Overburden Processing .
Overburden Processing .
Overburden Processing .
PROJECT REPORT
ON
DISSERTATION
AMIE
(DEGREE IN MINING ENGINEERING)
BY
SAYILA SURESH
AM-144449-5
1
CERTIFICATE
2
AKNOWLEDGEMENT
SAYILA SURESH
AM-144449-5
3
A
Project on
PROCESSING OF OVERBURDEN FOR STOWING
IN UNDERGROUND MINES.
By
SAYILA SURESH
AM-144449-5
4
INDEX
Hopper - 14
Vibrating Feeder - 16
Jaw Crusher - 18
Scrubber - 24
FBC - 26
Sand cyclone - 29
Clay cyclone - 31
Electric Control system - 33
Belt Conveyor - 35
8. Specifications of Sand - 38
9. General information of mine - 39
10. Mine silent features - 42
11. Plans showing opencast workings - 46, 47
12. Conclusion - 48
5
TITLE OF THE PROJECT:
6
7
ABSTRACT
The reserve of river sand, the traditional stowing material used in Indian coal
mines, is getting depleted due to over exploitation in civil works and low rate of
replenishment due to construction of dams. As a result, though river sand has proved
as the best natural material for stowing, its availability within economically
transportable distance from the mines is never assured. Coal seams earlier developed
in bord and pillar method or other methods of underground mining had been standing
on pillars for long in absence of stowing material causing mammoth loss of coal and
its conservation. Amongst the various alternatives to sand as the fill material for
mines, the first choice has been the overburden from closely located opencast mines
due to their ready stock at practically no price and cheaper transport cost.
8
SCOPE OF PROJECT:
1. Drawing overburden (excluding top soil, sub soil and clay) from
overburden dump yard.
9
PROCESS
1. The Lorry with overburden will dump the Overburden in Hopper which is
loaded from overburden dump yard.
3. From the Vibro Feeder only the particles with a size less than of -500 mm will
be sent to Primary Jaw Crusher through Belt Conveyor-1
5. From the Primary Jaw Crusher the particles with a size of -30 mm will sent to
Secondary Roller Crusher through Belt Conveyor-2.
7. From Secondary Roller Crusher the particles with a size of -18 mm will send to
Scrubber.
8. Water will be added in Scrubber for easy separation of clay from sand.
9. From Scrubber the mixture of sand and clay will be send to FBC (Fluidized Bed
Classifier).
10
10.In FBC both sand and clay will be separated.
11.From FBC sand will be sent to Sand Cyclone and clay will be sent to Clay
Cyclone.
14.From Clay Pond water will be separated from clay by adding chemical called
Alum.
15. The pure water Separated from clay will be recycled (Sent back
in to Scrubber)
11
PLANT LAY OUT
12
EQUIPMENT
Hopper,
Vibrating feeder,
Crushers,
Jaw Crusher,
Scrubber,
Sand Cyclone,
Clay Cyclone,
Belt conveyors,
13
Hopper:
o In this bunker the overburden will be dumped by Lorries from the over
burden dump yard.
o The hopper construction was made in such way that it can withstand even
though some big boulders hit to its sides.
14
Hopper
15
Vibrating Feeder:
16
Vibrating Feeder Features:
1. Flexible design.
17
Jaw crusher:
Jaw Crusher is used as primary crusher and secondary crusher since they can
achieve coarsely crushing and fine crushing. Jaw crusher of PE series can process
large stones with large capacity primarily and thus become the first choice for primary
crushes; the PEX series can be used as secondary crusher after the primary crushing.
The series products have complete specifications and the feeding size ranging from
125mm to 1020mm.
Jaw Crusher
18
Jaw Crusher features:
1. Crushing cavity is deep and there is no dead area, which improves feeding
capacity and output;
6. Energy-saving: single machine can save energy by 15% to 30%; the system
can save energy by over 30% to 60%;
7. Large adjustment range of discharge hole can meet the demands of different
users;
19
Jaw Crusher Technical Data:
20
Secondary Roller crusher:
Secondary roller crusher is especially used for providing high-quality sandstone
aggregate for expressway, high-speed railway, high-rise buildings, city planning,
construction of dam for hydropower plant and concrete mixing plant. It is the first
choice in the artificial sand making and the stone shaping fields.
21
Working Principle:
2. Main shaft is equipped with imported roller bearing. It makes main shaft
work stable, and then increase the life of time.
3. Hydraulic lifting mechanism can move away the feed hopper easily, which
saves man power during maintenance.
5. Special dust-proof design for main shaft bearing fully avoids dust entering
bearing lubrication part, which will make sure the machine work normally.
6. Special feed opening structure makes it possible that center feeding, center
feeding & ring feeding changes easily, in order to meet requirement of crushing and
reshaping stones.
22
Secondary Roller crusher technical Data:
23
Scrubber:
Scrubber is used to separate materials into various sizes for further processing
or for end use. The material is separated by passing it through a vibrating “screen box”
which has a number of different sized screens, or meshes, which the material falls
through like a sieve, the material falls onto attached conveyors which stock pile the
end products. The end products can then be used in the building and construction
industries.
24
Scrubber Features
4. Easy maintenance.
25
FBC (Fluidized Bed Classifier):
A fluidized bed is formed when a quantity of a solid particulate substance
(usually present in a holding vessel) is placed under appropriate conditions to cause a
solid/fluid mixture to behave as a fluid. This is usually achieved by the introduction of
pressurized fluid through the particulate medium. This results in the medium then
having many properties and characteristics of normal fluids, such as the ability to free-
flow under gravity, or to be pumped using fluid type technologies.
26
Properties of fluidized bed Classifier:
A fluidized bed consists of fluid-solid mixture that exhibits fluid-like properties.
As such, the upper surface of the bed is relatively horizontal, which is analogous to
hydrostatic behavior. The bed can be considered to be a heterogeneous mixture of
fluid and solid that can be represented by a single bulk density.
Furthermore, an object with a higher density than the bed will sink, whereas an
object with a lower density than the bed will float, thus the bed can be considered to
exhibit the fluid behavior expected of Archimedes' principle. As the "density",
(actually the solid volume fraction of the suspension), of the bed can be altered by
changing the fluid fraction, objects with different densities comparative to the bed can,
by altering either the fluid or solid fraction, be caused to sink or float.
In fluidized beds, the contact of the solid particles with the fluidization medium
(a gas or a liquid) is greatly enhanced when compared to packed beds. This behavior
in fluidized combustion beds enables good thermal transport inside the system and
good heat transfer between the bed and its container. Similarly to the good heat
transfer, which enables thermal uniformity analogous to that of a well mixed gas, the
bed can have a significant heat-capacity whilst maintaining a homogeneous
temperature field.
27
Fluidized bed types:
Stationary or bubbling fluidized bed : the classical approach where the gas at
low velocities is used and fluidization of the solids is relatively stationary, with
some fine particles being entrained.
Vibratory fluidized beds: are similar to stationary beds, but add a mechanical
vibration to further excite the particles for increased entrainment.
Annular fluidized bed (AFB): A large nozzle at the center of a bubble bed
introduces gas as high velocity achieving the rapid mixing zone above the
surrounding bed comparable to that found in the external loop of a CFB.
28
Sand Cyclone:
From FBC the sand will be sent to sand cyclone.
Sand Cyclone will dispatch the sand in to Lorries, in case of non availability of
Lorries the sand will be stored in dump yard.
29
Sand Dump Yard
30
Clay Cyclone:
From FBC the clay will be sent to clay cyclone.
31
Clay Pond
Clay
32
Electric Control System:
Input Power Supply was 3.3 KV and it is converted in to 550V and 440 V.
Every Equipment was provided with separate ON/OFF Controls and also provided
with EL (Earth Leakage) tripping system and OL (over load) tripping system.
33
Main power controls and Belt Conveyor Controls
34
Belt Conveyor :
35
36
Belt Conveyor Features:
1. High capacity.
2. Standard parts.
3. Simple structure.
4. Easy Maintenance.
5. Easy to operate.
Belt
Belt Speed Capacity
Width Belt Length(m) / Power (kW)
(m/s) (t/h)
(mm)
500 12-20/4- 20-30/5.5-
≤12/3 1.3-1.6 45-100
5.5 7.5
650 20-30/7.5-
≤12/4 12-20/5.5 1.3-1.6 70-120
11
800 15-30/7.5-
≤10/4 10-15/5.5 1.3-1.6 120-180
15
1000 10-20/7.5- 20-40/11-
≤10/5.5 1.3-2.0 160-250
11 22
1200 20-40/15-
≤10/7.5 10-20/11 1.3-2.0 200-400
30
37
Specifications of sand(Processed OB):
The suitability of any stowing material depends mainly on the operational and
safety requirements of coal mines. Depending upon the method of working, mining
cycles, safety requirements and the role of the fill is going to play in different geo-
mining environment, generalized stowing norms have been established. River sand the
most commonly used stowing material in the coal mining sector fulfills all the
operational and safety requirements. For substituting the river sand with processed
OB, such sand (Processed OB) shall contain following specifications.
Sl no Parameter Value
1 Specific gravity(cc/gm) 4.5
2 Bulk density(cc/gm) 1.5
3 Clay Content Below 1.5%
4 Porosity 40 %
5 Boulders/pebbles nil
6 % of Particles 600 -150 84 % - 96 %
microns size
38
General Information of the mine
KTK Opencast Sector Project is located in the northern part of Mulug Coal
belt. This project is located on the North – West side of Bhupalapalli village, which is
well connected by 3 km long all weather road. The feasibility report of KTK opencast
sector-1 project was approved by the board vide minute no 481 : 33 dated 03.01.2008
for a rated capacity of 1.25 Mtpa and peak output of 1.50 Mtpa an initial capital
investment of Rs. 91.20 crores.
Environmental clearance for the project was given by the MoEF, vide Lr No
J-/11015/692/2007 – 1A, II(M), dated : 1st May 2008. This is a cost plus project coal
from this project was envisaged fpoe supply to Kakatiya thermal power project,
Bhupalapalli, as per the MoU signed with APGENCO in June 2009.
Project construction work was started during the year 2008-09 and coal
production started from the year 2009-10 onwards. The project was brought to revenue
account from the year 2009-10 in accordance with the policy of the company.
39
In this RCE all the changes/modifications/suggestions recommended by the
scientific study. A committee constituted by SCCL and also the DGMS officials have
been considered for safe working.
40
Both the above studies have recommended to maintain the following
changes/modifications.
i. Maintaining the overall slope of low-wall OB benches at less than 22 deg form
the horizontal.
The following design criteria have been considered for waste dumps
v. Dump slope for each deck to be at natural angle of repose of 37.5 deg and
overall slope at 25.64 deg.
vi. Maximum height of external dump was planned up to120m above GL. In the
present proposal it is restricted to 90 m only.
vii. The maximum height of external dump in KTK OC sector-1 project was
planned up to ground level. In the present proposal it is planned up to 20 m
below the surface level.
41
Mine Salient features:
Mine started on : 23.11.2008
Total extractable coal : 8.33 Mt
Total overburden : 104.62 MCum
Average stripping ratio : 1 : 12.56
Project capacity : 1.25 MT (At peak 1.5 MT)
Life of the project : 10 years
Grade of the coal : G - 11 (4286 Kcal/KG)
Min depth of the quarry : 40 m
Max depth of the quarry : 165 m
Max strike length (Surface) : 2598 m
Min strike length (Surface) : 2340 m
Max width (Surface) : 728 m
Min width (Surface) : 317m
Overall pit slope of the quarry
42
Details of coal seams:
Coal reserves:
43
Details of HEMM working at KTK OC Sector 1 Project [01.01.2015]
Progressive
Sl no of Date of
Sl no Equipment Make & Model hours
Equipment commission
01.01.20.15
3 Cu.m Hyd.
L&T Komastu
1 Excavator NL 600206 05.12.2012 11228
PC 450
RUDRAMA
3 Cu.m Hyd.
2 L&T CK300 B 0581 14.05.2007 31916
Excavator [S2]
1 Cu.m Hyd. TATA Hitachi
3 2001 1589 20.07.2010 12256
Excavator Ex200
4 150 mm Drill REL 650 C 6021216 24.01.2013 2797
5 Dozer 320 HP BEML BD155 A 13241 24.04.2013 3588
6 Dozer 320 HP BEML BD155 A 13218 10.04.2014 2077
7 2.5 Cu.m loder HM 2021 HAPL 1212040 02.06.2013 5450
8 Water Sprinklr HM 1035 28 KL W 3 B 00298 17.03.2012 6126
Motor Grader
9 BG 6051 22514 05.09.2014 475
145 hp MG-2
/Dumper 35T
10 BEML H35 - 2 BH35-2 1369 22.03.2013 6405
B-369
Dumper 35T
11 BEML H35 – 2 BH35-2 1371 22.03.2013 5709
B-371
Dumper 35T
12 BEML H35 - 2 BH35-2 1373 24.03.2013 5745
B-373
Dumper 35T
13 BEML H35 – 2 BH35-2 1374 22.03.2013 5285
B-3374
Dumper 35T
14 BEML H35 – 2 BH35-2 1378 24.03.2013 5142
B-378
Dumper 35T
15 BEML H35 – 2 BH35-2 1380 22.03.2013 5791
B-380
Dumper 35T
16 BEML H35 – 2 BH35-2 1382 22.03.2013 6516
B-382
44
Departmental Equipment details :
45
KTK OC SECTOR – I PROJECT
46
KTK OC SECTOR – I PROJECT
WORKING PLAN.
47
Conclusion
In India crushed stone for underground stowing had been used in the limited
scale primarily because there was easy availability of river sand in the past, non-
availability of indigenously manufactured crusher and hence its spare parts and also
non availably high wear resistant pipes for reticulation of crushed overburden
hydraulically to underground mines. But the situation has undergone a sea change in
the current scenario due to scarcity of sand as a stowing material and being faced in
almost all the coal fields.
The underground coal mines of the Singareni Collieries Company Limited were
also facing the shortage of river sand for stowing. The study was undertaken with the
view to supply processed Overburden for stowing material in place of traditional river
sand. The Processed overburden of this plant is a technological substitute to the
natural river sand.
-------------------------- 0 ------------------------------
48