rs. 0.03 crore. The
repayment of loans during the year has been considered equal to the depreciation
claimed for the year, in accordance with the JERC (MYT) Regulations, 2014, and the
repayment has been considered proportionately based on the opening loan balance.
The details of loans with the computation of Interest on loan is shown in the Table
below:
Commission’s Analysis
The MSPDCL in its MYT petition for FY 2016-17 and FY 2017-18 has stated that there
are no outstanding loans at the beginning of FY 2016-17 and Rs.1 Crore each taken
during FY 2016-17 and FY 2017-18. Interest during FY 2016-17 and FY 2017-18 is
furnished as follows:
Table 5.22: Interest on Loan approved by the Commission for FY 2017-18
Sl.
Particulars FY 2016-17 FY 2017-18
No.
1 Opening Loan 0.00 0.77
2 Additions during the year 1.00 1.00
3 Repayment 0.23 0.26
4 Closing Loan 0.77 1.51
5 Average Loan 0.39 1.14
6 Rate of Interest 14% 14%
7 Interest charges 0.05 0.16
8 Interest on consumer S.D 0.02 0.03
9 Total Interest 0.07 0.19
In the absence of audited accounts for FY 2017-18 the interest amount of RS.0.19
Crore including interest on consumer security deposit is considered, tentatively.
The Commission provisionally considers interest and finance charges at Rs.0.19
Crore for FY 2017-18 including interest on consumer security deposit.
(i) The Distribution Licensee shall be allowed interest on the estimated level of
working capital for the financial year, computed as follows:
(a) Operation and maintenance expenses for one month; plus
(b) Maintenance spares at one (1) per cent of the historical cost escalated at 6%
from the date of commercial operation; plus
(c) Receivables equivalent to one (1) month of the expected revenue from sale of
electricity at the prevailing tariffs; minus
(d) Amount held as security deposits under clause (a) and clause (b) of sub-section
(1) of Section 47 of the Act from consumers except the security deposits held in
the form of Bank Guarantees;
(ii) Interest shall be allowed at a rate equal to the State Bank Advance Rate (SBAR)
as on 1st April of the financial year in which the Petition is filed.”
The computation of normative Interest on Working Capital (IoWC) for MSPDCL for FY
2017-18, in accordance with the above-reproduced Regulations, is shown in the Table
below:
MSPDCL requests the Hon’ble Commission to approve the IOWC of Rs 4.89 Crore for FY
2017-18.
Commission’s Analysis:
The SBAR as on 01.04.2017 is 13.85% but not 14.05%. Maintanance of spares also not
correctly calculated. As such interest on working capital revised as detailed in table
below:
Table 5.24: Interest on Working Capital for FY 2017-18 considered by the Commission for true-up
(Rs.Cr)
Sl.
Particulars Total Cost One Month
No
1 O&M Expenses one month (90.42 /12) 90.42 7.54
2 Maintenance of spares at 1% of GFA escalated by 6% 742.23 7.42
3 Receivables for one month 237.83 19.82
4 Less: Amount held under SD 0.67
5 Sub Total 34.106
6 SBAR rate as on 01.04.2017 13.85%
7 Interest on Working Capital 4.72
at Rs 3.00 Crore for FY 2017-18. The MSPDCL has not written off any amount.
Commission Analysis
As no amount is written off during FY 2017-18 the Commission has not considered
any amount, towards provision for bad debts.
The Commission provisionally approves Rs NIL Crore towards provision for bad
debts for FY 2017-18 after true up.
5.15 Return on Equity
The Commission in its Order dated 28.02.2017 had approved RoE at Rs 1.95 Crore for
FY 2017-18. The MSPDCL has now furnished RoE at Rs 1.95 Crore for FY 2017-18.
The Commission provisionally considers RoE at Rs 1.95 Cr for FY 2017-18 after true
up.
5.16 Non-Tariff Income
The Hon’ble Commission approved Non-Tariff Income of Rs. 0.37 Crore in the Tariff
Order for FY 2017-18. The actual Non-Tariff Income earned by MSPDCL in FY 2017-
18 was Rs. 5.35 Crore, as shown in the Table below:
Table 5.25: Non-Tariff Income for FY 2017-18
(Rs. Cr)
Sl.No Particulars Approved Actuals
1 Interest from Bank 4.19
2 3.75% Agency Charge 0.54
3 Miscellaneous Receipt 0.58
4 Fees from Tender forms 0.05
Total 0.37 5.35
The Commission provisionally considers non-tariff income at Rs. 5.35 Crore for FY
2017-18 after true up.
Table 5.26: Aggregate Revenue Requirement approved by the Commission for FY 2017-18
after true up
(Rs. Cr)
Approved
Sl. Actuals by Approved by the
Particulars in T.O dt
No MSPDCL Commission
28.02.17
1 Fuel Cost 1.19 - -
2 Power purchase cost 317.33 337.26 338.28
3 Transmission charges (MSPCL) 68.15 68.15 64.94
4 Transmission charges 57.45 45.16 45.16
5 SLDC Charges 3.10 0.14 0.14
6 NERLDC - - 0.64
6 Employee costs 83.98 74.20 74.20
7 Repair & Maintenance expense 6.88 8.91 8.91
Administration & General
8 2.65 7.31 7.31
Expenses
9 Depreciation 0.21 1.96 0.18
10 Interest & Finance Charges 0.19 6.70 0.19
11 Interest on Working capital 5.22 4.89 4.72
12 Provision for bad debts 3.00 -
Total Cost 549.35 554.68 544.67
13 Add: Return on Equity / ROE 1.95 1.95 1.95
14 Less: Non-Tariff income 0.37 5.35 (-) 5.35
15 Surplus on true up of FY 2014-15 10.89 (-) 10.89 (-) 10.89
Net Aggregate Revenue
540.04 540.39 530.38
Requirement
Commission’s Analysis:
Based on energy sales of 563.98 MU now approved by the Commission and the
surplus power of 270.34 MU arrived the revenue from sale of power has to be
worked out pending the details of the revenue from each category consumer is not
available from the ARR filings, the mere revenue amount of 237.83 crs cannot be
acceptable to the Commission and this will be taken up on submission of the audited
annual account in due course but this is not decided yet.
6.1 Background
The Commission in its Order dated 12.03.2018 had approved ARR and Tariffs for FY
2018-19 based on projected data by MSPDCL. Now MSPDCL has not filed the petition
for annual performance review for FY 2018-19 even in spite of protracted
correspondence. Though the JERC for M&M (MYT) Regulations, 2014 do not
specifically provide for annual performance review, the Commission considers it
appropriate and fair to revisit and review the approvals granted by it in the tariff
order for FY 2018-19 with the information for FY 2018-19 without altering the
principles and norms adopted earlier under suo-moto. These matters are discussed
in succeeding paragraphs.
6.2 Energy sales
The category wise sales approved by the Commission in its Order dated 12.03.2018
and now approved by the Commission are furnished in table below.
Table 6.1: Energy sales approved by the Commission for FY 2018-19 after review
(MU)
Approved Sales in Now Commission
Sl. No Name of category
T.O Dt.12.03.2018 approved
A LT Industrial 421.2 481.21
1 Kutir jyoti 15 20.96
2 Domestic 337 386.83
Commercial LT 42 44
3 Cottage and Small Industry 19 19.62
4 Public Lighting 5 5
5 Public Water Works 2 3.6
6 Irrigation and Agriculture 1.2 1.2
HT industrial 138.77 145.46
Commercial HT 6 7.89
1 Medium Industry 4 4.1
2 Large Industry 5 5
3 Bulk supply 106 110.21
4 Public water works 17 17.34
5 Irrigation and Agriculture 0.77 0.92
Total 559.97 626.67
(Source Table 5.6 of Order dated 12.03.2018)
The Commission approved energy sales at 626.67 MU for FY 2018-19 after review.
Commission analysis
The MSPDCL in their APR petition submitted on 27th February 2019 had indicated
that distribution losses would be at 17.715%. Therefore, distribution losses already
approved at 16.40% vide Commissions Order dated 12.03.2018 is now revised to
17.715% after review, as it is the reality that their losses have gone past the set
target and cannot be controlled in one month’s time during March 2019.
Thus the Commission approved distribution loss of 17.715% for FY 2018-19 after
review.
6.4 Energy Requirement
The Commission its Order dated 12.03.2018 had approved energy requirement at
669.82 MU with distribution loss of 16.40%.
But as agreed in the Tripartite Memorandum of understanding dated 26.07.2016
amongst MOP Government of India, Government of Manipur and MSPDCL at New
Delhi, transmission losses have to be reduced from 3.6% to 3.2% by FY 2018-19 and
AT & T loss be reduced to 25.15 % in 2016-17, 18.70% in 2017-18 and 15% in 2018-
19.
However, the distribution loss is considered at 17.715% for FY 2018-19 after
reviewing the reality. Accordingly, with the approved energy sales of 559.97 MU the
energy requirement arrived at 761.83 MU for FY 2018-19 after review as detailed in
the detailed in the table below.
The estimated energy requirement furnished by MSPDCL and now approved by the
Commission are furnished in table below.
Table 6.2: Energy requirement for FY 2018-19 approved by the Commission after review
Installed FY 2018-19
Sl.
Station Capacity Share Allocation AVG Allocation
No.
MVA (MWs) in (%)
A NEEPCO(Hydro)
1 Kopili I HEP 200 14.78 7.39%
2 Kopili II HEP 25 1.74 6.95%
3 Khandong HEP 50 3.28 6.56%
4 Ranganadi HEP 405 33.9 8.37%
5 Doyang HEP 75 5.9 7.87%
Sub total 755 59.60 7.89%
B NEEPCO(Gas Based)
1 Assam Gas based Power Project 291 23.6 8.11%
2 Agartala Gas Turbine Power Project 129.9 10.69 8.23%
Sub total 420.9 34.29 8.15%
C NHPC(Loktak HEP)
1 Purchased 105 31.62 42.50%
Sub total 105 31.62 30.11%
D TRIPURA
1 Baramura (Gas Based)(Unit IV) 21 5.25 25%
2 Baramura(Gas Based)(Unit V) 21 5.25 25%
Sub total 42 10.50 25%
E New Projects
Installed FY 2018-19
Sl.
Station Capacity Share Allocation AVG Allocation
No.
MVA (MWs) in (%)
1 OTPC- (Pallatana-Unit I) 363.3 21.035 5.79%
2 OTPC-(Pallatana-Unit II) 363.3 21.035 5.79%
Sub Total 726.6 42.07 5.79%
3 NTPC
i) Bongaigaon-1 500 37.5 7.50%
ii) Bongaigaon-1 500 37.5 7.50%
iii) Bongaigaon-1 500 37.5 7.50%
iv) Para HEP 110 7.84 7.13%
Sub Total 1610 120.34 7.47%
Total 3659.5 298.42 8.15%
The energy purchase approved for FY 2018-19 in MYT Order dated 12.03.2018 is
adopted for review also as detailed in the table below.
Table 6.4: Power purchase approved by the Commission for FY 2018-19 after review
Power purchase approved
Sl. No Name of source
by the Commission
A CGS- NEEPCO
1 Kopili I HEP 69.36
2 Kopili II HEP 7.16
3 Khandong HEP 13.74
4 Ranganadi HEP 108.77
5 Doyang HEP 19.60
6 AGBPP 121.63
7 AGTPP 62.41
B CGS-NHPC
1 Loktak HEP 195.46
2 Free Power 74.16
C Others
1 Baramura IV & V 60.42
2 OTPC-Pallatana I & II 251.38
3 NTPC-Bongaigaon 139.10
Total 1123.19
Commission’s analysis
The Commission approves power purchase of 1123.19 MU for FY 2018-19 including
free power of 74.16 MU from Loktak after review.
Table 6.5: Energy balance approved by the Commission for FY 2018-19 after review
Approved by
Now approved
SI. the Commission
Particulars Unit by the
No. in Order dated
Commission
12.03.2018
A Energy requirement
1 Energy sales MU 559.97 626.87
2 Distribution loss % 16.40 17.715
3 Distribution loss MU 109.85 134.96
4 Energy requirement (1+3) MU 669.82 761.83
B Energy availability
5 Own generation MU 0.68 0
6 Power purchase MU 1067.98 1123.19
7 Interstate loss on (6) % 2.65% 2.61
8 Interstate loss on (6) MU 28.30 29.32
9 UI purchase MU
Energy available at state
10
periphery (5+6-8+9) MU 1039.68 1093.87
11 Intra state transmission loss % 3.60 10.00
12 Intra state transmission loss MU 37.45 109.39
Net energy available at
13 distribution periphery 1004.35 984.49
14 Surplus (12-4) 334.53 222.66
15 Grossed up by Trans. Loss 345.24 247.40
Table 6.6: Power Purchase Cost estimated by the Commission for FY 2018-19 after review
FY 2018-19
S. No Source Purchased Total Cost Average rate
(MU) (Rs. Crs) (Rs/kWh)
A CGS - NEEPCO
1 Kopili -I HE 62.82 12.38 1.97
2 Kopili-II HE 6.93 1.39 2.006
3 Khandong HE 12.85 3.73 2.903
FY 2018-19
S. No Source Purchased Total Cost Average rate
(MU) (Rs. Crs) (Rs/kWh)
4 Ranganadi HE Project 109.18 36.50 3.343
5 Doyang HE Project 17.10 13.74 8.035
6 Assam GBPP 127.62 46.39 3.635
7 Agartala GTPP I & II 62.67 16.96 2.706
Kameng HEP Stage - 1
8 NA
(Upcoming on September 2016)
B CGS - NHPC
1 Loktak HEP 188.49 89.75 4.762
2 Loktak Free Power 74.16 0 0.00
C Other
1 Baramura GBPP Unit IV and V 75.47 13.21 1.75
2 OTPC Pallatana Unit I & II 214.06 81.67 3.815
D New Plants
1 NTPC Bongaigaon Unit I 45.56 24.67 5.41
2 NTPC Bongaigaon Unit II 45.56 24.67 5.41
3 NTPC Bongaigaon Unit III 22.78 12.33 5.41
4 Monarchak Gas Based PP (NEEPCO) NA
5 Kameng HEP Stage I NA
6 Kameng HEP Stage II NA
7 Para HEP 30.59 16.05 5.25
8 Tuirial HEP NA
9 Lower Subansiri Stage I NA
10 Lower Subansiri Stage II NA
11 Renewable-Solar 0 20.71
12 Renewable-Non Solar 0 1.73
Total 1095.84 415.88 3.795
The Commission approves power purchase cost of Rs.415.88 Cr including the RPO
Obligation of 22.44crs for FY 2018-19 after review.
Table 6.7: Transmission charges approved by the Commission for FY 2018-19 after review
(Rs. Cr)
SI. Approved by the
Particulars
No. Commission
1 PGCIL charges 58.21
2 MSPCL charges 71.57
3 SLDC charges 0.71
Total 130.49
Commission analysis
The Commission approves Administrative and General Expenses at Rs. 8.94 Cr for
FY 2018-19 after review.
Table 6.8: Summary of O&M expenses approved by Commission for FY 2018-19 after review.
(Rs. Cr)
Approved by the
SI. Approved by
Particulars Commission in its T.O
No. Commission
dated 12.03.2018
1 Employee cost 98.78 98.78
2 R&M expenses 7.27 7.27
3 Administrative and General expenses 8.94 8.94
4 Grand Total 114.99 114.99
The Commission approves depreciation at Rs. 0.24 Cr for FY 2018-19 after review.
Table 6.21: Interest and Finance charges estimated by MSPDCL for FY 2018-19
(Rs. Cr)
Repayment
Opening Drawals Closing
of loan Rate of Interest
Particulars Loan- during the balance
during the Interest on Loan
balance year of Loan
year
REC1 54.83 0 5.91 48.92 11.45% 5.94
Total Loan 54.83 0 5.91 48.92 11.45% 5.94
The Commission approves Interest and Finance charges at Rs.5.94 Crore for FY
2018-19 after review.
Commission’s Analysis
Commission in its Order dated 12.03.2018 had approved interest working capital at
Rs. 5.81 Cr for FY 2018-19 with the rate of interest at 13.85% providing then.
Now the rate of interest has been reduced to 13.45%. Accordingly, the interest on
working capital works out to Rs. 5.79 Cr for FY 2018-19.
Table 6.13: Interest on working capital approved by the Commission for FY 2018-19 after
review
(Rs. Cr)
Sl.
Particulars Total cost One month cost
No.
1 O & M Expenses one month 114.99 9.58
2 Maintenance of spares @ 1% of GFA
786.764 7.87
Escalated by 6%
3 Receivable one month 0.00 25.61
4 Total 43.06
5 SBAR as on 01-04-2018 13.45%
6 Interest on working capital 5.79
The Commission approves interest on working capital at Rs. 5.79 Cr for FY 2018-19.
The Commission had approved non-tariff income at Rs. 0.39 Cr for FY 2018-19 in its
Order dated 12.03.2018. While in the APR filing the same was indicated to be
Rs.5.40crs by the Licensee.
The Commission now approves the non-tariff income at Rs. 5.40 Cr for FY 2018-19
after review.
6.17 Revenue from energy sales for FY 2018-19
The revenue realization from the energy sales to be approved by the Commission for
FY 2018-19 could not be attempted as the Licensee fail to submit any sort of revenue
amount details in the entire APR filings and hence the Commission denies to assess
the expected revenue realization in their review for the FY 2018-19 in view of the in
adequate data submission.
The Commission approves revenue from sale of power at Rs. 369.76 Cr for FY 2018-
19 after review.
Table 6.14: Aggregate Revenue Requirement approved by the Commission for FY 2018-19
after review
Approved
Estimated by
SI. by Commission
Particulars MSPDCL
No. for FY 2017-18
(in Rs. Cr)
(in Rs. Cr)
1 Fuel cost
2 Power purchase cost 429.13 415.88
3 Interstate transmission charges 58.21 58.21
4 Intra state transmission charges 81.49 71.57
5 SLDC charges 1.42 0.71
6 Employee cost 98.78 98.78
7 R&M expenses 14.54 7.27
8 Administration & General expenses 4.16 8.94
9 Depreciation 0.24 0.24
10 Interest and finance charges 6.72 5.94
11 Interest on working capital 5.81 5.79
12 Provision for bad debt 3.00
13 RoE 1.95 1.95
14 Less: Non-tariff income 5.40 5.40
15 Net ARR 691.88 669.89
Approved in Approved by
SI. Tariff Order Commission for
Particulars
No. dated FY 2018-19
12.03.2018 (in Rs. Cr)
1 Net ARR 671.88 669.89
2 Total revenue 370.35 --
3 Revenue gap 301.70 --
Commission’s analysis
As seen from the above table the revenue gap could not be works out to due to non-
submission of the revenue related details of any sort for the Commission
examination for reasons not expressed at the time of review. Thus, no comments are
offered by the Commission on the revenue gap status.
7.1 Background
The ARR for the 2nd block of MYT control period from FY 2018-19 to FY 2022-23 was
approved in the Commission’s Tariff Order dt.12.03.2018.
Now, the MSPDCL has submitted revised ARR and Tariff petition for FY 2019-20. The
Commission has analysed the said petition in the following paras.
7.2 Energy Sales
Proper estimation of category wise energy sales is essential to determine the
quantum of power purchase and the likely revenue. This section examines in detail
the consumer category wise sales projected by the MSPDCL in its petition for
assessment of ARR.
7.3 Consumer Categories
The MSPDCL serves about 357750 consumers as on 31.03.2018 in its licensed area
and the consumers are categorized as under:
a) Kutir Joyti (LT)
b) Domestic(LT)
c) Commercial(LT&HT)
d) Public Lighting(LT)
e) Agricultural(LT&HT)
f) Public water works(LT&HT)
g) Cottage & Small industry(LT)
h) Medium industry(HT)
i) Large industry(HT)
j) Bulk supply(HT)
The MSPDCL serves the consumers at different voltages according to the consumer’s
requirement. In the categories, of Commercial, Agriculture and public water works
there are LT consumers as well as HT consumers, while medium Industry, Large
Industry and Bulk Supply categories are under HT only and Kutir Jyoti and domestic
categories are under LT only. Now the MSPDCL in its petition has stated that Kutir
Jyothi category has been clubbed with domestic (1st slab) category from 01.04.2019.
Commission’s Analysis
As verified from the Connected load with reference to number of connections during
FY 2019-20 the average connected load is not in conformity with the definition of
that particular category as detailed below.
Average
Sl. Connected
Category Consumer Connected Remarks
No load (KW)
Numbers load(KW)
Connected load of HT
1 Commercial HT 40 1127 28.18
supply should be > 50 KW.
Connected load of HT
2 Agriculture HT 39 118 3.026
supply should be > 50 KW.
Average
Sl. Connected
Category Consumer Connected Remarks
No load (KW)
Numbers load(KW)
Medium Industry Connected load of HT
3 73 1137 15.57
(HT) supply should be > 50 KW.
Connected load of HT
4 Bulk supply(HT) 735 29010 39.47
supply should be > 50 KW.
The MSPDCL is directed to verify the connected load of all the connections in the
above categories and furnish actual connected load on or before 30.06.2019. A
directive was also issued (Directive 11) in this regard long back. Under the
compliance to directives MSPDCL is silent over the physical verification of services. It
indicates that the seriousness of this directive is not felt by MSPDCL. MSPDCL is
directed to send a quarterly report on physical verification of services starting from
01.07.2019 onwards.
The Commission had made a revised estimation of the number of consumers and the
Contracted Load in MWs for the FY 2019-20 basing on the projected figures indicated
in their APR filings for FY2018-19 with suitable modifications where felt needed, The
estimates of the same is tabulated in the following table:
Table 7.1A: No. of Consumers and Contracted Loads revised by Commission for FY 2019-20
In this connection, it is to mention that the MSPDCL has projected category wise
energy rates during FY 2019-20 at 600 MU as against 599 MU approved by the
commission in its order dt.12.03.2018. The revenue from energy sales also calculated
on 600 MU.
But while furnishing energy requirement the MSPDCL has considered energy sales at
599 MU instead of 600 MU projected which is contradicting. However, as the
MSPDCL has considered energy sales of 600 MU for calculation of revenue etc.
The commission has considered energy sales at 631.44 MU and calculated energy
requirement as indicated in the above table.
Hence, the share of 72.10 MW is not considered till the COD of individual stations
are declared. As such the effective share of MSPDCL is 319.02 MW (391.12-72.10).
The Power Purchase approved by the commission in its MYT order dt.12.03.2018,
projected by MSPDCL and now approved by the commission is 1131 .37 MU.
Station wise details are furnished in table below:
Table 7.5: Power Purchase Quantum approved by the commission for FY 2019-20
(MU)
For FY 2019-
Total Power Purchase cost
20
Plant Licensee's Licensee's Energy
Sl.
Plant Capacity Share in Share in Quantity
No
(MW) % MW (MU)
For FY 2019-
Total Power Purchase cost
20
Plant Licensee's Licensee's Energy
Sl.
Plant Capacity Share in Share in Quantity
No
(MW) % MW (MU)
and V
2 OTPC Pallatana Unit I & II 726.60 5.79% 42.03 221.42
E New Plants
1 Para HEP 110.00 0.07 7.84 0
2 NTPC Bongaigaon Unit I 500 7.50% 37.50 48.85
3 NTPC Bongaigaon Unit II 500 7.51% 18.76 48.85
4 NTPC Bongaigaon Unit III 500 7.51% 18.76 48.85
Monarchak Gas Based
5 250.00 7.51% 18.76 NA
Power Project Neepco
6 Kameng HEP Stage I 101.00 4.00% 4.04 NA
7 Kameng HEP Stage II 300.00 2.33% 7.00 NA
8 Pare HEP 300.00 2.33% 7.00 NA
9 Tuirial HEP 110.00 4.00% 4.40 NA
10 Lower Subansiri Stage I 60.00 4.00% 2.40 NA
11 Lower Subansiri Stage II 1000.00 2.15% 21.50 NA
12 Renewable-Solar 0.00
13 Renewable-Non Solar 0.00
14 IEX
Total 6125.71 391.14 1131.37
Approved by
FY 2019-20 FY 2019-20
Sl. the commission
Particulars Unit Projected by Now
No in T.O
MSPDCL Approved
dt.12.03.2018
3 Distribution loss quantum MU 105.71 105.71 111.43
Energy Requirement at
4 MU 704.71 704.71 742.87
Distribution Periphery
B Energy Availability
5 Own Generation MU - - -
6 Power Purchase MU 1131.37 1131.37 1131.37
7 External Loss % 2.60% 2.60% 2.85%
8 External Loss MU 29.42 29.42 32.24
9 UI Purchases MU - - -
10 RPO Purchase MU - - -
Net Energy availability at MU
11 state Periphery 1101.95 1101.95 1099.13
(5+6-8+9+10)
12 Less: Transmission Losses % 3% 3% 8.5%
13 Transmission loss MU 33.06 33.06 93.43
Energy available for MU
14 1068.90 1068.90 1005.70
distribution (11-13)
15 Surplus (14-4) MU 364.19 364.19 262.83
Surplus grossed up by to
16 375.45 375.45 287.25
loss %
The MSPDCL is directed to sell these surplus power under UI through IEX by proper
planning in SLDC after meeting the states requirement without interruption and
realize maximum revenue.
Mizoram are adopted to all those commonly purchasing stations whose average
costs are lower than those adopted by MSPDCL, Manipur. The power purchase cost,
now approved by the commission for FY 2019-20, as a result of the above
modifications in the costs are detailed in table below:
Table 7.7: Power Purchase Cost approved by the Commission for FY 2019-20
FY 2019-20
Sl. No Source of Energy Purchases Total Cost Avg. CPU
(MU) (Rs.Crs) (Rs/kWh)
A CGS - NEEPCO
1 Kopili -I HE 65.41 7.97 1.22
2 Kopili-II HE 7.24 1.06 1.46
3 Khandong HE 13.42 2.41 1.80
4 Ranganadi HE Project 115.12 25.22 2.19
5 Doyang HE Project 18.13 8.01 4.42
6 Assam GBPP 131.75 49.74 3.77
7 Agartala GTPP I & II 64.55 22.99 3.56
Kameng HEP St- 1
8 NA
(Upcoming on 9/2016)
B CGS - NHPC
1 Loktak HE 194.10 64.89 3.34
2 Loktak Free Power 76.37 0 0.00
C Other
1 Baramura GBPP Unit IV and V 77.31 14.20 1.84
2 OTPC- Pallatana Unit I & II 221.42 72.65 3.28
D CGS - New Plants
1 NTPC Bongaigaon Unit I 48.85 27.77 5.68
2 NTPC Bongaigaon Unit II 48.85 27.77 5.68
3 NTPC Bongaigaon Unit III 48.85 27.77 5.68
Renewable Power
1 Renewable-Solar 0 23.12
2 Renewable-Non Solar 0 2.81
Grand Total 1131.37 378.36 3.34
The Commission approves the power purchase cost amount to be Rs. 378.36 Crore
for the energy quantity of 1131.37 MU including free power of 76.37 MU from
Loktak during the FY 2019-20.
7.13 Transmission Charges
Transmission charges approved by the commission for FY 2019-20 vide Tariff Order
Dt.12.03.2018 and projected by MSPDCL and now approved by the commission are
The Commission approves R & M expenses at Rs.7.69 Crore for FY 2019-20 same as
projected by MSPDCL.
7.14.3 Administrative and General Expenses
Petitioner’s submission
Table 7.11: Administrative & General Expenses approved by the commission for FY 2019-20
Approved in Projected by
Particulars Now Approved
MYT Order MSPDCL
A&G expenses 9.45 9.45 9.45
The Commission approves A & G expenses during Control period FY 2019-20 same
as projected by MSPDCL.
Table 7.4: Summary of O & M expenses approved by the Commission for FY 2019-20
(Rs. Cr)
Sl. FY
Particulars
No 2019-20
1 Employee Cost 106.68
2 R & M expenses 7.69
3 Administration and General expenses 9.45
Grand Total 123.82
GFA and depreciation approved by the commission in its order dated 12.03.2018,
same is assumed to be projected by MSPDCL (as they have not given any details in
their filing) and now approved by the commission are furnished in table below:
The Commission approves Interest and Finance charges at Rs.5.17 Crore for FY
2019-20 as projected by MSPDCL.
(c) Receivables equivalent to one month of expected revenue from charges for use
of distribution wires at the prevailing tariffs, minus
(d) Amount if any held as security deposit under change (b) of sub section (1) of
Section 47 of the Act from Distribution system users accept the security deposit
held in the form of bank guarantees.
Interest shall be allowed at a rate equal to the State Bank Advance Rate (SBAR) as
on 1st April of the financial year in which the petition is filed and the present rate
is 13.45 %.
Interest on working capital approved by the commission in its order
dt.12.03.2018, same is assumed to have projected by MSPDCL (as they have not
submitted any details in their filings) and now approved by the commission are
furnished in table below:
Table 7.16: Interest on Working Capital approved by the Commission for FY 2019-20
(Rs. Cr)
Approved Projected
Now
S. No. Particulars (Rs Cr) in Tariff by
Approved
Order MSPDCL
A) Receivables 739.02 316.87 587.67
A) ii) Receivables equivalent to 1 months 61.59 26.41 48.97
average billing
B) i) Maintenance spare (GFA) 1562.20 1136.99 833.97
B) ii) 1% of GFA escalated by 6% from the 16.43 12.05 8.34
CoD
C) i) O&M Expenses 132.15 123.82 123.82
C) ii) O&M Expenses one month 11.01 10.32 10.32
D) Total Working capital A) ii) - B) ii) - C)ii) 89.03 51.71 67.63
E) Less : Total Security Deposit - - 0.67
F) 89.03 51.71 66.91
Net working Capital requirement
Interest Rate 13.852 14.05 13.45
Interest on working capital 12.33 6.59 9.01
The Commission approves the interest on working capital at Rs. 9.01 Cr for FY 2019-
20 as against Rs.6.59 projected by MSPDCL.
submitted any details in their filings) and now approved by the commission are
furnished in table below:
Table 7.17: Provision for Bad & Doubtful debt approved by the Commission for FY 2019-20
(Rs. Cr)
Particular Approved in Projected by Now Approved
Tariff Order MSPDCL
Provision for Bad & Doubtful 3.00 3.00 3.00
Debts
The Commission approves provision for bad debts at Rs.3.00 Crore for FY 2019-20
as projected by MSPDCL.
The Commission approves ROE including MAT on ROE at 20.01 % at Rs. 1.95 Crore
during FY 2019-20 as projected by MSPDCL.
2. MSPDCL would like to submit that the detailed break up of non-tariff income is
not available with them since the company is in the process of adopting
Companies Act and a new accounting policy for compliance of the same. The
actual details of non- tariff income would be available next year while the
petition for FY 19-20 is filed. Till such time, we are constrained to project the
income based on the actual expenses available. At present, MSPDCL feels that
some components of other income might be booked/reported in the head of
revenue from sale of power because of which the non-tariff income is coming
less than the expected/estimated figures. From current year, accounting is
being done under new heads and the actual information under new heads shall
be submitted to the Commission along with the next tariff petition.
3. For projecting the non-tariff income, the approved figures by Hon’ble
Commission in the tariff order dt.12.03.2018 is taken. Details of non-tariff
income for FY 2019-20 is provided in table below:
Table 7.19: Non-tariff Income projected by MSPDCL for FY 2019-20
(Rs. Cr)
Particular FY 2019-20
Non-Tariff Income 0.41
Commission’s Analysis
The MSPDCL is directed to account for revenue from the heads specified in
Regulation 77 of JERC from MYT Regulations 2014 under Non-Tariff Income
invariably from next tariff petition.
For the present non-tariff income is approved as projected by MSPDCL.
The Commission approves the non-tariff income of Rs.5.40 Crore during FY 2019-20 as the
same amount was projected by the MSPDCL in APR filings made for FY 2018-19.
Commission’s Analysis
Based on the approved costs Aggregate Revenue Requirement for FY 2019-20 is
approved as detailed below:
Table 7.21: Aggregate Revenue Requirement approved by the Commission for FY 2019-20
(Rs. Crs)
Now approved by
Sl. No Particulars
Commission
A Expenditure
1 Cost of power purchase 378.36
2 Inter-State Transmission charges 61.12
3 Intra-state Transmission charges 85.68
4 NERLDC Charges 0.71
5 O&M Expenses 123.82
Employee Expenses 106.68
Repair & Maintenance Expenses 7.69
Administrative & General Expenses 9.45
Now approved by
Sl. No Particulars
Commission
6 Depreciation 0.31
7 Interest on Loan 5.17
8 Interest on Working Capital 9.01
9 Provision for bad debts 3.00
Total Cost 667.17
B Add: Return on Equity 1.95
Add: Income Tax
B: Total 1.95
C Total ARR: A+B 669.12
D Less (Non-Tariff Income) 5.40
Sub-total (D) 5.40
Net Aggregate Revenue Requirement (C-D) 663.72
Petitioner’s submission
1. Revenue from sale of power for FY 2019-20 at existing tariff has been determined
based on the category-wise energy sales approved by the Hon’ble Commission in
the MYT Order for FY 2019-20 and the category-wise tariff approved by the
Hon’ble Commission in the MYT Order for FY 2018-19.
2. Revenue from sale of power at existing tariff is estimated to be Rs 310.71 crore for
FY 2019-20.
For FY 2019-20, while approving the Energy Balance, the Hon’ble Commission has
approved quantum of surplus power to be sold by MSPDCL, as 375.45 MU. As the
actual distribution losses as well as the intra-State losses in Manipur are much
higher than that approved by the Hon’ble Commission, the actual quantum of
surplus power that would be available to MSPDCL for sale, would be significantly
lower. However, for the purposes of this Petition, MSPDCL has considered the
same quantum of surplus power to be sold, as the ARR approved by the Hon’ble
Commission for FY 2019-20 is being considered in totality.
3. MSPDCL has sold surplus power in the IEX at an average rate of Rs. 2.65/kWh in FY
2017-18 and at an average rate of Rs.2.65/kWh in the first half of FY 2018-19 (April
Table 7.22: Revenue from Sale of Power in FY 2019-20 projected by MSPDCL at Existing
Tariff of FY 2018-19
(Rs. Cr)
Energy Total Revenue Average Realization
Category of Consumers
Sales (MU) (Rs. Crore) (Rs/kWh)
LT Supply
Kutir Jyoti 16.00 4.23 2.65
Domestic 363.00 176.31 4.86
Commercial 45.00 27.19 6.04
Public Lighting System 5.00 3.34 6.68
Public Water works 2.00 1.36 6.82
Irrigation & Agriculture 1.00 0.43 3.57
Small Industry 20.00 8.98 4.49
Total LT Supply 452.00 221.86 4.91
HT Supply
Commercial 6.00 4.35 7.25
Public Water works 17.00 12.37 7.28
Irrigation & Agriculture 0.80 0.35 4.35
Medium Industry 4.00 2.11 5.28
Large Industry 6.00 4.25 7.08
Bulk Supply 114.00 65.43 5.74
Total HT Supply 148.00 88.86 6.01
TOTAL MSPDCL 600.00 310.72 5.18
Surplus Power 375.12 99.41 2.65
Total 975.12 410.11 4.21
Commission’s Analysis
As already discussed in Para 7.6 the surplus power to be sold under UI sales during FY
2019-20 is 371.42 MU. The petitioner projected the rate for U.I sales at Rs.2.65 /
KWH. Since surplus is net firm power the same has to be sold through exchange/UI
and realise the revenue at ruling price in the exchange by proper planning at SLDC.
Now with the category wise sales approved vide Para 7.5 the revenue from existing
tariff and the revenue from sale of surplus power of 371.42 MU works out to
Rs. 409.14 Cr for FY 2019-20 as detailed in the table below.
Table 7.24: Revenue from revised tariffs for FY 2019-20 as per the Commission
Energy Average
Sl. Revenue
Category Sales Rate
No (Rs.Crs)
(MU) (Rs/kWh)
A LT Supply
1 Kutir Jyoti 20.96 2.80 5.87
2 Domestic 386.83 5.28 204.24
3 Commercial 45.43 7.17 32.58
4 Public Lighting 5.08 7.13 3.62
5 Public Water Works 2.2 7.44 1.64
6 Agriculture 1.27 4.07 0.52
7 Small Industries 20 4.55 9.11
8 Total Low Tension 481.77 5.35 257.58
B HT Supply
9 Commercial 6.06 8.93 5.41
10 Public Water Works 18.66 8.04 15.00
11 Agriculture 0.85 6.00 0.51
12 Medium Industries 4.1 6.94 2.85
13 Large Industries 6 9.04 5.42
14 Bulk Supply 114 7.14 81.35
15 Total High Tension 149.67 7.39 110.54
16 Grand Total (LT+HT) 631.44 5.83 368.12
17 UI Sales 287.25 2.65 76.05
18 Total Sales 918.69 4.83 444.17
Detailed calculation of revenue from sale within the State is given in Annexure -IV.
The Commission, accordingly, approves the revenue with approved Revised
tariff at Rs.444.17 Crore as against Rs.410.11 Crore projected by MSPDCL.
7.24 Revenue Gap for FY 2019-20 with revised tariff
Table 7.25: Revenue Gap approved by the Commission for FY 2019-20
Projected Approved by
Particulars Unit by the
MSPDCL Commission
Net Revenue requirement Rs. Crore 741.49 663.72
Revenue from existing tariff Rs. Crore 310.70 368.00
Sale of surplus power Rs. Crore 99.41 76.05
Total Sales Proceeds Rs. Crore 410.11 444.17
Revenue Gap Rs. Crore 331.38 219.48
Internal Efficiency Rs.Crore 0 0.07
Energy sales MU 599.00 631.44
Sale of Surplus Power MU 375.45 287.25
Total Energy Sales MU 974.45 918.69
As seen from Para above, there is a revenue gap of Rs.219.48 Crore which is about
33.08% of Net ARR for FY 2019-20. The revised tariffs are approved w.e.f
01.04.2019. As such the Commission considers to revise the tariffs by an average
increase of 7.94% under telescopic billing as against 36% proposed by MSPDCL
without giving tariff shock to consumers to bridge the gap partially by revision in
Tariffs. Owing to revision of tariffs the MSPDCL is expected to get additional
revenue of Rs. 27.09 Crore (i.e Rs.368.12Crs – Rs.341.03 Crs), thereby the overall
gap is reduced to Rs.219.55Crore of which the MSPDCL shall meet Rs.219.48
crores from Government subsidy and the remaining Rs.7 (seven) lakhs from their
internal efficiency itself.
As seen from the above, it is clear that the revenue from sale of power is not sufficient
to meet the expenditure and the MSPDCL shall continue to depend upon the
subsidy/support from Government of Manipur. The net revenue gap of Rs. 219.55 Crore
is arrived at (including internal efficiency amount of Rs.7 lakhs), as indicated at Para 7.24
supra, shall be met from Government subsidy/ support against Rs. 220 Crore as
projected by MSPDCL.
The ARR & Tariff Petition for FY 2019-20 was filed by the MSPDCL, Manipur with the
prior approval of the State Government. The licensee, in their submitted Tariff Petition,
had proposed a tariff hike of 36% (i.e., for Rs.111.38 Crs) over the prevailing tariffs of FY
2018-19 resulting in a revenue gap amounting to Rs.220 Crs which needs to be
absorbed only by way of subsidy from the State Government of Manipur.
To achieve the objective of year on year tariffs progressively reflects the cost of
electricity supply, the grant of subsidy shall have to be reduced every year in
decrementing fashion and ultimately make the power utility to manage without
Government subsidy support. Keeping this in view, the Commission consciously
considers the overall subsidy requirement to the extent of Rs.219.55 crore (Rupees Two
hundred and nineteen crores and fifty-five lakhs only) for FY 2019-20 upon suitably
revising the prevailing tariffs of FY 2018-19 at an average rate of increase at 7.94%
(seven point nine four percent) only in order not to cause much burden to the
consumers.
The Section 65 of the Electricity Act 2003 mandates that the State Government shall
release subsidy amount due to the licensee in advance so as to enable the licensee to
implement the subsidized tariffs to their consumers as per Revised Subsidised Tariff
schedule at Table-8.2 & detailed calculation at Annex-IV. The State Government should
release the above stated subsidy amount in Twelve (12) equal monthly installment
amounting to Rs.18.29 (Rupees eighteen crore and twenty-nine lakhs only) per month.
The balance amounting to Rs.7.00 lakhs shall be met by MSPDCL through internal
efficiency improvement. However, in the event of non-receipt of subsidy in any month
from the Government, the licensee can adopt the applicable full cost tariff (FCT) at
Table-8.3, while issuing the monthly energy bill for that month (detail revenue
calculation is indicated at Annexure-IV). A brief summary of revenue amount from full
cost Tariff and sale of surplus power is tabulated below for reference.
Table: 7.26. Revenue details of MSPDCL at Full Cost Tariff for FY 2019-20
Energy Average
Sl. Revenue
Category Sales Rate
No (Rs.Crs)
(MU) (Rs/kWh)
A LT Supply
1 Kutir Jyoti 20.96 7.55 15.83
2 Domestic 386.83 8.76 338.90
3 Commercial 45.43 11.18 50.79
4 Public Lighting 5.08 9.70 4.93
5 Public Water Works 2.20 10.68 2.35
6 Agriculture 1.27 7.90 1.00
7 Small Industries 20.00 9.60 19.20
8 Total LT 481.77 8.99 432.99
B HT Supply
9 Commercial 6.06 11.21 6.7906
10 Public Water Works 18.66 11.15 20.8062
11 Agriculture 0.85 10.52 0.894
12 Medium Industries 4.1 11.16 4.5744
13 Large Industries 6 12.43 7.4569
14 Bulk Supply 114 10.08 114.9428
15 Total High Tension 149.67 10.39 155.4649
16 Grand Total (LT+HT) 631.44 9.32 588.46
17 UI Sales 287.25 2.65 76.05
18 Total Sales 918.69 7.23 664.51
8
There can be a situation where the outstanding subsidy was released by the
government after passage of much time and thereby if consumers were billed at full
cost tariffs in any relevant month or months. Given the situation, the entire excess
amount so charged on account of full cost tariff shall have to be reflected as rebate, by
the licensee at a time, in the immediate monthly billing cycle being issued to
respective consumers soon after receiving such subsidy pertaining to the past. If the
rebate amount is exceeding the monthly bill amount to be adjusted, then such excess
amount may be carried forward and be adjusted in the following monthly bills issued
to the consumer until full settlement is made.
Lastly, the brief summary of the calculations in support of subsidy amount arrived at,
the average cost of supply and the average revenue realisation details are tabulated in
the following table.
Table 7.27: Average Cost of Electricity supply within Manipur
Projected Approved by
Sl.
Particulars Units by the
No
MSPDCL Commission
1 Net overall ARR Rs. Cr 741.49 633.72
2 Sale of surplus power Rs. Cr 99.41 76.05
3 Net ARR within the state (1-2) Rs. Cr 642.08 587.67
4 Govt. subsidy/ Support Rs. Cr 220 219.55
5 Net ARR after Govt. subsidy (3-4) Rs. Cr 422.08 368.12
6 Energy sale within the state MU 599 631.44
7 Average cost of supply (3/6) Rs/KWH 10.72 9.32
8 Avg. Revn. realisation (If subsidy is paid)- (5/6) Rs/KWH 7.05 5.83
9 Avg. per unit Subsidy (7-8) Rs/kWh 3.67 3.48
8.1 Background
a. The Commission, in determining the revenue requirement of MSPDCL for the
year 2017-18 and the retail tariff, has been guided by the provisions of the
Electricity Act, 2003, the National Tariff Policy (NTP), Regulations on Terms
and Conditions of Tariff issued by the Central Electricity Regulatory
Commission (CERC) and Regulations on Terms and Conditions of Tariff
notified by the JERC for M&M. Section 61 of the Act lays down the broad
principles, which shall guide determination of retail tariff. As per these
principles the tariff should “Progressively reflect cost of supply” and also
reduce cross subsidies “within the period to be specified by the Commission”.
The Act lays special emphasis on safeguarding consumer interests and also
requires that the costs should be recovered in a reasonable manner. The Act
mandates that tariff determination should be guided by the factors, which
encourage competition, efficiency, economical use of resources, good
performance and optimum investment.
c. The mandate of the NTP is that tariff should be within plus / minus 20% of
the average cost. It is not possible for the Commission at this stage to lay
down the road map for reduction of cross subsidy within ±20% mainly
because of consumers’ low paying capacity and relatively high cost of power.
The gap in the year 2015-16 was 31.11% and that of 2017-18 is about 28.08
d. Clause 8.3 of National Tariff Policy lays down the following principles for tariff
design:
(i) In accordance with the National Electricity Policy, consumers below poverty
line who consume below a specified level, say 30 units per Month, may
receive a special support through cross subsidy. Tariffs for such designated
group of consumers will be at least 50% of the average cost of supply. This
provision will be re-examined after five years.
(ii) For achieving the objective that the tariff progressively reflects the cost of
supply of electricity, the SERC would notify the roadmap, within six Months
with a target that latest by the end of the year 2018-19 that tariffs are
within ± 20% of the average cost of supply. The road map would have
intermediate milestones, based on the approach of a gradual reduction in
cross subsidy.
For example, if the average cost of service is Rs.3 per unit, at the end of year
2015-16, the tariff for the cross subsidized categories excluding those
referred to in para-1 above should not be lower than Rs. 2.40 per unit and
that for any of the cross subsidizing categories should not go beyond Rs.3.60
per unit.
(iii) While fixing tariff for agricultural use, the imperatives of the need of using
ground water resources in a sustainable manner would also need to be kept
in mind in addition to the average cost of supply. The tariff for agricultural
use may be set at different levels for different parts of the State depending
on the condition of the ground water table to prevent excessive depletion of
ground water.
(ii) In the first place, the Commission shall determine the tariff, so that it
progressively reflects the combined average cost of supply of electricity and
also reduce cross-subsidies within a reasonable period. In the second phase,
the Commission shall consider moving towards category wise cost of supply
as a basis for determination of tariff.
f. The Commission has considered special treatment to Kutir Jyoti connections and
agricultural sector. It has also aimed at raising the per capita consumption of the
State from 100 kwh in 2010-11 to 162 kWh in 2014-15 and 300 kWh by the end
of 2018-19. The Commission endeavors that the tariffs progressively reflects cost
of supply in a shortest period and the Government subsidy is also to be reduced
gradually. The tariffs have been rationalized with regard to inflation, paying
capacity of consumers and to avoid tariff shock.
The MSPDCL has proposed tariff revision as indicated in table - 8.1 below. The
proposed increase in tariff by the MSPDCL would result in an overall increase of
about 36%.
Table 8.2: Category wise Subsidised Tariffs approved by the Commission for FY 2019-20
Approved
Existing Tariff
Subsidised Tariff
Consumer Category
Sl. No Fixed Energy Fixed Energy
(FY 2019-20)
Charges Charges Charges Charges
(P.M) (Rs./kWh) (P.M) (Rs./kWh)
LT SUPPLY (Rs./kWh/PM) (Rs./kWh/PM)
1 Kutir Jyoti
20
All Units/month 1.70 25.00 1.85
(Connection)
2 Domestic
First - 100 kwh/Month 60.00 3.60 60.00 3.90
Next 100 kwh/Month 60.00 4.35 60.00 5.20
Above 200 kwh/Month 60.00 5.60 60.00 6.00
3 Non-Domestic/Commercial
First - 100 kwh/Month 80.00 5.00 80.00 5.40
Next 100 kwh/Month 80.00 6.00 80.00 6.50
Above 200 kwh/Month 80.00 7.10 80.00 7.65
4 Public Lighting 65.00 6.50 65.00 7.00
5 Public Water Works 100.00 6.70 100.00 7.25
6 Irrigation & Agriculture 60.00 3.50 60.00 3.90
7 Small Industry 65.00 3.75 65.00 4.10
HT SUPPLY Rs/kVA/PM Rs/kVA/PM Rs/kVA/PM Rs/kVA/PM
1 Commercial 100.00 7.00 100.00 7.60
2 Public Water Works 100.00 6.10 100.00 6.75
3 Irrigation & Agriculture 100.00 3.30 100.00 3.60
4 Medium Industry 100.00 4.90 100.00 5.30
5 Large Industry 100.00 6.10 100.00 6.60
6 Bulk Supply 100.00 5.40 100.00 5.90
In Kutir Jyothi category, the Fixed charge is applicable on per connection basis and in
other categories under LT supply the Fixed charge is applicable on the Contracted
Load per KW. Detailed rates for all categories of consumers are indicated in the Tariff
Schedule.
Note:- The above table depicts fixed and energy charge only. Detailed Charges are given in
the tariff schedule appended at Annexure- III & IV at the end of the Tariff Order.
With the approved ARR for FY 2019-20, the Commission also works out the average
cost of supply at the rate of Rs.9.32/kWh. In the event of non-receipt of subsidy in
any month from the State Government, the Commission considers to make full cost
tariff as tabulated below:
Table 8.3: Category wise Full Cost Tariff (i.e., without subsidy) approved by the
Commission for FY 2019-20
Sl. Full Cost Tariff
Consumer Category
No. Energy Charges (Rs.) Fixed Charges (Rs.)
1 Kutir Jyothi
All Units 6.60/kWh 25 per Connection
2 Domestic
i) First 100 kWh 7.30/kWh 70/Contracted Load in kW
ii) Next 100 kWh 7.80/kWh 70/Contracted Load in kW
iii) Balance > 200 kWh 8.50/kWh 70/Contracted Load in kW
3 Non-Domestic/Commercial
A Low Tension
i) First 100 kWh 9.30/kWh 100/Contracted Load in kW
ii) Next 100 kWh 10.00/kWh 100/Contracted Load in kW
iii) Balance > 200 kWh 10.60/kWh 100/Contracted Load in kW
B High Tension 9.60/kVAh 110/Billing Demand in kVA
4 Public Lighting 9.50/kWh 100/Contracted Load in kW
5 Irrigation & Agriculture
A Low Tension 7.60/kWh 100/Contracted Load in kW
B High Tension 7.50/kVAh 110/Billing Demand in kVA
6 Public Water Works
A Low Tension 10.50/kWh 100/Contracted Load in kW
B High Tension 9.50/kVAh 110/Billing Demand in kVA
7 Industrial
A Small Industry (LT) 8.90/kWh 100/Contracted Load in kW
B Medium Industry 9.00/kVAh 110/Billing Demand in KVA
C Large Industry 9.50/kVAh 110/Billing Demand in KVA
9 Bulk Supply 8.50/kVAh 110/Billing Demand in kVA
9.1 Background
MSPDCL has wheeling charges at 1.18/kwh. The MSPDCL is not maintaining separate
accounts for the distribution wire business and retail supply business. So the ARR of
the wheeling business is arrived at as per the following matrix.
Table 9.1 Allocation matrix
Sl. Wire Retail Supply
Particulars
No. business business
1 Power purchase cost 0 100
2 Employee cost 60 40
3 R & M expenses 90 10
4 Adm. & General Expenses 50 50
5 Depreciation 90 10
6 Interest & Finance Charges 90 10
7 Interest on working Capital 10 90
8 Provision for bad debts 0 100
9 Income tax 90 10
10 Return on equity 90 10
11 Contribution to contingency reserves 100 0
12 Non-tariff Income 10 90
Wires Retail
Total Wires Supply
Sl. Business Supply
Particulars ARR ARR ARR
No (%) Business (%)
A Expenditure
1 Cost of power purchase 452.66 0% 100% 0.00 452.66
Inter-State Transmission
2 charges 61.12 0% 100% 0.00 61.12
Intra-State Transmission 0% 100%
3 charges 86.57 0.00 86.57
4 NERLDC Charges 0.71 0% 100% 0.00 0.71
5 O&M Expenses 123.82 75.65 48.17
Employee Expenses 106.68 60% 40% 64.01 42.67
Repair & Maintenance
7.69 90% 10% 6.92 0.77
Expenses
Administrative & General
9.45 50% 50% 4.73 4.73
Expenses
6 Depreciation 0.31 90% 10% 0.28 0.03
Wires Retail
Total Wires Supply
Sl. Business Supply
Particulars ARR ARR ARR
No (%) Business (%)
7 Interest on Loan 5.17 90% 10% 4.65 0.52
8 Interest on Working Capital 6.59 10% 90% 0.66 5.93
9 Provision for bad debts 3.00 0% 100% 0.00 3.00
Total Cost 739.95 81.24 660.01
B Add: Return on Equity 1.95 90% 10% 1.76 0.20
Add: Income Tax 0.00 90% 10% 0.00 0.00
B: Total 1.95 1.76 0.20
C Total ARR: A+B 741.90 83.00 660.20
D Less (Non-Tariff Income) 0.41 10% 90% 0.04 0.37
Sub-total (D) 0.41 0.04 0.37
Net Aggregate Revenue
Requirement (C-D) 741.49 82.96 658.53
The proposed Wheeling Charges for FY 2019-20 have been computed based on the
methodology adopted by the Hon’ble Commission for determining the Wheeling
Charges for FY 2018-19 in the MYT Order dated March 12, 2018, as shown in the Table
below:
Table 9.3: ARR for Wires Business for FY 2019-20 projected by MSPDCL
Thus, MSPDCL proposes Wheeling Charges of Rs. 1.18 per kWh for Open Access
transactions in the State of Manipur.
Commissions Analysis
ARR for wheeling business arrived based on approved ARR and methodology vide Table
9.1 supra is as detailed in table below.
Table 9.4: ARR of wheeling business approved by the Commission for FY 2019-20
ARR for wire Retail Supply for
Total ARR for FY
Sl. No Particulars business for FY FY 2019-20
2019-20
2019-20
Power purchase cost including
1 525.87 - 525.87
Transmission charges
2 Employee cost 106.68 64.01 42.67
3 R & M expenses 7.69 6.92 0.77
4 Adm. & General Expenses 9.45 4.73 4.72
5 Depreciation 0.31 0.28 0.03
9. Directives
10.1 General
While examining the information and data contained in the and Tariff Petition for FY
2019-20, it is observed that the computation and compilation of the data have been
done based on assumptions only and as a result, there has been difficulties in
finalization of the ARR and determination of retail tariff also. The above observation
itself substantiates the fact that the administrative, technical and commercial
performances of the MSPDCL require substantial improvement within a specified
time frame.
Similar situation was noticed in the ARR & Tariff petition for the FY 2019-20. The
Commission had observed that while there is ample scope for reducing cost and
increasing efficiency in the operation of the department, serious efforts appear to be
lacking. It is in the above context that certain directives were given in the earlier
Tariff Orders of which some were fully complied with. The Commission expected that
MSPDCL would take prompt action on the directives and monitor their
implementation. Unfortunately, action is yet to be taken on most of the important
directives, which could make significant difference to operational efficiency and cost.
In some cases action has no doubt been initiated, but overall seriousness with which
the directives were issued by the Commission does not appear to have been realized
by the MSPDCL.
A major part of the total power sales is constituted by domestic category consumers
and hence, the revenue arrears are expected to reduce through the actions initiated
by MSPDCL.
1. Prepaid Consumer
2. Post Paid Consumer
MSPDCL deducts 20% on every recharge from the outstanding arrears of the
respective consumers. HT consumers including hospitals have been sent
disconnection warning notices for clearing their outstanding dues. Other
government consumers having outstanding amount have been asked to clear the
amount through government funding, for which a request has been made.
Comments of the Commission
Through prepaid meters’ future accumulation of fresh arrears can be arrested. At
present we are in Post-paid meters’ usage stage. In the directive, it was requested to
submitted category wise year wise arrears due at a point of time say as on
31.03.2018.
This may be reported by 30.06.2019.
Further, another 207.74 MU of surplus power has been sold on the Power Exchange,
after fully meeting the State’s requirement.
Comment of the Commission
The average power purchase cost in Rs.6.84/kwh during FY 2017-18. While the
surplus power of 225.71 MU but not 207.74 MU was sold at an average cost of
Rs.2.438/kwh during FY 2017-18 by incurring loss in every unit sold. Instead had the
power drawn to the actual requirement by proper planning this type of loss can be
avoided.
Therefore, this practice of selling units at loss be discontinued forthwith. The loss on
account of this surplus power sell cannot be passed on to the consumers partially,
though Government subsidy is also absorbing to a greater extent. In future, the
Commission will flag this kind of loss transactions and would disallow to pass it on to
consumers from next year tariff determination.
shall be brought under billing once it is identified and regularized. In either case
physical verification of connections in only remedy.
Directive 12: Replacement of Defective Meters and Installation of Meters to Un-
Metered Connections
The MSPDCL was directed to provide meters to all unmetered consumers and
replace the defective meters within the time frame given in the commission order
No. 24012/2/5/09 – JERC dt: 7.1.2011 on 100% metering plan and submit quarterly
report regularly.
Compliance status
It is submitted that MSPDCL is allotting the New connection to the consumer only
after installation of the Meter.
List of Replacement of Defective Meters and installation of Meters to Un-Metered
Connection is under consideration & will be submitted once finalized.
Directive 13: Physical and Financial Status of RAPDRP & RGGVY Schemes
As per above directive MSPDCL has to submit physical and financial progress of work
done and the impact of the works on revenue performance and metering with
details of work done, amount of revenue increase etc.
Compliance Status
The details of Physical and financial status of RAPDRP & RGGVY Schemes are attached
as Annexure-2.
FY 2019-20.
Furthermore, MSPDCL would like to state that it has bought Virtual Private Network
and it is being planned to set up a physical server in one year to go digital with all the
files available on one electronic platform. All these steps are guided towards
making MSPDCL independent with its IT team and reducing dependency on
consultants.
Comments of the Commission
Targeted date by which MSPDCL will be independent with its IT team may be
indicated.
Directive 21:
Updation of computerised billing program of power factor and rebate/surcharge
MSPDCL should up-to-date computerised billing programme to facilitate adoption of
power factor rebate/surcharge as indicated in the tariff schedule.
Compliance Status
The computerised billing program for power factor rebate/surcharge is under
progress. The HT cell of MSPDCL is undertaking the necessary steps towards
installation of the program and it is expected to complete it in FY 2018-19.
Comments of the Commission
Compliance may be reported in next tariff order.
Directive 22:
Installation of meters to all 11 kV feeders and DT’s
MSPDCL should install meters for all 11 kV’s and DT’s in all RAPDRP covered towns by
30.06.2016. Sample study should be conducted to know the highest feeder loss and
highest DT loss and report to be submitted to the Commission by 30.09.2016.
Compliance Status
It is submitted that under RAPDRP Part-A 72 nos. of 11KV Feeder meters and 925
nos. of DT meters were installed.
Comments of the Commission
Targeted sale by which 100% metering of 11 KV feeders be achieved may be
intimated in the first insistence.
DIRECTIVES ISSUED IN FY 2017-18
Directive 23
As per Regulations 2 (19) of JERC (M&M) (MYT) Regulations, 2014 the Second
Control Period shall be five years from 01.04.2018. The MSPDCL is directed to submit
the next ARR for Control Period from FY 2018-19 to FY 2022-23 and Tariff Petition for
FY 2018-19 and true up petitions for FY 2015-16 and FY 2016-17 along with audited
annual accounts for FY 2015-16 and FY 2016-17 invariably.
Compliance status
The MYT Petition for the second Control Period was filed last year, and the Hon’ble
Commission has issued the MYT Order on 12th March, 2018. We would like to inform
the Hon’ble Commission that the provisional balance sheet along with the audited
balance sheet of MSPDCL for FY 2015-16 and FY 2016-17 are still being prepared and
will be made available soon.
Comments of the Commission
Audited Annual Accounts for FY 2015-16 to FY 2015-16 to FY 2017-18 along with
revised true up petitions be submitted soon.
Directive 24
The MSPDCL is directed to submit the required information in the format prescribed
in JERC M&M (MYT) Regulations, 2014 from next tariff petition onwards which are
mandatory.
Compliance status
MSPDCL has submitted all the necessary required information in the format
prescribed.
Comments of the Commission
The tariff petition for FY 2019-20 indicates how irregularly prepared. Even the
required formats as envisaged inn JERC for M&M (MYT) regulations are not
submitted. Even the formats submitted are not in order.
Directive 25
The Commission is of the view to introduce KVAH billing in energy charges to all HT
categories and LT categories with contracted load 20 kWh and above with effect
from FY 2018-19 onwards. The licensee is directed to see that all HT connections are
provided with trivector/MDI meters for such connections without fail.
Compliance status
MSPDCL has been installing MDI meters for HT categories and LT Categories
consumers on priority Basis. It is further submitted to Hon’ble Commission that once
The MSPDCL is directed to account for the income relating to above heads in the
respective heads and furnish the information in the format without omissions from
next ARR.
Compliance status
MSPDCL wishes to submit to the Hon'ble Commission that it has segregated the Non-
Tariff Income component wise as per directive of the Hon'ble Commission and it has
submitted the details accordingly in Provisional True-up Petition for FY 2017-18.
Comments of the Commission
Why the same procedure be followed for FY 2019-20 be explained.
DIRECTIVE 31
The Commission is of the view to introduce kVAH billing in energy charges to all HT
categories and LT categories with contracted load of 20 kWh and above with effect
from FY 2019-20 onwards. The licensee is directed to see that all HT connections are
provided with trivector/MDI meters for such connections without fail.
Compliance status
MSPDCL has been installing MDI meters for HT categories and LT Categories
consumers on priority Basis. It is further submitted to Hon’ble Commission that once
MSPDCL is able to achieve 100% Implementation of MDI meters for HT and LT
Categories Consumer it will introduce KVAH billing in the energy charges of all such
consumer.
Comments of the Commission
Targeted date by which KVAH billing will be introduced be reported by 30.06.2019.
DIRECTIVE 32
MSPDCL was directed to furnish invariably the slab wise consumption from next ARR
petition to assess the revenue correctly in respect of Domestic and Commercial / non
Domestic categories by proper consumer indexing.
Compliance status
It is Submitted that MSPDCL have submitted the slab-wise consumption for Domestic
and Commercial / non-Domestic categories in the ARR Petition for 2019-20.
Comments of the Commission
This directive is dropped as new directive is made in this respect.
DIRECTIVE 33
MSPDCL was directed to submit reliable average slab-wise monthly energy
consumption per consumer and number of consumer in each slab during the FY
2017-18 (Actual), FY 2018-19 (Revised Estimate based on last 6 months) and FY 2019-
20 (Projection) along with the Petition for determination of ARR & Tariff for FY 2019-
20 positively in respect of Kutir Jyoti, Domestic and Non Domestic/Commercial under
LT Categories. The Commission also directed to take necessary action immediately to
make available the requisite data at the time of the Petition mentioned above.
Compliance status
It is Submitted that MSPDCL have submitted the slab-wise consumption for Domestic
and Commercial / non-Domestic categories for FY 2019-20 in the ARR Petition.
Comments of the Commission
The data submitted in the is inadvertent and no conclusive decision could be made
from the submitted data in APR for FY 2018-19. The Licensee shall sincerely submit
the above data with full details in the future submissions. In the FY 2019-20, due to
the data inadequacy, Commission had to make lots of assumptions in estimating the
consumer related data and the quantum of consumption and the contracted loads in
the process of tariff design for the FY 2019-20.
New Directives
Directive 34
Reduction of consumption slabs in Domestic and Comercial Categories of
consumers:
The Licensee shall reduce the number of consumption slabs in the following
categories in the next year tariff filing proposals:
Directive 35
Licensee shall submit the detailed information on the following items latest by 15th
August 2019:-
a) Details of year wise pre-paid meters purchased so far with copies of
supply/work order since the adoption of the pre-paid metering system.
b) Year- wise installation of pre-paid meter since adoption of the pre-paid
metering system.
c) Circle wise installation of pre-paid meters giving details of sub-division with
category wise consumers with activated pre-paid meters.
d) Report on the year wise impact of pre-paid metering in the billing efficiency
and collection efficiency of -
1) Sub-division, Division and Circle since the adoption of prepaid meters.
2) Upto date circle wise, Division/Sub-division list of consumers with
activated/unactivated prepaid meter.
3) Plan and target date for installation and activation of pre-paid meter to all
the consumers under MSPDCL.
Directive 36
MSPDCL should work out strategy to arrive at slab-wise energy consumption per
consumer per month in respect of domestic and commercial categories. The
average number of consumers consuming electrical energy in the first slab,
second slab and third slab in domestic and Comercial categories respectively
should be submited alongwith their tariff petition for FY2020-21 positively for
proper assessment of revenue prjection.
Directive 37
MSPDCL should vigorously take up consumer metering either in Postpaid/Prepaid
mode not only in valley but also in hilly areas, 100% metering should be achieved
within September 2019. This will lead to meaningful consumption of Energy and
fruitful consumer awareness campaign in hill areas and plain areas. This will also
reduce un-accounted energy and Distribution losses of the DISCOM.
11.1 Background
Section 62 sub-section 4 of the Electricity Act, 2003 provides that no tariff or part of
any tariff may ordinarily be amended, more frequently than once in every financial
year, except in respect of any changes expressly permitted under the terms of any
fuel surcharge formula as may be specified. This provision of the Act requires the
Commission to specify the formula for fuel surcharge.
Accordingly, the Commission has specified the formula for working out the Fuel and
Power Purchase Cost Adjustment (FPPCA) charges and other terms and conditions of
FPPCA allowed the distribution licensee to recover the FPPCA charges from the
consumers.
Accordingly, the amount of Fuel and Power Purchase Cost Adjustment (FPPCA)
charges shall be computed as under:
FAC Qc(RC2–RC1)+Q0(RO2–RO1)+Qpp(RPp2–Rpp1)+Vz+A
= X 100
(Rs./kWh) (QPg1 + Qpp1 + L
X [1 - ]-PSE
Qpp2) 100
Where,
Qpp2 = Power Purchase from sources with delivery point within the
state transmission or distribution system (in kWh)
PSE = Power sold to exempted categories (presently agriculture and BPL-Kutir Jyoti
consumers)
If there are more than one power station owned by the Licensee Qc, Rc1, Rc2, Qo,
Ro1, Ro2, Qpg and Qpg1 will be computed separately for each power station and
sum of the increase/decrease of cost of all power stations shall be taken into
consideration.
The Generating Company can levy FPPCA charges with the prior approval of the
Commission.
The incremental cost per kWh due to this FPPCA arrived for a quarter shall be
recovered in the energy bill of the month subsequent to the order of the
Commission approving FPPCA with full details of rate and unit(s) on which FPPCA
charges have been billed. The Generating Company and the Distribution Companies
shall provide along with the proposal of FPPCA (as applicable to them) for a quarter,
a compliance report of the previous order of the commission in respect of FPPCA.
TARIFF SCHEDULE
Appendix
Tariff Schedule
1.1 Rebate for advance payment: For payment of energy bill in advance, a rebate of 1%
shall be allowed on the rate of charge of the applicable tariff. This will be applicable
only all consumers provided with prepaid energy meters.
1.2 Rebate/Surcharge for availing supply at voltage higher/lower than base voltage:
Those who avail supply at higher voltage than the classified supply voltage for
corresponding load as per clause 3.2 of the JERC for Manipur and Mizoram (Electricity
Supply Code) Regulations, 2013, with up to date amendment. shall be allowed rebate
and those availing at lower voltage than the specified voltage shall be levied surcharge
as detailed below:
(i) For consumers having contracted load up to 50 kW – If the supply is given at
HV/EHV, a rebate of 5 % would be admissible on the rate of energy charge and
fixed charge of the applicable tariff.
(ii) For consumers having contracted load above 50 kW – If supply is given at voltage
lower than the base voltage for corresponding load as per clause mentioned
above, the consumer shall be required to pay an extra charge of 10 % on the bill
amount (Energy charge + Fixed charge) calculated at the applicable tariff.
(iii) All voltages mentioned above are nominal rated voltages as per clause 3.2 of the
JERC for Manipur & Mizoram (Electricity Supply Code) Regulations, 2013. with up
to date amendment.
1.3 Payment: All payments shall be made by way of Cash (up to the amount as acceptable
to the licensee), Banker’s Cheque, Demand Draft or Money Order or e-transfer on line.
Cheques and demand drafts shall be payable at any branch of a scheduled commercial
bank that is a member of the clearing house for the area where the concerned Sub
Divisional Office is located.
However, part payment is subjected to acceptance by the competent authority. Bank
1.4 Validity of Existing Recharge Voucher: For a consumer with prepaid meter who has
purchased voucher prior to the effective date of new tariff, the existing voucher shall
continue till such voucher is exhausted. The licensee shall cautiously issue voucher so
that the existing voucher is valid for a minimum number of days beyond the effective
date of new tariff.
1.5 Surcharge for late payment of bills: If payment is not received within due date
surcharge @ 2% at simple interest on the outstanding principal amount for each 30
days’ successive period or part thereof will be charged, until the amount due is paid in
full.
1.6 Single Point Delivery: This tariff is based on the supply being given through a single
point of delivery and metering at one voltage. Supply at other points at other voltage
shall be separately metered and billed for and shall be considered as separate
connection.
1.7 Voltage and frequency: All voltages and frequency shall be as per clause 3.1 and 3.2 of
the JERC for Manipur & Mizoram (Electricity Supply Code) Regulations, 2013. with up
to date amendment.
1.9 Transformation loss: The consumers getting their supply at HT and metering done at
the L.T side, then he/she shall be charged for transformation loss in kWh as per clause
5.7 JERC for Manipur and Mizoram (Electricity Supply Code) Regulations, 2013
(together with latest amendment on date). However, the same is being reproduced for
the sake of reference:
(1) The average losses in the transformer shall be calculated as follows and added to
the energy consumption indicated by the meter:
730 X 1.0 X C
Average transformer loss = --------------------------- = kVAh per month
100
where C = KVA rating of the transformer. For conversion of kVAh to kWh or vice versa,
latest power factor as per JERC (M&M) (Electricity Supply Code) Regulations, 2013
with latest amendment is to be used.
(2) The transformer loss arrived at by the above formula shall be added to the
energy consumption, even when the recorded energy consumption is nil.
(3) 1% of the transformer capacity for transformer above 63 KVA will be added to
the recorded maximum demand on the Low Tension side to arrive at the
equivalent High Tension demand.
1.11 Mixed load:- Any part of the connection given for one specified category should not be
utilized for any other purpose to which higher rate of charge is applicable in the tariff
schedule. A separate connection shall have to be taken for such loads or purposes
falling under appropriate category, failing which the entire consumption so drawn
shall be treated and would be billed in that corresponding category with higher
applicable tariff for which any part of that connection is utilised.
1.12 Rounding-off to nearest Rupee: Each components of bill, such as energy charge,
fixed/demand charge, meter rent, surcharge, rebate of any kind, etc, including
interest, involving fraction of a rupee should be individually rounded-off to nearest
rupee (fraction of 50 paise and above to be rounded-off to the nearest higher rupee
and fraction less than 50 paise to be ignored). In case of non-availability/scarcity of
small change of rupees less the Rs.10/-, consumer may be allowed to tender next
higher amount divisible by 10. Such excess amount so tendered shall be carried
forward to the next bill as a credit and shall not entitle any interest of whatsoever.
1.13.2 HT Supply:-
Supply of Electricity to the Consumers at voltage above 400V as per Clause 3.2 of
JERC for Manipur and Mizoram (Electricity Supply Code) Regulations, 2013 with up
to date amendment.
1.14 The maximum demand means the highest load measured in average kVA or kW at
the point of supply of a consumer during any consecutive period of 30 (thirty)
minutes during the month or the maximum demand recorded by the MDI during
the month.
1.15 Billing demand: As defined in Clause 2.3(12) of the Joint Electricity Regulatory
Commission for Manipur and Mizoram (Electricity Supply Code) Regulations, 2013
with latest amendments.
Provided that no such direction of the State Government shall be operative if the
payment is not made in accordance with the provisions contained in this section and
the tariff fixed by the State Commission shall be applicable from the date of issue of
orders by the Commission in this regard.”
The subsidy should be released in advance, failing of which the licensee shall
implement tariff indicated under Full Cost Tariff (i.e Without Subsidy).
Therefore, if the government subsidy is regularly received, the licensee shall
adopt tariff ‘A’ (Subsidised Tariff) or in the event of non-receipt of said subsidy,
the Licensee shall be at liberty to implement tariff ‘B’ (Full Cost Tariff i.e.,
without Subsidy) during the period of non-receipt.
There can be a situation where the outstanding subsidy was released by the
government after passage of much time and thereby if consumers were billed at full
cost tariffs in any relevant month or months. Given the situation, the entire excess
amount so charged on account of full cost tariff shall have to be reflected as rebate,
by the licensee at a time, in the immediate monthly billing cycle being issued to
respective consumers soon after receiving such subsidy pertaining to the past. If the
rebate amount is exceeding the monthly bill amount to be adjusted, then such
excess amount may be carried forward and be adjusted in the following monthly
bills issued to the consumer until full settlement is made.
1.18 Contingency: - In case of any inconsistency between this Tariff schedule and the
prevailing JERC for Manipur and Mizoram (Electricity Supply Code) Regulations, 2013,
with up to date amendment. the provision, meaning and contents of the said Code
shall prevail.
A: SUBSIDISED TARIFF
2. LT Supply:-
2.1 LT Category -1:- KutirJyoti / BPL(Below Poverty Line) Connection
Applicability: Applicable to all households who have been given connection under
KutirJyoti Scheme or similar connection under any scheme of the State Govt. or
Central Govt. for the benefit of poorer section. As per existing norms unless
supersedes by other new norms of KJS, if the total consumption in the last three
months exceed 45 kWh, the connection should be converted to LT Category-2
(Domestic).
Permitted load:-Initially single light point connection which can be extended by one or
two light points or as per the norms specified by competent Authority from time to
time
Tariff Rates:
A) Fixed Charge : Rs 25.00 per month per connection.
B) Energy charge per month:
1) Metered Supply:
All Unit @ Rs 1.85 per kWh
Note: 1- if the total consumption of any consecutive three months is more than 45
kWh, then such consumer shall be re-categorised/converted into normal domestic
category permanently from the very 1st/2nd/3rd month of that consecutive three
months, if the total unit consumed exceed the specified limit of 45 kWh from that
instance and the bill be served as domestic category. (clause 4.90 of the JERC for
Manipur and Mizoram (Electricity Supply Code) Regulations, 201 3 with latest
amendments may be referred to.)
Note 2: In case a KutirJyoti /BPL consumer on getting converted into a domestic
consumer, the re–categorised/converted consumer shall be required to pay towards
load security/meter security deposit as applicable for domestic consumers. But, it
shall not contradict clause 5.9 of the JERC for Manipur and Mizoram (Electricity
Supply Code) Regulations, 2013 with latest amendments.
Tariff Rates:
A) Fixed Charge : Rs 60.00 per month per kW of contracted load.
B) Energy charge per month:-
1) Metered Supply:
First 100 kWh @ Rs3.90 per kWh
Next 100 kWh @ Rs 5.20 per kWh
200 kWh @ Rs 6.00 per kWh
dispensaries, health centres, restaurants, bars, hotels, clubs, guest houses, circuit
houses/rest houses, tourist lodges, picnic spots, resorts, farm/garden houses, clubs,
markets, optical houses, public buildings, community halls, stadiums,
meeting/conference halls, religious premises like churches, temples, mosques,
gurudwaras, religious offices, all types of studios, tea stalls, professional chambers (like
Advocates, chartered Accountants, consultants, Doctors, etc.), private trusts, marriage
halls, public halls, show rooms, centrally air-conditioning units, commercial
establishments, X-ray plants, diagnostic centres’, pathological labs, carpenters and
furniture makers, repair workshops, laundries, typing institutes, internet cafes,
STD/ISD PCO’s, FAX/photocopy shops, tailoring shops, Government/Non-Government
Institutions, schools, colleges, libraries, research institutes, boarding/lodging houses,
railway stations, fuel/oil stations/pumps, bottling or filling stations /plants, service
stations, Railway/Bus stations/terminals, All India radio/T.V. installations, printing
presses, commercial trusts, societies, banks, financial institutions, theatres, cinema
halls, circus, coaching institutes, common facilities in multi-storeyed commercial
offices/ buildings, public museums, crematoriums, graveyards, orphanages/recognized
charitable institutions where rental or fees of any kind are charged, non-recognized
charitable institutions, power supply to tele-communication system/towers and others
applications not covered under any other categories.
Tariff Rates:
A) Fixed Charge : Rs 80.00 per month per kW of contracted load.
B) Energy charge per month:
1) Metered Supply:
First 100 kWh @ Rs.5.40 per kWh
Next 100 kWh @Rs.6.50 per kWh
200 kWh @ RS 7.65 per kWh
Tariff Rates:
A) Fixed Charge : Rs 65.00 per month per kW of contracted load.
1) Metered Supply:
All units : @ Rs 7.25 per kWh
horticulture and any other type of industry where raw material is converted into
finished products with the help of electrical motive power, printing press, etc. This
will include domestic or commercial within the industrial complex.
Tariff Rates:
A) Fixed Charge : Rs 65.00 per month per kW of contracted load.
B) Energy charge per month:
1) Metered Supply:
All units : @ Rs 4.10 per kWh
3. HT Supply: The tariffs are applicable for Consumer availing supply at voltage above
400 V irrespective of connected load/contracted demand. It is mandatory to supply
with voltage above 400 V, to consumer having a contracted Load of above 50 kW or
Contract Demand of above 59 kVA, as per clause 3.2 of JERC for M&M (Electricity
Supply Code) Regulations, 2013 with up to date amendment.
Tariff Rates:
A) Demand Charge : Rs 100.00 per month per kVA of Billing Demand.
B) Energy charge per month:
1) Metered Supply:
All kVAh : @ Rs 6.75 per kVAh
Tariff Rates:
A) Demand Charge : Rs 100.00 per month per kVA of Billing Demand.
B) Energy charge per month:
1) Metered Supply:
All kVAh : @ Rs 3.60 per kVAh
Tariff Rates:
A) Demand Charge : Rs 100.00 per month per kVA of Billing Demand.
B) Energy charge per month:
1) Metered Supply:
All kVAh : @ Rs 5.90 per kVAh
provisions of the supply code mentioned above. If the service line is arranged by
consumer, it shall be adopted as per clause 4.133 of the JERC for Manipur & Mizoram
(Electricity Supply Code) Regulations, 2013 (with latest amendments) and it shall be
returned to the consumer after the period of supply is over. Energy charges bill shall
be served as per the following rates:
Tariff Rates:
A) Fixed / Demand charge at 1.5 times the rate of fixed/demand charge of the
applicable tariff category for which power supply is
given.
B) Energy charge per month : at 1.5 times the rate of the highest slab rate of
the applicable tariff category for which energy is
supplied.
5 Computation of energy consumed for cases given below: -
5.1 Unmetered supply:- As per Section 55 of Electricity Act 2003 and as per clause 5.1 of
the JERC for Manipur & Mizoram (Electricity Supply Code) Regulations, 2013 (with
latest amendments), no installation should be serviced without appropriate and
correct meter. As many years has elapsed from the effective date of the EA 2003 and
even from the effective date of the Supply Code, the formula based computation of
energy consumption in respect of unmetered supply is not acceptable and hence it is
withdrawn through this order. Licensee should invariably install the requisite meters
for all existing service connections and should not release any service connection
without installing an appropriate and correct meter complying with provisions of
Electricity Act 2003.
5.2 Short period of unmetered supply: - For un-meter (meter not available) supply as a
result of defective, burnt, lost meter shall be treated as per the provisions of 6.11 –
6.13 of the Electricity Supply Code Regulations, 2013 (together with latest
amendment) issued in this regard by this Commission.
6.1.1 Meter Rent for non-prepaid meters: Monthly charges for hiring of the meter,
indicator payable shall be as follows:
a) AC, Single phase Energy meter, whole current Rs. 10.00 per month
b) AC, Three phase Energy meter, whole current Rs. 20.00 per month
c) AC, Three phase Energy meter, CT operated Rs. 50.00 per month
d) AC, Three phase Energy meter, CT & PT operated Rs.500.00 per month
6.1.2 Meter Rent for Pre-Paid Meters: Monthly charges for hiring of the meter, indicator
payable shall be as follows:
AC, Single phase PP, Energy meter, whole
a) Rs. 20.00 per month
current
AC, Three phase PP, Energy meter, whole
b) Rs. 40.00 per month
current
These charges shall be payable by the consumer in advance. The aforesaid charges do
not include the charges payable by the consumer for other works connected due to
change of connected load. Rerating shall be carried out as per clause 4.94 to 4.107 of
the JERC for Manipur and Mizoram (Electricity Supply Code) Regulations, 2013. with up
to date amendment.
6.12 Mutation Fee: Mutation fee i.e. fee for change of name shall be Rs 50 per
change. This shall be carried out as per clause 4.81 to 4.84 of the Joint
Electricity Regulatory Commission for Manipur and Mizoram (Electricity Supply
Code) Regulations, 2013. with up to date amendment.
6.13 Cost of Application Form: The application form shall be free of cost
vide clause 4.14 of the Joint Electricity Regulatory Commission for Manipur
and Mizoram (Electricity Supply Code) Regulations, 2013. with up to date
amendment.
ANNEXURES
ANNEXURE - I
The Chairman of the Committee, Mr. Lalchharliana Pachuau, Chairperson of the Joint
Commission for Manipur & Mizoram chaired the meeting.
After welcoming the Members and Invitees, the Chairperson initiated the agenda wise
discussion as below:
Agenda No.1. Confirmation on the Minutes of the 18 th Meeting of the SAC, Manipur held
on 19th February, 2018.
Requesting the members to express their views and comments on the minutes of the 18 th
SAC and after obtaining nods from the members, the minutes were declared as confirmed.
Agenda No. 2. Action taken report on the minutes of 18 th SAC Meeting, Manipur.
As per the action taken report furnished by MSPDCL, the up-to-date status of the installation
of reliable meters on 11 kV feeder at all injecting points of MSPDCL and check meters as on
31st January, 2019 are as shown below:
It is decided that reliable meters shall be provided to all the 11 kV incomers of MSPDCL lines
within 4 (four) month by MSPCL to enable meter reading of energy injection to MSPDCL and
MSPCL shall provide all necessary meters at 132 kV and 33 kV level within 6 months from
now. At these 33/11 kV substation which are having RE type construction (i.e, without
panels/control room etc.) The interface metering between MSPCL & MSPDCL can be
achieved by installing correct rating of CT/PT combination (like that of used in boundary
metering with meter as per CEA Meter Regulations) the interface meter should have
accuracy class of 0.2S and the CT/PT should be compatible to accuracy class of the meter.
The MD, MSPCL informed the Committee that he shall look into the feasibility of such
outdoor metering in Non-Conventional Substations and will achieved metering as
committed in line with the foregone commitment.
ii) Action taken towards recovery of outstanding dues or writing off outstanding debt of
different Department and installation of pre-paid meters in all Government Offices and
residents (vide Agenda No. 4 of the minutes of 18 th Meeting of SAC, Manipur).
As per the report given by Mr. L. Priyokumar, MD (MSPDCL), recovery of the outstanding
dues of the different Departments is one of the major efforts that MSPDCL takes seriously
and there is no plan of writing-off the outstanding dues of the different Departments.
Disconnection letters were served to all the defaulting Departments. However, it may be
noted that the budgetary provision of all Departments for the energy consumed is very
meager. A reminder letter to the different Departments to clear all their respective
outstanding dues was also served from time to time with a copy to the Principal Secretary
(Finance), Government of Manipur vide file no. MSPDCL/ Comml/Govt. Dues 17-18/Letters.
The total Govt Outstanding dues as on 31st December 2018 is Rs. 92.35 crores. The
Department wise breakup of the Govt. Outstanding Dues is also furnished in the Meeting.
He further stated that the working capacity of a pre-paid meter is limited within 50kW load
and so providing pre-paid meters to Government Offices consuming energy through a
dedicated transformer with load of above 50kW is not possible. Separate DTR meters are
installed for such cases. Hence installation of pre-paid meters in all Government Offices is
not considered mandatory.
In this regard, Dr. Ch Ibohal Meitei, Prof Manipur Institute of Management Studies, Manipur
University has stated that the recovery of bad debt is very critical for the running of the
company and to put more pressure to the defaulting Department their names should be
published in the local domain for more public pressure. This suggestion was also endorsed
by Dr. L. Sadananda Singh, General Secretary, Senior Citizens for Society, Manipur. It was
also decided that the Commission will write to the Chief Secretary, Government of Manipur
to take steps for the recovery of the bad debt at the earliest possible time and deduction to
be made at source. Mr. L. Manglem Singh, Director, MANIREDA stated that MANIREDA has
no outstanding due and the Department are paying bills regularly. It was decided that
MSPDCL may come out with the real outstanding dues upto 31 st December, 2018. Mr.
Nobert Khayi, Social Worker, W.Phungreitang, Ukhrul informed the Committee that in
Ukhrul there are hardly 2 / 3 staffs and people has to wait long hours to clear up their dues
in the office and requested MSPDCL to look after this matter urgently. He further suggested
outsourcing of billing and collection of bill and conducting awareness programme regarding
transmission and distribution status in Manipur. Mr. L. Priyokumar informed the members
that they have been taking actions to improve billing and payment through internet to sort
out various difficulties being faced by the consumers. The Meeting also agreed that MSPDCL
should come up with more revenue collection centres.
iii) Reports on energy audit in RAPDRP towns (vide Agenda no. 5 of the minutes of 18 th
Meeting of SAC, Manipur).
MSPDCL furnished the energy audit report for the month of September, 2018 in RAPDRP
Towns. After going through the report, Member of the Commission, Mr. Ng Sarat Singh
suggested to improve billing efficiency above 90%. They should take 3 months reading to
assess monthly consumption rate. Managing Director, MSPDCL should gear up so that there
is no loss in revenue collection. It was again suggested to have joint meter reading s at 33 kV
and 11 kV Sub Station in presence of both MSPDCL and MSPCL representatives as per the
schedule dates well prepared in advance by both of them together for taking the reading.
iv) The latest reconciled status of feeder meter installation at 11 kV feeders in the single
line diagram of all the sub-stations showing incoming/outgoing 11 kV feeders. Details
of sub-station-wise incoming/outgoing feeders of all voltage levels with meter
installation status under MSPCL (vide Agenda No. 9 of the minutes of 19 th Meeting of
SAC Manipur).
Managing Director, MSPCL Mr. N.Sarat Singh explained in detail the status of metering of 11
kV, 33 kV and 132 kV feeders and furnished the detail network diagram to the Commission
and promised that metering in all the 11 kV incoming feeders in all substations will be
completed within 2 (two) months and all the outgoing 11 kV feeders will be completed
within 6 (six) months.
The MD, MSPDCL explained in detail the basis of the proposal for the increase of the retail
tariff for FY 2019–20. Mr. Elangbam Dolendra Singh, Adviser, All Manipur Power Consumer’s
Association enquired why the Commission always prepare different Tariff rates for Manipur
and Mizoram. The Member of the Commission informed him that the situation of Manipur
and Mizoram is different and the Commission cannot issue a common tariff for the two
States. He further mentioned that the amount of fix charge in the proposed tariff is very
high and it should not be increased and in view of huge number of urban poor consumers
the proposed tariff is very high and is not agreeable at all. Dr. Ch. Ibohal Meitei has stated
that there should not be a tariff shock and a nominal increase in tariff would be accepted by
the consumers. He further stated that the MSPDCL should come up with better billing and
collection centre by use of social network i.e. internet etc. where the consumers can pay
their bills. Mr. Priyokumar, MD, MSPDCL replied that consumers will very soon can pay their
dues through internet banking system. The Committee agreed for a small hike in the tariff
for FY 2019- 20.
Agenda 4 : Truing Up
The 2 (two) companies has an Annual Audited Accounts for the year up to 2015 – 16 only.
Chairman informed them they should take immediate steps for auditing of their accounts
without which truing up cannot be a carried one. Both MDs, MSPDCL and MSPCL assured
that audited annual accounts shall be made available at least up to FY 2016-17 in the next
Tariff Petition.
The Chairman informed the Committee that on visit by the Commission at faraway places
like Chandel, Ukhrul and Senapati for Consumer awareness programmes, the public has
informed the Commission that more payment counters are required. This also was affirmed
by Mr. Nobert Khayi and he suggested that outsourcing of billing and collection of revenue
may be thought of for far-flung areas. Mr. PriyoKumar, MD, MSPDCL informed the
Committee that the Company already have taken steps and franchisee systems will be in
operation very soon.
Agenda 6: Subsidy
As per the Electricity Act, 2003 the Government has to specify the specific category of
consumer which should be given subsidy. The Government of Manipur has so far not
reacted on this matter. MSPDCL shall make proposal to the Government of Manipur for
incorporation in their filling of next Tariff Petition.
The Chairman enquired from the MSPDCL whether the different prepaid meters
manufactured by different companies could be integrated together. The MSPDCL informed
the Committee that with a new software, the system could be integrated now, and there is
no difficulty in re-calibrating the machines with new tariff rates.
The Meeting ended at 2:30 PM with a vote of thanks from the Chair.
ANNEXURE - II
LIST OF PERSONS WHO ATTENDED PUBLIC HEARING ON MULTI YEAR ARR &
TARIFF PETITION FOR FY 2019-20 IN RESPECT OF MSPCL, MANIPUR
ANNEXURE – III
1 2 3 4 5 6 7 8 9 10 11 12=(9+11) 13 14
1 Kutir Jyothi (Domestic)
Per
All units 66442 20.96 26.29 1.70 44.69 29.69
Connection
Sub Total (a) 66442 10963 20.96 20 13.29 44.69 29.69 42.98 515.76 2.46
2 Domestic (General)
i) First 100 kWh 281114 149.00 44.17 3.60 159.01 447.00
ii) Next 100 kWh 108121 132.00 101.74 4.35 367.57 397.42
iii) Balance >200 kWh 43248 105.83 203.92 5.60 816.95 353.32
Sub Total (b) 432483 637639 386.83 60 382.58 1343.53 1197.74 1580.32 18963.84 4.90
Total Domestic (a+b) 498925 648602 407.79 395.87 1388.22 1227.43 1623.30 19479.60 4.78
3 Commercial
i) First 100 kWh 9238 11.00 99.22 5.00 496.10 45.83
ii) Next 100 kWh 11548 25.00 180.41 6.00 982.46 113.45
iii) Balance >200 kWh 2310 9.43 340.25 7.10 2095.78 48.40
Sub Total (a) 23096 58815 45.43 80 47.05 3574.34 207.68 254.73 3056.76 6.73
4 Commercial-HT (b) 481 2224 6.06 1049.90 100 7.00 2.47 8165.89 39.28 41.75 501.01 8.27
Total Commercial (a&b) 23577 61039 51.49 49.52 11740.23 246.96 296.481 3557.77 6.91
5 Public Lighting 601 864 5.08 704.38 65 6.50 0.56 4578.47 27.52 28.08 336.96 6.63
6 Public Water Suply - LT 37 373 2.20 4945.47 100 6.70 0.37 33134.65 12.26 12.63 151.56 6.90
7 Public Water Suply - HT 102 7531 18.66 15248.54 100 6.10 8.37 103351.22 105.42 113.79 1365.45 7.32
8 Agri & Irrigation - LT 53 303 1.27 2000.00 60 3.50 0.18 7000.00 3.71 3.89 46.68 3.67
9 Agri & Irrigation - HT 11 1276 0.85 6424.24 100 3.30 1.42 23555.55 2.59 4.01 48.09 5.67
10 Micro & Small Industry LT 2375 11640 20.00 701.75 65 3.75 7.57 2631.56 62.50 70.07 840.84 4.20
11 Medium Industy HT 44 3232 4.10 7765.15 100 4.90 3.59 42276.93 18.60 22.19 266.29 6.49
12 Large Industry - HT 14 7659 6.00 35714.29 100 6.10 8.51 242063.52 33.89 42.40 508.80 8.48
13 Bulk Supply HT 432 49612 114.00 21990.74 100 5.40 55.12 131944.44 570.00 625.12 7501.49 6.58
Grand Total 526171 792131 631.44 531 603665 2311 2842 34103.53 5.40
ANNEXURE – IV
MSPDCL - Expected Revenue during FY2019-20 from Aproved Subsidised Tariff effective from 01.04.2019
Subsidised Tariff Revenue /month
Sales/Consu Annual
Contracted Annual Fixed Energy Energy Total Avg.
Sl. No. of mer/ Total Fixed Total energy Revenue
Consumer Category Load Units Sales Charge charge charge per Revenue Revenue
No. Consumers Month (in Charges charge ( in Rs.
(in kW) (in MU) (Rs/kVAh or (Rs./kWh Consumer (in Rs (Rs/kWh)
kWh) (Rs. lakhs) (Rs. lakhs) lakhs)
kwh) or kVAh) (Rupees) lakhs)
1 2 3 4 5 6 7 8 9 10 11 12=(9+11) 13 14
1 Kutir Jyothi (Domestic)
All units 66442 20.96 26.29Per Connection 1.85 48.64 32.32
Sub Total (a) 66442 10963 20.96 25 16.61 48.64 32.32 48.93 587.16 2.80
2 Domestic (General)
i) First 100 kWh 281114 149.00 44.17 3.90 172.26 484.25
ii) Next 100 kWh 108121 132.00 101.74 5.20 399.05 431.46
iii) Balance >200 kWh 43248 105.83 203.92 6.00 933.52 403.73
Sub Total (b) 432483 637639 386.83 60 382.58 1504.83 1319.44 1702.02 20424.24 5.28
Total Domestic (a+b) 498925 648602 407.79 399.19 1553.47 1351.76 1750.95 21011.40 5.15
3 Commercial
i) First 100 kWh 9238 11.00 99.22 5.40 535.79 49.50
ii) Next 100 kWh 11548 25.00 180.41 6.50 1062.67 122.72
iii) Balance >200 kWh 2310 9.43 340.25 7.65 2262.91 52.26
Sub Total (a) 23096 58815 45.43 80 47.05 3861.37 224.48 271.53 3258.36 7.17
4 Commercial-HT (b) 481 2224 6.06 1049.90 100 7.60 2.47 8865.82 42.64 45.11 541.33 8.93
Total Commercial (a&b) 23577 61039 51.49 49.52 12727.19 267.12 316.641 3799.69 7.38
5 Public Lighting 601 864 5.08 704.38 65 7.00 0.56 4930.66 29.63 30.19 362.28 7.13
6 Public Water Suply - LT 37 373 2.20 4945.47 100 7.25 0.37 35854.66 13.27 13.64 163.68 7.45
7 Public Water Suply - HT 102 7531 18.66 15248.54 100 6.75 8.37 114364.05 116.65 125.02 1500.21 8.04
8 Agri & Irrigation - LT 53 303 1.27 2000.00 60 3.90 0.18 7800.00 4.13 4.31 51.72 4.07
9 Agri & Irrigation - HT 11 1276 0.85 6424.24 100 3.60 1.42 25696.96 2.83 4.25 50.97 6.01
10 Small Industry LT 2375 11640 20.00 701.75 65 4.10 7.57 2877.18 68.33 75.90 910.80 4.55
11 Medium Industy HT 44 3232 4.10 7765.15 100 5.30 3.59 45728.11 20.12 23.71 284.53 6.94
12 Large Industry - HT 14 7659 6.00 35714.29 100 6.60 8.51 261904.79 36.67 45.18 542.16 9.04
13 Bulk Supply HT 432 49612 114.00 21990.74 100 5.90 55.12 144161.52 622.78 677.90 8134.85 7.14
Grand Total 526171 792131 631.44 534 657599 2533 3068 36812.3 5.83
Annexure-V
MSPDCL - Expected Revenue during FY2019-20 from Approved Full Cost Tariff (i.e Witout Subsidy)
Full Cost Tariff Revenue /month
Sales/Consu Annual
Contracted Annual Fixed Energy Energy Total Avg. ABR to
Sl. No. of mer/ Total Fixed Total energy Revenue
Consumer Category Load Units Sales Charge charge charge per Revenue Revenue Avg Rev
No. Consumers Month (in Charges charge ( in Rs.
(in kW) (in MU) (Rs/kVAh or (Rs./kWh Consumer (in Rs (Rs/kWh) (%)
kWh) (Rs. lakhs) (Rs. lakhs) lakhs)
kwh) or kVAh) (Rupees) lakhs)
1 2 3 4 5 6 7 8 9 10 11 12=(9+11) 13 14 15
1 Kutir Jyothi (Domestic)
All units 66442 20.96 26.29 per conectn 6.60 173.51 115.28
Sub Total (a) 66442 10963 20.96 25 16.61 173.51 115.28 131.89 1582.68 7.55 81.01%
2 Domestic (General)
i) First 100 kWh 281114 149.00 44.17 7.30 322.44 906.42
ii) Next 100 kWh 108121 132.00 101.74 7.80 743.57 803.95
iii) Balance >200 kWh 43248 105.83 203.92 8.50 1543.32 667.46
Sub Total (b) 432483 637639 386.83 70 446.35 2609.33 2377.83 2824.18 33890.16 8.76 93.99%
Total Domestic (a+b) 498925 648602 407.79 462.96 2782.84 2493.11 2956.07 35472.84 8.70 93.35%
3 Commercial
i) First 100 kWh 9238 11.00 99.22 9.30 922.75 85.25
ii) Next 100 kWh 11548 25.00 180.41 10.00 1734.10 200.25
iii) Balance >200 kWh 2310 9.43 340.25 10.60 3416.65 78.91
Sub Total (a) 23096 58815 45.43 100 58.82 6073.50 364.41 423.23 5078.76 11.18 119.96%
4 Commercial-HT (b) 481 2224 6.06 1049.90 110 9.60 2.72 11198.93 53.87 56.59 679.06 11.21 120.28%
Total Commercial (a&b) 23577 61039 51.49 61.54 17272.43 418.28 479.818 5757.82 11.18 119.96%
5 Public Lighting 601 864 5.08 704.38 100 9.50 0.86 6691.61 40.22 41.08 492.96 9.70 104.08%
6 Public Water Suply - LT 37 373 2.20 4945.47 100 10.50 0.37 51927.44 19.21 19.58 234.96 10.70 114.81%
7 Public Water Suply - HT 102 7531 18.66 15248.54 110 9.50 9.20 160956.81 164.18 173.38 2080.62 11.15 119.64%
8 Agri & Irrigation - LT 53 303 1.27 2000.00 100 7.60 0.30 15200.00 8.06 8.36 100.32 7.89 84.66%
9 Agri & Irrigation - HT 11 1276 0.85 6424.24 110 7.50 1.56 53535.33 5.89 7.45 89.40 10.54 113.09%
10 Micro & Small Industry LT 2375 11640 20.00 701.75 100 8.90 11.64 6245.58 148.33 159.97 1919.64 9.60 103.00%
11 Medium Industy HT 44 3232 4.10 7765.15 110 9.00 3.95 77651.50 34.17 38.12 457.44 11.16 119.74%
12 Large Industry - HT 14 7659 6.00 35714.29 110 9.50 9.36 376984.17 52.78 62.14 745.69 12.43 133.37%
13 Bulk Supply HT 432 49612 114.00 21990.74 110 8.50 60.64 207690.32 897.22 957.86 11494.28 10.08 108.15%
Grand Total 526171 792131 631.44 622 976938 4281 4904 58846 9.32 100.00%