Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Rate Analysis For Reinforced Cement Concrete

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

3

RATE ANALYSIS FOR REINFORCED CEMENT CONCRETE


DOWNLOADED FROM THECONSTRUCTOR.ORG

RCC 1 :1.5 :3 Analysis for 1


Wet Volume 1.00 m 3

Dry Volume 1.54

MATERIAL Qty. Units Rs. / Unit


CEMENT BAGS 8.07 bags 300
SAND 0.42 m3 900
Aggregate 0.84 m3
700
Reinforcement 78.50 Kg 60

LABOUR With
Mechanical Mixer & Vibrartor Days
MASON 0.37 300
LABOUR 3.50 200
WATER CARRIER 1.39 200
BAR BENDER 0.79 200
MIXER OPERTOR 0.071 200
MIXER VIBRATOR 0.071 200
0.00
PRIME COST (Rs.):

Water Charges 1.5%


Sundries (including mixer machine, transportation etc) 7.5 %
Contractor's Profit 14 %

Total Cost per m3 of RCC =

Cost of RCC for Given Data = Rs.


CONCRETE
Steel % by volume
of Concrete
SLAB 1.00%
BEAM 2.00%
COULMN 2.50%
Road 0.60%
AMOUN SUBTOT
T (Rs.) AL (Rs.)
2421
378
588
4710
8096.75

111.00
700.00
278.00
157.00
14.28
14.28 1274.56

9371

141
703
1312

11527

11527

You might also like