083 Pioneering Mass Caving at El Teniente
083 Pioneering Mass Caving at El Teniente
083 Pioneering Mass Caving at El Teniente
in the 1800s. Exploitation first began in formed around a central, barren, brec- underground, each sector being, in effect,
1819, when the highest-grade minerals, cia pipe of 1.0 to 1.2 km diameter, sur- a large mine in its own right. This case
from what became the Fortuna sector, rounded by a mineralized rock mass. story focuses on the Esmeralda Sector,
were mined manually and transported on The bulk of the mineralization within which is set to become the most impor-
animals to the coast. In 1904, William the orebody is typical of massive, homo- tant section of the mine, producing
Braden, an American engineer, founded geneous copper porphyries. In fact, El 45,000 t of the 130,000 t/day planned
the first El Teniente company, Braden Teniente is one of the largest porphyry for El Teniente.
Copper Company, and built a road for deposits of copper in the world. The main Since El Teniente began operations
carts and a concentration plant. rock types of the deposit are: andesite in the early 1900s, several exploitation
In 1916, Braden Copper became a sub- 73%, diorite 12%, dacite 9% and breccia methods have been used, though the se-
sidiary of the Kennecott Corporation, 6%. At some time during its history, condary mineralization was ideally sui-
which was able to supply the funds nec- the deposit was affected by supergene ted to conventional block caving.
essary to expand the mine. Kennecott alteration through percolation of mete- However, the last mining sector lo-
operated El Teniente until 1971. In April, orological water close to surface, which cated in secondary ore, Quebrada
1967 the Chilean Government acquired gave rise to secondary mineralization. Teniente, was exhausted in 2003, and
a 51% interest in the property, and foun- This secondary ore is high in copper all current mining is in primary ore
ded the Sociedad Minera El Teniente. grade, but weak, and of good fragmen- for processing at the expanded Colón
Following this agreement, major mine tation and caveability. In contrast, the concentrator.
expansion was undertaken, and a new deeper primary mineralization is rela- El Teniente started large-scale mi-
concentration plant was built in Colón, tively low in copper grade, harder, and ning of the primary ore in 1982, using
which increased total production capac- of moderate fragmentation and cavea- LHDs and the fully mechanized panel
ity to 63,000 t/day. Full nationalization bility. As can be appreciated, secondary caving method. The essential difference
followed in 1971, and El Teniente mine ore and primary ore require very differ- between panel caving and conventional
became a fully state-owned company. ent approaches in terms of mining. block caving is that the former is a dy-
In 1976 Codelco was formed, and El namic method in which the undercut is
Teniente became part of it. Mining method being continuously developed, and
drawpoints incorporated at the extrac-
Reserves El Teniente produces some 334,000 t fine tion front, rather than being fully de-
copper and 4,720 t molybdenum each veloped before caving is started. This
In total, the El Teniente orebody meas- year. Mass caving methods are employed method has been broadly successful at
ures 2.8 km-long, 1.9 km-wide, and 1.8 to deliver approximately 98,000 t/day El Teniente, and close to 250 million t
km-deep. Schematically, the deposit is of ore to the mill from several sectors of ore have been extracted using panel
Exploitation sequence
The panel caving exploitation sequence
initially used involved development
and construction of production levels,
undercutting at the undercut level, and
ore extraction. However, the dynamic
caving fronts, under high stress condi-
tions of 40-60 Mpa, resulted in sub-
stantial damage to the infrastructure.
Indeed, extraction in El Teniente Sub
6 Sector had to be stopped in March,
1992 after several rockbursts caused
fatal accidents, reflecting the low level
of knowledge at the time about mining
in primary rock.
Between June, 1994 and August, 1997,
El Teniente carried out experimental
mining in a pilot area of 12,000 sq m.
This process was closely monitored, and
the data served as the basis for a full
geomechanical study. From September,
1997 to June, 1998, during the pre-
operational phase, it was realized that
it was necessary to research the rela-
tionship between seismic potential,
undercutting speed and the mining of Panel caving with pre-undercut at Esmeralda.
new areas. Because of this, and for the
first time since the 1992 production Esmeralda pre-undercut on the west by the Braden breccia pipe,
freeze, El Teniente carried out prepara- and in the north by El Teniente Sub 6
tory work in a 6,000 sq m area using Following on from the studies and con- Sector, and is below the Teniente 4 Sur
simultaneous production techniques. trolled tests, El Teniente introduced a Sector. Lithologically, it occurs mainly
The test succeeded, with no significant variation of its conventional panel ca- in andesite, and contains a total mineral
rockbursts, thus proving the relation- ving undercut sequence. Known as reserve of 365 million t, with an average
ship between seismicity and caving pre-undercut, it essentially consists of grade of 1.01% of copper and 0.024%
speed. Indeed, it is now recognized that developing the production level behind of molybdenum. The total investment
the uncontrolled seismicity induced by the undercut, rather than the more for Esmeralda was US$205.6 million,
the mining extraction rate of advance typical method where the production with conceptual engineering and design
of the caving face and extraction speed development is carried in parallel with initiated in 1992, and caving starting in
has been the main cause of damage to the undercut ahead of the caving face. August, 1996. Ore production started in
the tunnels and infrastructure on the The pre-undercut achieves a better re- September, 1997, and has built up from
lower levels. distribution of the stresses ahead of the an average of 4,000 t/day in 1998 to
Nowadays, there are variables incor- production development, resulting in 19,500 t/day in 2001, and full produc-
porated into the mining design and plan- less damage and improved safety. tion of 45,000 t/day from 2005.
ning concept to control the excess of Although the pre-undercut variant Caving at Esmeralda was achieved
seismic activity, not only improving the had been tested in some small sectors of with 16,800 sq m of available produc-
working conditions on the production the mine, it was first used on an indus- tion undercut, once a problem of 'sup-
level, but also increasing productivity. trial scale in the new Esmeralda sector. port points' was solved. These formed
During the pre-operational phase, over Occupying a total area of 714,000 sq above the apex of the crown pillar, and
2 million t were removed from Teniente m, Esmeralda is located at 2,210 m asl reduced the interaction between draw-
Sub 6, with only two small rockbursts. within the El Teniente deposit, bounded points, making the flow of ore from
Basic concepts
In the conventional panel caving and the
pre-undercut variant, the same basic con-
cepts apply. The main difference is the
sequence of each of the operational ele-
ments. In the conventional panel caving
Standard drill plan with 4 hole-fans method, the sequence of activities is:
development of tunnels on each level
for production and undercut; drawbell
opening; undercut blasting; and extrac-
tion. In the pre-undercut variant, the un-
dercut is excavated first, and the pro-
duction level is developed subsequently
within the stress-relieved zone: devel-
opment of the undercut level; undercut
blasting; development of the production
level; drawbell opening; and extraction.
The main challenge associated with
this variant involved the undercutting.
Several alternatives were tried, with
the current preference being a flat, low
Plan of pre-undercut holes. height 3.6 m undercut. The undercut is
blasted some 80 m ahead of the actual
the undercut level difficult. The effec- through the ore pass and into the loa- production zone, with the production
tive extraction rate defined for the Es- ding bin. On the haulage level, the level and drawbell development follow-
meralda sector was 0.14 to 0.44 t/day/ mineral is loaded into trains featuring ing around 22.5 m behind the undercut,
sq m at the initial caving stage, and Automatic Train Protection (ATP) and and 57.5 m ahead of the production
reached 0.28 to 0.65 t/day/sq m at the consisting of a locomotive with eight 50 zone.
steady-state caving stage. The height t cars. These trains, which were retrofit- The undercut comprises drives, 3.6
of primary ore column to be exploited ted with an Automatic Train Operation m-wide by 3.6 m-high, developed paral-
is around 150 m, relatively low if com- (ATO) system, tip into storage bins lel to each other on 15 m centres. The
pared with Teniente 4 Sur, where the which feed a 5.0 m-diameter orepass excavation of the undercut is achieved by
height is over 240 m. to the main transport level Teniente 8. blasting three- or four-hole fans, some
At Esmeralda, 7 cu yd LHDs work- Trains with 90 t electric locomotives 7 m to 10 m length, drilled into the side-
ing on the production level load and tip and 18 cars each of 80 t capacity carry wall. The drill holes are fanned slightly,
into 3.5 m-diameter ore passes. Here, the mineral out to the Colón concentra- to ensure an undercut height equal to
teleremote controlled hydraulic break- tor. The main haulage level at Teniente the height of the drives. Swell material
ers positioned above 1 m x 1 m grizzlies 8 was recently upgraded, incorporating from each undercut blast is removed by
break any oversize rock before it goes new technology similar to Esmeralda. LHD to provide a free face for the next
blast. The production haulage level is
Drilling patterns in andesite and breccia. developed 18 m below the undercut,
giving a crown pillar thickness of 14.4
m through which the drawbells are then
developed straight into the pre-blasted
undercut. The production level requires
substantial support, with fully grouted
HW FW HW FW 2.3 m rebar installed in a 0.9 m x 1.0
Drill plan with 3 x 3 hole-fans Drill plan with 4 x 4 hole-fans m pattern immediately behind the face,
followed by chain mesh and shotcrete.
Permanent support is added around 15 m
behind the face, and consists of fully
grouted long cable bolts, with additional
reinforcement at drawpoints. One of the
challenges of this method is that two
HW FW HW FW
mining fronts have to be managed, one
on the undercut level, and the other lo-
cated on the production level, and these
57,5 m 22,5 m
spacing mesh, 10 cm-thick shotcrete, and
Undercut area
6 in-diameter cable bolts. There are two
Production types of cable bolts, plain and birdcage,
area
which are 4 m to 10 m-long, and 5 m to
Preparation area
80 m
www.atlascopco.com