GT2009 59268
GT2009 59268
GT2009 59268
GT2009
Proceedings
June 8-12, 2009, Orlando, of 2009
Florida, USA
ASME Turbo Expo 2009: Power for Land, Sea and Air
June 8-12, 2009, Orlando, Florida, USA
GT2009-59268
GT2009-59268
Mechanical limits
- New Parts
The above listed design targets had to be achieved
under rather restrictive boundary conditions:
To minimize costs, re-work scope and
implementation time of the engine upgrade, the rotor
had to remain unchanged, and any new blade design
had to fit into the existing blade grooves. Since all
four blade rows have axial root fixations, there was
no possibility of changing the number of rotating
blades.
For the same reasons, the turbine vane carrier had to
remain unchanged: only additional machining
operations that can be carried out on-site were Figure 2. Principle turbine layout
allowed. However, since the stationary vanes are
mounted in radial grooves in the turbine vane carrier, The following basic modifications, directed at the
changing the vane count was a possibility. improvement of turbine blading efficiency, were
As stated earlier, the turbine upgrade needed to be introduced during the development phase:
compatible with the existing exhaust diffuser. Apart - Optimization of turbine stage-to-stage
from the design requirements with respect to the loading;
turbine outflow conditions, this also meant that - New airfoil profiling using advanced 3D
mechanical parameters like flow path diameter and aerodynamic approaches;
distance between turbine exit and diffuser struts - Optimization of stator-rotor sealing,
could not be changed. Finally, the turbine upgrade including a reduction of the maximum
had to insure a prescribed swallowing capacity to allowable radial gap and a decrease in
allow the engine to be operated with an enlarged sealing pressure ratio;
compressor pressure ratio (+3.4% in comparison with - Replacement of the damping bolt in the last
the current machine) to provide additional gross stage blade with a full shroud.
efficiency gain. On top of that, cooling air consumption was reduced
by optimizing the cooling system for Vane 1, Blade
1, Vane 2, Blade 2 and Stator Heat Shield A. This
allowed an increase in TIT (inlet turbine mixed
temperature), while keeping the hot gas temperature
at the turbine inlet and, consequently, combustor
lifetime and emissions unchanged.
0.40
Cycle improvement 1
Power gain, MW
New profiling 70%
1.5 60%
0.45 Sealing optimization Turbine Efficiecy gain 0.9
50%
0.50
20%
0.6
GT11N2M
10%
0 0%
0.5
0.4
0.3
Figure 3. The contribution of the different 0.2
improvement measures to turbine efficiency and gross 0.1
power growth 0
0.6 0.62 0.64 0.66 0.68 0.7 0.72 0.74 0.76
2.2.1 Stage-to-stage loading optimization T/THG
Figure 4 shows the original GT11N2 turbine stage Figure 5. Vane 3 inlet gas temperature in GT11N2
pressure ratio distribution (blue bars) in comparison and GT11N2M turbine
with that of the upgraded turbine (red bars). The
concept behind the turbine loading optimization is
based on a de-loading of the front stages, which have Blade3 inlet relative gas temperature
the lowest aerodynamic efficiency, in favor of the
1
rear stages with higher efficiency. That is why, in the
0.9
GT11N2 M turbine, the pressure ratio was reduced at
T/THG
1.2
1.15 GT11N2
Figure 6. Blade 3 inlet gas temperature in GT11N2
GT11N2M and GT11N2M turbine
Pressure ratio
1.1
1.05
2.2.2. Airfoil profiling
1 As indicated above, new advanced airfoils had to be
0.95 developed for the GT11N2 turbine upgrade, using
0.9
previously published 3D aerodynamic design
Stage1 Stage2 Stage3 Stage4 approaches ([4], [5]). Each row was tuned
Figure 4. Turbine stage-to-stage pressure ratio individually using 2D and 3D Navier-Stokes codes
distribution ([6], [7]).
The advantages of this approach are illustrated in
The fundamental disadvantage of front stage de- Figure 7, which shows a comparison of predicted
loading is the increase in gas temperature for the isentropic Mach number distributions for the original
downstream stages, namely the un-cooled stages 3 GT11N2 Blade 1 and the newly designed GT11N2 M
and 4. Owing to temperature profiles gradually Blade 1. The 3D Navier-Stokes code was used for
increasing towards larger radii (Figure 5, 6), the tip optimization of the aerodynamic shape of the airfoils,
regions of these uncooled rows became the most avoiding local overexpansion zones and controlling
critical areas for the upgrade. The mitigation and minimizing the level of profile, secondary and
measures comprised a 3D aerodynamic profiling radial gap losses. The chosen approach allows
combined with an aerodynamic loading optimization calculation of the loss coefficients in the turbine rows
over the turbine radius. Usage of a significantly more precisely, which is illustrated in Figure 8, where
higher loading of the tip sections of turbine stages 1,
the results of Blade1 loss assessment performed by
2 and 3 led to a substantial reduction in gas
the 3D Navier-Stokes code are compared with those
temperature for the tip sections of the uncooled blade
calculated by 2D methods. All blades and vanes of
rows (see Figure 5, 6).
© ALSTOM 2009. All rights reserved. Information contained in this document is provided without liability
for information purposes only and is subject to change without notice. No representation or warranty is
given or to be implied as to the completeness of information or fitness for any particular purpose.
Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
4
5
the turbine upgrade were redesigned using this
approach.
Furthermore, adopting a compound lean design
approach (Figure 9) for Vanes 3 and 4 was beneficial
from the aerodynamic performance point of view,
providing:
- Substantial growth in stage reaction at the
inner diameter of stages 3 and 4;
- A noticeable reduction of outlet Mach Vane 4
number at the inner diameter of vanes 3 and
4;
- An increase of inlet flow angle for blades 3
and 4 (at inner diameter)
The total turbine blading efficiency benefit as a result
of advanced airfoil profiling has been estimated to be
0.45%.
Figure 9. Vane 4 compound lean design
Mλis is
1.2
1.1
1.
GT11N2 2.2.3. Turbine sealing optimization
0.9 The improvement of the turbine sealing was defined
0.8
0.7
as another important design target for the GT11N2
0.6 turbine upgrade. This resulted in a number of
0.5
0.4
modifications dedicated to minimizing cooling air
0.3 leakages through the stator parts (vanes, stator heat
0.2
shields) by introducing up-to-date seals, an improved
0.1
0.9
GT11N2M achieved by reducing the hot gas leakages at the inner
0.8 diameter by:
− Adding platforms on vanes 2 and 3 (vane 1
0.7
0.6
0.3
the original design );
0.2 − Introduction of staggered honeycomb
0.1
0.
labyrinth seals with fins on the rotor and
0. 0.1 0.2 0.3 0.4
-- hub
0.5
-- mid
0.6
-- tip
0.7 0.8 0.9 S
S axially stepped honeycombs on the
Suction side Pressure side platforms of vanes 2, 3, and 4, which is
more efficient than the previously used
Figure 7. Blade1 surface isentropic Mach number “look-through” seal design (Figure 10)
distribution (3D Navier-Stokes code) A comparison of the old and new inner diameter seal
design of vanes 2, 3 and 4 is shown in detail in Figure
Blade1. Loss radial variation
10. Figure 11 illustrates how the introduction of a
staggered honeycomb labyrinth seal has almost
1
halved the leakage-flow for vane 4, compared to the
0.9
original “look-through” design. The introduction of
0.8
the honeycombs in vanes 2, 3 and 4 also permitted a
Channel relative height
0.7
significant reduction of the stator-rotor radial
0.6
3D N-St.GT11N2
clearances and, subsequently, the leakages flows.
0.5
3D N-St. GT11N2M In total, the optimization of the vane’s inner platform
0.4
2D N-St. GT11N2
sealing contributes about 0.65% of turbine blading
0.3 2D N-St. GT11N2M
0.2
efficiency gain.
0.1
0
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4
Losses
© ALSTOM 2009. All rights reserved. Information contained in this document is provided without liability
for information purposes only and is subject to change without notice. No representation or warranty is
given or to be implied as to the completeness of information or fitness for any particular purpose.
Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
5
6
Anti-vibration
GT11N2 Damping bolts platform
Blade 4
GT11N2M
5
Turbine exit Total pressure
Current design (GT11N2) 1
4 0.9
Leakage, kg/s
p*, bar
Figure 11. Leakage vs. radial gap over vane 4 inner
platform ( 2D CFD FLUENT analysis) Figure 13. Impact of damping bolt on total pressure
radial distribution
2.2.4. Introduction of a tip shroud for the last
stage blade. 2.2.5 Turbine cooling optimization.
In addition to the measures listed above, the bolts As mentioned above, about 50% of the GT11N2
used in the original design to dampen blade 4 turbine power gain comes from the reduction of the
vibrations were replaced by an interlocking full cooling air mass flow (see fig. 3). This was achieved
shroud. (Figure 12). This measure helped to further by the application of state-of-the-art cooling
improve the turbine performance due to the technology and the use of advanced cooling design
elimination of aerodynamic losses caused by the methods and tools.
damping bolt and the reduction of tip-clearance As an example, Figure 14 presents the principle
losses. cooling schemes of GT11N2M vane 1 and blade 1.
A comparison of the old and new designs is shown in For vane 1, a cooling system consisting of two
Figure 12. The impact of a damping bolt on the cavities was chosen. The front part of the airfoil is
aerodynamic losses is illustrated in Figure 13. This cooled by the air passing through the channels
figure shows, measurements of the total pressure between the inner wall and the insert in the front
downstream of the last stage blade of the GT11N2. cavity and is then discharged on the leading edge
These measurement results, obtained from two 5-hole surface through the shower head consisting of 3
probes, were used to calibrate the GT11N2 through- vertical film cooling rows. The rear part has a multi-
flow model and for a more reliable evaluation of the pass cooling system supported by two rows of film
delta in losses for blade 4, with and without the cooling on the pressure side.
damping bolts. Blade 1 is a convectively cooled with a separate
According to the aerodynamic analysis the total channel in the leading edge. The air cooling the
turbine blading efficiency gain related to the leading edge passes through this channel and then
replacement of the damping bolts with a full shroud discharges into the tip crown of the blade. The rear
was predicted to be 0.5%. part of blade 1 has a multi-pass cooling system with
two turnings providing highly effective cooling with
a relatively small cooling mass flow.
© ALSTOM 2009. All rights reserved. Information contained in this document is provided without liability
for information purposes only and is subject to change without notice. No representation or warranty is
given or to be implied as to the completeness of information or fitness for any particular purpose.
Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
6
7
2.3 Turbine manufacturing.
One of the biggest challenges of this project was
getting so many new parts through the supply chain
on time and meeting cost and quality targets at the
same time.
As short time to market was one of the key success
factors for this project, and taking into consideration
that there has been a world-wide bottleneck in the
supply of gas-turbine blading over the last years, this
represented a great challenge for the design team,
logistics and the suppliers. As a consequence, a great
deal of effort was spent on optimizing the way
design, logistics and suppliers interacted. Throughout
the whole turbine development and purchasing
phases, processes were adapted to support this.
One measure was to assign dedicated people from the
design/project team and the supplier’s side and to
empower them in order to efficiently take care of all
design, logistics and manufacturing issues as soon as
they arose.
Another measure was to have the suppliers selected
and involved in the design at the earliest possible
point in time. This meant, the suppliers were fully
aware of the design intent right from the beginning
and were able to directly feed back their input with
respect to expected tolerances, manufacturability and
potential quality risks to the design team.
Establishing this close loop between design teams
and suppliers saved a lot of time, which in the past
typically had to be spent correcting or revising
drawings and to re-analyzing based on supplier
feedback available only after the majority of the
design was already completed. Furthermore, this
approach also helped reduce tooling, qualification
Figure 14. Cooling scheme of vane 1 and blade 1 and first-set production time, since the design already
considered supplier-specific capabilities and
This article cannot go into all the details of the experience, avoiding e.g. long qualification loops to
turbine cooling design, and therefore only the main meet unnecessary or unrealistic tolerance
changes to the cooling flow are summarized in Figure requirements etc.
15. Overall, this approach helped to identify critical
issues, to share knowledge, to identify cost drivers
Cooling Air Consumption for Components and potential improvements at the earliest point in
time, and as a result to avoid potential causes for
40
35.7 delay or poor quality.
35
GT11N2: total -100% Another key aspect in working closely with logistics
% of GT11N2 TCLA
30
23.8 GT11N2M: total -82.1% and the suppliers was to identify and realize jointly
25
20.1 the opportunities to further reduce lead-times e.g. by
20
14.6
the parallelization of tasks that are independent of
15
9.3
each other, but traditionally have been performed
10
5.9 4.9 4.4 sequentially; joint agreements on the minimum
5
information necessary to start a certain task (i.e. key
0
geometric data sufficient to order raw material for
Vane1 Blade1 Vane2 Blade2
tools prior to having final drawings available), further
Figure 15. Contribution of the different turbine helped to minimize lead-times.
components cooling optimization to the cooling flow During workshops held together with people from
reduction % of total cooling air. logistics and the suppliers, a unique Design & Make
plan was established, offering a basis for monitoring
As shown, the mass flow of the cooling air was and controlling all engineering and production
reduced by a total of 18%, including the effects of tasks/steps and, therefore, the whole project plan.
sealing optimization, described above. Also, the delivery dates for all components were
© ALSTOM 2009. All rights reserved. Information contained in this document is provided without liability
for information purposes only and is subject to change without notice. No representation or warranty is
given or to be implied as to the completeness of information or fitness for any particular purpose.
Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
7
8
generated from this Design & Make plan. This meant, The comparison of measured turbine flange
that only one master plan was available/agreed on efficiency of the original and re-designed turbines is
during the whole project phase, and this plan was the shown in Figure 16. The measurements in the field
basis for everyone involved in the project. confirmed the expected turbine performance targets.
Last but not least, such joint workshops were also an
excellent way to establish communication between Table 2. Comparison of target and achieved
the various suppliers and to get them committed to performance gain for Performance Mode option
the project plan. In many cases, smaller issues could
be resolved between the suppliers directly, without
Engine and Target Test data
the design team directly being involved.
turbine parameters analysis
When production of the first parts started a dedicated
πk +3.5% +4.0%
NCR (Non Conformance Report) process established
specifically for this development project allowed for TIT +1.9% +1.9%
quick responses to the suppliers in case parts were η*fl +1.9% +1.91%
manufactured outside of the specifications. Thanks to
this process, in one specific incidence, the issue could GT11N2 Turbine flange polytropic efficiency
In the end, all parts were delivered on time and the GT11N2 test
GT11N2 pretest
1.0
whole design/manufacturing throughput time was GT11N2
Baseline
considered to be one of the fastest ever achieved 0.5
Typical performance data available from the engines Figure 16. Measured turbine flange efficiency of the
in the existing fleet include GT power output, GT original and a redesigned turbine.
efficiency (evaluated based on measured power and
fuel consumption), pressures and temperatures The measurements of the flow structure with the 5-
downstream of the compressor and the exhaust hole probe traverse at the turbine exit/diffuser inlet on
diffuser. The latter allows the evaluation of the both original GT11N2 and upgraded GT11N2 M
turbine flange efficiency. In addition to this, in order units permits the derivation of turbine blading
to have sufficient data available for a proper efficiency and diffuser performance from of the
baselining and model calibration, a special test turbine flange-efficiency measurements. The
campaign was performed on an existing GT11N2 unit comparison of measured turbine blading efficiency
prior to the start of the design phase. This test between the original and re-designed turbines is
campaign, in addition to standard performance shown in Figure 17. It confirms that the expected
measurements as described above, included the increase in turbine blading efficiency, as a result of
measurement of the radial distribution of the inlet gas the described improvement measures, is achieved
temperature by means of thermal crystals, metal fully. The measured pressure loss characteristics of
temperature measurements of vane row 3 and flow the exhaust diffuser for original and upgraded engine
traversing downstream of the turbine at the diffuser is presented in Figure 18. The measurements confirm
inlet (using 5-hole probe measurements). Almost the that the exhaust diffuser performance is nearly
same scope of measurements was carried out later on unchanged, which was one of the design objectives.
during the validation of the first upgrade installation GT11N2 Turbine blading polytropic efficiency
in May 2008 in a customer engine. 2.5
2.0
© ALSTOM 2009. All rights reserved. Information contained in this document is provided without liability
for information purposes only and is subject to change without notice. No representation or warranty is
given or to be implied as to the completeness of information or fitness for any particular purpose.
Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
8
9
GT11N2/N2M. Diffuser total pressure loss 4. REFERENCES
[1] Harasgama, S.P., Kreitmeier, F., 1994, “A new
220%
upgraded turbine for the GT8 and GT8C turbine
200%
180%
family”, ASME Paper 1994-GT-65, The Nague,
160% GT11N2M.
GT11N2. Netherlands.
Baseline
[2] Schneider, C., Navrotsky, V., Harasgama, P.,
dP*/P*in
© ALSTOM 2009. All rights reserved. Information contained in this document is provided without liability
for information purposes only and is subject to change without notice. No representation or warranty is
given or to be implied as to the completeness of information or fitness for any particular purpose.
Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
9