Tender No.: CEG/IGC/1543/2019
Tender No.: CEG/IGC/1543/2019
Tender No.: CEG/IGC/1543/2019
CEG/IGC/1543/2019
FORM 'A'
FINANCIAL INFORMATION
I. Financial Analysis - Details to be furnished duly supported by figures in balance sheet/ profit
and loss account for the last five years duly certified by the Chartered Accountant, as submitted by
the applicant to the Income Tax Department (copies to be attached).
Name and
address of
Chartered
Accountant
Note: Further details if required may be asked from the contractor after opening of the bids. There
is no need to upload the entire voluminous balance sheet.
Tender No. CEG/IGC/1543/2019
FORM 'C' : DETAILS OF ALL SIMILAR WORKS COMPLETED IN ALL RESPECTS DURING THE LAST SEVEN YEARS ENDING ON THE LAST DAY OF
THE MONTH JULY 2019
Sl. Name of work /project Owner or Cost of Date of Stipulated Actual date Litigation / Name & Address / Remarks
No. and location sponsoring work commencement date of arbitration Phone No. of officer
organisation Rupees as per contract of completion pending / in to whom reference
(in Lakhs) completion progress may be made.
with details*
Sl. Name of work /project Owner or Cost of Date of Stipulated Up to date Slow Name and address / Remarks
No. and location sponsoring work commencement date percentage progress if telephone number of
organisation Rupees as per contract of progress of any and officer to whom
(in Lakhs) completion work reasons reference may be
thereof made
3 Legal status of the applicant (Please tick and attach attested copies of original document
defining the legal status)
(a) An individual; (b) A proprietary firm; (c) A firm in partnership
(d) A limited company or Corporation
5 Names and Titles of Director & Officers with designation proposed to be concerned with this
work
7 Was the applicant ever required to suspend construction for a period of more than six months
continuously after you commenced the construction? If so, give the name of the project and
reasons of suspension of work.
8 Has the applicant or any constituent partner in case of partnership firm, ever abandoned the
awarded work before its completion? If so, give name of the project and reasons for
abandonment.
Tender No. CEG/IGC/1543/2019
9 Has the applicant, or any constituent partner in case of partnership firm, ever been debarred /
black listed for tendering in any organisation at any time? If so give details.
10 Has the applicant, or any constituent partner in case of partnership firm , ever been convicted
by a court of law? If so, give details.
11 In which fields of Engineering construction the applicant has specialisation and interest?
FORM 'G' : DETAILS OF TECHNICAL & ADMINISTRATIVE PERSONNEL TO BE EMPLOYED FOR THIS
WORK
FORM'H' - DETAILS OF CONSTRUCTION PLANT AND EQUIPMENT LIKELY TO BE USED IN CARRYING OUT THIS WORK
Sl. Name of Equipment/ Plant Nos Capacity or Age Condition Ownership status Current Remarks
No. Type & Presently Leased To be Proposed Location
make owned purchased to be hired
I Earth moving equipment
1. Excavators(various sizes)
2. Dumpers
2
1. Concrete batching plant
2.Concrete pump
a) with Placer Boom
2.Concrete pump
b) with Stationary
3.Concrete transit mixer
4.Concrete mixer (diesel)
5.Concrete mixer (electrical)
6.Needlevibrator(electrical)
7.Needle vibrator(petrol)
8.Concrete pump
9. Curing pumps (various
capacities)
3 Equipment for building
work
1. Bar bending machine
2. Bar cutting machine
3. Drilling machine
4. Welding generators
5. Welding transformers
6. M.S.pipes
7. Steel shuttering
8. Steel scaffolding
Tender No. CEG/IGC/1543/2019
FORM'H' - DETAILS OF CONSTRUCTION PLANT AND EQUIPMENT LIKELY TO BE USED IN CARRYING OUT THIS WORK
Sl. Name of Equipment/ Plant Nos Capacity or Age Condition Ownership status Current Remarks
No. Type & Presently Leased To be Proposed Location
make owned purchased to be hired
4 Testing Equipments for
1. Cube Testing
2. Sieve analysis
3. Ultrasonic test
4. Silt test
5. Micron gauger
6. Moisture Metre
7. Any other
FORM'H' - DETAILS OF CONSTRUCTION PLANT AND EQUIPMENT LIKELY TO BE USED IN CARRYING OUT THIS WORK
Sl. Name of Equipment/ Plant Nos Capacity or Age Condition Ownership status Current Remarks
No. Type & Presently Leased To be Proposed Location
make owned purchased to be hired
2. Air Compressors ( Elect)
8 Dewatering equipment
1. Pump (diesel)
2. Pump (electric)
9 Power equipment
1.Diesel generators