Blue Book Item 400
Blue Book Item 400
Blue Book Item 400
400.1 Description
400.1.1 Scope
This Item shall consist of piling, furnished, driven or placed, cut and spliced
in accordance with this Specification and in reasonably close conformity with the
Plans.
The Contractor shall furnish the piles in accordance with an itemized list,
which will be provided by the Engineer, showing the number and lengths of all piles.
When cast-in-place concrete piles are specified on the Plans, the Engineer will not
furnish the Contractor an itemized list showing the number and length of piles.
When test piles and load tests are required in conformance with Sub-section
400.1.2 and 400.1.3, respectively, the data obtained from driving test piles and
making test loads will be used in conjunction with other available sub-soil
information to determine the number and lengths of piles to be furnished. The
Engineer will not prepare the itemized list of piles for any portion of the foundation
area until all specified loading tests in the Contract representative of the portion
have been completed.
For his own information, the Contractor may drive at the location of the
regular piles indicated on the Plans such test piles as he may consider necessary
in addition to the test piles specified in the Contract and shall be considered as
regular piles. When called for in the Bill of Quantities, a pile if required to be
subjected to load test shall conform to the provision as provided in Subsection
400.1.3, Load Tests. The Contractor shall furnish and drive test piles of the
dimensions and at the locations designated by the Engineer. They shall be of the
material shown in the Bill of Quantities and shall be driven to refusal or to such tip
elevation or approximate bearing value as the Engineer may request. Test piles
shall be driven with the same hammer that is used for driving foundation piles.
When the Engineer requests a load test to determine a bearing value, the
first load test pile shall be driven to the specified bearing value as determined by
the applicable formula in Subsection 400.1.4 for Timber Pile Bearing Value by
Formula. Subsequent test piles to be load-tested shall be driven to the specified
bearing value as determined by the applicable formula modified by the results of
prior test loads and foundation data. The ground at each test pile shall be
excavated to the elevation of the bottom of the footing before the pile is driven.
134
400.1.3 Load Tests
Load tests for files shall be either Static or Pile Testing by Low-Strain
Dynamic Method, High-Strain Dynamic Method and Cross-Hole Sonic Logging.
When load tests are specified, the number and location of piles to be tested
will be designated by the Engineer. Load tests shall be done by methods approved
by the Engineer. The Contractor shall submit to the Engineer for approval detailed
plans of the loading apparatus he intends to use. The apparatus shall be so
constructed as to allow the various increments of the load to be placed gradually
without causing vibration to the test piles. If the approved method requires the use
of tension (anchor) piles, such tension piles shall be of the same type and diameter
as the permanent piles and shall be driven in the location of permanent piles when
feasible. Piling not a part of the structure shall be removed or cut off at least 300mm
below the bottom of the footing or finished elevation of the ground upon completion
of the test load. Permanent piling used as anchor piling which is raised during the
test load shall be redriven to original grade and bearing.
Suitable approved apparatus for determining accurately the load on pile and
the settlement of the pile under increment of load shall be supplied by the
Contractor.
Each load increment shall be held for an interval of two and one-half minutes.
Each succeeding increment shall be as directed by the Engineer or as shown on
the Plans and shall be applied immediately after the two and one-half minute
interval readings have been made.
When a load-settlement curve obtained from these data shows that the pile
has failed; i.e., the load can be held only by the constant pumping and the pile or
shaft is being driven into the ground, pumping shall cease. Gross settlement
readings, loads and other data shall be recorded immediately after pumping has
ceased and again after an interval of two and one-half minutes for a total period of
five (5) minutes. All loads shall then be removed and the member allowed to
recover. Gross settlement readings shall be made immediately after all loads have
been removed and at each interval of two and one-half minutes for a total period of
five (5) minutes.
135
All load tests shall be carried to failure or to the capacity of the equipment,
unless otherwise noted on the Plans.
After the completion of loading tests, the load used shall be removed and the
piles including tension piles, shall be utilized in the structure if found by the Engineer
to be satisfactory for such use. Test piles not loaded shall be utilized similarly. If
any pile, after serving its purpose as a test or tension pile, is found unsatisfactory
for utilization in the structure, it shall be removed if so ordered by the Engineer or
shall be cut off below the ground line of footings, whichever is applicable.
136
contamination, soft concrete, honeycombing, voids, or intrusions of foreign objects
exhibit delayed arrival time with reduced signal strength.
1000 WH
P = ----------- x -----------------
6 S+2.54
1000 E
P = ------------ x -----------------
6 S+2.54
1000 E
P = ---------- x ------------------------
6 S+2.54 (Wp/W)
Where:
137
2. The head of the pile is free from broomed or crushed wood fiber
or other serious impairment.
3. The penetration is reasonably quick and uniform.
4. There is no measurable bounce after the blow.
5. A follower is not used.
The bearing values for concrete and steel pile will be determined by the
Engineer using the following formulas:
2WH (W)
Ru = ----------------------------
(S+K) (W+Wp)
Ru
Ra = ---------------
FS
Where:
b. Hiley’s Formula shall be used when the ratio of the weight of ram
or hammer to weight of pile is less than one fourth (1/4).
138
efWH (W) (W + n2 Wp)
Ru = ------------------------------ x ---------------------------
S+1/2 (C1+C2+C3) (W + Wp)
Ru
Ra = --------------
FS
where:
Note:
Formula for other pile hammers with suggested factor of safety should
be as provided/recommended by their respective manufacturer.
139
Materials to which Easy Driving: Medium Driving: Hard Driving: Very Hard
blow is applied P1 = 3.45 MPa P1 = 6.90 MPa P1 = 10.34 MPa Driving:
(500 psi) (1000 psi) (1500 psi) P1 = 13.88 MPa
on Pile Butt If on Head or Cap. on Head or Cap. (2000 psi)
no cushion, mm (in.) mm (in.) on Head or Cap.
mm (in.) mm (in.)
Head of timber pile 1.27 (0.05) 2.54 (0.10) 3.81 (0.15) 5.08 (0.20)
Concrete Pile 0.635 (0.025) 1.27 (0.05) 1.905 (0.075) 2.54 (0.10)
Steel-covered cap.
containing wood
packing but steel
piling at pipe 1.016 (0.04) 2.032 (0.08) 3.048 (0.12) 4.064 (0.16)
bThe first figure represent the compression of the cap and wood dolly or
packing above the cap, whereas the second figure represent the
compression of the wood packing between the cap and the pile head.
P1 = Ru/A
Values of Efficiency of Hammer, ef
Hammer Type ef
140
Diesel
Hammer
Reinforced Helmet with composite plastic or
Concrete green heart dolly on top of pile 0.40 0.50
The formulas specified in the preceding Subsection for timber piling may be
used in determining a rough approximation for the bearing power of precast and
cast-in-place concrete piles and of steel piles.
In all cases when the bearing power of concrete and steel piles is determined
by formula, the piles shall be driven until the safe bearing power of each is
computed to be not less than 27 tonnes.
When the safe bearing power of any pile is found by test or computation to
be less than the design load, longer piles or additional piles shall be driven as
ordered in writing by the Engineer.
The safe bearing power of jetted piles shall be determined by actual tests or
by the appropriate methods and formulas given in the preceding Subsections. No
jet shall be used during the test blows.
The kind and type of piles shall be as specified on the Plans and Bill of
Quantities. No alternative type or kind of piling shall be used.
Timber shall conform to the requirements of Item 713, Treated and Untreated
Timber. The specie shall be specified on the Plans. Unless otherwise noted on the
Plans or Special Provisions, only the best grade shall be used. It shall be free from
loose knots, splits, wormholes, decay, warp, ring separation or any defect which will
impair its strength or render it unfit for its intended use. Any specie specified on the
141
Plans may be used for untreated timber and if the specie is not available, a specie
of equivalent strength and durability may be used if authorized by the Engineer.
Round piles shall be cut above the ground swell and shall taper from butt to
tip. A line drawn from the center of the tip to the center of the butt shall not fall
outside of the cross-section of the pile at any point more than one percent of the
length of the pile.
In short bends, the distance from the center of the pile to a line stretched
from the center of the pile above the bend to the center of the pile below the bend
shall not exceed four percent of the length of the bend or a maximum of 65mm.
Unless otherwise specified, all piles shall be peeled removing all rough bark
and at least 80 percent of the inner bark. Not less than 80 percent of the surface
on any circumference shall be clean wood. No strip of inner bark remaining on the
pile shall be more than 20mm wide and 200mm long. All knots shall be trimmed
close to the body of the pile.
The pile sizes shall conform to the dimensions shown in Table 400.1.
The diameter of the piles shall be measured in their peeled condition. When
the pile is not exactly round, the average of three measurements may be used. For
any structure, the butt diameters for the same lengths of pile shall be as uniform as
possible.
Timber shall conform to the requirements of Item 713, Treated and Untreated
Timber. Treatment shall consist of the forcing of either creosote oil or creosote
petroleum oil mixture into the outer fibers of the timber by a heat and pressure
process. The process shall be in accordance with ASTM D-1760 Standard
Specification for Pressure Treatment of Timber Products, but with such changes as
temperatures, pressures, duration of treatment and other factors affecting the final
treatment that experience has shown to be necessary in the treatment of structural
timbers sawn from woods native to the Philippines. The treatment shall be so
regulated that the curing process will not induce excessive checking. The minimum
penetration of the preservative into the surface of the timber shall be 20 mm. All
piles shall retain the minimum amount of preservative specified in Table 400.2.
142
Table 400.2 – Minimum Preservative Per Cubic Metre of Wood
Type of Processing
Use Empty Cell Process Full Cell Process
General Use 195 kg
Marine Use 320 kg
The Engineer shall inspect the timber prior to the treatment to determine
conformance with the Specifications and suitability of conditions for treatment. He
shall be permitted free access to the plant in order that temperatures, pressures
and quantities and type of treatment materials used may be observed. Samples of
the creosote or creosote petroleum mixtures shall be furnished as required for test.
The timber shall be checked to determine penetration of treatment, quantity
of free preservative remaining on the timber and any visual evidence that the
treatment has been performed in a satisfactory manner. The penetration of
treatment shall be determined by boring a sufficient number of well-distributed holes
to determine the average penetration. All such holes shall be plugged with plugs
approximately 2 mm larger in diameter than the bit used in boring the holes.
If the penetration of preservative is less than the required amount, the entire
charge, or such parts thereof shall be retreated. If after treatment the penetration is
still insufficient, the treated pieces shall be rejected.
Unless otherwise called for on the Plans or Special Provisions, shells for
cast-in-place concrete piles shall have a minimum 305mm diameter at cut off and
a minimum 203mm diameter at tip: made from not less than 4.55mm in thickness
143
plate stock conforming to AASHTO M 183. Shells may either be spirally welded or
longitudinally welded and may either be tapered or constant in section. Tips shall
be sealed as shown on the Plans.
Filled Steel Pipes (filled with concrete) shall conform to the requirements of
ASTM A 252, Grade 2, Welded and Seamless Pipe Piles. Closure Plates for closed
piles shall conform to the requirements of AASHTO M 183.
Steel H-Piles shall be rolled steel sections of the weight and shape called for
on the Plans. They shall be structural steel meeting the requirements of AASHTO
M 183 provided that, where the Special Provisions called for copper-bearing
structural steel, the steel shall not contain less than one-fifth percent nor more than
zero point thirty five percent (0.35%) of copper, except that steel manufactured by
the acid-bessemer process shall not be used.
Steel sheet piles shall meet the requirements of AASHTO M 202 (ASTM A
328), or AASHTO M 223. All other sheet piles shall meet the requirements
prescribed above the particular material specified. The joints shall be practically
water-tight when the piles are in place.
400.2.9 Splices
Material for pile splices, when splicing is allowed, shall be of the same quality
as the material used for the pile itself and shall follow the requirements given on
the Plans.
400.2.10 Paint
144
It shall conform to Item 709, Paints.
All excavations for the foundation on which the piles are to be driven shall
be completed before the pile driving, unless otherwise specified or approved by the
Engineer. After driving is completed, all loose and displaced materials shall be
removed from around the piles by hand excavation, leaving clean solid surface to
receive the concrete of the foundation. Any requirement for granular fill and lean
concrete shall be indicated on the Plans or as directed by the Engineer.
Pile length and bearing capacity shall be determined by the Engineer from
the results of the test piling and load tests.
The Contractor shall be responsible for obtaining the correct pile length and
bearing capacity according to the criteria given by the Engineer.
All piles shall be driven as shown on the Plans or as ordered in writing by the
Engineer. They shall be driven within an allowed variation of 20mm per metre of
pile length from the vertical or batter as shown on the Plans. The maximum
allowable variation at the butt end of the pile shall be 75mm in any direction from
the location shown on the Plans or as directed by the Engineer. Each pile shall,
after driving, be within 150mm from the theoretical location underneath the pile cap
or underneath the superstructure in case of pile bents. All piles pushed up by the
driving of adjacent piles or any other cause shall be redriven.
145
All pile driving equipment is subject to the Engineer’s approval. The
Contractor is responsible for sufficient weight and efficiency of the hammers to drive
the piles down to the required depth and bearing capacity. Hammers shall be
gravity hammers, single and double acting steam or pneumatic hammers or diesel
hammers. Gravity hammers shall not weigh less than 60 percent of the combined
weight of the pile and driving head but not less than 2,000 kg. The fall shall be
regulated so as to avoid injury to the pile and shall in no case exceed 4.50m for
timber and steel piles and 2.50m for concrete piles unless otherwise specified or
approved by the Engineer.
The plant and equipment furnished for steam hammers shall have sufficient
capacity to maintain, under working condition, the pressure at the hammer specified
by the manufacturer. The boiler or pressure tank shall be equipped with an accurate
pressure gauge and another gauge shall be supplied at the hammer intake to
determine the drop in pressure between the gauges. When diesel hammers or any
other types requiring calibration are used, they shall be calibrated with test piling
and/or test loads in accordance with Subsection 400.1.2, Test Piles.
Water jets shall be used only when permitted in writing by the Engineer.
When water jets are used, the number of jets and the nozzle volume and pressure
shall be sufficient to erode freely the material adjacent to the pile. The plant shall
have sufficient capacity to deliver at all time a pressure equivalent to at least 690
KPa at two 19 mm (3/4 inch) jet nozzles. The jets shall be shut off before the
required penetration is reached and the piles shall be driven solely by hammers to
final penetration as required by the Engineer.
Piles shall be supported in line and position with leads while being driven.
Pile driving leads shall be constructed in such a manner as to afford freedom of
movement of the hammer, and shall be held in position by guys or steel braces to
insure rigid lateral support to the pile during driving. The leads shall be of sufficient
length to make the use of a follower unnecessary and shall be so designed as to
permit proper placing of batter piles. The driving of the piles with followers shall be
avoided if practicable and shall be done only under written permission from the
Engineer.
The method used in driving piles shall not subject them to excessive and
undue abuse producing crushing and spalling of the concrete, injurious splitting,
splintering and brooming of the wood or deformation of the steel. Manipulation of
piles to force them into proper position if considered by the Engineer too excessive
will not be permitted.
Full length piles shall be used where practicable. Splicing of piles when
permitted, shall be in accordance with the provisions of Subsection 400.3.7 and
146
400.3.8. All piles shall be continuously driven unless otherwise allowed by the
Engineer.
Piles shall not be driven within 7 m of concrete less than 7 days old.
Piles shall be strapped with three metal straps: one about 450mm from the
butt, one about 600mm from the butt, and the third, about 300mm from the tip.
Additional straps shall be provided at about 4.5m on centers between tip and butt.
Strapping should encircle the pile once and be tensioned as tightly as possible.
Straps shall be 38mm wide, 0.8mm thick, cold rolled, fully heat treated, high tensile
strapping, painted and waxed.
Point protection shall be considered for all timber piles. Where timber piles
must penetrate dump fill, or may encounter obstructions or be driven to hard strata,
point protection shall be used. A boot that encompasses and utilizes the entire end
area of the pile is preferred.
Piles for any one bent shall be carefully selected as to size, to avoid undue
bending or distortion of the sway bracing. Care shall be exercised in the distribution
of piles of various sizes to obtain uniform strength and rigidity in the bents of any
given structure.
Cut offs shall be made accurately to insure full being between caps and piles
of bents.
Piles shall be cured and finished in accordance with Items 405, Structural
Concrete and 406, Prestressed Concrete Structures.
Cylinder specimens shall be made and tested in accordance with Item 405.
Piles shall not be moved until the tests indicate that the concrete has attained a
compressive strength of at least 80 percent (80%) of the design 28-day
147
compressive strength and they shall not be transported or driven until the design
28-day compressive strength has been attained.
When concrete piles are lifted or moved, they shall be supported at the points
shown on the Plans; if not shown, they shall be supported at the quarter points.
1. Drilled Holes
All holes for concrete piles cast in drilled holes shall be drilled dry to tip
elevation shown on the Plans. All holes will be examined for straightness and any
hole which on visual inspection from the top shows less than one-half the diameter
of the hole at the bottom of the hole will be rejected. Suitable casings shall be
furnished and placed when required to prevent caving of the hole before concrete
is placed.
All loose material existing at the bottom of the hole after drilling operations
have been completed shall be removed before placing concrete.
The use of water for drilling operations or for any other purpose where it may
enter the hole will not be permitted. All necessary action shall be taken to prevent
surface water from entering the hole and all water which may have infiltrated into
the hole shall be removed before placing concrete.
The inside of shells and pipes shall be cleaned and all loose materials
removed before concrete is placed. The concrete shall be placed in one continuous
operation from tip to cut-off elevation and shall be carried on in such a manner as
to avoid segregation.
The top 3m of concrete filled shells, or to the depth of any reinforcing cage,
whichever is greater, shall be consolidated by acceptable vibratory equipment.
148
Pipes shall be of the diameter shown on the Plans. The pipe wall thickness
shall not be less than that shown on the Plans but in no case less than 5mm. The
pipe, including end closures, shall be of sufficient strength to be driven by the
specified methods without distortion.
Closure plates and connecting welds shall not project more than 12.5mm
beyond the perimeter of the pile tips.
No shell or pipe shall be filled with concrete until all adjacent shells, pipes,
or piles within a radius of 1.5m or 4 ½ times the average pile diameter, whichever
is greater, have been driven to the required resistance.
After a shell or pipe has been filled with concrete, no shell, pipe or pile shall
be driven within 6m thereof until at least 7 days have elapsed.
3. Drilled Shafts
Drilled shafts are deep foundations formed by boring a cylindrical hole into
soil and/or rock and filling the hole with concrete. Drilled shafts are also commonly
referred to as caissons, bored piles or drilled piers.
Drilled shafts, like driven piles, transfer structural loads to bearing stratum
well below the base of the structure by passing soils having insufficient strength to
carry the design loads.
Drilled shafts are classified according to their primary mechanism for deriving
load resistance either as floating shafts (i.e., shafts transferring load primarily by
side resistance), or end-bearing shafts (i.e., shafts transferring load primarily by tip
resistance). Occasionally, the bases of shafts are enlarged (i.e., belled or
underreamed) to improved the load capacity of end bearing shafts on less than
desirable soils, or to increase the uplift resistance of floating shafts.
Drilled shafts are normally sized in 15.24cm (6-inch diameter increments with
a minimum diameter of 45.72cm (18”). The diameter of a shaft socketed into rock
should be a minimum of 15.24cm (6”) larger than the socket diameter. If a shaft
must be inspected by the entry of a person, the shaft diameter shall not be less
than 76.20cm (30”).
149
Drilled shafts constructed in dry, noncaving soils can usually be excavated
without lateral support of the hole. Other ground conditions where caving,
squeezing or sloughing soils are present require installation of a steel casing or use
of a slurry for support of the hole. Such conditions and techniques may result in
loosening of soil around the shaft, or altering of frictional resistance between the
concrete shaft and surrounding soil.
a. The construction of the pile or shaft in a wet condition while the walls of
the excavation are stabilized by hydrostatic pressure of water or a mineral slurry
until the concrete is placed by tremie methods for the full length of the pile.
Mineral slurry used in the drilling process shall have both a mineral grain size
that will remain in suspension and sufficient viscosity and gel characteristics to
transport excavated material to a suitable screening system. The percentage and
specific gravity of the material used to make the suspension shall be sufficient to
maintain the stability of the excavation and to allow proper concrete placement. The
level of the slurry shall be maintained at a height sufficient to prevent caving of the
hole.
The mineral slurry shall be premixed thoroughly with clean fresh water and
adequate time allotted for hydration prior to introduction into the shaft excavation.
Adequate slurry tanks will be required when specified. No excavated slurry pits will
be allowed when slurry tanks are required on the project without written permission
of the Engineer. Adequate desanding equipment will be required when specified.
Steps shall be taken as necessary to prevent the slurry from “setting up” in the shaft
excavation, such as agitation, circulation, and adjusting the properties of the slurry.
150
Control tests using suitable apparatus shall be carried out by the Contractor
on the mineral slurry to determine density, viscosity, and pH. An acceptable range
of values for those physical properties is shown in the following table.
Viscosity 28 to 45 28 to 45 Marsh
(sec. per quart) Cone
pH 8 to 11 8 to 11 pH Paper
or Meter
Note:
a) Increase density values by 0.314 KN/m3 (2 pcf) in salt water.
Tests to determine density, viscosity and pH values shall be done during the
shaft excavation to establish a consistent working pattern.
Prior to placing shaft concrete, slurry samples shall be taken from the bottom
and at intervals not exceeding 3.05m (10 feet) for the full height of slurry. Any
heavily contaminated slurry that has accumulated at the bottom of the shaft shall
be eliminated. The mineral slurry shall be within specification requirements
immediately before shaft concrete placement.
Excavation Inspection
The Contractor shall provide equipment for checking the dimensions and
alignment of each shaft excavation. The Contractor under the direction of the
Engineer shall determine the dimensions and alignment of the drilled shaft. Final
shaft depth shall be measured after final cleaning.
The base of the shaft excavation may be cleaned using a cleaning bucket
followed by airlifting. Reverse circulation techniques may also be used to clean the
base of the shaft.
151
b. The use of steel casing which is installed during drilling operations to hold
the hole open and usually withdrawn during concrete placement.
c. The use of a permanent casing which is left in place within the portion of
the pile which is in unstable material.
The reinforcing steel cage consisting of the steel shown on the Plans plus
cage stiffener bars, spacers, centralizers and any other necessary appurtenances
shall be completely assembled and placed as a unit immediately after the shaft
excavation is inspected and accepted and prior to shaft concrete placement.
Where the reinforcing cage length is too long for placement as a single unit
the cage may be placed in separate units such that appropriate means of splicing
the longitudinal steel is provided for. The Contractor shall submit his plans for such
splices to the Engineer for approval.
The reinforcing steel in the hole shall be tied and supported so that the
reinforcing steel will remain within allowable tolerances until the concrete will
support the reinforcing steel. When concrete is placed by suitable tubes, temporary
hold-down devices shall be used to prevent uplifting of the steel cage during
concrete placement. Concrete spacers or other approved noncorrosive spacing
devices shall be used at sufficient intervals not exceeding 1.50 meters along the
shaft to insure concentric location of the cage within the shaft excavation. When
the size of the longitudinal reinforcing steel exceeds 25mm, such spacing shall not
exceed 3.0 meters.
152
Concrete shall be placed as soon as possible after reinforcing steel cage
placement. Concrete placement shall be continuous in the shaft to the top elevation
of the shaft. Placement shall continue after the shaft is full until good quality
concrete is evident at the top of the shaft. Concrete shall be placed through a
suitable tube.
For piles less than 2.5 meters in diameter, the elapsed time from the
beginning of concrete placement in the shaft to the completion of placement shall
not exceed 2 hours. For piles 2.50 meters and greater in diameter, the concrete
placing rate shall not be less than 9.0 meters of pile height per each 2-hour period.
The concrete mix shall be of such design that the concrete remains in a workable
plastic state throughout the 2-hour placement limit.
When the top of pile elevation is above ground, the portion of the pile above
ground shall be formed with a removable form or permanent casing when specified.
After placement, the temporarily exposed surfaces of the shaft concrete shall
be cured in accordance with the provision in Sub-section 407.3.8 – Curing
Concrete.
For at least 48 hours after pile concrete has been placed, no construction
operations that would cause soil movement adjacent to the shaft, other than mild
vibration, shall be conducted.
Construction Tolerances:
a. The drilled shaft shall be within 7.62cm (6”) of the plan position in the
horizontal plane at the plan elevation for the top of the shaft.
b. The vertical alignment of the shaft excavation shall not vary from the plan
alignment by more than 20.83 mm/m (1/4 inch per foot) of depth.
c. After all the shaft concrete is placed, the top of the reinforcing steel cage
shall be no more than 15.24 cm (6”) above and no more than 7.62 cm
(3”) below plan position.
d. When casing is used, its outside diameter shall not be less than the shaft
diameter shown on the plans. When casing is not used, the minimum
diameter of the drilled shaft shall be the diameter shown on the plans for
diameters 60.96 cm (24”) or less, and not more than 2.54 cm (1 inch) less
than the diameter shown on the plans for diameters greater than 60.96
cm (24”).
153
e. The bearing area of bells shall be excavated to the plan bearing area as
a minimum. All other plan dimensions shown for the bells may be varied,
when approved, to accommodate the equipment used.
f. The top elevation of the shaft shall be within 2.54 cm (1 inch) of the plan
top of shaft elevation.
g. The bottom of the shaft excavation shall be normal to the axis of the shaft
within 62.5 mm/m (3/4 inch per foot) of shaft diameter.
Steel H-Pile shall consist of structural steel shapes of the sections indicated
on the Plans.
When placed in the leads, the pile shall not exceed the camber and sweep
permitted by allowable mill tolerance. Piles bent or otherwise damaged will be
rejected.
Cutting shoes for piles driven open end may be inside or outside of the pipe.
They may be high carbon structural steel with a machined ledged for pile bearing
or cast steel with a ledge, designed for attachment with a simple weld.
400.3.10 Splicing
a. By using prefabricated joints mounted in the forms and cast together with
the piles sections and joined together as specified by the manufac-turer
and approved by the Engineer. The joints shall be of the design and type
as specified or shown on the Plans.
154
b. By cutting away the concrete at the end of the pile, leaving the reinforcing
steel exposed for a length of 40 bar diameters for corrugated or deformed
bars and 60 bar diameters for plain bars. The final cut of the concrete
shall be perpendicular to the axis of the pile. Reinforcement of the same
size as that used in the pile shall be spliced to the projecting steel in
accordance with Item 404, Reinforcing Steel, and the necessary
formwork shall be placed, care being taken to prevent leakage along the
pile. The concrete shall be of the same quality as that used in the pile.
Just prior to placing concrete, the top of the pile shall be wetted
thoroughly and covered with a thin coating of neat cement, retempered
mortar, or other suitable bonding material to the satisfaction of the
Engineer. The forms shall remain in place not less than seven (7) days.
The pile shall not be driven until the safe design has been reached.
2. Prestressed Piles
If the length of the steel pile, shell or pipe driven is insufficient to obtain
the specified bearing power, an extension of the same cross-section shall be
spliced to it. Unless otherwise shown on the Plans, splices shall be made
by butt-welding the entire cross-sections to form an integral pile using the
electric arc method. The sections connected shall be properly aligned so
that the axis of the pile shall be straight. Bent and/or damaged piles shall be
rejected.
Concrete piles shall, when approved by the Engineer, be cut off at such a
level that at least 300mm of undamaged pile can be embedded in the structure
above. If a pile is damaged below this level, the Contractor shall repair the pile to
the satisfaction of the Engineer. The longitudinal reinforcement of the piles shall be
embedded in the structure above to a length equal to at least 40 times the diameter
of the main reinforcing corrugated bars (60 diameters for plain bars). The distance
155
from the side of any pile to the nearest edge of the cap shall not be less than
200mm.
When the cut off elevation for a precast pile or for the steel shell or pile for a
cast in place concrete pile is below the elevation of the bottom of the pile cap, the
pile may be built-up from the butt of the pile to the elevation of the bottom of the cap
by means of reinforced concrete extension constructed in accordance with
Subsection 400.3.10 or as approved by the Engineer.
Cut-offs of structural steel piles shall be made at right angles to the axis of
the pile. The cuts shall be made in clear, straight lines and any irregularity due to
cutting or burning shall be leveled-off with deposits of weld metal prior to placing
bearing caps.
Any pile delivered with defects, or damaged in driving due to internal defects
or by improper driving, or driven out of its proper location, or driven below the
elevation fixed by the Plans or by the Engineer, shall be corrected at the
Contractor’s expense by one of the following methods approved by the Engineer
for the pile in question:
When a new pile is driven or cast to replace a rejected one, the Contractor
at his own expense, shall enlarge the footing as deemed necessary by the
Engineer.
156
400.3.15 Painting Steel Piles
Unless otherwise provided, when required steel piles extend above the
ground surface or water surface, they shall be protected by paint as specified for
cleaning and painting metal surfaces in accordance with Item 403, Metal Structures.
This protection shall extend from the elevation shown on the Plans to the top of the
exposed steel.
The Contractor shall keep records of all piles driven or installed. A copy of
the record shall be given to the Engineer within two (2) days after each pile is driven.
The record form to be used shall be approved by the Engineer. The pile records
shall give full information on the following:
157
10. Details of any interruption in
driving
1. Piles Furnished
The quantity to be paid for will be the sum of the lengths in metres of the
piles of the several types and lengths ordered in writing by the Engineer,
furnished in compliance with these Specifications and stockpiles in good
condition at the project site by the Contractor and accepted by the Engineer.
The length to be paid for will include test and tension piles ordered by the
Engineer, but not those furnished by the Contractor at his option. No
allowance will be made for piles, including test piles, furnished by the
Contractor to replace piles previously accepted by the Engineer that are
subsequently lost or damaged while in stockpile, or during handling or
driving, and are ordered by the Engineer to be removed from the site of work.
2. Piles Driven
The quantity to be paid for will be the sum of the lengths in metres of the
piles driven in the completed work measured from the pile tip elevation to the
bottom of pile caps, footings or bottom of concrete superstructure in the case
of pile bents. Measurement will not include additional piles or test piles
driven that may be necessary to suit the Contractor’s method of construction
and were driven at his option.
The quantity to be paid for will be the sum of actual lengths in meters of the
piles cast and left in-place in the completed and accepted work. Measurements will
be from the pile tip to the bottom of cap or footing. Portions of
158
piles cast deeper than the required length through over-drilling will not be measured
for payment.
The quantity to be paid for, including test pile shoes, will be the number of
pile shoes driven shown on the Plans or ordered in writing by the Engineer,
furnished by the Contractor in accordance with these Specifications and accepted
by the Engineer. Pile shoes furnished by the Contractor at his option or to replace
those that are lost or damaged in stockpile or handling will not be measured for
payment.
The quantity of the load tests to be paid for will be the number of tests
completed and accepted except that load tests made to calibrate different types of
hammers, if not included in the Bill of Quantities, will not be measured for payment.
Anchor and test piling which are not part of the completed structure, will be
included in the unit bid price for each “Load Test”. Anchor and test piling or anchor
and test shafts which are a part of the permanent structure will be paid for under
the appropriate Item.
400.4.5 Splices
The quantity to be paid for will be the number of splices which may be
required to drive the pile in excess of the estimated length shown on the Plans for
cast-in-place steel pipes or shells or in excess of the order length furnished by the
Engineer for all other types of piling. Splices made for the convenience of the
Contractor or to fabricate piles cut offs will not be paid for.
159
400 (6) Structural Steel Sheet Piles, furnished Meter
400 (7) Precast Concrete Sheet Piles, furnished Meter
400 (8) Untreated Timber Piles, driven Meter
400 (9) Treated Timber Piles, driven Meter
400 (10) Steel H-Piles, driven Meter
400 (11) Steel Pipes Piles Meter
400 (12) Structural Steel Sheet Piles, driven Meter
400 (13) Precast Concrete Sheet Piles, driven Meter
400 (14) Precast Concrete Piles, driven Meter
400 (15) Precast, Prestresssed Concrete Piles, driven Meter
400 (16) Test Piles, furnished and driven Meter
400 (17) Concrete Piles cast in Drilled Holes Meter
400 (18) Concrete Piles cast in Steel Shells Meter
400 (19) Concrete Piles cast in Steel Pipes Meter
400 (20) Pile Shoes Each
400 (21) Splices Each
400 (22) Load Tests Each
400 (23) Bored Piles (dia. __m) Meter
400 (24) Permanent Casing (dia. ___m) Meter
401.1 Description
This Item shall consist of furnishing or fabricating and/or placing railings, for
bridges and other structures of the material or combination of materials shown on
the Plans, constructed in reasonably close conformity with this Specification and to
the lines, grades and dimensions shown on the Plans. Railings shall be classified
as concrete, steel, aluminum or timber in accordance with the predomi-nating
material contained in each.
401.2.1 Concrete
It shall conform to the requirements of Item 710, Reinforcing Steel and Wire
Rope.
401.2.3 Steel
160
Structural steel consisting of steel and iron plates, shapes, pipes, fittings and
castings shall conform to the requirements of Item 403, Metal Structures.
401.2.4 Aluminum
401.2.5 Timber
These shall conform to the requirements of Item 505, Stone Masonry and
Item 704, Masonry Units.
401.2.7 Paint
401.3.1 General
Railings shall be constructed to the lines and grades shown on the Plans and
shall not reflect any unevenness in the structure. All railing posts shall be set plumb
in hand or mechanically dug holes, unless driving is permitted. In the latter case,
the manner of driving shall be such as to avoid battering or distorting of post. Post
holes shall be backfilled with acceptable material placed in layers and thoroughly
compacted. When it is necessary to cut post holes in existing pavement, all loose
materials shall be removed and the paving replaced in kind. Bridge railings shall
not be placed on a span until centering or falsework has been removed, rendering
the span self-supporting.
161
Galvanized surfaces which have been abraded so that the base metal is
exposed, threaded portions of all fittings and fasteners and cut ends of bolts shall
be painted with two (2) coats of zinc-dust and zinc oxide paint.
Metal railing shall be carefully adjusted prior to fixing in-place to insure proper
matching of abutting joints, correct alignment and camber throughout their length.
Holes for field connection shall be drilled with the railing in-place in the structure at
proper grade and alignment. Welding may be substituted for rivets or bolts in field
connections with the approval of the Engineer.
1. Railing Cast-In-Place
Forms shall either be of single width boards or shall be lined with suitable
material to have a smooth surface which shall meet the approval of the
Engineer or as shown on the Plans.
All moldings, panel work and bevel strips shall be constructed according
to the detailed Plans with metered joints, and all corners in the finished work
shall be true, sharp and clean-cut and shall be free from cracks, spalls and
other defects.
2. Precast Railings
Moist tamped mortar precast members shall be removed from the molds
as soon as practicable and shall be kept damp for a period of at least ten
(10) days. Any member that shows checking of soft corners of surfaces shall
be rejected.
162
401.3.4 Wooden Railing
The materials used in masonry brick railing and parapet and the work to be
done shall conform to the requirements of this Specification. The workmanship
shall be first class and the finished construction shall be neat in appearance and
true to line and grade.
The quantity to be paid for shall be the number of linear meters of specified
railing actually completed and accepted measured from center to center of end
posts.
402.1 Description
163
402.2.1 Timber
402.2.2 Hardware
All hardware shall be of the kind and size specified on the Plans. All bolts,
including drift bolts, shall be either wrought iron or medium steel. Washers shall be
either ogee gray iron casting or malleable cast iron unless cut washers are specified
on the Plans.
Bolts shall have square heads and nuts, unless otherwise specified. Nails
shall be cut or round wire of standard form. Spikes shall be cut wire or spikes, or
boat spikes, as specified. All hardware shall be galvanized in conformity with
AASHTO M 232 or cadmium plated per ASTM M 165 Type OS, unless otherwise
specified on the Plans or Special Provisions.
402.2.3 Paint
It shall conform to the requirements of Item 709, Paints or Item 411, Paint.
402.2.5 Preservatives
When timber is intended for marine use, creosote petroleum oil blend shall
not be used.
All timber which is to be stored on the job for any length of time prior to its
use in the structure shall be neatly stacked in piles to prevent warping or distortion.
Untreated timber shall be open-stacked at least 300mm above the ground and the
stack shall be sloped so as to shed water. Creosote-treated timber shall be close-
stacked and piled to prevent warping. The ground under-neath and in the vicinity
of all material piles shall be cleared of all weeds and rubbish.
164
All treated timber shall be framed prior to treating. Care shall be exercised
in handling all treated timber so as not to break or penetrate the treatment with any
tool or handling equipment. Any piece of timber that has been damaged by the
Contractor shall be replaced by him without extra compensation.
Any cut made or hole bored in treated timber that shall expose untreated
wood shall be given three coats of hot creosote or carbolineum before the exposed
part is assembled.
The minimum penetration of the preservative with the surface of the timber
shall be 20mm. The minimum retention of preservative per cubic metre of timber
shall be as follows:
The Engineer shall be notified at least ten (10) days in advance of the date
that the treating process will be performed in order that the untreated timber, the
treatment process, and the finished treated timber may all be inspected. The
Engineer will inspect the timber prior to treatment to determine conformance with
the Specifications and suitability of conditions for treatment. He shall be permitted
free access to the plant in order that temperatures, pressures and quantities and
types of treatment materials used may be observed. Samples of the creosote or
creosote-petroleum mixture shall be furnished as required for tests.
If the penetration of preservative is less than the required amount, the entire
charge, or such parts thereof as are determined by the Engineer or his authorized
representative to be unsatisfactory, may be retreated. If after retreatment, the
penetration is still insufficient, the retreatment pieces shall be rejected.
Any excessive checking caused by the treating process shall be cause for
rejection of the pieces in which the excessive checking occurs.
165
The treating plant shall be equipped with adequate thermometers and
pressure gages so that the process can be accurately controlled and a continuous
record made of stages of the treating process. If requested by the Engineer,
records shall be furnished showing the duration, maximum and minimum
temperatures and pressures used during all stages of the process.
Washers of the size and type specified shall be used under all bolt heads
and nuts that would otherwise be in contact with wood. Cast iron washers shall
have a thickness equal to one fourth the diameter of the bolt and the diameter of
the washer shall be four times its thickness. For malleable or plate washers, the
diameter or side size of the square shall be equal to four times the diameter of the
bolt. Cap washers shall be used when the timber is in contact with earth. All nuts
shall be checked effectively after being finally tightened.
The pile shall be driven as indicated on the Plans, with a variation of the
portion above the ground of not more than 6mm per 300mm from the vertical or
batter indicated, or so that the cap may be placed in its proper location without
inducing excessive stresses on the piles. Excessive manipulation of piles will not
be permitted and the Contractor will be required to redrive or use other satisfactory
methods to avoid such manipulations. No shimming on tops of piles will be
permitted.
The piles for any one bent shall be carefully selected as to size and quality
to avoid undue bending or distortion of the sway bracing. However, care shall be
exercised in the distribution of piles of various sizes to secure uniform strength and
rigidity in the bents of any given structure. Cut offs shall be accurately made to
insure perfect hearing between caps and piles.
Concrete pedestal for the support of framed bents shall be finished carefully
so that sills or posts will take even bearing on them. Dowels for anchoring sills or
posts shall be set the concrete is cast and shall project at least 150mm above the
tops of the pedestals.
Sills shall have true and even bearing on piles or pedestals. They shall be
drift-bolted with bolts extending into the piles or pedestals at least 150mm. When
166
possible, all earth shall be removed from contact with sills so that there will be free
circulation of air around the sills.
402.3.8 Caps
Timber caps shall be placed to obtain even and uniform bearing over the
tops of the supporting posts or piles with their ends in alignment. All caps shall be
secured by driftbolts, set approximately at the center extending at least 230mm into
the post or piles.
402.3.9 Bracing
402.3.10 Stringers
Planks for laminated or strip floors shall have a nominal thickness of 50mm
and shall be surfaced to a uniform width (SIE), and when so specified, to a uniform
thickness (SIS). Unless otherwise stipulated, no splicing of planks will be allowed.
Planks shall be laid with the surfaced edge down and each plank shall be
toe-nailed to each alternative stringer. The nailing of successive planks shall be
staggered so that the spacing of nails along each stringer shall not be less than
100mm. In addition, each piece shall be nailed horizontally to adjacent pieces at
450mm centers, and staggered both horizontally and vertically with nails in adjacent
pieces. All floors shall be cut to a straight line along the sides of the roadway.
167
402.3.13 Railing and Rail Posts
Railing and rail posts shall be built as shown on the Plans and shall be
constructed in a workmanlike and substantial manner. All railing and rail post
materials shall be surfaced on four sides (S4S). All rails shall be continuous and
squarely butt-joined at the post.
Unless otherwise specified, wheel guards shall be surfaced on one side and
one edge (SISIE). Wheel guards shall be laid in sections not less than 3.60mm
long.
403.1 Description
This work shall consist of steel structures and the steel structure portions of
composite structures, constructed in reasonably close conformity with the lines,
grades and dimensions shown on the Plans or established by the Engineer.
168
The work will include the furnishing, fabricating, hauling, erecting, welding
and painting of structural metals called for in the Special Provision or shown on the
Plans. Structural metals will include structural steel, rivet, welding, special and
alloy steels, steel forgings and castings and iron castings. This work will also
include any incidental metal construction not otherwise provided for, all in
accordance with these Specifications, Plans and Special Provisions.
Materials shall meet the requirements of Item 712, Structural Metal; Item
409, Welded Structural Steel, and Item 409, Welded Structural Steel; and Item 709,
Paints.
403.3.1 Inspection
The Contractor shall give the Engineer at least fifteen (15) days notice prior
to the beginning of work at the mill or shop, so that the required inspection may be
made. The term “mill” means any rolling mill, shop or foundry where material for
the work is to be manufactured or fabricated. No material shall be rolled or
fabricated until said inspection has been provided.
The Contractor shall furnish the Engineer with copies of the certified mill
reports of the structural steel, preferably before but not later than the delivery of the
steel to the job site.
The Contractor shall furnish all facilities for inspection and the Engineer shall
be allowed free access to the mill or shop and premises at all times. The Contractor
shall furnish, without charge, all labor, machinery, material and tools necessary to
prepare test specimens.
169
directed, the Contractor shall select such material as he wishes to use from stock,
and place it in such position that it will be accessible for inspection and sampling.
The Contractor shall select identified material from as few heat numbers as
possible, and furnish the certified mill test reports on each of such heat numbers.
Two samples shall be taken from each heat number as directed, one for a tension
test and one for a bend test.
In the case of unidentified stock, the Engineer may, at his discretion, select
any number of random test specimens.
Each bin from which rivets or bolts are taken shall subject to random test.
Five rivets or bolts may be selected by the Engineer from each bin for test purposes.
403.3.3 Fabrication
Finished members shall be true to line and free from twists, bends and open
joints.
1. Edge Planing
170
Sheared edges of plates more than 15.9 mm in thickness and
carrying calculated stresses shall be planed to a depth of 6.3 mm. Re-
entrant cuts shall be filleted before cutting.
The surface finish of bearing and based plates and other bearing
surfaces that are to come in contact with each other or with concrete
shall meet the American National Standards Institute surface
roughness requirements as defined in ANSI B-46.1-47, Surface
Roughness Waviness and Lay, Part I:
3. Abutting Joints
5. Lacing Bars
The ends of lacing bars shall be neatly rounded unless another form
is required.
6. Fabrication of Members
171
Fabricated members shall be true to line and free from twists, bends
and open joints.
At web splices, the clearance between the ends of the plates shall
not exceed 9.5 mm. The clearance at the top and bottom ends of the
web slice plates shall not exceed 6.3 mm.
8. Bent Plates
a. They shall be so taken from the stock plates that the bendline will
be at right angles to the direction of rolling, except that cold-bent ribs
for orthotropic deck bridges may be bent in the direction of rolling if
permitted by the Engineer.
ASTM THICKNESS, t in mm
DESIG- Up to Over 6.3 Over 12.7 Over 25.4 Over 38.1
ATION 6.3 To 12.7 To 25.4 to 38.1 to 50.08
A36 1.5t 1.5t 2t 3t 4t
A242 2t 3t 5t a--- a---
A440 2.5t 3.5t 6t a--- a---
A441 2t 3t 5t a--- a---
A529 2t 2t ---- ---- ----
Gr.42 2t 2t 3t 4t 5t
Gr.45 2t 2t 3t 4t ----
Gr.50 2.5t 2.5t 4t a--- ----
Gr.55 3t 3t 5t a--- ----
Gr.60 3.5t 3.5t 6t ---- ----
172
Gr.65 4t 4t ---- ---- ----
A572
A588 2t 3t 5t a--- a---
A514b 2t 2t 3t 3t
2
t
a
It is recommended that steel in this thickness range be bent hot. Hot bending
however, may result in a slight decrease in the as-rolled mechanical
properties.
b
The mechanical properties of ASTM A 514 steel results from a quench-and-
temper-operation. Hot bending may adversely affect these mechanical
properties. If necessary to hotbend, fabricator should discuss procedure with
steel supplier.
9. Fit of Stiffeners
10. Eyebars
173
accurately located on the centerline of the bar. The inclination of any
bar to the plane of the truss shall not exceed 1.6 mm to 305 mm.
12. Tests
174
Pins and rollers shall be accurately turned to the dimensions shown on the
Plans and shall be straight, smooth, and free from flaws. Pins and rollers more
228.6 mm or less in diameter may either be forged and annealed. Pins and rollers
228.6 mm or less in diameter may either be forged and annealed or cold-finished
carbon-steel shafting.
In pins larger than 228.6 mm in diameter, a hole not less than 50.8 mm in
diameter shall be bored full length along the axis after the forging has been allowed
to cool to a temperature below the critical range under suitable conditions to prevent
injury by too rapid cooling and before being annealed.
Pin holes shall be bored true to the specified diameter, smooth and straight,
at right angles with the axis of the member and parallel with each other unless
otherwise specified. The final surface shall be produced by a finishing cut.
The diameter of the pin hole shall not exceed that of the pin by more than
0.51 mm for pins 127 mm or less in diameter, or 0.8 mm for larger pins.
The pilot and two driving nuts for each size of pin shall be furnished, unless
otherwise specified.
All holes for rivets or bolts shall be either punched or drilled. Material forming
parts or a member composed of not more than five thickness of metal may be
punched 1.6 mm larger than the nominal diameter of the rivets or bolts whenever
the thickness of the material is not greater than 19 mm for structural steel, 15.9 mm
for high-strength steel or 12.7 mm for quenched and tempered alloy steel, unless
subpunching and reaming is required for field connections.
When there are more than five thicknesses or when any of the main material
is thicker than 19 mm for structural steel, 15.9 mm for high-strength steel, or 12.7
mm for quenched and tempered alloy steel, all holes shall either be subdrilled or
drilled full size.
When required for field connections, all holes shall either be subpunched or
subdrilled (subdrilled if thickness limitation governs) 4.8 mm smaller and, after
assembling, reamed 1.6 mm larger or drilled full size 1.6 mm larger than the nominal
diameter of the rivets or bolts.
When permitted by design criteria, enlarged or slotted holes are allowed with
high-strength bolts. For punched holes, the diameter of the die shall not exceed
175
the diameter of the punch by more than 1.6 mm. If any holes must be enlarged to
admit the fasteners, they shall be reamed. Holes shall be clean cut, without torn
or ragged edges. Poor matching of holes will be cause for rejection.
Unless otherwise specified, holes for all field connections and field splices of
main truss or arch members, continuous beams, towers (each face), bents, plate
girders and rigid frames shall be subpunched (or subdrilled if subdrilling is required)
and subsequently reamed while assembled in the shop in accordance with
Subsection 403.3.7.
All holes for floor-beam and stringer field end connections shall be
subpunched and reamed to a steel template reamed while being assembled.
Alternately, for any field connection or splice designated above in lieu of sub-
sized holes and reaming while assembled, or drilling holes full-size while
assembled, the Contractor shall have the option to drill bolt holes full-size in
unassembled pieces and/or connections including templates for use with matching
sub-sized and reamed holes means of suitable numerically-controlled (N/C) drilling
equipment subject to the specific provisions contained in this Subsection.
The Contractor shall submit to the Engineer for approval a detailed outline of
the procedures that he proposes to follow in accomplishing the work from initial
drilling through check assembly, if required, to include the specific members of the
structure that may be N/C drilled, the sizes of the holes, the location of common
176
index and other reference points, composition of check assemblies and all other
pertinent information.
When holes are reamed or drilled, 85 percent of the holes in any continuous
group shall, after reaming or drilling, show no offset greater than 0.8 mm between
adjacent thickness of metal.
All steel templates shall have hardened steel bushings in holes accurately
dimensioned from the center lines if the connections as inscribed on the template.
The center lines shall be used in locating accurately the template from the milled or
scribed ends of the members.
2. Shop Assembling
177
The field connections of main members of trusses, arches,
continuous beam spans, bents, towers (each face), plate girders and
rigid frames shall be assembled in the shop with milled ends of
compression members in full bearing, and then shall have their sub-
size holes reamed to specified size while the connections are
assembled. Assembly shall be “Full Truss or Girders Assembly”
unless “Progressive Chord Assembly” or “Special Complete Structure
Assembly” is specified in the Special Provisions or on the Plans.
178
tower, than reaming their field connection holes while the
members are assembled; and reaming the web member
connections to steel templates set at geometric (not cambered)
angular relation to the chord lines. Field connection holes in
web members shall be reamed to steel templates. At least
one end of each web member shall be milled or shall be scribed
normal to the longitudinal axis of the member and the
templates of both ends of the member shall be accurately
located from one of the milled ends or scribed line.
179
The check assemblies shall be preferably be the first such sections of
each major structural type to be fabricated.
The size of rivets called for on the Plans shall be the size before heating.
Rivet heads shall be of standard shape, unless otherwise specified, and of uniform
size for the same diameter of rivet. They shall be full, neatly made, concentric with
the rivets holes, and in full contact with the surface of the member. Sufficient rivets
for field connections shall be furnished to rivet the entire structure with an ample
surplus to replace all rivets burned, lost or cut out.
Rivets shall be heated uniformly to a “light cherry red color” and shall be
driven while hot. Any rivet whose point is heated more than the remainder shall
not be driven. When a rivet is ready for driving, it shall be free from slag, scale and
other adhering matter. Any rivet which is sealed excessively, will be rejected.
All rivets that are loose, burned, badly formed, or otherwise defective shall
be removed and replaced with satisfactory rivets. Any rivet whose head is defective
in size or whose head is driven off center will be considered defective and shall be
removed. Stitch rivets that are loosened by driving of adjacent rivets shall be
removed and replaced with satisfactory rivets. Caulking, recapping, or double
gunning of rivets heads will not be permitted.
Rivets may be driven cold provided their diameter is not over 9.5 mm.
1. General
180
Bolts shall be unfinished, turned or an approved form of ribbed
bolts with hexagonal nuts and heads except that ribbed bolts shall
have button heads. Bolted connections shall be used only as
indicated by the Plans or Special Provisions. Bolts not tightened to
the proof loads shall have single self locking nuts or double nuts.
Bevel washers shall be used where bearing faces have a slope or
more than 1:20 with respect to a plane normal to the bolt axis. Bolts
shall be of such length that will extend entirely through their nuts but
not more than 6.3 mm beyond them.
2. Unfinished Bolts
3. Turned Bolts
The surface of the body of turned bolts shall meet the ANSI
roughness rating value of 125. Heads and nuts shall be hexagonal
with standard dimensions for bolts of the nominal size specified or the
next larger nominal size. Diameter of threads shall be equal to the
body of the bolt or the nominal diameter of the bolt specified. Holes
for turned bolts shall be carefully reamed with bolts furnished to
provide for a light driving fit. Threads shall be entirely outside of the
holes. A washer shall be provided under the nut.
4. Ribbed Bolts
181
turn in the holes during tightening. If for any reason the bolt twists
before drawing tight, the holes shall be carefully reamed and an
oversized bolt used as a replacement. The Contractor shall provide
and supply himself with oversize bolts and nuts for this replacement
in an amount not less than ten percent (10%) of the number of ribbed
bolts specified.
1. Bolts
2. Bolted Parts
The slope of surface of bolted parts in contact with the bolt head
and nut shall not exceed 1:20 with respect to a plane normal to the
182
bolt axis. Bolted parts shall fit solidly together when assembled and
shall not be separated by gaskets or any other interposed
compressible material. When assembled, all joint surfaces, including
those adjacent to the bolt head, nuts or washers, shall be free of scale,
except tight mill scale, and shall also be free of burrs, dirt and other
foreign material that would prevent solid seating of the parts. Paint
is permitted unconditionally in bearing-type connections.
3. Installation
183
Threaded bolts shall be tightened with properly calibrated
wrenches or by the turn-of-nut method. If required, because of
bolt entering and wrench operation clearances, tightening by
either procedure may be done by turning the bolt while the nut is
prevented from rotating. Impact wrenches, if used, shall be of
adequate capacity and sufficiently supplied with air to perform the
required tightening of each bolt in approximately ten seconds.
184
of this value. These wrenches shall be calibrated at least once
each working day by tightening, in a device capable of indicating
actual bolt tension, not less than three typical bolts of each
diameter from the bolts to be installed. Power wrenches shall be
adjusted to installed or cut-out at the selected tension. If manual
torque wrenches are used, the torque indication corresponding to
the calibrating tension shall be noted and used in the installation
of all the tested lot. Nuts shall be turned in the tightening direction
when torque is measured. When using calibrated wrenches to
install several bolts in a single joint, the wrench shall be returned
to “touch-up” bolts previously tightened which may have been
loosened by the tightening of adjacent bolts, until all are tightened
to the prescribed amount.
e. Lock Pin and Collar Fasteners. The installation of lock pin and
collar fasteners shall be by methods approved by the Engineer.
185
not exceeding
8 diameters
Over 8
diameters but 0.66 turn 0.83 turn 1 turn
not exceeding
12 diameters2
1 Nut rotation is relative to bolt, regardless of the element (nut or bolt) being
turned. For bolts installed by ½ turn and less the tolerance should be plus or
minus 300, for bolts installed by 2/3 turn and more, the tolerance should be
plus or minus 450.
2
No research work has been performed by the Research Council on Riveted
and Bolted Structural joints to establish the turn-of-nut procedure when bolt
lengths exceed 12 diameters. Therefore, the required rotation must be
determined by actual tests in a suitable tension device simulating the actual
conditions.
4. Inspection
b. Three bolts of the same grade, size and condition as those under
inspection shall be placed individually in a calibration device
capable of indicating bolt tension. Length may be any length
representative of bolts used in the structure. There shall be a
washer under the part turned in tightening each bolt.
186
the tightening direction shall be determined. The average torque
measured in the tests of three bolts shall be taken as the job
inspection torque to be used in the manner specified below.
403.3.11 Welding
Welding shall be done in accordance with the best modern practice and the
applicable requirements at AWS D1.1 except as modified by AASHTO “Standard
Specifications for Welding of Structural Steel Highway Bridges”.
403.3.12 Erection
1. General
The Contractor shall provide the falsework and all tools, machinery and
appliances, including driftpins and fitting-up bolts, necessary for the expeditious
handling of the work and shall erect the metal work, remove the temporary
construction, and do all work necessary to complete the structure as required by
the Contract and in accordance with the Plans and these Specifications.
187
skids placed near enough together to prevent injury from deflection. If the Contract
is for erection only, the Contractor shall check the material turned over to him
against the shipping lists and report promptly in writing any shortage or damage
discovered. He shall be responsible for the loss of any material while in his care,
or for any damage caused to it after being received by him.
403.3.14 Falsework
The false work shall be properly designed and substantially constructed and
maintained for the loads which will come upon it. The Contractor shall prepare and
submit to the Engineer working drawings for falsework and working drawings for
changes in any existing structure for maintaining traffic, in accordance with Clause
45 of Part G, Div. II, Vol. I.
Before starting the work of erection, the Contractor shall inform the Engineer
fully as to the method of erection he proposes to follow, and the amount and
character of equipment he proposes to use, which shall be subject to the approval
of the Engineer. The approval of the Engineer shall not be considered as relieving
the Contractor of the responsibility for the safety of his method or equipment or from
carrying out the work in full accordance with the Plans and Specifications. No work
shall be done until such approval by the Engineer has been obtained.
Following the straightening of a bend or buckle, the surface of the metal shall
be carefully inspected for evidence of fracture.
188
403.3.17 Assembling Steel
403.3.18 Riveting
Pneumatic hammers shall be used for field riveting except when the use of
hand tools is permitted by the Engineer. Rivets larger than 15.9 mm in diameter
shall not be driven by hand. Cup-faced dollies, fitting the head closely to insure
good bearing, shall be used. Connections shall be accurately and securely fitted
up before the rivets are driven.
Drifting shall be only such as to draw the parts into position and not sufficient
to enlarge the holes or distort the metal. Unfair holes shall be reamed or drilled.
Rivets shall be heated uniformly to a “light cherry red” color and shall be driven
while hot. They shall not be overheated or burned. Rivet heads shall be full and
symmetrical, concentric with the shank, and shall have full bearing all around. They
shall not be smaller than the heads of the shop rivets. Rivets shall be tight and
shall grip the connected parts securely together. Caulking or recupping will not be
permitted. In removing rivets, the surrounding metal shall not be injured. If
necessary, they shall be drilled out.
Pilot and driving nuts shall be used in driving pins. They shall be furnished
by the Contractor without charge. Pins shall be so driven that the members will
take full bearing on them. Pin nuts shall be screwed up tight and the threads burred
at the face of the nut with a pointed tool.
189
Shoes and bearing shall not be placed on bridge seat bearing areas that are
improperly finished, deformed, or irregular. They shall be set level in exact position
and shall have full and even bearing. The shoes and bearing plates may be set by
either of the following methods:
1. Method 1
The bridge seat bearing area shall be heavily coated with red lead
paint and then covered with three layers of 405 to 472 g/m 2 duck, each
layer being coated thoroughly on its top surface with red lead paint.
The shoes and bearing plates shall be placed in position while the
paint is plastic.
2. Method 2
All surfaces of new structural steel which are to be painted shall be blast
cleaned unless otherwise specified in the Special Provisions or approved in writing
by the Engineer.
190
In repainting existing structures where partial cleaning is required, the
method of cleaning will be specified in the Special Provision.
Blast cleaning shall leave all surfaces with a dense and uniform anchor
pattern of not less than one and one-half mills as measured with an approved
surface profile comparator.
Blast cleaned surfaces shall be primed or treated the same day blast
cleaning is done. If cleaned surface rust or are contaminated with foreign material
before painting is accomplished, they shall be recleaned by the Contractor at his
expense.
When paint systems No. 1 or 3 are specified, the steel surfaces shall be blast
cleaned in accordance with SSPC – SP – 10. When paint systems No. 2, 4 or 5
are specified, the steel surface shall be blast cleaned in accordance with SSPC –
SP – 6.
The paint system to be applied shall consist of one as set forth in Table 403.4
and as modified in the Special Provisions.
1. Time of Application
191
absence of a pretreatment, the prime coat of paint shall be applied
immediately after the surface has been cleaned.
When a skin has formed in the container, the skin shall be cut loose
from the sides of the container, removed, and discarded. If such
skins are thick enough to have a practical effect on the composition
and quality of the paint, the paint shall not be used.
192
shall be inspected for unmixed pigment. Tinting pastes or colors shall
be wetted with a small amount of thinner, vehicle, or paint and
thoroughly mixed. The thinned mixture shall be added to the large
container of paint and mixed until the color is uniform.
Paint which does not have a limited pot life, or does not deteriorate
on standing, may be mixed at any time before using, but if settling has
occurred, it must be remixed immediately before using. Paint shall
not remain in spray pots, painter’s buckets, etc., overnight, but shall
be gathered into a container and remixed before use.
Note:
1. Paint system shown for severe areas are satisfactorily in less
severe areas.
2. Coastal - within 304.8 m of ocean or tidal water.
High pollution-air pollution environment such as industrial areas.
Mild-other than coastal areas not in air pollution environment.
193
3rd Coat 708.03 (b) 38.10 – 50.80
4th Coat 708.03 (b) 38.10 – 50.80
Finish Coat 708.03 (b) 38.10 – 50.80
Total thickness 165.10 – 203.20
System 2 – Epoxy-Polymide System
Prime Coat 708.03 (c) 50.80 – 76.20
Intermediate Coat 708.03 (c) 50.80 – 76.20
3rd Coat 708.03 (c) 50.80 – 76.20
Finish Coat 708.03 (c) 38.10 – 50.80
Total thickness 190.50 – 279.40
* The third coat may be eliminated in mild climates
4. Application of Paint
a. General
The oldest of each kind of paint shall be used first. Paint shall be
applied by brushing or spraying or a combination of these methods.
Daubers or sheepskins may be used when no other method is
practicable for proper application in places of difficult access.
Dipping, roller coating, or flow coating shall be used only when
194
specifically authorized. All paints shall be applied in accordance with
the manufacturer’s instructions.
195
of paint shall be in a proper state of cure or dryness before application
of the succeeding coat.
b. Brush Application
Paint shall be worked into all crevices and corners where possible
and surfaces not accessible to brushes shall be painted by spray,
doubers, or sheepskins. All runs or rags shall be brushed out. There
shall be a minimum of brush marks left in the paint.
The pressure on the material in the pot and of the air at the guns
shall be adjusted for optimum spraying effectiveness. The pressure
on the material in the pot shall be adjusted when necessary for
changes in elevation of the gun above the pot. The atomizing air
pressure at the gun shall be high enough to atomize the paint properly
but not so high as to cause excessive fogging of paint, excessive
evaporation of solvent or loss by overspray.
196
wet layer of paint is deposited on the surface. The trigger of the gun
should be released at the end of each stroke.
All rums and sags shall be brushed out immediately or the paint
shall be removed and the surface repainted. Spray application of
prime coats shall in all cases be immediately followed by brushing
d. Shop Painting
Erection marks and weight marks shall be copied on area that have
been previously painted with the shop coat.
e. Field Painting
197
Metal which has been shop coated shall be touched up with the
same type of paints as the shop coat. This touch-up shall include
cleaning and painting of field connections, welds, rivets and all
damaged or defective paint and rusted areas. The Contractor may,
at his option, apply an overall coat of primer in place of touch-up spot
painting.
Painted steel shall not be handled until the paint has dried, except
for necessary handling in turning for painting or stacking for drying.
a. Instrumentation
198
include Elcometric, Minitector, General Electric, Verimeter and
Accuderm models.
b. Calibration
c. Measurement Procedures
199
gage reading. Discard any unusually high of flow gage reading that
cannot be repeated consistently. Take the average of the three gage
readings as the spot measurement.
d. Special Notes
200
Much larger, external errors may be caused by variations in
method of use of the gages or by unevenness of the surface of the
substrate or of the coating. Also, any other film present on the steel
(rust or mill scale or even a blast cleaned profile zone) will add to the
apparent thickness of the applied paint film.
The surface of the paint and the probe of the gage must be free
from dust, grease and other foreign matter in order to obtain close
contact of the probe with the paint and also to avoid adhesion of the
magnet. The accuracy of the measurement will be affected if the
coating is tacky or excessively soft.
403.3.24 Clean-up
Upon completion and before final acceptance, the Contractor shall remove
all falsework, falsework piling down to at least 609.6 mm below the finished ground
line, excavated or unused materials, rubbish and temporary buildings. He shall
replace or renew any fences damaged and restored in an acceptable manner all
property, both public and private, which may have been damaged during the
prosecution of the work and shall leave the work site and adjacent highway in a
neat and presentable condition, satisfactory to the Engineer. All excavated material
or falsework placed in the stream channel during construction shall be removed by
the Contractor before final acceptance.
The quantity of structural steel to be paid for shall be the number of kilos
complete in place and accepted. For the purpose of measurement for payment
components fabricated from metals listed in (1) below, such as casting, alloy steels,
steel plates, anchor bolts and nuts, shoes, rockers, rollers, pins and nuts, expansion
dams, roadway drains and souppers, welds metal, bolts embedded in concrete,
cradles and brackets, posts, conduits and ducts, and structural shapes for
expansion joints and pier protection will be considered as structural steel.
201
Unless otherwise provided, the mass of metal paid for shall be computed
and based upon the following mass:
The mass of steel shapes and plates shall be computed on the basis of
their nominal mass and dimensions as shown on the approved shop
drawings, deducting for copes, cuts and open holes, exclusive of rivets
holes. The mass of all plates shall be computed on the basis of nominal
dimensions with no additional for overrun.
The mass of railing shall be included as structural steel unless the Bill of
Quantities contains as pay item for bridge railing under Item 401, Railings.
3. Casting
4. Miscellaneous
The mass of erection bolts, shop and field paint, galvanizing the boxes,
crates and other containers used for shipping, together with sills, struts, and
rods used for supporting members during the transportation, bridge
hardware as defined in Subsection 402.2.2 excluding steel plates and
bearings, connectors used for joining timber members, nails, spikes and
bolts, except anchor bolts will be excluded.
5. Rivets Heads
The mass of all rivet heads, both files and shop, will be assumed as
follows:
202
Diameter of rivet kg per 100 heads
(mm)
12.7 1.80
15.9 3.20
19.0 5.44
22.2 8.16
25.4 11.80
28.6 16.33
31.7 21.8
6. High-Strength Bolts
7. Welds
The mass of shop and field fillet welds shall be assumed as follows:
The mass of other welds will be computed on the basis of the theoretical
volume from dimensions of the welds, with an addition of 50 mass percent
as an allowance for overrun.
8. Other Items
The quantities of other Contract Items which enter into the completed and
accepted structure shall be measured for payment in the manner prescribed
for the Items involved.
Lump sum will be the basis of payment unless noted otherwise in the bidding
documents. No measurements of quantities will be made except as provided in
Subsection 403.5.1 (4).
203
403.5.1 Structural Steel
When a quantity and unit price for “Structural Steel, furnished and
fabricated” are shown in the Bill of Quantities, the quantity, determined
as provided above, will be paid for at the contract unit price per kilogram
which price and payment shall be full compensation for furnishing,
galvanizing, fabricating, radiographing, magnet particle inspection, shop
painting and delivering the structural steel and other metal free of charges
at the place designated in the Special Provisions and for all labor,
equipment, tools and incidentals necessary to complete the work, save
erection and except as provided in Subsection 403.5.2, 403.5.3 and
403.5.4.
3. Erected
When a quantity and unit price for “Structural Steel Erected” are
shown in the Bill of Quantities, the quantity, determined as provided
above, will be paid for at the said contract unit price per kilogram which
price and payment shall be full compensation for unloading all the
structural steel and other metal, payment of any demurrage charges,
transporting to the bridge site, erecting, magnetic particle inspection and
radiographing, complete ready for use including furnishing and applying
the field paint including all labor, equipment, tools and incidentals
necessary to complete the work, save furnishing and fabrication, and
except as provided in Subsections 403.5.2, 403.5.3 and 403.5.4.
4. Lump Sum
When the Bill of Quantities calls for lump sum price for “Structural
Steel, furnished, fabricated and erected”, the Item will be paid for at the
contract lump sum price and payment shall be full compensation for
furnishing, fabricating and erecting material and for all work herein before
prescribed in connection therewith, including all labor, equipment, tools
and incidentals necessary to complete the work, except as provided in
Subsections 403.5.2, 403.5.3 and 403.5.4.
204
The estimate of the mass of structural steel shown on the Plans is
approximate only and no guarantee is made that it is the correct mass to
be furnished. No adjustment in the contract price will be made if the
mass furnished is more or less than estimated mass.
If changes in the work are ordered by the Engineer, which vary the
mass of steel to be furnished, the lump sum payment shall be adjusted
as follows:
For the purpose of Subsection 403.5.1 and unless otherwise shown on the
Plans, castings, forgings, special alloy steels and steel plates, wrought iron, and
structural shapes of expansion joints and pier protection shall be considered as
structural steel except that when quantities and unit price for certain alloy steels,
forgings, castings or other specific categories of metal are called for in the Bill of
Quantities, the mass of such selected material, determined as provided above, shall
be paid for at the respective contract unit price per kilogram for “Structural Steel
(Alloy steel, forgings, castings, and/or other category), furnished and fabricated,
and erected” or “Structural Steel (Subsection 403.4.1), furnished and fabricated” as
named in the Bill of Quantities.
The quantities of all other Contract Items which enter into the completed and
accepted structure shall be paid for at the contract unit prices for the several Pay
Items as prescribed for the Items involved.
When the Bill of Quantities does not contain a pay item for structural steel,
the quantities of metal drains, scuppers, conduits, ducts and structural shapes for
expansion joints and pier protection, measured as provided above will be paid for
as Reinforcing Steel under Item 404.
205
Payment will be made under:
404.1 Description
This Item shall consist of furnishing, bending, fabricating and placing of steel
reinforcement of the type, size, shape and grade required in accordance with this
Specification and in conformity with the requirements shown on the Plans or as
directed by the Engineer.
Reinforcing steel shall meet the requirements of item 710, Reinforcing Steel
and Wire Rope.
Before materials are ordered, all order lists and bending diagrams shall be
furnished by the Contractor, for approval of the Engineer. The approval of order
lists and bending diagrams by the Engineer shall in no way relieve the Contractor
of responsibility for the correctness of such lists and diagrams. Any expense
206
incident to the revisions of materials furnished in accordance with such lists and
diagrams to make them comply with the Plans shall be borne by the Contractor.
Steel reinforcement shall be stored above the surface of the ground upon
platforms, skids, or other supports and shall be protected as far as practicable from
mechanical injury and surface deterioration caused by exposure to conditions
producing rust. When placed in the work, reinforcement shall be free from dirt,
detrimental rust, loose scale, paint, grease, oil, or other foreign materials.
Reinforcement shall be free from injurious defects such as cracks and laminations.
Rust, surface seams, surface irregularities or mill scale will not be cause for
rejection, provided the minimum dimensions, cross sectional area and tensile
properties of a hand wire brushed specimen meets the physical requirements for
the size and grade of steel specified.
404.3.3 Bending
All reinforcing bars requiring bending shall be cold-bent to the shapes shown
on the Plans or required by the Engineer. Bars shall be bent around a circular pin
having the following diameters (D) in relation to the diameter of the bar (d):
Bends and hooks in stirrups or ties may be bent to the diameter of the
principal bar enclosed therein.
Distance from the forms shall be maintained by means of stays, blocks, ties,
hangers, or other approved supports, so that it does not vary from the position
indicated on the Plans by more than 6mm. Blocks for holding reinforcement from
contact with the forms shall be precast mortar blocks of approved shapes and
dimensions. Layers of bars shall be separated by precast mortar blocks or by other
equally suitable devices. The use of pebbles, pieces of broken stone or brick, metal
pipe and wooden blocks shall not be permitted. Unless otherwise shown on the
Plans or required by the Engineer, the minimum distance between bars shall be
40mm. Reinforcement in any member shall be placed and then inspected and
approved by the Engineer before the placing of concrete begins. Concrete placed
in violation of this provision may be rejected and removal may be required. If fabric
207
reinforcement is shipped in rolls, it shall be straightened before being placed.
Bundled bars shall be tied together at not more than 1.8m intervals.
404.3.5 Splicing
All reinforcement shall be furnished in the full lengths indicated on the Plans.
Splicing of bars, except where shown on the Plans, will not be permitted without the
written approval of the Engineer. Splices shall be staggered as far as possible and
with a minimum separation of not less than 40 bar diameters. Not more than one-
third of the bars may be spliced in the same cross-section, except where shown on
the Plans.
In lapped splices, the bars shall be placed in contact and wired together.
Lapped splices will not be permitted at locations where the concrete section is
insufficient to provide minimum clear distance of one and one-third the maximum
size of coarse aggregate between the splice and the nearest adjacent bar. Welding
of reinforcing steel shall be done only if detailed on the Plans or if authorized by the
Engineer in writing. Spiral reinforcement shall be spliced by lapping at least one
and a half turns or by butt welding unless otherwise shown on the Plans.
Sheets of mesh or bar mat reinforcement shall overlap each other sufficiently
to maintain a uniform strength and shall be securely fastened at the ends and
edges. The overlap shall not be less than one mesh in width.
The quantity of reinforcing steel to be paid for will be the final quantity placed
and accepted in the completed structure.
No allowance will be made for tie-wires, separators, wire chairs and other
material used in fastening the reinforcing steel in place. If bars are substituted upon
the Contractor’s request and approved by the Engineer and as a result thereof more
steel is used than specified, only the mass specified shall be measured for payment.
When there is no item for reinforcing steel in the Bill of Quantities, costs will
be considered as incidental to the other items in the Bill of Quantities.
208
404.5 Basis of Payment
405.1 Description
405.1.1 Scope
This Item shall consist of furnishing, bending, placing and finishing concrete
in all structures except pavements in accordance with this Specification and
conforming to the lines, grades, and dimensions shown on the Plans. Concrete
shall consist of a mixture of Portland Cement, fine aggregate, coarse aggregate,
admixture when specified, and water mixed in the proportions specified or approved
by the Engineer.
Five classes of concrete are provided for in this Item, namely: A, B, C, P and
Seal. Each class shall be used in that part of the structure as called for on the
Plans.
Class B – Footings, pedestals, massive pier shafts, pipe bedding, and gravity
walls, unreinforced or with only a small amount of reinforcement.
Class C – Thin reinforced sections, railings, precast R.C. piles and cribbing
and for filler in steel grid floors.
209
405.2 Material Requirements
63 2-1/2” 100
50 2” 100 95 – 100
37.5 1-1/2” 95 – 100 - 100
25 1” - 35 – 70 100 95 – 100
19.0 ¾” 35 – 70 - 100 95 – 100 -
12.5 ½” - 10 – 30 90 – 100 - 25 – 60
9.5 3/8” 10 – 30 - 40 – 70 20 – 55 -
4.75 No.4 0-5 0-5 0 – 15* 0 – 10* 0 – 10*
* The measured cement content shall be within plus (+) or minus (-) 2 mass
percent of the design cement content.
405.2.4 Water
It shall conform to the requirements of Item 710, Reinforcing Steel and Wire
Rope.
405.2.6 Admixtures
210
405.2.8 Expansion Joint Materials
As work progresses, at least one (1) sample consisting of three (3) concrete
cylinder test specimens, 150 x 300mm (6 x 12 inches), shall be taken from each
seventy five (75) cubic meters of each class of concrete or fraction thereof placed
each day.
211
405.4.1 Proportioning and Strength of Structural Concrete
405.4.2 Consistency
Concrete shall have a consistency such that it will be workable in the required
position. It shall be of such a consistency that it will flow around reinforcing steel
but individual particles of the coarse aggregate when isolated shall show a coating
of mortar containing its proportionate amount of sand. The consistency of concrete
shall be gauged by the ability of the equipment to properly place it and not by the
212
difficulty in mixing and transporting. The quantity of mixing water shall be
determined by the Engineer and shall not be varied without his consent. Concrete
as dry as it is practical to place with the equipment specified shall be used.
405.4.3 Batching
1. Portland Cement
2. Water
3. Aggregates
The batching plant shall include separate bins for bulk cement, fine
aggregate and for each size of coarse aggregate, a weighing hopper, and
scales capable of determining accurately the mass of each component of
the batch.
213
5. Batching
6. Admixtures
214
For batch mixing at the site of construction or at a central point, a batch mixer
of an approved type shall be used. Mixer having a rated capacity of less than a
one-bag batch shall not be used. The volume of concrete mixed per batch shall not
exceed the mixer’s nominal capacity as shown on the manufacturer’s standard
rating plate on the mixer except that an overload up to 10 percent above the mixer’s
nominal capacity may be permitted, provided concrete test data for strength,
segregation, and uniform consistency are satisfactory and provided no spillage of
concrete takes place. The batch shall be so charge into the drum that a portion of
the water shall enter in advance of the cement and aggregates. The flow of water
shall be uniform and all water shall be in the drum by the end of the first 15 seconds
of the mixing period. Mixing time shall be measured from the time all materials,
except water, are in the drum. Mixing time shall not be less than 60 seconds for
mixers having a capacity of 1.5m3 or less. For mixers having a capacity greater
than 1.5m3, the mixing time shall not be less than 90 seconds. If timing starts, the
instant the skip reaches its maximum raised position, 4 seconds shall be added to
the specified mixing time. Mixing time ends when the discharge chute opens.
The timing device on stationary mixers shall be equipped with a bell or other
suitable warning device adjusted to give a clearly audible signal each time the lock
is released. In case of failure of the timing device, the Contractor will be permitted
to continue operations while it is being repaired, provided he furnishes an approved
timepiece equipped with minute and second hands. If the timing device is not
placed in good working order within 24 hours, further use of the mixer will be
prohibited until repairs are made.
215
Equipment having components made of aluminum or magnesium
alloys, which would have contact with plastic concrete during mixing,
transporting or pumping of Portland Cement concrete, shall not be used.
When bulk cement is used and volume of the batch is 0.5m3 or more,
the scale and weigh hopper for Portland Cement shall be separate and
distinct from the aggregate hopper or hoppers. The discharge
mechanism of the bulk cement weigh hopper shall be interlocked against
opening before the full amount of cement is in the hopper. The
discharging mechanism shall also be interlocked against opening when
the amount of cement in the hopper is underweight by more than one (1)
mass percent or overweight by more than 3 mass percent of the amount
specified.
When the aggregate contains more water than the quantity necessary
to produce a saturated surface dry condition, representative samples
shall be taken and the moisture content determined for each kind of
aggregate.
216
The batch shall be so charged into the mixer that some water will enter
in advance of cement and aggregate. All water shall be in the drum by
the end of the first quarter of the specified mixing time.
Cement shall be batched and charged into the mixer so that it will not
result in loss of cement due to the effect of wind, or in accumulation of
cement on surface of conveyors or hoppers, or in other conditions which
reduce or vary the required quantity of cement in the concrete mixture.
The entire content of a batch mixer shall be removed from the drum
before materials for a succeeding batch are placed therein. The materials
composing a batch except water shall be deposited simultaneously into
the mixer.
All concrete shall be mixed for a period of not less than 1-1/2 minutes
after all materials, including water, are in the mixer. During the period of
mixing, the mixer shall operate at the speed for which it has been
designed.
The first batch of concrete materials placed in the mixer shall contain
a sufficient excess of cement, sand, and water to coat inside of the drum
without reducing the required mortar content of the mix. When mixing is
to cease for a period of one hour or more, the mixer shall be thoroughly
cleaned.
217
The maximum size of batch in truck mixers shall not exceed the
minimum rated capacity of the mixer as stated by the manufacturer and
stamped in metal on the mixer. Truck mixing, shall, unless other-wise
directed be continued for not less than 100 revolutions after all
ingredients, including water, are in the drum. The mixing speed shall not
be less than 4 rpm, nor more than 6 rpm.
Mixing shall begin within 30 minutes after the cement has been added
either to the water or aggregate, but when cement is charged into a mixer
drum containing water or surface wet aggregate and when the
temperature is above 32oC, this limit shall be reduced to 15 minutes. The
limitation in time between the introduction of the cement to the aggregate
and the beginning of the mixing may be waived when, in the judgement
of the Engineer, the aggregate is sufficiently free from moisture, so that
there will be no harmful effects on the cement.
218
The Contractor shall have sufficient plant capacity and transportation
apparatus to insure continuous delivery at the rate required. The rate of
delivery of concrete during concreting operations shall be such as to
provide for the proper handling, placing and finishing of the concrete. The
rate shall be such that the interval between batches shall not exceed 20
minutes. The methods of delivering and handling the concrete shall be
such as will facilitate placing of the minimum handling.
The quantity of structural concrete to be paid for will be the final quantity
placed and accepted in the completed structure. No deduction will be made for the
volume occupied by pipe less than 100mm (4 inches) in diameter or by reinforcing
steel, anchors, conduits, weep holes or expansion joint materials.
406.1 Description
219
particular prestressing system to be used, including but not limited to ducts,
anchorage assemblies and grouts used for pressure grouting ducts.
The materials for concrete and grout shall conform to Item 405, Structural
Concrete. The concrete shall be Class P as shown in Table 405.2, unless otherwise
shown on the Plans or specified in the Special Provisions. The proportions of the
grout will be as set out in Subsection 406.3.11, Bonding Steel.
It shall conform to the requirements of Item 710, Reinforcing Steel and Wire
Rope.
All prestressing steel shall be protected against physical damage and rust or
other results of corrosion at all times from manufacture to grouting. Prestressing
steel that has sustained physical damage at any time shall be rejected.
This shipping package or form shall be clearly marked with a statement that
the package contains high-strength prestressing steel and the care to be used in
handling, and the type, kind and amount of corrosion inhibitor used, including the
date when placed, safety orders and instructions for use.
406.2.6 Water
220
406.2.7 Enclosures
All wire, strand, anchorage assemblies or bars to be shipped to the site shall
be assigned a lot number and tagged for identification purposes.
All of the materials specified for testing shall be furnished free of cost and
shall be delivered in time for tests to be made well in advance of anticipated time of
use.
The Contractor shall furnish for testing the following samples selected from
each lot, if ordered by the Engineer. The selection of samples will be made at the
manufacturer’s plant by the Engineer or his representative.
When prestressing system has been previously tested and approved for
similar projects by an agency acceptable to the Engineer, complete tendon samples
need not be furnished, provided there is no change whatsoever in the materials,
design or details previously approved.
221
406.3 Construction Requirements
406.3.1 General
222
Enclosures for prestressed reinforcement shall be accurately placed at
locations shown on the Plans or approved by the Engineer.
Steel units shall be accurately placed at the position shown on the Plans and
firmly held during the placing and setting of the concrete.
After installation in the forms, the end of ducts shall at all times be covered
as necessary to prevent the entry of water of debris.
All ducts for continuous structures shall be vented over each intermediate
support, and at additional locations as shown on the Plans. Vents shall be 12.7 mm
(1/2 inch) minimum diameter standard pipe. Connections to ducts shall be made
with metallic structural fasteners. The vents shall be mortar tight, taped as
necessary, and shall provide means for injection of grout through the vents and for
sealing the vents. Ends of vents shall be removed 25.4 mm (1 inch) below the
roadway surface after grouting has been completed.
Distances from the forms shall be maintained by stays, blocks, ties, hangers
or other approved supports. Blocks for holding units from contact with the forms
shall be precast mortar blocks of approved shape and dimensions. Layers of units
shall be separated by mortar blocks or other equally suitable devices. Wooden
blocks shall not be left in the concrete.
223
Wires, wire groups, parallel-lay cables and any other prestressing elements
shall be straightened to insure proper positioning in the enclosures.
406.3.7 Pretensioning
Concrete shall not be deposited in the forms until the Engineer has inspected
the placing of the reinforcement, enclosures, anchorages and prestressing steel
and given his approval thereof. The concrete shall be vibrated with care and in
such a manner as to avoid displacement of reinforcement, conduits, or wires.
406.3.9 Curing
During the waiting period, the temperature within the curing chamber shall
not be less than 10.0oC (50oF) and live steam or radiant heat may be used to
maintain the curing chamber at the proper minimum temperature. The steam shall
be at 100 percent relative humidity to prevent loss of moisture and to provide
moisture for proper hydration of the cement. Application of the steam shall not be
directly on the concrete. During application of the steam, or of radiant heat, the
ambient air temperature shall increase at a rate not to exceed 4.41 oC per hour until
the curing temperature is reached. The maximum curing temperature within the
enclosure shall not exceed 71.1oC. The maximum temperature shall be held until
the concrete has reached the desired strength. Detensioning shall be
224
accomplished immediately after the steam curing or the heat curing has been
discontinued and additional curing is not required after detensioning.
Radiant heat may be applied by means of pipes circulating steam, hot oil or
hot water, or by electric heating elements. Radiant heat curing shall be done under
a suitable enclosure to contain the heat and moisture loss shall be minimized by
covering all exposed concrete surfaces with plastic sheeting or by applying an
approved liquid membrane curing compound to all exposed concrete surfaces. Top
surface of concrete members to be used in composite construction shall be clear of
residue of the membrane curing compound so as not to reduce bond below design
limits.
If the Contractor proposes to cure by any other special method, the method
and its details shall be subject to the approval of the Engineer.
406.3.10 Post-tensioning
After all concrete has attained the required strength, the prestressing
reinforcement shall be stressed by means of jacks to the desired tension and the
stress transferred to the end anchorage.
Cast-in-place concrete shall not be post-tensioned until at least ten (10) days
after the last concrete has been placed in the member to be the post-tensioned and
until the compressive strength of said placed concrete has reached the strength
specified for the concrete at the time of stressing.
All side forms for girders shall be removed before post-tensioning. The
falsework under the bottom slab supporting the superstructure shall not be released
until a minimum of 48 hours have elapsed after grouting of the post-tension tendons
nor until all other conditions of the Specifications have been met. The supporting
falsework shall be constructed in such a manner that the superrestructure will be
free to lift off the falsework and shorten during post-tensioning. Formwork left inside
box girders to support the roadway slab shall be detailed in such a manner so as to
offer minimum resistance to girder shortening due to shrinkage and post-tensioning.
The tensioning process shall be so conducted that the tension being applied
and the elongation of the prestressing elements may be measured at all times. The
225
friction loss in the element, i.e., the difference between the tension of the jack and
the minimum tension, shall be determined in accordance with Article 1.6.7 of
AASHTO Standard Specifications for Highway Bridges.
Suitable shims or other approved devices shall be used to insure that the
specified anchor set loss is attained.
A record shall be kept of gage pressure and elongation at all times and
submitted to the Engineer for his approval.
Prestressing steel shall be bonded to the concrete by filling the void space
between the duct and the tendon with grout
.
Grout shall consist of Portland Cement, water and an expansive admixture
approved by the Engineer.
Water shall first be added to the mixer followed by cement and admixture.
The grout shall be mixed in mechanical mixing equipment of a type that will
produce uniform and thoroughly mixed grout. The water content shall be not more
than 19 litres (5 gallons) per sack of cement. Retempering of grout will not be
permitted. Grout shall be continuously agitated until it is pumped.
All ducts shall be clean and free of deleterious materials that would impair
bonding of the grout or interfere with grouting procedures. All grout shall pass
through a screen with a 2 mm (0.0787 inch) maximum clear openings prior to being
introduced into the grout pump.
Grout injection pipes shall be fitted with positive mechanical shutoff valves.
Vents and ejection pipes shall be fitted with valves, caps or other devices capable
226
of withstanding the pumping pressures. Valves and caps shall not be removed or
opened until the grout has set.
Immediately after completion of the concrete pour, the metal conduit shall be
blown out with compressed oil free air to the extent necessary to break up and
remove any mortar in the conduit before it hardens. Approximately 24 hours after
the concrete pour, the metal conduits shall be flushed out with water and then blown
out with compressed oil free air.
Prior to placing forms for roadway slabs of box girder structures, the
Contractor shall demonstrate to the satisfaction of the Engineer that all ducts are
unobstructed and if the prestressing reinforcement has been placed, that the steel
is free and unbonded in the duct.
After the tendons have been stressed to the required tension, each conduit
encasing the prestressing steel shall be blown out with compressed oil free air. The
conduit shall then be completely filled from the low end with grout under pressure.
Grout shall be pumped through the duct and continuously wasted at the outlet until
no visible slugs of water or air are ejected and the efflux time of ejected grout is not
less than 11 seconds. All vents and openings shall then be closed and the grouting
pressure at the injection end shall be raised to a minimum of 0.6894 MPa (100 psi)
and held for a minimum of 10 seconds.
406.3.13 Handling
227
Extreme care shall be exercised in handling and moving precast prestressed
concrete mortar members. Precast girders and slabs shall be transported in an
upright position and the points of support and directions of the reactions with respect
to the member shall be approximately the same during transportation and storage
as when the members are in their final position. If the Contractor deems it expedient
to transport or store precast units in other than this position, it shall be done at his
own risk after notifying the Engineer of his intention to do so.
The manufacturing tolerances for pre-cast members shall not exceed those
given for length, cross-section and straightness on the Plans, as specified in the
Contract or as approved by the Engineer. In addition, where beams are laid side
by side in a deck:
1. The difference on soffit level between adjacent units before the in-situ
concrete is placed shall not exceed 5 mm for units up to 10 mm for longer
units.
2. The width of the deck soffit shall be within ±25 mm.
3. In adjacent span, the continuity of the outside beams shall be maintained.
4. The width of gap between individual beams shall not exceed twice the
nominal gap.
5. The alignment of transverse holes shall permit the reinforcement or
prestressing cables to be placed without distortion.
The quantity to be measured for payment will be the actual number of precast
prestressed concrete structural members, except piling, of the several types and
sizes, installed in place, completed and accepted. Each member will include the
concrete, reinforcement and prestressing steel, anchorages, plates, nuts,
elastomeric bearing pads, and other such material contained within or attached to
the unit.
228
The quantities of other Contract items which enter into the completed and
accepted structure will be measured for payment in the manner prescribed for the
several items involved.
407.1 Description
This Item shall consist of the general description of the materials, equipment,
workmanship and construction requirements of concrete structures and the
concrete portions of composite structures conforming to the alignment, grades,
design, dimensions and details shown on the Plans and in accordance with the
Specifications for piles, reinforcing steel, structural steel, structural concrete and
other items which constitute the completed structure. The class of concrete to be
used in the structure or part of the structure shall be as specified in Item 405,
Structural Concrete.
2. Reinforcing Steel
229
Reinforcing steel shall conform to the requirements in Item 404, Reinforcing
Steel.
3. Structural Steel
5. Paints
b. AASHTO M 116 Primer for the use with Asphalt in dampproofing and
waterproofing.
c. AASHTO M 117 Woven cotton fabrics saturated with bituminous
substances for use in waterproofing.
d. AASHTO M 118 Coal-Tar pitch for roofing, dampproofing and water-
proofing.
e. AASHTO M 121 Creosote for priming coat with coal-tar pitch damp-
proofing and waterproofing.
f. AASHTO M 159 Woven burlap fabric saturated with bituminous
substances for use in waterproofing.
g. AASHTO M 166 Numbered cotton duck and array duck.
h. AASHTO M 239 Asphalt for use in waterproofing membrane construction.
8. Joint Filler
230
a. AASHTO M 33 Preformed expansion joint filler for concrete.
b. AASHTO M 153 Preformed sponge rubber and cork expansion joint fillers
for concrete paving and structural construction.
d. AASHTO M 213 Preformed expansion joint filler for concrete paving and
structural construction-non-extruding and resilient bituminous types.
Concrete shall not be placed until forms and reinforcing steel have been
checked and approved by the Engineer.
In preparation for the placing of concrete all sawdust, chips and other
construction debris and extraneous matter shall be removed from inside the
formwork, struts, stays and braces, serving temporarily to hold the forms in correct
shape and alignment, pending the placing of concrete at their locations, shall be
removed when the concrete placing has reached an elevation rendering their
service unnecessary. These temporary members shall be entirely removed from
the forms and not buried in the concrete.
No concrete shall be used which does not reach its final position in the forms
within the time stipulated under “Time of Hauling and Placing Mixed Concrete”.
231
Open troughs and chutes shall be of metal lined; where steep slopes are
required, the chutes shall be equipped with baffles or be in short lengths that
reverse the direction of movement to avoid segregation.
All chutes, troughs and pipes shall be kept clean and free from coatings of
hardened concrete by thoroughly flushing with water after each run. Water used
for flushing shall be discharged clear of the structure.
When placing operations would involve dropping the concrete more than 1.5
m, concrete shall be conveyed through sheet metal or approved pipes. As far as
practicable, the pipes shall be kept full of concrete during placing and their lower
end shall be kept buried in the newly placed concrete. After initial set of the
concrete, the forms shall not be jarred and no strain shall be placed on the ends of
projecting reinforcement bars.
The concrete shall be placed as nearly as possible to its final position and
the use of vibrators for moving of the mass of fresh concrete shall not be permitted.
232
Concrete shall not be placed in water except with approval of the Engineer
and under his immediate supervision. In this case the method of placing shall be
hereinafter specified.
A tremie shall consist of a tube having a diameter of not less than 250 mm
constructed in sections having flanged couplings fitted with gaskets with a hopper
at the top. The tremie shall be supported so as to permit free movement of the
discharge and over the entire top surface of the work and so as to permit rapid
lowering when necessary to retard or stop the flow of concrete. The discharge end
shall be closed at the start of work so as to prevent water entering the tube and
shall be completely submerged in concrete at all times; the tremie tube shall be kept
full to the bottom of the hopper. When a batch is dumped into the hopper, the flow
of concrete shall be induced by lightly raising the discharge end, but always keeping
it in the placed concrete. The flow shall be continuous until the work is completed.
When the concrete is placed with a bottom-dump bucket, the top of the
bucket shall be open. The bottom doors shall open freely downward and outward
when tripped. The buckets shall be completely filled and slowly lowered to avoid
backwash. It shall not be dumped until it rests on the surface upon which the
concrete is to be deposited and when discharged shall be withdrawn slowly until
well above the concrete.
233
withdrawn from the concrete slowly. The vibration shall be of sufficient duration and
intensity to compact the concrete thoroughly but shall not be continued so as to
cause segregation and at any one point to the extent that localized areas of grout
are formed. Application of vibrators shall be at points uniformly spaced, and not
farther apart than twice the radius over which the vibration is visibly effective.
Vibration shall not be applied directly or thru the reinforcement to sections or layers
of concrete that have hardened to the degree that the concrete ceases to be plastic
under vibration. It shall not be used to make concrete flow in the forms over
distances so great as to cause segregation, and vibrators shall not be used to
transport concrete in the forms of troughs or chutes.
In general, the base slab of box culverts shall be placed and allowed to set
before the remainder of the culvert is constructed. In the construction of box
culverts the side walls and top slab may be constructed as a monolith.
234
If the concrete in the walls and top slab is placed in two separate operations,
special care shall be exercised in order to secure bonding in the construction joint
and appropriate keys shall be left in the sidewalls for anchoring the top slab. Each
wingwall shall be constructed, if possible, as a monolith. Construction joints where
unavoidable, shall be horizontal and so located that no joints will be visible in the
exposed face of the wingwall above the ground line.
Vertical construction joints shall be at right angles to the axis of the culverts.
Concrete in slab spans shall be placed in one continuous operation for each
span unless otherwise provided.
In box girders, the concrete in the bottom slab be poured first, as a separate
operation.
The concrete in the webs and the top slab shall be placed in one continuous
operation unless otherwise specified. If it is permitted to place the concrete in more
than one operation, the requirements for T-beam shall apply.
235
Construction joints shall be made only where shown on the Plans or called
for in the pouring schedule, unless otherwise approved by the Engineer. Shear
keys or reinforcement shall be used, unless otherwise specified, to transmit shear
or to bond the two sections together.
The placing of concrete shall be carried continuously from joint to joint. The
face edges of all joints which are exposed to view shall be carefully finished true to
line and elevation.
All concrete shall be given Class 1, Ordinary Finish and additionally any
further finish as specified.
Excluded, however, are the tops and bottoms of floor slabs and sidewalks,
bottoms of beams and girders, sides of interior beams and girders, backwalls above
bridge seats or the underside of copings. The surface finish on piers and abutments
shall include all exposed surfaces below the bridge seats to 20 cm below low water
elevation or 50 cm below finished ground level when such ground level is above the
water surface. Wingwalls shall be finished from the top to 50 cm below the finished
slope lines on the outside face and shall be finished on top and for a depth of 20
cm below the top on the back sides.
236
Unless otherwise specified, the surface of the traveled way shall be Class 3,
Floated Finish.
Immediately following the removal of forms, all fins and irregular protection
shall be removed from all surface except from those which are not to be exposed
or are not to be waterproofed. On all surfaces the cavities produced by form ties
and all other holes, honeycomb spots, broken corners or edges and other defects
shall be thoroughly cleaned, and after having been kept saturated with water for a
period of not less than three hours shall be carefully pointed and made true with a
mortar of cement and fine aggregate mixed in the proportions used in the grade of
the concrete being finished. Mortar used in pointing shall not be more than one
hour old. The mortar patches shall be cured as specified under Subsection 407.3.8.
All construction and expansion joints in the completed work shall be left carefully
tooled and free of all mortar and concrete. The joint filler shall be left exposed for
its full length with a clean and true edges.
The resulting surface shall be true and uniform. All repaired surfaces, the
appearance of which is not satisfactory to the Engineer, shall be “rubbed” as
specified below.
After all concrete above the surface being created has been cast, the final
finish shall be obtained by rubbing with a fine carborundum stone and water. This
rubbing shall be continued until the entire surface is of smooth texture and uniform
color.
After the final rubbing is completed and the surface has dried, it should be
rubbed with burlap to remove loose powder and shall be left free from all unsound
patches, paste, powder and objectionable marks.
237
shall be made for camber if required. The strike board may be operated
longitudinally or transversely and shall be moved forward with a combined
longitudinal and transverse motion, the manipulation being such that neither is
raised from the side forms during the process. A slight excess of concrete shall be
kept in front of the cutting edge at all times.
After striking off and consolidating as specified above, the surface shall be
made uniform by longitudinal or transverse floating or both. Longitudinal floating
will be required except in places where this method is not feasible.
The longitudinal float, operated from foot bridges, shall be worked with a
sawing motion while held in a floating position parallel to the road centerline and
passing gradually from one side of the pavement to the other. The float shall then
be moved forward one-half of each length and the above operation repeated.
Machine floating which produces an equivalent result may be substituted for the
above manual method.
After the longitudinal floating has been completed and the excess water
removed, but while the concrete is still plastic, the slab surface shall be tested for
trueness with a straight-edge. For the purpose, the Contractor shall furnish and use
an accurate 3 m straight-edge swing handless 1 m longer than one half the width
of the slab.
When the concrete has hardened sufficiently, the surface shall be given a
broom finish. The broom shall be an approved type. The strokes shall be square
across the slabs from edge to edge, with adjacent strokes slightly overlapped, and
shall be made by drawing the broom without tearing the concrete, but so as to
produce regular corrugations not over 3 mm in depth. The surface as thus finished
shall be free from porous spots, irregularities, depressions and small pockets or
rough spots such as may be caused by accidental disturbing, during the final
brooming of particles of coarse aggregate embedded near the surface.
238
After the concrete has been deposited in place, it shall be compacted and
the surface shall be struck off by means of strike board and floated with a wooden
or cork float. An edging tool shall be used on all edges and at all expansion joints.
The surface shall not vary more than 3 mm under a 3 m straight-edge. The surface
shall have a granular or matted texture which will not slick when wet.
1. Water Method
2. Curing Compound
239
the damaged portion shall be repaired immediately with additional
compound.
240
Should any portion of the sheets be broken or damaged within 72
hours after being placed, the broken or damaged portions shall be
immediately repaired with new sheets properly cemented into place.
4. Forms-in-Place Method
The top surface of highway bridge decks shall be cured by either the
curing compound method or the water method. The curing compound
shall be applied progressively during the deck finishing operations. The
water cure shall be applied not later than 4 hours after completion of the
deck finishing.
Pre-cast concrete members shall be cured for not less than 7 days by
the water method or by steam curing. Steam curing for pre-cast members
shall conform to the following provisions:
241
b. To prevent moisture loss on exposed surfaces during the pre-
steaming period, members shall be covered immediately after casting
or the exposed surface shall be kept wet by fog spray or wet blankets.
c. Enclosures for steam curing shall allow free circulation of steam about
the member and shall be constructed to contain the live steam with a
minimum moisture loss. The use of tarpaulins or similar flexible
covers will be permitted, provided they are kept in good condition and
secured in such a manner to prevent the loss of steam and moisture.
Detailed working drawings and supporting calculations of the false work shall
be furnished by the Contractor to the Engineer. No falsework construction shall
start until the Engineer has reviewed and approved the design. The Contractor
shall provide sufficient time for the Engineer to complete this review. Such time
shall be proportionate to the complexity of the falsework design and in no case be
less than two weeks.
242
The Contractor may review the falsework drawings at any time provided
sufficient time is allowed for the Engineer’s review before construction is started on
the revised portion.
Assumptions used in design of the falsework shall include but not be limited
to the following:
The falsework design at the locations where said openings are required shall
include but not be limited to the following minimum provisions:
243
The falsework drawings shall show pedestrian openings which are required
through the falsework.
The Contractor shall provide tell-tales attached to the soffit forms easily
readable and in enough systematically-placed locations to determine the total
settlement of the entire portion of the structure where concrete is being placed.
244
Unless otherwise shown on the drawings, or permitted by the Engineer,
falsework supporting any span of a supported bridge shall not be released before
14 days after the last concrete, excluding concrete above the bridge deck, has been
placed. Falsework supporting any span of a continuous or rigid frame bridge shall
not be released before 14 days after the last concrete excluding concrete above the
bridge deck, has been placed in that span and in the adjacent portions of each
adjoining span for a length equal to at least half the length of the span where
falsework is to be released.
Falsework supporting deck overhangs and deck slabs between girders shall
not be released until 7 days after the deck concrete has been placed.
All debris and refuse resulting from work shall be removed and the site left
in a neat and presentable condition.
The Contractor shall prepare drawings and materials data for the
formwork and shutters to be submitted to the Engineer for approval
unless otherwise directed.
The requirements for design of formwork are the same as described under
Section 407.3.9.
245
coating which will permit the ready release of the forms and will not discolor the
concrete.
Concrete shall not be deposited in the forms until all work in connection with
constructing the forms has been completed, all materials required for the unit to be
poured, and the Engineer has inspected and approved said forms and materials.
Such work shall include the removal of all dirt, chips, sawdust and other foreign
material from the forms.
Forms for all concrete surfaces which will not be completely enclosed or
hidden below the permanent ground surface shall conform to the requirements
herein for forms for exposed surfaces. Interior surfaces of underground drainage
structures shall be completely enclosed surfaces.
Formwork for concrete place under water shall be watertight. When lumber
is used, this shall be planed, tongued and grooved.
Forms for exposed surfaces shall be constructed with triangular fillets at least
20 mm wide attached so as to prevent mortar runs and to produce smooth straight
chamfers at all sharp edges of the concrete.
246
Anchor devices may be cast into the concrete for later use in supporting
forms or for lifting precast members. The use of driven types of anchorage for
fastening forms of form supports to concrete will not be permitted.
Forms and falsework shall not be removed without the consent of the
Engineer. The Engineer’s consent shall not relieve the Contractor of responsibility
for the safety of the work. Blocks and bracing shall be removed at the time the
forms are removed and in no case shall any portion of the wood forms be left in the
concrete.
When concrete strength tests are used for removal of forms and supports,
such removal should not begin until the concrete has attained the percentage of the
specified design strength shown in the table below.
Forms and falsework shall not be released from under concrete without first
determining if the concrete has gained adequate strength without regard to the time
element. In the absence of strength determination, the forms and falsework are to
remain in place until removal is permitted by the Engineer.
The forms for footings constructed within cofferdams or cribs may be left in
place when, in the opinion of the Engineer, their removal would endanger the safety
of the cofferdam or crib, and when the forms so left intact will not be exposed to
247
view in the finished structure. All other forms shall be removed whether above or
below the ground line or water level.
All forms shall be removed from the cells of concrete box girders in which
utilities are present and all formwork except that necessary to support the deck slab
shall be removed from the remaining cells of the box girder.
Falsework and centering for spandrel-filled arches not be struck until filling
at the back of abutments has been placed up to the spring line. Falsework
supporting the deck of rigid frame structure shall not be removed until fills have
been placed back to the vertical legs.
248
407 (1) Lean Concrete Cubic Meter
408.1 Description
This Item shall consist of the construction of steel structure conforming to the
lines, grades, dimensions and designs shown on the Plans and in accordance with
the Specifications for piling, concrete metal reinforcement, structural steel and other
items which constitute the completed structure.
408.2 Materials
All materials shall conform to the detailed requirements specified for the
component parts of the completed structure. Where special materials are required,
they shall be shown on the Plans or in the Special Provisions.
During the progress of the work the Contractor shall have a competent
foreman or superintendent, experienced in steel erection, in personal charge of the
work.
Before starting work, the Contractor shall inform the Engineer as to the
method of erection he proposes to follow and the amount and character of
equipment he proposes to use, which shall be subject to the approval of the
Engineer. The approval of the Engineer shall not be considered as relieving the
Contractor of the responsibility for the safety of his method or equipment or from
carrying out the work in full accordance with the Plans and Specifications. Erection
diagrams shall be approved by the Director, Bureau of Design.
Steel and timber shall be placed on skids above the ground and shall be kept
clean. The underlying ground shall be kept free from vegetation and properly
drained. Girders and beams shall be placed upright and shored. Long members,
such as columns and chords, shall be supported on skids placed close enough
together to prevent injury by deflection. The Contractor shall be responsible for the
loss of any material, which has been paid for by the Bureau, while it is in his care,
or for any damage, resulting from his work. The loading, transporting, unloading
and piling of structural material shall be so conducted that the metal will be kept
free from injury from rough handling.
249
408.3.3 Erection
The Contractor shall furnish and place all falsework, erect all metal work,
remove the temporary construction, and do all work required to complete the
structure as covered by the Contract, including the removal of the old structure or
structures if so stipulated, all in accordance with the Plans and these Specifications.
If the substructure and superstructure are built under separate contracts, the
Department will provide the substructure, constructed to correct lines and
elevations and properly finished, and will establish the lines and elevation required
for setting the steel.
If the fabrication and erection of the superstructure are done under separate
contract, the Department will furnish detail plans for the bridge or bridges to be
erected, including shop details, camber diagrams, erection diagrams, list of field
rivets and bolts, and copy of shipping statements showing a list of parts and their
weights.
The Contractor shall provide all tools, machinery, and appliances including
drift pins and fitting up bolts, necessary for the expeditious handling of the work.
The parts shall be accurately assembled as shown on the Plans and any
matchmarks shall be followed. The material shall be carefully handled that no parts
will be bent, broken or otherwise damaged. No hammering shall be done that will
in any way injure or damage a member. Bearing surface and surfaces to be in
permanent contact shall be cleaned before the members are assembled. Unless
erected by the cantilever method, truss spans shall be erected on blocking so
placed as to give the trusses proper camber. The blocking shall be left in place,
until the tension chord splices are fully riveted and all other truss connection pinned
and bolted. Rivets in splices of butts joints of compression members and rivets in
railings shall not be driven until the span is swung. Splices and filled connections
shall have one-half of the holes filled with bolts and cylindrical erection pin (half
bolts and half pins) before riveting. Splices and connections carrying traffic during
erection shall have three-fourths of the holes so filled. Fitting up bolts shall be of
the same nominal diameter as the rivets and cylindrical erection pins shall be 0.75
mm (1/32 inch) larger.
408.3.4 Welding
250
Society. Field welding shall conform to the requirement of Item 409, Welded
Structural Steel.
408.3.6 Alignment
Before beginning the field riveting, the structural steel shall be adjusted to
correct grade and alignment and elevation of panel points (end of floor beams)
properly regulated. For truss spans a slight excess camber will be permitted while
the bottom chords are being riveted.
Pneumatic hammers shall be used for field riveting. Cup-faced dollies, fitting
the head closely, shall be used to insure good bearing. Connections shall be
secured and accurately fitted up before the rivets are driven. Drifting shall be only
such as to draw the parts into position and not sufficient to enlarge the holes or
distort the metal. Unfair holes shall be reamed or drilled. Rivets shall be heated
uniformly to light cherry-red color and shall be driven while hot. They shall not be
overheated or burned. Rivet heads shall be full and symmetrical, concentric with
the shank, and shall have full bearing all around. They shall not be smaller than
the heads of the shop rivets. Rivets shall be tight and shall grip the connected parts
securely together. Caulking or recupping will not be permitted. In removing rivets,
the surrounding metal shall not be injured, and if necessary they shall be drilled out.
In bolted connections, the nut shall be drawn up tight and set by center
punching the threads of the bolt at the face of the nut.
Pilot and driving nuts shall be used in driving pins. Pins shall be so driven
that the members will take full bearing on them. Pin nuts shall be screwed up tight
and threads burred at the face of the nut with a center punch.
251
transportation which prevents the proper assembling and fitting up of parts by the
moderate use of drift pins or a moderate amount of reaming and slight chipping and
cutting shall be reported immediately to the Engineer, and his approval of the
method of correction obtained. If the Contract provides for completed fabrication
and erection, the Contractor shall be responsible for all misfits, errors and injuries
and shall make the necessary correction and replacements. If the Contract is for
erection only, the inspector, with the cooperation of the Contractor shall keep a
correct record of labor and materials and be used in correction of misfits, errors and
injuries, not due to actions of the Contractor, and the Contractor shall render within
30 days of itemized bill for the approval of the Engineer.
Shoes and bearing plates shall not be placed on bridge seat bearing areas
that are improperly finished or that are deformed or irregular. They shall be set
level in exact position and elevation and shall have full even bearing. Unless
otherwise specified, the shoes and bearing plates shall be set by the following
methods:
a. The bridge seat bearing area shall be heavily coated with lead paint and
then covered with three layers of 340.2 to 369.8 g (12 to 14 ounces) duck,
each layer being coated thoroughly on its top surface with red-lead paint.
The shoes and bearing plates shall be placed in position while the paint
is plastic. As an alternate to canvas and red lead 3 mm (1/8 inch) sheet
lead may be used if called for on the Plans or is approved by the
Engineer.
b. The shoes and bearing plates shall be properly supported and fixed with
grout. No lead shall be placed upon them until the grout has set for at
least 96 hours, adequate provision being made to keep the grout well
moistened during this period. The grout shall consist of one part Portland
Cement to one part fine-grained sand.
The location of the anchor bolts in relation to the slotted holes in the
expansion shoes correspond to the temperature at the time of erection. The nuts
on the anchor bolts at the expansion end of spans shall be adjusted to permit the
free movement of span. Anchor bolt nuts shall be set by center punching the
threads of the bolts at the face of the nut.
408.3.13 Painting
Unless otherwise specified, metal work shall be given two shop coats of red
lead paint and two field coats of paint as specified under Item 411, Paint.
252
On steel spans, the concrete floor shall not be placed until the span has been
swung or released from the falsework.
Timber floors of the species and grade indicated on the plans shall be built
as specified under Timber Structures, Item 402.
All materials and work of erection shall be subject to the inspection of the
Engineer, who shall be given all facilities required.
Materials and workmanship not previously inspected will not inspected after
its delivery to the site of the work. Any materials inspected and accepted prior to
delivery on the work shall be subject to rejection if found defective after delivery.
The quantity of structural steel and other Contract Pay Items which constitute
the completed and accepted structure shall be measured for payment in the manner
prescribed in the several items involved.
253
ITEM 409 – WELDED STRUCTURAL STEEL
409.1 Description
This work shall consist of the joining of structural steel members with welds
of the type, dimensions, and design shown on the Plans and in accordance with the
Specifications.
Welding of Structural Steel shall be done only when shown on the Plans or
authorized in writing by the Engineer.
409.3.1 Equipment
409.3.1.1 General
All items of equipment for welding and gas cutting shall be so designed and
manufactured and in such condition as to enable qualified welders to follow the
procedures and attain the results prescribed in this Specification.
254
quickly to changes in power requirements due to variations in arc length and shall
deliver full current promptly on striking an arc.
Electrode holders shall grip the electrode firmly and with good electrical
contact.
Torches and tips shall be of proper size and type of the work at hand.
Suitable regulators shall afford the welder complete control over the pressure and
rate of flow of each gas.
The Contractor shall enforce the use of approved accessories necessary for
the protection and convenience of the welders and for the proper and efficient
execution of the work.
Suitable protection against the light of the arc shall be maintained by the
Contractor when arc-welding operation might be viewed within harmful range by
persons other than the actual welders and inspectors.
409.3.2 Welding
409.3.2.1 General
Surfaces to be welded shall be smooth, uniform and free from fins, tears,
and other defects which would adversely affect the quality of the weld. Edges of
material shall be trimmed by machining, chipping, grinding, or machine gas-cutting
to produce a satisfactory welding edge wherever such edge is thicker than: 13 mm
for sheared edge of material; 16 mm for toes of angles or rolled shapes (other than
wide flange sections); 25 mm for universal mill plate or edges of flange sections.
255
The width of root face used, shall be not more than 1.5 mm for parts less
than 10 mm in thickness nor more than 3 mm for parts 10 mm or more in thickness.
Butt welds shall be proportioned so that their surface contours will lie in
gradual transition curves. For butt welded joints between base metal parts of
unequal thickness, a transition shall be provided on a slope or level not greater than
1 in 2.5 to join the offset surfaces. This transition may be provided by sloping the
surface of the weld metal or by bevelling the thicker part or by combination of these
two methods.
Surfaces to be welded shall be free from loose scale, slag, rust, grease or
other material that will prevent proper welding. Mill scale that withstands vigorous
wire brushing or a light film of drying oil or rust inhibitive coating may remain.
Surfaces within 50 mm of any weld location shall be free of any paint or other
material that would prevent proper welding or produce objectionable fumes while
welding.
409.3.2.2 Welders
All welding shall be done by approved competent and experienced and fully
qualified welders.
Structural steel which is to be welded shall preferably not be painted until all
welding is completed.
409.3.2.4 Assembly
The parts to be joined by fillet welds shall be brought into a close contact as
practicable, and no event shall be separated more than 5 mm. If the separation is
1.5 mm or greater, the leg of the fillet weld shall be increased by the amount of
separation. The separation between faying surfaces of lap joints and of butt joints
256
landing on a backing structure shall not exceed 1.5 mm. The fit of joints which are
not sealed by welds throughout their length shall be sufficiently close to exclude
water after painting. Where irregularities in rolled shape or plates, after
straightening, do not permit contact within the above limits, the procedure
necessary to bring the material within these limits shall be subject to the approval
of the Engineer.
Cutting parts to be joined by butt welds shall be carefully aligned. Where the
parts are effectively restrained against bending due to eccentricity or alignment, a
maximum offset of 10 percent of the thickness or the thinner part joined, but in no
case more than 3 mm, may be permitted as a departure from the theoretical
alignment. In connecting alignment in such cases, the parts shall not be drawn into
a greater slope than two degrees (1 in 30). Measurement of offset shall be between
centerline of parts unless otherwise shown on the Plans.
When parts abutting edge to edge differ in thickness, the joint shall be of
such form that the slope of either surface through the transition zone does not
exceed 1 in 2.5, the thicker part being bevelled, if necessary.
Plug and slot welds may be used to transmit shear in a lap joint or to prevent
the buckling or separation of lapped parts.
The diameter of the hole for a plug weld shall not be less than the thickness
of the part containing it plus 8 mm nor shall it be greater than 2.25 times the
thickness of the weld.
The minimum center spacing of plug welds shall be four times the diameter
of the hole.
The length of the slot for a slot weld not exceed ten times the thickness of
the weld. The width of the slot shall not be less than the thickness of the part
containing it plus 8 mm nor shall it be greater than 2.25 times the thickness of the
weld.
The ends of the slot shall be semicircular or shall have the corners rounded
to a radius not less than the thickness of the part containing it, except those ends
which extend to the edge of the part.
257
The thickness of plug or slot welds in material 16 mm or less in thickness
shall be equal to the thickness of the material. In material over 16 mm in thickness,
it shall be at least one-half the thickness of the material but not less than 16 mm.
Tack welds, located where the final welds will later be made, shall be subject
to the same quality requirements as the final weld. Tack welds shall be as small as
practicable and where encountered in the final welding, shall be cleaned and fused
thoroughly with the final weld. Defective, cracked or broken tack welds shall be
removed before final welding.
A weld designed to sustain tensile stress shall be made in such a way that
their welding is being performed at any point, all parts that would offer restraint
against shrinkage can shrink, deform or move enough to preclude serious
shrinkage stresses.
258
members of such heavy section, the temperature of contiguous areas about a
welding operation shall be equal, and not less than 55 oC. If necessary, the lighter
parts shall be heated while the weld is cooling, to keep the temperature of
contiguous parts substantially equal.
The ends of all butt welds in flanges of beams and girders shall be made with
extension bars regardless of the thickness of such flanges.
Welding shall not be done when surfaces are wet from condensation or rain
which is falling on the surfaces to be welded; nor during periods of high winds unless
the welding operator and the work are properly protected.
The welding current shall conform with respect to voltage and current (and
polarity, of direct current is used) to the recommendations of the manufacturer of
the electrode being used, as indicated in the instructions that are included with
each container of electrodes.
Arc lengths and electrical potential and current shall be suited to the
thickness of material, type of groove and other circumstances attendant to the work.
1. The maximum size for flat position welding of all passes except the root
pass shall be 8 mm.
The electrode for the single pass fillet weld and for the root passes of all
multiple layer welds in all cases shall be of the proper size to insure thorough fusion
and penetration with freedom from slag inclusions.
259
A single layer of the weld metal, whether deposited-in one pass or made up
of several parallel beads, shall not exceed 3 mm in thickness except that the bead
at the root may be 6 mm in thickness if the position of welding and the viscosity of
the weld metal permit control of the latter so that it does not over flow upon unfused
base metal.
The maximum size of fillet weld which may be made in one pass shall be 8
mm except that for vertical welds made upward the maximum size made in one
pass shall be 13 mm.
In vertical welding the first root pass shall be formed from the bottom upward.
Succeeding passes may be formed by any technique that will fulfill the requirements
of the Specification and Plans.
1. Complete fusion between the base metal and the deposited weld metal
is obtained.
3. The molten weld metal floats all slag, oxide and gases to the surface
behind the advancing arc.
Each time the arc is started, either to begin a weld or to continue partly
completed weld, the arch shall be manipulated to obtain complete fusion of the
deposited weld metal with the base metal and with any previously deposited weld
metal, before any progression of the arc along the joint.
Before welding over previously deposited metal, the slag shall be removed
and the weld and adjacent base metal shall be brushed clean. This requirement
shall apply not only to cratered areas but also when welding is resumed after any
interruption. It shall not, however, restrict the making of plug and slot welds, in
accordance with the following paragraphs.
1. For flat welds, the arc shall be carried around the root of the joint and
then weaved along a spiral path to the center of the hole, fusing and
depositing a layer of weld metal in the root and bottom of the joint. The
arc shall then be carried to the periphery of the hole, and the procedure
repeated, fusing and depositing successive layers to fill the hole to the
depth required. The slag covering the weld metal shall be kept molten,
or nearly so, until the weld is finished. If the arc is broken, except briefly
for changing electrodes, the slag must be allowed to cool and shall be
completely removed before restarting the weld.
260
2. For vertical welds, the arc shall be started at the root of the joint, at the
lower side of the hole and carried upward on the zigzag path, depositing
a layer about 5 mm thick on the exposed face at the thinner plate and
fused to it and to the side of the hole. After cleaning the slag from the
weld, other layers shall be similarly deposited to fill the hole to the
required depth.
3. For overhead welds, the procedure shall be the same as for flat welds
except that the slag shall be allowed to cool and shall be completely
removed after depositing each successive layer until the hole is filled to
the required depth.
Slot welds shall be made with a technique similar to that specified above for
plug welds, except that if the length of the slot exceeds three times the width, or if
the slot extends to the edges of the part of the technique specified above for making
plug welds shall be followed for the type of flat position welds.
The following tabulation shows that the relation between weld size and the
maximum thickness of material on which various sizes of fillet welds may be used:
The maximum size of fillet weld that may be used along the edge of material
6 mm or more in thickness shall be 1.5 mm less than the thickness of the material.
The minimum effective length of fillet weld shall be four times its size and in
no case less than 38 mm.
Intermittent fillet welds, preferably, shall not be used. They shall be permitted
only where the required weld area is less than that of a continuous fillet weld of the
minimum size. If used on main members, they shall be chain intermittent welds. In
all other cases, chain intermittent welding is preferable to staggered intermittent
welding.
261
1. At the end of members, there shall preferably be continuous longitudinal
fillet welds at least as long as the width of the element or member being
connected.
2. The clear spacing in the direction of stress of stitch welds that connect
plates to other plates or to shapes shall not exceed:
3. For members composed of two or more rolled shapes in contact with one
another, the longitudinal spacing of stitch welds shall not exceed 600 mm.
Fillet welds in holes or slots may be used to transmit shear in lap joints or to
prevent the buckling or separation of lapped parts. The fillet welds in a hole or slot
may overlap.
Exposed faces of welds shall be made reasonably smooth and regular, shall
conform as closely as practicable to the design requirements and shall not at any
place be inside the intended cross-section. Weld dimension in excess of the design
requirements shall not be a cause for rejection, but in case excess weld metal
involves serious malformation, such work shall be rejected.
All fillet welds shall be of acceptable types. All fillet welds that carry reversed
stresses running in a direction perpendicular to their longitudinal axis shall be of the
concave type or the 0-gee type when the fillet weld is flushed with the edge of a
member. When one of these types is specifically indicated on the Plans for a weld,
it shall be of that type.
All butt welds, except produced with aid of backing material, shall have the
root of the initial layer chipped out or otherwise cleaned to sound metal and welded
in accordance with the requirements of the Specification. Butt welds made with the
use of a backing of the same materials as the base metal shall have the weld metal
thoroughly fused with the backing materials.
Ends of butt welds shall be extended past the edges of the parts joined by
means of extension bars providing a similar joint preparation and having a width not
262
less than the thickness of the thicker part jointed; or for material 19 mm or less in
thickness, the ends of the welds shall be chipped or cut down to solid metal and
side welds applied to fill out the ends to the same reinforcement as the face of the
welds. Extension bars shall be removed upon completion and cooling of the weld
and the ends of the weld made smooth and flush with the edges of the abutting
parts.
Weld metal shall be solid throughout except that very small gas pockets and
small inclusions of oxide or slag may be accepted if well dispersed and if none
exceeds 1.5 mm in greatest dimension, and if the sum of the greatest dimensions
of all such defects of weld metal area does not exceed 15 mm in an area of 10 cm2.
There shall be complete fusion between the weld metal and the base metal
and between successive passes throughout the joint.
Welds shall be free from overlap and the base metal free from undercutting.
All craters shall be filled to the full cross-section of the welds.
409.3.2.9 Correction
263
4. A cracked weld shall be removed throughout its length, unless by the use
of acid etching, magnetic inspection or other equally positive means, the
extent of the crack can be ascertained to be limited, in which case sound
metal 50 mm or more beyond each end of the crack need not be
removed.
Painting shall not be done until the work has been accepted and shall be in
accordance with the Specification. The surface to be painted shall be cleaned of
spatter, rust, loose scale, oil and dirt. Slag shall be cleaned from all welds.
409.3.2.12 Identification
The operator shall place his identification mark with crayon, or paint, near
the welds made by him.
409.3.2.13 Inspection
264
On completion of the welding work, inspection shall be carried out by an
Inspector appointed by the Engineer.
The size and contour of welds shall be measured with suitable gauges. The
inspector shall identify with a distinguishing mark all welds that he has inspected
and accepted.
The Contractor shall remove and replace, or correct as instructed, all welds
found defective or deficient. He shall also replace all methods found to produce
inferior results, with methods which will produce satisfactory work.
In the event that fault welding or the removal for rewelding of faulty welding
shall damage the base metal, the Contractor shall remove and replace the damaged
material.
410.1 Description
This Item shall consist of structural timber of the specie and size called for
on the Plans, either treated or untreated as called for in the Proposal. It shall include
the furnishing of the timber, the framing, erecting, furnishing of hardware and the
furnishing of paint and paintings if paint is called for on the Plans or in the Special
Provisions.
410.2.1 Timber
Timber shall be the specie specified on the Plans. Unless otherwise noted
on the Plans or in the Special Provisions, only the best grade shall be used. It shall
be free from loose knots, splits, worm holes decay, warp, ring separation, or any
defect which will impair its strength or render it unfit for its intended use. Any specie
specified on the Plans may be used for untreated timber and if that specie is not
available, a specie of equivalent strength and durability may be used if authorized
by the Engineer. If the timber is to be treated, only those species shall be used
which are known to possess properties which make them favorable to treatment.
265
410.2.2 Paint
410.2.3 Hardware
410.2.4 Preservatives
When timber is intended for marine use, the creosote petroleum oil blend
shall not be used.
The minimum penetration of the preservative into the surface of the timber
shall be 20 mm. The minimum retention of the preservative per cubic metre of
timber shall be as follows:
The Engineer shall be notified at least 10 days in advance of the date that
the treating process will be performed in order that the untreated timber, the
treatment process, and the finished treatment timber may all be inspected. The
Engineer shall inspect the timber prior to treatment to determine conformance with
those Specifications and suitability of conditions for treatment. He shall be
permitted free access to the plant in order that temperatures, pressures and
quantities and type of treatment materials used may be observed. Samples of the
creosote or creosote petroleum oil mixture shall be furnished as required for tests.
266
has been performed in a satisfactory manner. The penetration of treatment shall
be determined by boring a sufficient number of well-distributed holes to determine
the average penetration. All such holes shall be plugged with plugs approximately
1.6 mm larger in diameter that the bit used in boring the holes.
If the penetration of preservative is less than the required amount, the entire
charge, or such parts thereof as are determined by the Inspector to be
unsatisfactory, may be retreated. If after retreatment the penetration is still
insufficient, the treated pieces shall be rejected.
Any excessive checking caused by the treating process shall be cause for
rejection of the pieces in which the excessive checking occurs.
The quantity to be paid for shall be the number of cubic meter of timber
complete in place and accepted. Measurement of timber shall be computed from
the nominal dimension of the timber even though the actual dimensions may be
scant. The measurement of timber shall include only such timber as a part of the
completed and accepted work and will not include any timber required for a
falsework, bracing or other timber required in the erection.
411.1 Description
267
This Item shall consist of furnishing and applying all paint materials including
vehicles, pigments, pastes, driers, thinners and mixed paints for steel and wooden
structures; sampling testing and packing; preparation of the surface and application
of paint to structures.
411.2.1 General
The paint shall be furnished for use in ready mixed, paste or powder form.
1. The paint shall show no excessive settling and shall easily redisperse
with a paddle to a smooth, homogeneous state. The paint shall show no
curdling, livering, caking or color separation and shall be free from lumps
and skins.
3. The paint shall dry to a smooth uniform finish, free from roughness grit,
unevenness and other imperfections.
4. The paint shall not skin within 48 hours in a ¾ filled tightly closed
container.
411.2.2 The paint shall conform to the requirements of the Specifications indicated
as follows:
268
Basic Lead-Silico-Chromate
Ready Mixed Primer AASHTO M 229
Ready Mixed Aluminum Paint AASHTO M 260 and PNS
411.2.3 Drier
This Specification covers both straight oil drier (material free from resins and
gums), and Japan drier (material containing varnish gums). The drier shall be
composed of lead manganese or cobalt or a mixture of any of these elements,
combined with a suitable fatty oil, with or without resins or gums, and mineral spirits
or turpentine, or a mixture of these solvents. The drier shall conform to the following
requirements:
3. Elasticity – The drier when flowed on metal and baked for 2 hours at
100oC shall have an elastic film.
4. Drying – It shall mix with pure raw linseed oil in the proportion of 1 volume
of drier to 19 volume of oil without curdling and the resulting mixture when
flowed on glass shall dry in not more than 18 hours.
5. Color – When mixed with pure, raw linseed oil in the proportion of 1
volume of drier to 8 volume of oil, the resulting mixture shall be darker
than a solution of 6 grams of Potassium Dichromate in 13 cc of pure
Sulfuric Acid (sp.gr. 1.84).
The paint shall be mixed in the proportion of 240 grams of aluminum powder
or paste per liter of vehicle of long oil spar varnish. This makes a paint containing
21 percent pigment and 79 percent vehicle. The weighed amount of powder or
paste shall be placed in a suitable mixing container and the measured volume of
vehicle poured over it. The paste or powder shall be incorporated in the paint by
vigorous stirring with a paddle. The powder or paste will readily disperse in the
vehicle. Before removing any paint from the container, the paint shall be thoroughly
stirred to insure a uniform mixture, and the paint shall be suitably stirred during use.
The paint shall be mixed on the job and only enough for one day’s use shall be
mixed at one time.
269
When two field coats of aluminum paint are specified, the first coat shall be
tinted with lampblack paste or Prussian blue paste in the quantity of 24 grams/liter
of paint. The exact quantity used shall be sufficient to give a contrast in color which
can be readily distinguished. When three field coats of aluminum paint are
specified, the second coat shall be tinted.
The paint shall be mixed as specified for Aluminum Paint for Structural Steel
except that the proportions shall be 270 grams of aluminum powder or paste to one
litre of vehicle.
Other paint composition may be used when and as stipulated in the Special
Provisions.
411.3.6 Painting
411.3.6.1
The painting of structure shall include the proper preparation of the surface;
the application, protection and drying of the paint coatings, the protection of the
pedestrians, vehicular or other traffic upon or underneath the structures, the
protection of all parts of the structure (both superstructure and substructure) against
disfigurement by spatters, splashes and smirches of paint or of paint materials; and
the supplying of all tools, tackle, scaffolding labor, paint and materials necessary
for the entire work.
270
Paint shall not be applied during rain, storms or when the air is misty, or
when, in the opinion of the Engineer, conditions are otherwise unsatisfactory for
the work. Paint shall not be applied upon damp surfaces or upon metal which has
absorbed heat sufficient to cause the paint to blister and produce a pervious paint
film.
No wide flat brush shall be used. All brushes preferably shall be either round
or oval but if flat brushes are used, they shall not exceed 100 mm in width.
When a paint gun is used, the equipment used shall be of an approved type
and shall have provision for agitation of paint in the spray container. In the case of
aluminum paint, the pressure used shall be only that necessary to secure adequate
atomization. If in the opinion of the Engineer unsatisfactory results are obtained
from the use of a spray gun, its use shall be discontinued and the painting
completed by the use of brushes.
1. Hand Cleaning
The removal of rust, scale and dirt shall be done by the use of metal
brushes, scrapers, chisels, hammers or other effective means. Oil and
grease shall be removed by the use of gasoline or benzene. Bristle or
wood fiber brushes shall be used for removing loose dust.
2. Sandblasting
Sandblasting shall remove all scale and other substances down to the
base metal. Special attention shall be given to the cleaning of corners
and re-entrant angels. Before painting, sand adhering to the steel in
corners and elsewhere shall be removed. The cleaning shall be
approved by the Engineer prior to any painting. The material shall be
painted before the rust forms and not later than 2 hours after cleaning.
271
3. Flame Cleaning
272
5. Field Painting of Structural Steel
As soon as the Engineer has examined and approved all field rivets,
the heads of such rivets and field bolts, all welds and any surfaces from
which the shop coat of paint has become worn off or has otherwise
become defective, shall be cleaned and thoroughly covered with one coat
of shop coat paint.
When the paint applied for “touching up” rivet heads and abraded
surfaces has become thoroughly dry, such field coats as called for shall
be applied. In no case shall a succeeding coat be applied until the
previous coat has dried throughout the full thickness of the film. All small
cracks and cavities which were not sealed in water-tight manner by the
first field coat shall be filled with a pasty mixture of red lead and linseed
oil before the second field coat is applied.
The following provisions shall apply to the application of all field coats.
To secure a maximum coating on edges of plates or shapes, rivet heads
and other parts subjected to special wear and attack, these parts shall
first be stripped, followed immediately by the general painting of the
whole surface, including the edges and rivet heads.
Timber structures shown on the Plans to be painted, shall be given two coats
of the specified materials, which shall be thoroughly brushed in. Additional coats
shall be required when so specified on the Plans. All surfaces shall be thoroughly
dry before painting, and each coat shall be allowed to stand for three or four days,
or until thoroughly dry before applying the succeeding coat.
The entire surface of all untreated timber that is to be painted, shall be given
a priming coat immediately after the material is delivered to the project. All contact
surfaces shall receive the second coat paint.
Special care shall be taken during construction and handling so that the
pieces to be painted do not come in contact, except when required, with the
creosoted materials and that no oil is brushed on the same during construction
operations. The Contractor shall be required to pile such pieces separately from
273
the creosoted materials and keep them from contact with same until ready for
erection.
When called for on the Plans or in the Special Provisions, existing structures
shall be given the number and kind of coats of field paint as stipulated. The surface
to be repainted shall be cleaned as specified under Subsection 411.3.6.2, Painting
Structural Steel, with the added provisions that all dead or loose paint shall be
removed by scraping, chipping, or brushing as may be necessary. Timber railings,
name plates, planking and other interfering parts shall be removed before cleaning
is begun and shall be replaced after the painting has been completed and the last
coat has thoroughly dried. The application of the coat shall be as specified under
Subsection 411.3.6.2, (5), Field Painting of Structural Steel.
Painting shall not be measured and paid for separately, but the cost thereof
shall be considered as included in the contract unit price of the items where called
for.
412.1 Description
412.1.1 Scope
274
This Item shall consist of the requirement for elastomeric bearing pads
whose main function is to transfer loads or accommodate relative movement
between a bridge superstructure and its supporting structure, or both while avoiding
damaging strain and additional tension. Elastomeric bearings shall include
unreinforced pads (consisting of elastomer only) and reinforced bearings with steel
laminates.
A laminated bearing pad is required when the thickness of the plain pad is
more than 31.75 mm and the compressive strain is more than 15%.
The elastomer for the manufacture of the bearing is furnished in two types
as follows:
Steel laminates used for reinforcement shall be made from rolled mild steel
conforming to ASTM A 36, A 570 or equivalent, unless otherwise specified by the
Engineer. The laminates shall have a minimum nominal thickness of 20 gage.
275
All elastomeric layers, for example, plain bearing pads, laminates, and
covers, shall be of uniform thickness unless otherwise specified in the contract or
purchase order.
276
Ozone Resistance (D1149)
Partial Pressure, MPa 25 25 100 100
Duration, Hours 48 48 100 100
Tested at 20% strain 37.7 oC ±1 oC No No
Mounting procedure D518 - - cracks cracks
Procedure A
Brittleness D2137, low temp.
Brittleness at -40 oC Pass Pass Pass Pass
Shear Modulus
Nominal Hardness Shear
Modulus at 23 oC, MPa 0.85- 1.13- 0.85- 1.13-
1.1 1.84 1.1 1.84
Table 2 – Tolerances
Mm
Overall vertical dimensions
Design thickness 32 mm (1 ¼ in) or less -0, +3
Design thickness over 32 mm (1 ¼) -0, +6
Overall horizontal dimensions
914 mm (36 in) and less -0, +6
Over 914 mm (36 in) -0, +12
Thickness of individual layers of ±20 percent of design value but
elastomer (laminated bearing only) at no more than ±3 mm (1/8 in)
any point within the bearing
Variation from a plane parallel to the
theoretical surface: (as determined by
measurements at the edge of the
bearings)
Top Slope relative to the bottom of no
more than 0.005 radian
Sides 6
Position of exposed connection members 3
Edge cover of embedded laminated -0, +3
connection members
Size of holes, slots or inserts ±3
Position of holes, slots, or inserts ±3
277
412.3.1 Handling, Transport, Storage and Installation
Bearings shall be placed on surfaces that are plane to within 1.6 mm and
unless the bearings are placed in opposing pairs, horizontal to within 0.01 radians.
Any lack of parallelism between the top of bearing and the underside of the
girder that exceeds 0.01 radians shall be corrected either grinding of the surface,
grout pack bearing seats or modification of the bearing such that the intended
bearing placement is as originally designed with the least amount of bearing
modification, or as otherwise directed by the Engineer.
Exterior plates of the bearing shall not be welded unless at least 38.1 mm of
steel exists between the weld and the elastomer.
Dismantling at the site shall not be done unless absolutely necessary for
inspecting or installation.
412.3.2 Sampling
For acceptance purposes, bearing from within the lot shall be selected at
random as samples for inspection and testing.
A minimum of three bearings shall be taken from the lot for testing. If the
number of bearings in the lot exceeds 50 then for each additional 50 or part thereof,
one additional bearing shall be taken for testing.
278
3. If there are at least three separate surface cracks which are each at least
2 mm wide and 2 mm deep. The bearing shall be rejected.
4. Record the median compressive stiffness (K) of the bearing of median
stiffness.The compressive stiffness of each bearing tested shall not differ form (K)
by more than 10%.
5. For each bearing that fails to meet the requirements in (1), two
additional bearings maybe sampled and shall meet the requirements in (1) or the
lot shall be rejected.
6. If the lot is not rejected, the bearing of median stiffness (K) shall be
subjected to the elastomeric material tests in (2).
The quantity of elastomeric bearing pad to be paid for will be the final quantity
placed and accepted in the completed structure. The dimensions of elastomeric
bearing pads will be the quantity placed in accordance with the Plans or as
otherwise directed by the Engineer.
Preformed sponge rubber and cork expansion joint fillers for concrete paving
and structural construction shall conform to the applicable requirements of
AASHTO M 153.
279
280