Completed Mini Project
Completed Mini Project
Completed Mini Project
ON
BACHELOR OF TECHNLOGY IN
CIVIL ENGINEERING
BY
Somidi,Kazipet
Warangal-506003
DEPARTMENT OF CIVIL ENGINEERING (2017-2020)
Somidi,Kazipet
Warangal-506003
CERTIFICATE
This is to certify that the industrial oriented mini project entitled “RESTORATION OF ALL THE
MINOR IRRIGATION TANKS” is the bonafide work done by AVUNOORI ANIL
(17UC5A0122),BAIRI ANIL (17UC5A0127),DHARAVATH MANMOHAN (17UC5A0125),&
MEDIPELLY SRAVANI (17UC5A0110) under graduate students of department of Civil
engineer, TALLA PADMAVATHI COLLEGE OF ENGINEERING, Warangal during the period
of 2019-2020 in the partial fulfillment of the requirements for the award of degree of
BACHELOR of TECHNOLOGY is a record of their own work,carried out by them under my
supervision and guidance during the academic year 2019-2020.
Miss K APARNA
Assistant professor
TALLA PADMAVATHI COLLEGE OF ENGINEERING
WARANGAL -5063003
Place :
Date :
PROJECT ASSOCIATES :
ACKNOWLEDGEMENT
We wish to take the opportunity to express our deep gratitude to all the
people who have presented their cooperation in various ways during our project
work. It is our pleasure to acknowledge the help of all those individuals.
BY-
AVUNOORI ANIL (17UC5A0122)
BAIRI ANIL (17UC5A0127)
DHARAVATH MANMOHAN (17UC5A0125)
MEDIPELLY SRAVANI (17UC5A0110)
2
ABSTRACT
INDEX
INTRODUCTION TO IRRIGATION
IRRIGATION STRUCTURES
REGULATION OF CANAL
MISSION KAKATIYA
INTRODUCTION TO IRRIGATION :-
Irrigation is a science of artificially supplying water to the
land to grow crops. It is the application of controlled intervals. It helps to
grow agriculture crops, re vegetate disturbed soils in dry areas and during
periods of less than average rainfall.
TYPES OF IRRIGATION:
Flow irrigation:
In this method water is supplied to the fields by gravity flow
Lifted irrigation:
In this method water is lifted to the level and then allowed to
flow by gravity.
Methods of application of water:
1 surface irrigation
2. Sub surface irrigation
3. Sprinkler irrigation
DELTA(∆) OF CROP:
Each crop requires a certain amount of water
at fixed intervals of time through outs its growth period.
Total depth of water required for crop to come to harvest is called its
Delta in cm.
The total quantity of water required for a crop through outs its base period
is expressed as
1) million cubic meters of water
2) Hectre-metre
3) The depth of water standing throughout its crop period.
DUTY OF WATER:
Duty of water is the relationship between the
volume of water and the area of the crop it irrigates.
This is expressed as area irrigated by one cumec discharge running
for base period ‘B’ days i.e, Hectres/cumec or Hectre/ million cumec
CROPS SEASONS:-
The agricultural crop year in India is from July to June. The
Indian cropping season is classified into two main seasons-(i) Kharif and (ii)
Rabi based on the monsoon. The kharif cropping season is from July –
October during the south-west monsoon and the Rabi cropping season is
from October-March (winter). The crops grown between March and June
are summer crops. Pakistan and Bangladesh are two other countries that are
using the term ‘kharif’ and ‘rabi’ to describe about their cropping patterns.
6
IRRIGATION STRUCTURES :-
HEAD WORKS:
A head work is a combination of hydraulic
structures constructed at the head of a canal at the point of take off to
divert the water from the river to the head canal.
Classification of head work:
• Diversion head work
• Storage head work
Diversion head work:-
In diversion works a weir or anicut is constructed across the river
and the water is discharge or diverted in to a canal for irrigation purpose.
Storage head work:-
In storage worker a dams is constructed across the river to
store for irrigation or power generation purpose.
COMPONENT PARTS OF DIVERSION WORKS:-
1) A weir or barrage across the river
2) Scouring sluices
3) Dividing wall or groyne
4) Head regulator
5) Flood banks
6) Fish ladder
Restoration of tanks
6. To delay floods.
on u/s.
Upstream Apron :
Downstream apron :
Creep :
Types of Weirs :
Weirs are classified according to,
STORAGE WORKS :
TYPES OF RESERVIOR :
DAM:-
A dam is a barrier that stops or restricts the flow of water or
underground streams. Reservoirs created by dams not only suppress
floods but also provide water for activities such as irrigation, human
consumption, industrial use, aquaculture, and navigability.
Classification of dams:-
1) Gravity dam:- A gravity dam s a masonry or concrete dam which resists
the sliding and other forces by its weight.
2) Arch dam:- Arch dams are curved in plan which resists the
disturbing forces by arch action.
3) Embankment dam:- It is a non rigid dam which resists the
disturbing forces by its shear strength.
Dams are also classified depending on the functions performed by its as:-
1) Storage Dam
2) Diversion Dam
3) Detention Dam
4) Coffer Dam
5) Debris Dam
DISTRIBUTION WORKS:
Distribution works includes the canals and channel to convey water
from head works to the fields for irrigation together with the
masonry works required for regulation of water.
Classfication of canals:-
Based on source of supply:-
1) Permanent Canals
2) Inundation Canals
Based on Discharge:-
1) Main canal
2) Branch canal
3) Distributaries
4) Field channels
Based on alignment:-
1) Contour canal
2) Ridge or watershed canal
3) Side slope canal
REGULATION OF CANAL:
The discharge through canals is regulated by means of regulators
or according to the demand.
1) Head regulator (sluice):-
It is provided at the head or off-take point of a
distributory channel and controls the supply of water in to the channel.
2) Cross regulators:-
A cross regulator is provided in the main canal towards
to downstream side of the of taking channel and operated when necessary
so as to rise the water in the main canal thus ensure required supply in the
off take channel.
3) Canal Drop or falls:-
Whenever the natural ground slope is steeper than
the designed bed slope of the canal. The difference of elevations are
adjusted by constructing vertical falls or drops in the canal bed at suitable
intervals. It is constructed so as to maintain design slope of bed.
10
2) Syphon aqueduct:-
In a syphon aqueduct, canal water is carrier above the drainage but
the high flood level (HFL) of drainage is above the canal trough. The
drainage water flows under syphonic action and there is no presence of
atmospheric pressure in the natural drain.The construction of the
syphon aqueduct structure is such that, the flooring of drain is
depressed downwards by constructing a vertical drop weir to discharge
high flow drain water through the depressed concrete floor.
11
3) Super passage:-
Super passage structure carries drainage above canal as the canal
bed level is below drainage bed level. The drainage trough is to be
constructed at road level and drainage water flows through this from
upstream to downstream and the canal water flows through the piers
which are constructed below this drainage trough as supports.The full
supply level of canal is below the drainage trough in this structure. The
water in canal flows under gravity and possess the atmospheric
pressure. This is simply a reverse of Aqueduct structure.
4) Level crossing:-
When the bed level of canal is equal to the drainage
bed level, then level crossing is to be constructed. This
consists of following steps:
1. Construction of weir to stop drainage water behind it
2. Construction of canal regulator across a canal
3. Construction of head regulator across a Drainage
MISSION KAKATIYA
Introduction :
Works involved:
c) Before laying the soil, the initial moisture content of the material
shall be determined at the source of supply.
(d) After the soil is added the water shall be added to it through sprinklers.
15
(e) After adding the required quantity of water, the soil shall be processed
by means of harrows, rotary mixers or as specified, till the layer is uniform
with OMC.
This gives good grip to the embankment soil with the subgrade.
(f) The compaction of this soil embankment is done up to 98%
Proctor’s density.
(g) Soil Compaction Equipment, Vibratory Roller, Pneumatic
Compaction Device, Slope Compaction Machine e.t.c., are
the machinery utilized for compacting the bank.
(h) Each earth-fill shall be laid in suitable layers not exceeding 25cm before
compaction and should be spread over full width of embankment.
(i) Rolling shall commence at edges and progress towards
centre longitudinally, in a direction parallel to the axis.
(o) The soils used for the embankment shall be as determined by Engineer
In-Charge and shall be obtained from required excavation or from
approved borrow areas and shall confirm to clause 6.4 of IS 4701.
(p) The compaction shall be ensured that 98% of the maximum dry
density at OMC is obtained. The OMC shall be determined
in accordance with IS2720 (Part VII)– 1973.
(q) Chute drains shall be provided at suitable intervals on down-stream
connected to toe drain all along the bund in order to prevent the
erosion of soil in the bund during the times of rains or overflow.
(bi) Repairs and replacement of tank sluices and gates:-
(a) Irrigation Sluices, approach RCC platforms, plugs with screw gear
operated shutters e.t.c., are repaired in accordance with clause 9.1,
9.2 of IS 1597 – Part 1.
(b) All the required designs are to be obtained from the CDO (Central
Designs Organization), Hyderabad.
17
Advantages of De-siltation:
1. Increased availability of fresh water, eliminates fluoride
risks through improvement of ground water levels.
2. Usage of silt in the farms improves soil fertility thus reducing
fertiliser usage.
3. The soil moisture content in the farm fields also increases.
4. This will rejuvenate the flood channels taking off from rivers
and augment supplies to irrigation tanks.
5. There will be increase in storage.
CASE STUDY: 1
Name of the Tank : JAGANNATHAPURAM TANK
Unique ID : 30315000801101
GEO ID : 795090181767
Longitude : 79o 50’ 90” E
Latitude : 18o17’67” N
Ayacut (in acres) : 1272.00
Capacity (in MCFt.) : 299.36
Ayacut irrigated (in acres) : 1272.00
Bund before development works Bund after development Works
This tank is undertaken for restoration during the second phase of
Mission Kakatiya. The details of the work are mentioned below
19
CASE STUDY: 2
Name of the Tank : DANDEPALLI TANK
Unique ID : 303150008052202
GEO ID : 7950901877411
Longitude : 85o 20’ 90” E
Latitude : 26o17’62” N
Ayacut (in acres) : 1802.00
Capacity (in MCFt.) : 312.36
Ayacut irrigated (in acres) : 1340.00
Bund before development works Bund after development Works
This tank is undertaken for restoration during the second phase of
Mission Kakatiya. The details of the work are mentioned below
After the bund widening is finished stones of 225mm thickness are pitched
on the upstream side.
3. Repairs to the Sluice:
Due to increase in top width of the bund, the length of the bund slope is
increased. Due to this it is necessary to construct the guide wall at the
cistern portion. Concrete of M10 and M15 grades are utilized for this
improvement of Sluice and construction of guide wall.
4. Repairs to the Weir:
The weir is maintained to create the level of storage of water in
the tank corresponding to the contour levels of that location.
5. Construction of Chute drains and Turfing:
Chute drains are necessary to maintain and protect the bund during the
times of rain or overflow. They divert the runoff water from the top of the
bund to its bottom without giving a chance of erosion of the bund.
6. Feeder Channel:
It is a canal which feeds up the tank with the runoff or flood water during
monsoons. The overall cost of reconstruction and restoration activities is
7,18,00,000/-
2. CHECK DAMS:
Check dams are constructed across the natural streams in order to slow
down the flow velocity and to enhance infiltration of that flow. There by
increases the ground water table. A system of several check dams situated at
regular intervals in the area of interest works effectively. They also protect
the channel from getting eroded by the flow. They do serve as small
reservoirs and act as source of irrigation to a little extent.
· In the body wall, 12mm thick expansion joints are given during concreting
and are filled with Asphaltic filler and 300mm wide PVC water stopper
at 30m interval.
· Backfilling of Abutments and return walls are done simultaneously
with raising of the wall with soils of ø value not less than 28o.
· All aggregates should confirm to IS383
· Concrete and workmanship should confirm to IS456:2000
· Embankments for flood banks should confirm to IS12094:2000
22
CONCLUSION:-
The basic objective of this mini project is to discover
improvements in practise and procedures that will enable planning
and designing of tanks .