Auxilixry Relay Testing

Testing

Uploaded by

Vijaya Kumar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views

Auxilixry Relay Testing

Testing

Uploaded by

Vijaya Kumar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Auxiliary Relays Testing

Testing Procedures
 Measure Relay Pick up &
Drop off Voltage/current.
 Measure Relay Pick up &
Drop off Timing.
 Measure Relay Burden.
 Measure Relay Contact
Resistance.

Equipment
Required
1. Injection Kit
(Sverker, Freja,
.. etc).
2. Measurement Sverker 760 Multi-meter Connection Cables
Device (Multi-
meter).
3. Connection
Cables (Banana
Type).

Pick Up & Drop Off Test


 Connection will be same as the shown
figure.
 Increase voltage until the relay picks
up. Note down the pick up value for
voltage & current.
 Decrease voltage until the relay
drops off. Note down the drop off
value for voltage & current. Connection Circuit

Pick Up & Drop Off Timing Test


 For timing test we will use one pole of MCB series with Ammeter to cut dc supply off.
 Use the other pole of MCB for starting sverker timer.
 Use any contact from the aux. relay to stop sverker timer.
 Inject 125V directly to the relay coil. Note down the pick up time.
 Energize the relay with 125V then switch the supply off. Note down the drop off time.

Burden Test
 Energize the relay with 125V and measure the dc current.
 Calculate the relay power (W) = 125v x measured current