Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Insulation Coordination

Download as pdf or txt
Download as pdf or txt
You are on page 1of 62

INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Table of Contents: 
CONTENTS 

Table of Contents: ........................................................................................................................ 1 

1  The voltage stresses ............................................................................................................. 4 

2  Surge Arresters Sizing and Verification:............................................................................... 5 

2.1  Continuous Operating Voltage Check: .......................................................................... 5 

3  Temporary Overvoltage: ...................................................................................................... 6 

3.1  Temporary Overvoltage on 220 KV System: ................................................................. 7 

3.1.1  Temporary Overvoltage Observation on 220 KV BB with HV Neutral Earthed 
System: .............................................................................................................................. 7 

3.1.2  TOV Observation on 220 KV BB with HV Isolated Neutral System: ................... 10 

3.2  Temporary Overvoltage on neutral of 220 KV System: .............................................. 12 

3.3  Temporary Overvoltage on neutral of 22 KV System: ................................................ 13 

3.4  Temporary Overvoltage on 22 KV BB: ......................................................................... 15 

3.4.1  TOV Observed on 22kv BB with 22kv Neutral Earthed System: ........................ 15 

3.4.2  TOV Observed on 22kv BB with 22kv Neutral Isolated System: ........................ 17 

3.5  Temporary Overvoltage on 22 KV TR Incomer: .......................................................... 19 

3.5.1  Temporary Overvoltage on 22 KV transformer side and 22kv Neutral is Earthed:
  ............................................................................................................................ 19 

3.5.2  Temporary Overvoltage on 22 KV transformer side and 22kv Neutral is Isolated:


  ............................................................................................................................ 21 

3.6  Temporary Overvoltage on Tertiary Winding: ............................................................ 24 

3.6.1  Case‐1: ................................................................................................................ 24 

    Page 1/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

3.6.2  Case‐2: ................................................................................................................ 24 

3.7  Temporary Overvoltage on 22 KV Capacitor Bank: ..................................................... 27 

4  Energy Absorption Capability Check: ................................................................................. 30 

4.1  Arrester of 220KV System: .......................................................................................... 30 

4.2  22kv Transformer Medium Voltage Side, 22kv Transformer Tertiary Side, BB, and 
Capacitor Bank Arresters: ...................................................................................................... 31 

4.3  220kv and 22kv Transfomer Nuetral Surge Arresters: ................................................ 32 

4.4  Conclusion: .................................................................................................................. 32 

5  Slow Front Overvoltages: ................................................................................................... 33 

5.1  Switching on 220KV System: ....................................................................................... 33 

5.2  Conclusion: .................................................................................................................. 35 

5.3  Capacitor Bank Switching Study: ................................................................................. 36 

5.3.1  Energizing the First Leg of a Capacitor Bank ...................................................... 36 

5.3.2  Back‐to‐Back Capacitor Switching Study: .......................................................... 38 

5.4  Conclusion: .................................................................................................................. 40 

6  Fast Transient Phenomena: ............................................................................................... 41 

6.1  Direct Strokes to Phase Conductors: ........................................................................... 41 

6.2  Calculation of Maximum Current, Im for Direct Lightning Stroke .............................. 41 

6.3  Back Flashover Stroke Current: ................................................................................... 42 

6.4  Modelling of Various Elements of the Network for PSCAD: ....................................... 45 

6.4.1  Transmission line: .............................................................................................. 45 

6.4.2  Tower Model: ..................................................................................................... 45 

    Page 2/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

6.4.3  Power Transformer: ........................................................................................... 46 

6.4.4  Surge Arresters: ................................................................................................. 46 

6.4.5  Stroke Current Wave shape: .............................................................................. 47 

6.4.6  Other Substation Equipment: ............................................................................ 47 

6.5  Study and Results: ....................................................................................................... 48 

6.5.1  Direct stroke. ...................................................................................................... 48 

6.5.2  Back Flashover Stroke: ....................................................................................... 55 

7  Attachments: ...................................................................................................................... 62 

    Page 3/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Introduction: 

The prime objective of the study is to verify adequacy of surge arresters proposed for Marassi 
‐  Sidi  Abdul  Rahman  220/22  KV  GIS  Substation  and  to  check  whether  sufficient  protection 
against  fast  transient  overvoltages  and  switching  overvoltages  are  achieved  with  proposed 
rating and locations of surge arresters. 

This  report  presents  results  of  temporary  over  voltage,  slow  front  over  voltage,  and  fast 
transient study. The SLD for Marassi ‐ Sidi Abdul Rahman 220/22 kv substation is shown in the 
attached document. Studies were carried out using PSCAD Version 4.5.4 program.

1 The voltage stresses  

Voltage stresses in the electrical systems can be classified as follows: 

1. Continuous  power  frequency  voltages  vary  in  the  power  systems,  and  the  limits  are 
defined in the standards. 
2. Lightning (fast front) overvoltages, caused by lightning. 
3. Switching (slow front) overvoltages, caused by switching. 
4. Temporary overvoltages, caused by faults and load rejection. 

Figure 1: Typical Voltage Stresses in Power Systems

    Page 4/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS 02/02/2019

2 Surge Arresters Sizing and Verification:


2.1 Continuous Operating Voltage Check:

Determination of arrester Maximum Continuous Operating Voltage (MCOV) - as per Cl.3.2.1 -


IEC-60099-5, selected MCOV of phase to earth arrester shall be greater than maximum power
frequency system voltage:

Table 1: Surge Arresters Continous Operating Voltage Verfications

RMS Value of the Continuous Maximum System Voltage (RMS


Surge arrester
operating Voltage Value)

SS Outdoor
Arrester (214KV 171KV 245/√3=141.45 KV
rated)

22KV Transformer
20kv 24/√3 =13.86kv
Incomer Arrester

22KV MV SWGR
20kv 24/√3 =13.86kv
BB Arrester

22KV Capacitor
19.2kv 24/√3 =13.86kv
Bank Arrester

The Continuous operating voltage of phase to earth surge arresters as listed in above table-1
are more than r.m.s value of maximum rated power frequency phase voltage, so they are
accepted.

As per IEC-60099-5, cl 5.1.2, it is mentioned that the selection of transformer neutral point
SA will be only based on the rated voltage value and energy capability.

As per below checks of both rated/energy capability of 220kv and 22 kv neutral SA, they are
verified. So the standard continuous voltage which corresponding to selected rated voltage
is accepted.

 220kv Neutral SA with (108kv/86kv)(rated /continuous) voltages is accepted.

Page 5/62
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

 22kv NER SA with (15kv/12.9kv) (rated /continuous) voltages is accepted. 

3 Temporary Overvoltage: 

Determination of arrester rated voltage as per Cl.3.2.2 ‐ IEC‐60099‐5. The rated voltage of the 
arrester is selected based on the temporary overvoltage in the system at the arrester location, 
considering their amplitudes and their durations. These overvoltages are mainly due to load 
rejection and single‐phase faults occurring in the system. 

Temporary overvoltage of system should be less than capabilty temporary overvoltage (for one 
second “clearing time”) of surge arrester that can be calculated as below equation‐1 :  

∗ 1.19             (1) 

Temporary overvoltage of system (for 0.5 second “clearing time”) of surge arrester that can be 
calculated as below equation‐2 :  

∗ 1.21             (2) 

Above equations 1&2 are derived from below figure‐2 of HV SA manufacturer test report sheet.  

    Page 6/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Figure 2: Power Frequency Voltage Versus Time C/C'S 

Temporary over voltage model 

Matrooh SS Im Is
E_A5
E_A4

Marasi SS
P+jQ

#2
Bl1
BRK_A4 161km BRK_A5 #1 #3 PI Section
Lumped
Load
A Btr3 Btr5
TL1 V
E_A7 E_C
RRL

20 [ohm]

BRK_B4 BRK_B5

0.00005 [H] 11.83 [uF] E_A6


E_B5
E_B4

E_B
E_A8
E_A6
E_A7
Bcap

0.00005 [H] 23.7 [uF] E_A8


PI Section E_A
Bcap Bcap

0.00005 [H] 23.7 [uF] E_A5 E_A5


A->G

Bcap

TL2 #2

55 km #1 #3 PI Section
P+jQ

Btr4 Btr6
Timed
Logic
Fault

Bl2
Lumped
20 [ohm]

Load

0.00005 [H] 11.83 [uF]

Bcap
El-Omid SS
0.00005 [H] 23.7 [uF]
RRL

PI Section
Bcap Bcap

0.00005 [H] 23.7 [uF]

Bcap

3.1 Temporary Overvoltage on 220 KV System: 
3.1.1 Temporary Overvoltage Observation on 220 KV BB with HV Neutral Earthed System: 

TOV  observation  on  220kv  BB  with  neutral  earthed  system  (220kv  TR  neutral  DS  is  closed), 
where single line to ground fault at SS 220KV bus (at t=0.5 second) followed by load rejection 

    Page 7/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

(at t=0.55 second) are subjected. The voltage is measured at the SS 220kv BB as shown in figures 
3, 4, and 5. 

Main : Graphs
E_B
250
205.286
200
-39.880
150 -245.166
100 Min -212.341
50 Max 212.678
0
-50
-100
-150
-200
-250
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 0.57
0.90
f 3.06  

Figure 3: The voltage of phase‐B at SS 220kv BB 

Main : Graphs
E_C
250
-209.499
200
-106.969
150 102.529
100 Min -210.927
50 Max 211.229
0
-50
-100
-150
-200
-250
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 0.57
1.05
f 2.07  

Figure 4: The voltage of phase‐C at SS 220kv BB 

    Page 8/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
E_A
200
26.551
150 103.103
100 76.552
Min -179.317
50
Max 178.935
0
-50
-100
-150
-200
sec 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 0.25
0.42
f 5.80  

Figure 5: The voltage of the faulty phase at SS 220kv BB 

From previous figures (3, 4, and 5), the maximum temporary overvoltage is 212.68 KVp (phase 
voltage) then the rms value equal 150.38 KVrms (phase voltage) for one second. 

Maximum temporary overvoltage in the system (k) = 1.184 pu. 

r.m.s value of maximum power frequency voltage = Um / √3  = 141.45kVrms 

Therefore, phase‐earth power frequency over voltage = k x Um / √3 = 167.5kVrms 

While, the temporary overvoltage capability (TOV) of 214 kV surge arrester (SB214/20.5) for 
0.5 second is: 1.21*214KV=258.94KV and (TOV) of 214 kV surge arrester for one second is: 1.19 
*214KV=254.66KV (as per attachment document: B7005428)  

 As per above case study, it can be seen that temporary overvoltage capability (TOV) 
for  214  kV  surge  arrester  (SB214/20.5)  is  greater  than  maximum  temporary 
overvoltage 167.5 kVrms. 

According to contract specs: 

 214kv SA shall withstand (1.4*(245/√3) =198kvrms for 1sec, while 214 kV surge arrester 
TOV for one second is 254.66KV (as per attachment document: B7005428). 
 214kv SA shall withstand (1.8*(245/√3) =254.61kvrms for 0.5sec, while 214 kV surge 
arrester TOV for 0.5sec is 258.94KV (as per attachment document: B7005428). 

    Page 9/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

3.1.2 TOV Observation on 220 KV BB with HV Isolated Neutral System: 

TOV observation on 220kv BB with isolated neutral system (220kv TR neutral DS is opened), 
where single line to ground fault at SS 220KV bus (at t=0.5 second) followed by load rejection 
(at t=0.55 second) are subjected. The voltage is measured at the SS 220kv BB as shown in figures 
6, 7, and 8. 

Main : Graphs
E_A
200
169.019
150 -175.149
100 -344.168
Min -178.781
50
Max 178.778
0
-50
-100
-150
-200
sec 0.20 0.40 0.60 0.80 1.00 1.20 0.17
0.44
f 3.70  

Figure 6: The voltage of the faulty phase at SS 220kv BB 

Main : Graphs
E_C
250
-65.810
200
214.845
150 280.656
100 Min -216.741
50 Max 218.177
0
-50
-100
-150
-200
-250
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 0.61
0.94
f 3.06  

Figure 7: The voltage of phase‐C at SS 220kv BB 

    Page 10/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
E_B
250
-220.934
200
-19.304
150 201.630
100 Min -222.212
50 Max 224.155
0
-50
-100
-150
-200
-250
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 0.60
0.90
f 3.39  

Figure 8: The voltage of phase‐B at SS 220kv BB 

From previous figures (6, 7, and 8), the maximum temporary overvoltage is 224.2 KVp (phase 
voltage) then the rms value equal 158.53 KVrms (phase voltage) for one second. 

Maximum temporary overvoltage in the system (k) = 1.25 pu. 

r.m.s value of maximum power frequency voltage = Um / √3  = 141.45kVrms 

Therefore, phase‐earth power frequency over voltage = k x Um / √3 = 176.54kVrms 

While, the temporary overvoltage capability (TOV) of 214 kV surge arrester (SB214/20.5) for 
0.5 second is: 1.21*214KV=258.94KV and (TOV) of 214 kV surge arrester for one second is: 1.19 
*214KV=254.66KV (as per attachment document: B7005428). 

 As per above case study, it can be seen that temporary overvoltage capability (TOV) 
for  214  kV  surge  arrester  (SB214/20.5)  is  greater  than  maximum  temporary 
overvoltage 176.54 kVrms. 

According to contract specs: 

 214kv  SA  shall  withstand  (1.4*(245/√3))  =198kvrms  for  1sec,  while  214  kV  surge 
arrester TOV for one second is 254.66KV (as per attachment document: B7005428). 
 214kv SA shall withstand (1.8*(245/√3)) =254.61kvrms for 0.5sec, while 214 kV surge 
arrester TOV for 0.5sec is 258.94KV (as per attachment document: B7005428). 

    Page 11/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

220kv  HV  surge  arrester  (SB214/20.5)  with  rating  voltage  214kV  is  verified  for  above 
mentioned case. 

3.2 Temporary Overvoltage on neutral of 220 KV System: 
The voltage will be observed at the isolated neutral point of 220KV system (ES is opened) in 
case of single line to ground short circuit at SS 220KV bus (at t=0.5 second) followed by load 
rejection (at t=0.55  second). The observed voltage of neutral voltage is shown  in the below 
figure 9. 

Main : Graphs
E_N
100
0.000
75 8.545
50 8.545
Min -92.581
25
Max 93.556
0
-25
-50
-75
-100
sec 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 0.50
0.94
f 2.28  
Figure 9: Measured Voltage at isolated 220KV neutral of transformer 

As  per  the  previous  figure‐9,  the  maximum  temporary  overvoltage  observed  on  neutral  of 
220KV power transformer is 93.56 KVp (phase voltage) and the rms value equal 66.16 KVrms 
(phase voltage) for one second. 

Maximum temporary overvoltage in the system (k) = 0.52 pu. 

r.m.s value of maximum power frequency voltage = Um / √3  = 141.45 kVrms 

Therefore, phase‐earth power frequency over voltage = k x Um / √3 = 73.68kVrms 

While, the temporary overvoltage capability (TOV) of 108 kV surge arrester for 0.5 second is: 
1.21*108KV=130.68KV  and  (TOV)  of  108  kV  surge  arrester  for  one  second  is:  1.19 
*108KV=128.52KV (as per attachment document: B7005428). 

    Page 12/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

 As per above case study, it can be seen that temporary overvoltage capability (TOV) 
for  108  kV  surge  arrester  (SB108/20.5)  is  greater  than  maximum  temporary 
overvoltage 73.68 kVrms. 

According to contract specs: 

Rated voltage of 220kv neutral surge arrester of power transformer shall be 108kv. 

220kv neutral surge arrester of Power transformer (SB108/20.5) with rating voltage 108kV is 
verified. 

3.3 Temporary Overvoltage on neutral of 22 KV System: 
The voltage will be observed at the isolated neutral point of 22KV system (ES is opened) in case 
of single line to ground short circuit at SS 22KV bus (at t=0.5 second) followed by load rejection 
(at t=0.55 second). The observed voltage of neutral voltage is shown in the below figure 10  

Main : Graphs
E_N
17.321
20
18.943
1.622
10 Min -20.981
Max 20.195
0

-10

-20

sec 0.40 0.60 0.80 1.00 1.20 1.40 0.59


0.86
f 3.80  

Figure 10: Measured Voltage at isolated 22KV neutral of transformer 

As  per  the  previous  figure‐10,  the  maximum  temporary  overvoltage  observed  on  neutral  of 
22KV  power  transformer  is  20.2  KVp  (phase  voltage)  and  the  rms  value  equal  14.3  KVrms 
(phase voltage) for one second. 

Maximum temporary overvoltage in the system (k) = 1.125 pu. 

r.m.s value of maximum power frequency voltage = Um / √3  = 13.86 kVrms 

    Page 13/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Therefore, phase‐earth power frequency over voltage = k x Um / √3 = 15.6kVrms 

While, the temporary overvoltage capability (TOV) of 15 kV surge arrester for 0.5 second is: 
1.22*15KV=18.3KV and (TOV) of 15 kV surge arrester for one second is: 1.2 *15KV=18KV (as 
per attachment document: TR‐E 15011TO) 

 As per above case study, it can be seen that temporary overvoltage capability (TOV) 
for  15  kV  surge  arrester  (SBKC15/SL‐10.2)  is  greater  than  maximum  temporary 
overvoltage 15.6 kVrms. 

According to contract specs: 

Rated voltage of 22kv neutral surge arrester of power transformer earthing resistor shall be 
15kv. 

22kv  surge  arrester  of  power  transformer  earthing  resistor  (SBKC15/SL‐10.2)  with  rating 
voltage 15kV is verified. 

   

    Page 14/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

3.4 Temporary Overvoltage on 22 KV BB: 
3.4.1 TOV Observed on 22kv BB with 22kv Neutral Earthed System: 

The voltage will be observed on 22KV side of BB in case of single line to ground short circuit at 
22KV bus (at t=0.5 second) followed by load rejection (at t=0.55 second), where TR 22kv side 
neutral is earthed through resistance. The observed voltage of three phases are shown in the 
below figures 11, 12, and 13. 

Main : Graphs
E_A
20.0
16.405
15.0 -17.004
10.0 -33.410
Min -17.318
5.0
Max 17.317
0.0
-5.0
-10.0
-15.0
-20.0
sec 0.20 0.40 0.60 0.80 1.00 1.20 0.17
0.44
  f 3.70  

Figure 11: Voltage of faulty phase at 22 kv BB 

Main : Graphs
E_B
40
28.445
30 6.405
20 -22.040
Min -33.472
10
Max 33.420
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 0.57
0.90
f 3.06  

Figure 12: Voltage of phase‐B at 22 kv BB 

    Page 15/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
E_C
40
-30.414
30 -7.396
20 23.018
Min -34.655
10
Max 34.397
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 0.57
1.05
f 2.07  

Figure 13: Voltage of phase‐C at 22 kv BB 

From  previous  figures  11,  12,  and  13,  maximum  temporary  overvoltage  is  34.66kVp  (phase 
voltage) and the rms value equal 24.51 KVrms (phase voltage) for one second. 

Maximum temporary overvoltage in the system (k) = 1.92. 

r.m.s value of maximum power frequency voltage = Um / √3  = 13.86kVrms 

Therefore, phase‐earth power frequency over voltage = k x Um / √3 = 26.61kVrms 

While, the temporary overvoltage capability (TOV) of 24 kV surge arrester (on 22KV BB) for one 
second is: 1.18* 24KV=28.32KV. (TOV) of 24 kV surge arrester (on 22KV BB) for 0.5 second is: 
1.2* 24KV=28.8KV. It is assumed as 24kv capacitor bank SA (SB24/10.2) .  

 As per above case study, it can be seen that temporary overvoltage capability (TOV) 
for 24  kV BB surge arrester  is greater than maximum temporary overvoltage  26.61 
kVrms. 

According to contract specs: 

 24kv BB SA shall withstand (1.7*(24/ √3)) =23.56kvrms for 3sec, while 24 kV BB surge 
arrester TOV for three second is (1.16*24) =27.84KV. 

    Page 16/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

 24kv SA shall withstand (1.8*(24/ √3)) =24.94kvrms for 0.5sec, while 24 kV BB surge 
arrester TOV for 0.5sec is 28.8KV. 

3.4.2 TOV Observed on 22kv BB with 22kv Neutral Isolated System: 

The voltage will be observed on 22KV side of BB in case of single line to ground short circuit at 
22KV bus (at t=0.5 second) followed by load rejection (at t=0.55 second), where TR 22kv side 
neutral is isolated. The observed voltage of three phases are shown in the below figures 14, 15, 
and 16.  

Main : Graphs
E_A
20.0
16.305
15.0 -16.911
10.0 -33.216
Min -17.035
5.0
Max 17.035
0.0
-5.0
-10.0
-15.0
-20.0
sec 0.20 0.40 0.60 0.80 1.00 1.20 0.17
0.44
f 3.70  

Figure 14: Voltage of faulty phase at 22 kv BB 

Main : Graphs
E_B
40
-26.078
30 7.653
20 33.730
Min -34.011
10
Max 35.529
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 0.63
0.90
f 3.68  

Figure 15: Voltage of phase‐B at 22 kv BB 

    Page 17/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
E_C
40
-2.918
30 30.239
20 33.157
Min -35.896
10
Max 33.787
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 0.61
0.94
f 3.06  

Figure 16: Voltage of phase‐C at 22 kv BB 

From  previous  figures  14,  15,  and  16,  maximum  temporary  overvoltage  is  35.9kVp  (phase 
voltage) and the rms value equal 25.38 KVrms (phase voltage) for one second. 

Maximum temporary overvoltage in the system (k) = 1.99 pu. 

r.m.s value of maximum power frequency voltage = Um / √3  = 13.86kVrms 

Therefore, phase‐earth power frequency over voltage = k x Um / √3 = 27.58kVrms 

While, the temporary overvoltage capability (TOV) of 24 kV surge arrester (on 22KV BB) for one 
second is: 1.18* 24KV=28.32KV. (TOV) of 24 kV surge arrester (on 22KV BB) for 0.5 second is: 
1.2* 24KV=28.8KV. It is assumed as 24kv capacitor bank SA (SB24/10.2).  

 As per above case study, it can be seen that temporary overvoltage capability (TOV) 
for 24  kV BB surge arrester  is greater than maximum temporary overvoltage  27.58 
kVrms. 

According to contract specs: 

 24kv BB SA shall withstand (1.7*(24/ √3)) =23.56kvrms for 3sec, while 24 kV BB surge 
arrester TOV for three second is (1.16*24) =27.84KV. 
 24kv SA shall withstand (1.8*(24/ √3)) =24.94kvrms for 0.5sec, while 24 kV BB surge 
arrester TOV for 0.5sec is 28.8KV. 

    Page 18/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Surge arrester of voltage rating 24 kV of SWGR BB is verified. It is assumed as 24kv capacitor 
bank SA (SB24/10.2). 

3.5 Temporary Overvoltage on 22 KV TR Incomer: 
3.5.1 Temporary Overvoltage on 22 KV transformer side and 22kv Neutral is Earthed: 

The voltage will be observed on 22KV side of transformer in case of single line to ground short 
circuit at 22KV bus (at 0.5 second) followed by load rejection (at 0.55 second), where TR 22kv 
side neutral is earthed through resistance. The observed voltage of three phases are shown in 
figures 17, 18, and 19. 

Main : Graphs
E_A
20.0
16.416
15.0 -17.016
10.0 -33.431
Min -17.328
5.0
Max 17.328
0.0
-5.0
-10.0
-15.0
-20.0
sec 0.20 0.40 0.60 0.80 1.00 1.20 0.17
0.44
f 3.70  

Figure 17: Voltage of faulty phase of 22kv TR incomer 

    Page 19/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
E_B
40
28.444
30 6.402
20 -22.043
Min -33.470
10
Max 33.418
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 0.57
0.90
f 3.06  

Figure 18: Voltage of phase‐B of 22kv TR incomer 

Main : Graphs
E_C
40
-14.429
30 31.505
20 45.935
Min -34.002
10
Max 35.860
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 0.55
0.94
f 2.58  

Figure 19: Voltage of phase‐C of 22kv TR incomer 

From previous figures 17, 18, and 19, maximum temporary overvoltage is 35.86 kVp (phase 
voltage) and the rms value equal 25.35 KVrms (phase voltage) for one second. 

Maximum temporary overvoltage in the system (k) = 1.99 pu. 

r.m.s value of maximum power frequency voltage = Um / √3  = 13.86kVrms 

Therefore, phase‐earth power frequency over voltage = k x Um / √3 = 27.58kVrms 

    Page 20/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

While, the temporary overvoltage capability (TOV) of 24 kV incomer surge arrester (HI‐24G), 
(on  22KV  transformer  winding)  for  one  second  is:  1.25*  24KV=30  KV.  (TOV)  of  24  kV  surge 
arrester  (on  22KV  transformer  winding)  for  0.5  second  is:  1.27*  24KV=30.48KV.  (as  per 
attachment document: VARSIL‐HI Catalogue) 

 As per above case study, it can be seen that temporary overvoltage capability (TOV) 
for 24 kV TR incomer surge arrester is greater than maximum temporary overvoltage 
27.58 kVrms. 

According to contract specs: 

 24kv TR incomer SA shall withstand (1.7*(24/ √3)) =23.56kvrms for 3sec, while 24 kV TR 
incomer surge arrester TOV for three second is (1.225*24) =29.4KV (as per attachment 
document: VARSIL‐HI Catalogue).  
 24kv TR incomer SA shall withstand (1.8*(24/ √3)) =24.94kvrms for 0.5sec, while 24 kV 
TR  incomer surge  arrester TOV  for 0.5sec  is  30.48KV  (as  per  attachment  document: 
VARSIL‐HI Catalogue). 

3.5.2 Temporary Overvoltage on 22 KV transformer side and 22kv Neutral is Isolated: 

The voltage will be observed on 22KV side of transformer in case of single line to ground short 
circuit at 22KV bus (at 0.5 second) followed by load rejection (at 0.55 second), where TR 22kv 
side neutral is isolated. The observed voltage of three phases are shown in figures 20, 21, and 
22. 

    Page 21/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
E_A
20.0
16.316
15.0 -16.922
10.0 -33.237
Min -17.046
5.0
Max 17.045
0.0
-5.0
-10.0
-15.0
-20.0
sec 0.20 0.40 0.60 0.80 1.00 1.20 0.17
0.44
f 3.70  

Figure 20: Voltage of faulty phase of 22kv TR incomer 

Main : Graphs
E_B
40
-30.838
30 7.648
20 38.486
Min -34.009
10
Max 36.061
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 0.60
0.90
f 3.40  

Figure 21: Voltage of phase‐B of 22kv TR incomer 

    Page 22/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
E_C
40
-2.913
30 30.237
20 33.150
Min -35.894
10
Max 33.786
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 0.61
0.94
f 3.06  

Figure 22: Voltage of phase‐C of 22kv TR incomer

From previous figures 20, 21, and 22, maximum temporary overvoltage is 36.01 kVp (phase 
voltage) and the rms value equal 25.45 KVrms (phase voltage) for one second. 

Maximum temporary overvoltage in the system (k) = 2 pu. 

r.m.s value of maximum power frequency voltage = Um / √3  = 13.86kVrms 

Therefore, phase‐earth power frequency over voltage = k x Um / √3 = 27.72kVrms 

While, the temporary overvoltage capability (TOV) of 24 kV incomer surge arrester (HI‐24G), 
(on  22KV  transformer  winding)  for  one  second  is:  1.25*  24KV=30  KV.  (TOV)  of  24  kV  surge 
arrester  (on  22KV  transformer  winding)  for  0.5  second  is:  1.27*  24KV=30.48KV  (as  per 
attachment document: VARSIL‐HI Catalogue).  

 As per above case study, it can be seen that temporary overvoltage capability (TOV) 
for 24 kV TR incomer surge arrester is greater than maximum temporary overvoltage 
27.72 kVrms. 

According to contract specs: 

 24kv TR incomer SA shall withstand (1.7*(24/ √3)) =23.56kvrms for 3sec, while 24 kV TR 
incomer surge arrester TOV for three second is (1.225*24) =29.4KV (as per attachment 
document: VARSIL‐HI Catalogue). 

    Page 23/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

 24kv TR incomer SA shall withstand (1.8*(24/ √3)) =24.94kvrms for 0.5sec, while 24 kV 
TR  incomer surge  arrester TOV  for 0.5sec  is  30.48KV  (as  per  attachment  document: 
VARSIL‐HI Catalogue). 

Surge arrester of voltage rating 24 kV of TR incomer (HI‐24G) is verified.

3.6 Temporary Overvoltage on Tertiary Winding: 
3.6.1 Case‐1: 

The voltage will be observed on tertiary winding of power transformer during short circuit on 
22KV system at 0.5 second followed by load rejection at 0.55 second. 

Main : Graphs
E_TE
40
3.444
30 -22.367
20 -25.811
Min -23.526
10
Max 23.525
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 0.61
0.94
f 3.06  

Figure 23: Voltage signal on 22KV tertiary winding 

As shown in previous figure‐23, the maximum peak value of temporary overvoltage observed 
on tertiary winding is 23.52KVp that equal 16.63KVrms. 

3.6.2 Case‐2: 

The voltage will be observed on tertiary winding of power transformer during short circuit on 
tertiary winding at 0.5 second followed by load rejection at 0.55 second as worst case. 

    Page 24/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
E_A
20.0
0.433
15.0 4.995
10.0 4.562
Min -17.867
5.0
Max 17.866
0.0
-5.0
-10.0
-15.0
-20.0
sec 0.20 0.40 0.60 0.80 1.00 1.20 0.18
0.45
f 3.72  

Figure 24: Voltage of Ph‐A of Tertiary Winding 

Main : Graphs
E_B
40
-30.695
30 21.133
20 51.828
Min -31.671
10
Max 31.679
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 0.65
0.90
f 3.97  

Figure 25: Voltage of Ph‐B of Tertiary Winding 

    Page 25/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
E_C
40
-12.553
30 -31.483
20 -18.929
Min -31.675
10
Max 31.712
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 0.62
0.81
f 5.45  

Figure 26: Voltage of Ph‐C of Tertiary Winding 

As shown in previous Figures (23, 24, 25, and 26), maximum observed temporary overvoltage 
on tertiary winding is 31.7KVp that equal 22.42KVrms. 

Maximum temporary overvoltage in the system (k) = 1.76 pu. 

r.m.s value of maximum power frequency voltage = Um / √3  = 13.86kVrms. 

Therefore, phase‐earth power frequency over voltage = k x Um / √3 = 24.4 kVrms 

While, the temporary overvoltage capability (TOV) of 24 kV surge arrester (HI‐24G), (on 22KV 
TR tertiary winding) for one second is: 1.25* 24KV=30 KV. (TOV) of 24 kV surge arrester (on 
22KV  TR  tertiary  winding)  for  0.5  second  is:  1.27*  24KV=30.48KV  (as  per  attachment 
document: VARSIL‐HI Catalogue).  

As per above case study, it can be seen that temporary overvoltage capability (TOV) for 24 
kV TR tertiary winding surge arrester is greater than maximum temporary overvoltage 24.4 
kVrms. 

According to contract specs: 

 24kv TR tertiary SA shall withstand (1.7*(24/ √3)) =23.56kvrms for 3sec, while 24 kV TR 
tertiary surge arrester TOV for three second is (1.225*24) =29.4KV(as per attachment 
document: VARSIL‐HI Catalogue). 

    Page 26/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

 24kv TR tertiary SA shall withstand (1.8*(24/ √3)) =24.94kvrms for 0.5sec, while 24 kV 
TR  tertiary  surge  arrester  TOV  for  0.5sec  is  30.48KV  (as  per  attachment  document: 
VARSIL‐HI Catalogue). 

Surge arrester of voltage rating 24 kV of TR tertiary winding (HI‐24G) is verified. 

3.7 Temporary Overvoltage on 22 KV Capacitor Bank: 

The voltage will be observed on 22KV of capacitor bank in case of single line to ground short 
circuit at 22KV bus (at 0.5 second) followed by load rejection (at 0.55 second). The observed 
voltage of three phases are shown in the below figures 27, 28, and 29. 

Main : Graphs
E_A
20.0
16.748
15.0 -17.012
10.0 -33.760
Min -17.030
5.0
Max 17.006
0.0
-5.0
-10.0
-15.0
-20.0
sec 0.20 0.40 0.60 0.80 1.00 1.20 0.17
0.44
f 3.70  

Figure 27: Voltage of the faulty phase of 22kv shunt capacitor 

    Page 27/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
E_B
40
22.009
30 10.417
20 -11.592
Min -32.677
10
Max 32.641
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 0.57
0.90
f 3.06  

Figure 28: Voltage of phase‐B of 22kv shunt capacitor 

Main : Graphs
E_C
40
-7.830
30 31.341
20 39.172
Min -33.373
10
Max 33.787
0
-10
-20
-30
-40
sec 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 0.57
0.94
f 2.73  

Figure 29: Voltage of phase‐C of 22kv shunt capacitor 

From  previous  figures  (27,  28,  and  29),  the  maximum  temporary  overvoltage  is  33.78kVp 
(phase voltage) and the rms value equal 23.88 KVrms (phase voltage) for one second. 

Maximum temporary overvoltage in the system (k) = 1.88 pu. 

r.m.s value of maximum power frequency voltage = Um / √3  = 13.86kVrms 

Therefore, phase‐earth power frequency over voltage = k x Um / √3 = 26kVrms 

    Page 28/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

While,  the  temporary  overvoltage  capability  (TOV)  of  24  kV  surge  arrester  (SB24/10.2),  (on 
22KV  capacitor  bank)  for  one  second  is:  1.18*24KV=28.32KV.  (TOV)  of  24  kV  surge  arrester 
(SB24/10.2), (on 22KV capacitor bank) for 0.5 second is: 1.2* 24KV=28.8KV (as per attachment 
document: B7004269)

 As per above case study, it can be seen that temporary overvoltage capability (TOV) 
for  24  kV  capacitor  bank  surge  arrester  is  greater  than  maximum  temporary 
overvoltage 26 kVrms. 

According to contract specs: 

 24kv capacitor bank SA shall withstand (1.7*(24/ √3)) =23.56kvrms for 3sec, while 24 
kV capacitor bank SA TOV for three second is (1.16*24) =27.84KV (as per attachment 
document: B7004269). 
 24kv capacitor bank SA shall withstand (1.8*(24/ √3)) =24.94kvrms for 0.5sec, while 24 
kV  capacitor  bank  SA  TOV  for  0.5sec  is  28.8KV  (as  per  attachment  document: 
B7004269). 

Surge arrester of voltage rating 24 kV of Capacitor bank (SB24/10.2) is verified. 

   

    Page 29/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

4 Energy Absorption Capability Check: 

The  energy  absorbed  by  the  Metal  Oxide  Surge  Arrester  is  estimated  based  on 
procedure/formulas described IEC 60099‐5, clause 3.2.3.3. 

 
4.1 Arrester of 220KV System: 

Minimum absorbed energy due to transient overvoltage is arising from lightning strokes to 
overhead line conductors with high insulation level or back‐flashovers close to the arrester 
location can be estimated by the following formula.  

2 1 ln 2 /  

  Where: 

      is the lightning impulse protection level of the arrester; 

      is the negative flashover voltage of the line insulation (CFO); 

      is the line surge impedance; 

      is the number of lines connected to the arrester; 

  is the equivalent duration of the current of a lightning flash including 
first and subsequent strokes. Typical value 3 × 10–4 s. 

Surge Arrester Rating    214KV 

Critical Flashover Voltage of Insulator for 220 KV 
  1050KV 
Grids 

Arrester Lightning Impulse Prot. Level    1368KV 

    Page 30/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

No. of lines connected to arrester    1 

Duration of a lightning flash current    3 × 10–4 s 

Line Surge Impedance as per IEC‐ 60099‐4   0.5 ∗   107 Ω 

Lightning Min. Required Energy  W  558.8 KJ 

Min. KJ Energy per Surge KV Rating  2.61 KJ/KV 

So the arrester with 10KJ/KV capability can be selected. 

4.2 22kv Transformer Medium Voltage Side, 22kv Transformer Tertiary Side, BB, and 
Capacitor Bank Arresters: 

Minimum absorbed energy due to transient overvoltage is arising from the switching of cables 
and capacitor banks with can be calculated using the following equation; 

1
3 √2  
2

Where: 

    C   is the capacitance of the bank or the cable. That equal 60µf. 

U o   is the phase‐to‐earth operating voltage peak. Equal 17.96KV. 

Ur   is the rated voltage of the arrester (r.m.s. value). That equal 24KV. 

The minimum absorbed energy in this case = 52.560KJ that equal 2.19KJ/KV, so the arrester 
with 2.5KJ/KV can be selected. 

    Page 31/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

4.3 220kv and 22kv Transfomer Nuetral Surge Arresters: 

As per IEC‐ 60099‐5, section‐5, line discharge energy absorption capability of neutral arresters 
should be at least the same as required for the phase‐to‐earth arresters or higher. 

220kv transformer neutral SA with 10KJ/KV capability can be selected. 

22kv transformer neutral SA with 2.5KJ/KV capability can be selected. 

4.4 Conclusion: 

Absorbed energy by arresters can be summarized as following. 

Actual absorbed 
Arrester  energy  Recommendation 
(KJ/KV) 
Arrester of 220KV System  2.61  10KJ/KV capability can be selected 

220KV Transformer Neutral Arrester  As per Sec. 4.3  10KJ/KV capability can be selected 

22KV Transformer Neutral Arrester  As per Sec. 4.3  2.5KJ/KV can be selected. 


Transformer Medium Voltage Side/ 
2.19  2.5KJ/KV can be selected. 
Tertiary side Arresters 
22KV bus bar Voltage Side Arrester  2.19  2.5KJ/KV can be selected. 

Capacitor Bank Arrester  2.19  2.5KJ/KV can be selected. 

   

    Page 32/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

5 Slow Front Overvoltages: 

Slow front overvoltages due to switching are of particular importance for arresters protecting 
equipments in Range‐II (Um>245kVrms, L‐L). Hence switching overvoltages are analyzed in the 
present study for 220 kV system. Switching over voltages becomes important, increasing with 
higher system voltages. Over voltage may cause flashover and serious damage to equipment 
and there by endanger supply of power to users. It is essential, to prevent this by proper co‐
ordination of surge arrester with the insulation. 

5.1  Switching on 220KV System: 

CASE‐1:  

Energization line of Matrooh s/s to Marassi circuit line from Matrooh substation end, without 
surge arresters at 0.55 sec. The voltage wave form at the entrance of GIS is shown in figure 30, 
maximum fundamental component reaches 199.8KVp that equal 141.28KVrms,  that represent 
1.12p.u. There is voltage oscillation. 

Voltage at GIS entry


3-phase voltage
400
0.476
300 166.588
166.113
200
Min -199.802
100 Max 195.411

-100

-200

-300
x 0.540 0.550 0.560 0.570 0.580 0.590 0.600 0.610 0.548
0.583
f 28.520  

Figure 30: Maximum observed Phase‐earth voltages for case (1) 

    Page 33/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

CASE‐2:  

Energization  line  of  Matrooh  s/s  to  Marassi  circuit  line  from  Matrooh  substation  end,  with 
installation of surge arrester at 0.55 sec. The maximum voltage wave form is shown in figure 
31,  maximum  fundamental  component  reaches  181.7KVp  that  equal  128.48KVrms  that 
represent 1.01p.u. The voltage oscillation is damped through half cycle. 

Voltage at GIS entry


3-phase voltage
400
0.283
300 97.759
97.476
200
Min -180.722
100 Max 181.377

-100

-200

-300
x 0.530 0.540 0.550 0.560 0.570 0.580 0.590 0.600 0.610 0.620 0.547
0.568
f 46.927  

Figure 31:  Maximum observed Phase‐earth voltages for case (2) 

CASE‐3:  

Energization line of Elomid s/s to Marassi circuit line from Elomid substation end, without surge 
arresters  at  0.55  sec.  The  maximum  voltage  wave  form  is  shown  in  figure  32,  maximum 
fundamental component reaches 185.6KVp that equal 131.24KVrms that represent 1.03p.u. 
There is voltage oscillation. 

    Page 34/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Voltage at GIS entry


3-phase voltage
400
1.163
300 156.065
154.902
200
Min -185.585
100 Max 182.345

-100

-200

-300
x 0.530 0.540 0.550 0.560 0.570 0.580 0.590 0.600 0.610 0.620 0.548
0.567
f 54.458  

Figure 32: Maximum observed Phase‐earth voltages for case (3) 

CASE‐4:  

Energization  line  of  Elomid  s/s  to  Marassi  circuit  line  from  Elomid  substation  end,  with 
installation of surge arrester at 0.55 sec. The maximum voltage wave form is shown in figure 
33,  maximum  fundamental  component  reaches  179.65KVp  that  equal  127.03KVrms  that 
represent 1p.u. The voltage oscillation is damped through half cycle. 

Voltage at GIS entry


3-phase voltage
400
0.259
300 155.330
155.071
200
Min -179.580
100 Max 179.654

-100

-200

-300
x 0.530 0.540 0.550 0.560 0.570 0.580 0.590 0.600 0.610 0.620 0.548
0.567
f 54.458  

Figure 33: Maximum observed Phase‐earth voltages for case (4) 

5.2 Conclusion: 

Line SA arresters limits switching overvoltage and its oscillations. 

    Page 35/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

5.3 Capacitor Bank Switching Study: 

It is recommended by IEC 60099‐5 that Capacitor bank study to be independent to the entire 
system.  

5.3.1 Energizing the First Leg of a Capacitor Bank 

Capacitor banks are used in power systems to control bus voltages. The purpose of this study 
is to study the system behaviour when the first leg of a capacitor bank is energized. 

System is represented by a Thévanin voltage source, voltage source impedance corresponding 
to the fault level of the system, as measured from the capacitor bank location. 

The  voltage  will  be  observed  on  22KV  of  capacitor  bank  in  case  of  energizing  first  leg  of 
capacitor bank (at 0.5 second) without connecting SA. The observed voltage of three phases 
are shown in the below figure 35, maximum Phase voltage is 27.61KVp and the maximum rms 
value is 19.52KVrms. 

Capacitor bank switching study model 
MOV1

MOV

Thevanin Voltage Source


22 kV, 50 Hz
RLC

Vcap Vcs
B1

B2

B3

Vcs Vcs

11.83 [uF] 23.7 [uF] 23.7 [uF]


0.00005 [H] 0.00005 [H] 0.00005 [H]  

Figure 34:  Capacitor bank switching study model 

    Page 36/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
Vcs
30

20

10

0
(kV)

-10

-20

-30

-40
sec 0.490 0.500 0.510 0.520 0.530 0.540 0.550 0.560

Figure 35: 22kv BB phase voltage in case of energizing first leg of capacitor bank 

The  voltage  will  be  observed  on  22KV  of  capacitor  bank  in  case  of  energizing  first  leg  of 
capacitor bank (at 0.5 second) and SA is installed. The observed voltage of three phases are 
shown in the below figure 36, maximum Phase voltage is 20KVp and the maximum rms value 
is 14.14KVrms. Oscillation is damped in one cycle. 

Main : Graphs
Vcs
30

20

10

0
(kV)

-10

-20

-30

-40
sec 0.470 0.480 0.490 0.500 0.510 0.520 0.530

Figure 36: 22kv BB phase voltage in case of energizing first leg of capacitor bank and SA installed 

    Page 37/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

5.3.2 Back‐to‐Back Capacitor Switching Study: 

In a back‐to‐back capacitor switching study after an energized capacitor reaches steady‐state, 
another capacitor in the bank is energized. 

Case‐1 

The observed voltage of three phases are shown in the below figure 37 in case of capacitor 
bank SA is disconnected. Capacitor bank first leg is energized at t=0sec, Second leg is energized 
at 0.5 sec, maximum observed phase voltage is 24.55KVp, maximum rms value is 17.36KVrms. 

Main : Graphs
Vcs
30

20

10

0
(kV)

-10

-20

-30

-40
sec 0.480 0.490 0.500 0.510 0.520 0.530 0.540 0.550 0.560 0.570

Figure 37: Back to back switching case‐1 

The observed voltage of three phases are shown in the below figure 38 in case of capacitor 
bank SA is installed. Capacitor bank first leg is energized at t=0sec, Second leg is energized at 
0.5  sec,  maximum  observed  phase  voltage  is  21KVp,  maximum  rms  value  is  14.85KVrms. 
Oscillation recovered in one cycle. 

    Page 38/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Main : Graphs
Vcs
30

20

10

0
(kV)

-10

-20

-30

-40
sec 0.480 0.490 0.500 0.510 0.520 0.530 0.540 0.550 0.560

Figure 38: Back to back switching case‐1, SA installed 

Case2 

The observed voltage of three phases are shown in the below figure 39 in case of capacitor 
bank SA is disconnected. Capacitor bank first and second legs are energized at t=0sec, Third leg 
is energized at 0.5 sec, maximum observed phase voltage is 22.55KVp, maximum rms value is 
15.95KVrms. 

Main : Graphs
Vcs
30

20

10

0
(kV)

-10

-20

-30

-40
sec 0.470 0.480 0.490 0.500 0.510 0.520 0.530 0.540 0.550 0.560 0.570

Figure 39: Back to back switching case‐2 

    Page 39/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

The observed voltage of three phases are shown in the below figure 40 in case of capacitor 
bank SA is installed. Capacitor bank first and second legs are energized at t=0sec, Third leg is 
energized  at  0.5  sec,  maximum  observed  phase  voltage  is  20.2KVp,  maximum  rms  value  is 
14.28KVrms. 

Main : Graphs
Vcs
30

20

10

0
(kV)

-10

-20

-30

-40
sec 0.460 0.470 0.480 0.490 0.500 0.510 0.520 0.530 0.540 0.550 0.560 0.570

Figure 40: Back to back switching case‐2, SA installed 

5.4 Conclusion: 

Capacitor banks surge arresters limits switching overvoltage and its oscillations. 

   

    Page 40/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

6 Fast Transient Phenomena: 

One of the primary causes of such transient is the lightning stroke to the transmission lines or 
on tower top and associated back flashovers. The lightning over voltages are caused by either 
shielding failures or back flashovers of the tower insulation on the transmission lines.   Both 
direct  stoke  to  the  phase  conductor  as  well  as  the  back  flashover  cases  are  included  in  this 
report. 

6.1 Direct Strokes to Phase Conductors: 

Direct  strokes  to  the  phase  conductors  of  a  shielded  transmission  line  occur  typically  when 
lightning  strokes  of  low  magnitude  (a  few  kA)  bypass  the  overhead  shield  wires  (shielding 
failure). Lightning strokes of amplitude below the critical shielding current, generally less than 
20kA, can bypass the overhead shield wires and strike directly on the phase conductors.  Direct 
strokes to the  substations are ignored  usually, since the substation is perfectly shielded, via 
shield wires or lightning masts near the sub‐station. 

6.2 Calculation of Maximum Current, Im for Direct Lightning Stroke 

The peak value of the lightning current for the direct stroke depends on the height of ground 
wire and its protection angle.  The current peak can be estimated according to the reference 
book  by  Andrew  R.  Hileman,  Insulation  Coordination  for  Power  Systems,  Taylor  &  Francis 
Group, LLC. 

Table 2: Calculation of Maximum Current, Im for Direct Lightning Stroke 

Calculation of Maximum Current, Im for Direct Lightning Stroke 
R =AIb  Striking Distance
rc =Ac Ib  Striking Distance r to phase conductors  Ac=7.1 & b=0.75 
rg = Ag Ib  Striking Distance r to earth or ground  Ag=6.4 & b=0.75 
h(m)  Average height of ground wire, h  45.05 
y(m)  Average height of phase wire, y  30.7
a(m)  a is horizantal distance between ground and conductor wires  3.75 
r = rc/rg  r = rc/rg  1.109 
α(degree)  Angle, α=tan‐1(a/(h‐y)) 14.65
rgm  rgm = (h+y)/(2 x [1‐ rsinα])   52.64 
Im (KA)  Im=(rgm/A)(1/b)  16.6 

    Page 41/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Sm(kA/μsec)  Sm, Maximum steepness= 12* I0.171  22.62


tf(μsec)  tf, the time to crest  = 1.77 * I0.188  3.37 

The lightning tail duration is fixed to 100 µs, irrespective of the crest‐current value. 

Figure 41:Finding Im and the perfect shielding angle 

6.3 Back Flashover Stroke Current: 

Back flashover occurs when lightning strikes the tower  or the shield wire, and  the resultant 


tower top voltage is large enough to cause flashover of the line insulation from the tower to 
the  phase  conductor.    When  back  flashover  occurs,  a  part  of  the  surge  current  will  be 
transferred to the phase conductors through the arc across the insulator strings. 

The distribution of negative lightning current amplitude recommended by CIGRE for lightning 
statistical studies is shown in Fig 43. The probability of back flash over is based on this Graph 
and explained in the following section. The formulae used for the calculations are based on 
Eriksson  A.  and  Weck  K,  Simplified  procedures  for  determining  representative  substation 
impinging lightning  overvoltages, CIGRÉ Paper No. 33‐16, Paris, 1988. 

    Page 42/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

 
Figure 42:Annual frequency of thunderstorm days in the world 

Figure 43: Cumulative frequency distribution of lightning current 

    Page 43/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Table 3: Back flashover current 
Lightning Current  for backflashover Stroke Im 
BIL (Basic Impulse Level)  1368 
 kV 
Up (Surge arrester lightning protection level (at 20kA)  536 
Uwc  (Station Coordination Withstand Voltage)=BIL/1.2  1140  kV 

Up  Surge arrester lightning protection level (at 20kA)  536  kV 

K  Corona damping constant  1.5 X 10‐6  μs/kV.m 

L  longest possible open bus connection  100  m 

v  surge velocity  2.90 X 108  m/s 

surge travel time along the longest possible open bus 
T  3.448 X 10‐7  s 
connection in the station = L/v 

X  critical lengths = 2 * T / (K* (Uwc‐Up))  761.21  m 

Hgw  Height of ground wire  45.05  m 


Hsag  Sag of ground wire  7  m 

H  Effective tower height (Hgw‐(2(Hsag/3))  40.38  m 

Ra  14 * H 0.6  128.78  m 


b  distance between shield wires  0  m 
A  (2*Ra + b) * X * 10‐3  196.06  m 2 

Td   Number of lightning flashes to ground (as in figure 42)  10    

Ng  Avg. annual ground flash density = 0.04 Td^1.25  0.711    

Nsx  no. of flashes to the line within the critical distance = Ng * A  139.46    

target design failure rated in % per year (400 years between 
Nd  0.25    
failures) 
(Nd/Nsx)
Eriksson A. and Weck K, Simplified procedures for determining 
P(I)  0.179   % 
representative substation impinging lightning  overvoltages, 
CIGRÉ Paper No. 33‐16, Paris, 1988. Equation‐11 
 Lightning current corresponding to P(I) (approximately from the 
200  kA 
curve). Figure 43. 
Sm, Maximum steepness= 6.5 * I 0.376  55.57  kA/µsec 
tf, the time to crest = 0.906 * I 0.411  9  µsec 

The lightning tail duration is fixed to 100 µs, irrespective of the crest‐current value. 

    Page 44/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

6.4 Modelling of Various Elements of the Network for PSCAD: 

Attachments show a model used for the PSCAD study to simulate the lightning over voltage 
study. 

6.4.1 Transmission line: 

The transmission lines are modelled as Frequency dependent model for the transmission line 
are used for the analysis. 

6.4.2 Tower Model: 

The steel towers are usually represented by a surge impedance and the velocity of propagation. 
The tower footing resistance varies from 10 Ohms to 100 Ohms. The surge impedance of the 
tower depends on the geometry of the structure. The travel time is obtained by dividing the 
height of the tower by the speed of light. 

The  insulators  are  represented  by  voltage  dependent  switches  in  parallel  with  capacitors 
connected between the phase conductors to the tower. The capacitors simulate the coupling 
effects  of  conductors  to  the  tower  structure.  Typical  capacitance  values  of  suspension 
insulators are of the order of 80 pF/unit 

   

Figure 44: Tower modelling. 

    Page 45/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

High magnitude of lightning current, which flows through the ground resistance, reduces the 
resistance  significantly  below  the  low‐current  values.  When  the  gradient  exceeds  a  critical 
gradient  E0,  breakdown  of  the  soil  occurs.  When  the  current  increases,  streamers  are 
generated, evaporating the soil moisture and producing arcs. Within the streamer and arcing 
zones,  the  resistivity  decreases  from  its  original  value.  When  the  limit  approaches  zero,  it 
becomes a perfect conductor. 

So we can assume the footing resistance of tower is 10 ohm as worst. 

6.4.3 Power Transformer: 

Power  transformer  is  modelled  by  its  typical  capacitance  recommended  by  ‘’Transients  in 
electrical systems: analysis, recognition, mitigation. J.C.Das, MC Graw Hill, 2010’’.  

6.4.4 Surge Arresters: 

The surge arrester is a device with nonlinear volt‐ampere characteristics used to clamp the 
bus voltage to the specified limit. ‘’MODELING OF METAL OXIDE SURGE ARRESTERS, IEEE 
WORKING GROUP 3.4.11, Transactions on Power Delivery, Vol. 7 No.1, January 1992’’  

 
Figure 45:Frequency dependent surge arrester model proposed by IEEE working 

Table 4: Arrester modelling 
ARRESTER MODELING 
d (m)  Height of arrestor  3.08 
N  No.of parallel clomuns of disks  1 
L0 (uH)  .2d/n   0.616 
L1 (uH)  15d/n  15.4 
R0(ohm)  100d/n  308 
R1(ohm)  65d/n  200 
C (pF)  100n/d  32.47 

    Page 46/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

6.4.5 Stroke Current Wave shape: 

The stroke current waves (Direct and Back flash stroke) are derived as per table 2&3.  

6.4.6 Other Substation Equipment: 

The  other  substation  equipment  such  as  circuit  breakers,  instrument  transformers  and  the 
stepdown  transformers  are  represented  by  the  stray  capacitance  to  ground.  Typical 
capacitance values of substation equipment 

Table 5: The Capacitance to Ground on Various Substation Equipment 

 
 

    Page 47/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

6.5 Study and Results: 
6.5.1 Direct stroke. 

Lightning strike directly to phase conductor (phase A) the closest tower to station. The lightning 
with  expected  crest  value  as  evaluated  previously  in section‐6.2  (16.6KA)  with  time  to  crest 
(rise  time)  3.37µs  and  tail  time  100µs  as  shown  in  figure  46,  and  the  phase  voltage  will  be 
observed at GIS entrance, and power transformer primary (on phase A). 

 
Ligthning : Graphs
Surge
18.0

16.0

14.0

12.0

10.0
y

8.0

6.0

4.0

2.0

0.0
x 0.00 0.02m 0.04m 0.06m 0.08m 0.10m 0.12m

Figure 46: Lightning current (direct stroke)

CASE‐1: Line circuit breaker contacts are closed and all surge arresters are disconnected. 

observed over voltage on enterance of GIS


Phase A
22.5k
168.325
20.0k 20982.404
20814.080
17.5k
Min 167.767
15.0k Max 21013.1...

12.5k
KV

10.0k

7.5k

5.0k

2.5k

0.0
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.00m
0.12m
f 8484320....  
Figure 47: Case‐1 observed voltage at GIS incomer 

    Page 48/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
22.5k
4316.680
20.0k 19636.242
17.5k 15319.562
Min 4316.555
15.0k
Max 21013.1...
12.5k
10.0k
7.5k
5.0k
2.5k
0.0
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.0000
0.0010
f 1019.6817  
Figure 48: Case‐1 observed voltage at TR HV side 

As noted in previous figures 47 and 48, overvoltage at GIS entry will be 21013KVpeak and at TR 
HV side is 21013KVpeak while withstand value (LIWL) of GIS not more than 1368KVpeak as per 
specs.  

CASE‐2: Line circuit breaker contacts are closed and line surge arresters installed. 

observed over voltage on enterance of GIS


Phase A
600
164.671
500 35.418
-129.252
400 Min -127.296
Max 539.282
300

200
KV

100

-100

-200
x 0.00 0.05m 0.10m 0.15m 0.20m 0.25m 0.30m 0.00m
0.12m
f 8484320....  

Figure 49: Case‐2 observed voltage at GIS incomer 

    Page 49/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
600
523.449
500 -26.324
-549.773
400
Min -127.492
300 Max 539.139

200

100

-100

-200
x 0.00 0.05m 0.10m 0.15m 0.20m 0.25m 0.30m 0.00m
0.07m
f 14115942....  

Figure 50: Case‐2 observed voltage at TR HV side 

As shown in previous figures 49 and 50, peak value of overvoltage that will be observed on 
phase A during the direct stroke not more than 539KVpeak at GIS entrance and TR HV side that 
represent 39.4% of BIL. 

CASE‐3:  Line  circuit  breaker  contacts  are  closed  and  line  and  TR  HV  side  surge  arresters 
installed. 

observed over voltage on enterance of GIS


Phase A
600
490.934
500 25.009
-465.925
400 Min -98.993
Max 495.492
300

200
KV

100

-100

-200
x 0.00 0.05m 0.10m 0.15m 0.20m 0.25m 0.30m 0.00m
0.12m
f 8589065....  

Figure 51: Case‐3 observed voltage at GIS incomer 

    Page 50/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
600
490.774
500 -13.106
-503.880
400
Min -99.191
300 Max 495.316

200

100

-100

-200
x 0.00 0.05m 0.10m 0.15m 0.20m 0.25m 0.30m 0.00m
0.07m
f 14115942....  

Figure 52: Case‐3 observed voltage at TR HV side 

As shown in previous figures 51 and 52, the peak value of overvoltage that will be observed on 
phase  A  during  the  direct  stroke  not  more  than  495.5KVpeak  that  represent  36.2%  of  BIL. 
Voltage reduction is gained when both line and TR SA are installed compared to case‐2.  

CASE‐4: Line circuit breaker contacts are opened and all surge arresters are disconnected. 

observed over voltage on enterance of GIS


Phase A
90.00k
2498.837
80.00k 87339.724
84840.887
70.00k
Min 2498.704
60.00k Max 87705.7...

50.00k
KV

40.00k

30.00k

20.00k

10.00k

0.00
x 0.00000 0.00010 0.00020 0.00030 0.00040 0.00050 0.00060 0.00070 0.00080 0.00090 0.00100 0.00000
0.00012
f 8589.065...  

Figure 53: Case‐4 observed voltage at GIS incomer 

    Page 51/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
7.0k
40.034
6.0k 1566.222
1526.188
5.0k Min 40.032
Max 1566.195
4.0k

3.0k

2.0k

1.0k

0.0
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.00m
0.07m
f 14115942....  

Figure 54: Case‐4 observed voltage at TR HV side 

As noted in previous figures 53 and 54, overvoltage at GIS entry will be 88705.7KVpeak and 
6500 KVpeak for TR HV side, while withstand value (LIWL) of GIS not more than 1368KVpeak 
as per specs. 

CASE‐5: Line circuit breaker contacts are opened and line surge arresters installed. 

observed over voltage on enterance of GIS


Phase A
600
0.5563k
500 0.0392k
-0.5171k
400 Min -0.1711k
Max 0.5635k
300

200
KV

100

-100

-200
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.00000
0.00012
f 8589.065...  

Figure 55: Case‐5 observed voltage at GIS incomer 

    Page 52/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
25.0
0.0089k
20.0 -0.0010k
-0.0099k
15.0 Min -0.0050k
Max 0.0233k
10.0

5.0

0.0

-5.0

-10.0
x 0.00000 0.00010 0.00020 0.00030 0.00040 0.00050 0.00060 0.00070 0.00080 0.00090 0.00100 0.0000
0.0001
f 14115.9420  

Figure 56: Case‐5 observed voltage at TR HV side 

As shown in previous figures 55 and 56 the peak value of overvoltage that will be observed on 
phase  A  during  the  direct  stroke  not  more  than  563.5KVpeak  that  represent  41.2%  of  BIL. 
Voltage at TR HV side is reduced to 23.3KVpeak when compared to case‐4. 

CASE‐6:  Line  circuit  breaker  contacts  are  opened  and  line  and  TR  HV  side  surge  arresters 
installed. 

observed over voltage on enterance of GIS


Phase A
600
556.300
500 39.193
-517.107
400 Min -171.056
Max 563.549
300

200
KV

100

-100

-200
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0000
0.0001
f 8589.0653  

Figure 57: Case‐6 observed voltage at GIS incomer 

    Page 53/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
15.0
7.003
-1.991
10.0
-8.994
Min -12.009
5.0
Max 13.971

0.0

-5.0

-10.0

-15.0
x 0.00000 0.00010 0.00020 0.00030 0.00040 0.00050 0.00060 0.00070 0.00080 0.00090 0.00100 0.00000
0.00007
f 14115.942...  

Figure 58: Case‐6 observed voltage at TR HV side 

As shown in previous figures 57 and 58 the peak value of overvoltage that will be observed on 
phase  A  during  the  direct  stroke  not  more  than  563.5KVpeak  that  represent  41.2%  of  BIL. 
Voltage at TR HV side is reduced to 13.97KVpeak when compared to case‐4 and 5. 

    Page 54/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

6.5.2 Back Flashover Stroke: 

The lightning will strike the ground wire and there is flashover occur on insulator of stroked 
tower with wave 9/100µs and crest value 200KA as shown in figure 59. 

Ligthning : Graphs
Surge
200

175

150

125

100
y

75

50

25

0
x 0.000 0.010m 0.020m 0.030m 0.040m 0.050m 0.060m 0.070m 0.080m 0.090m 0.100m

Figure 59: Back Flash Stroke Wave Form 

CASE‐1: Line circuit breaker contacts are closed and all surge arresters are disconnected. 

observed over voltage on enterance of GIS


Phase A
20.0k
1.2483k
17.5k 17.7089k
16.4606k
15.0k Min 1.2482k
Max 18.3637k
12.5k

10.0k
KV

7.5k

5.0k

2.5k

0.0
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.0000
0.0004
f 2376.7692  

Figure 60: Case‐1 observed voltage at GIS incomer 

    Page 55/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
20.0k
1.2480k
17.5k 17.9446k
16.6967k
15.0k
Min 1.2479k
12.5k Max 18.3637k

10.0k

7.5k

5.0k

2.5k

0.0
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.0000
0.0003
f 4028.1224  

Figure 61: Case‐1 observed voltage at TR HV side 

As noted in previous figures 60 and 61, overvoltage at GIS entry will be 18363.7KVpeak and at 
TR HV side is 18363.7KVpeak while withstand value (LIWL) of GIS not more than 1368KVpeak 
as per specs.  

CASE‐2: Line circuit breaker contacts are closed and line surge arresters installed. 

observed over voltage on enterance of GIS


Phase A
800
0.5717k
-0.0029k
600
-0.5746k
Min -0.4731k
400
Max 0.6862k

200
KV

-200

-400

-600
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0000
0.0004
f 2376.7692  

Figure 62: Case‐2 observed voltage at GIS incomer 

    Page 56/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
800
0.5714k
600 0.0075k
-0.5639k
400 Min -0.4733k
Max 0.6847k
200

-200

-400

-600
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.0000
0.0003
f 4028.1224  

Figure 63: Case‐2 observed voltage at TR HV side 

As shown in previous figures 62 and 63, peak value of overvoltage that will be observed on 
phase A during the back flash over stroke not more than 686.2KVpeak at GIS entrance and TR 
HV side 684.7KVpeak that represent about 50.16% of BIL. 

CASE‐3:  Line  circuit  breaker  contacts  are  closed  and  line  and  TR  HV  side  surge  arresters 
installed. 

observed over voltage on enterance of GIS


Phase A
800
530.945
-5.527
600
-536.472
Min -466.770
400
Max 586.125

200
KV

-200

-400

-600
x 0.00000 0.00010 0.00020 0.00030 0.00040 0.00050 0.00060 0.00070 0.00080 0.00090 0.00100 0.0000
0.0004
f 2376.7692  

Figure 64: Case‐3 observed voltage at GIS incomer 

    Page 57/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
800
530.544
600 4.927
-525.617
400 Min -466.978
Max 584.393
200

-200

-400

-600
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.0000
0.0003
f 4028.1224  

Figure 65: Case‐3 observed voltage at TR HV side 

As shown in previous figures 64 and 65, peak value of overvoltage that will be observed on 
phase A during the back flash over stroke not more than 586.12KVpeak at GIS entrance and TR 
HV side 584.4KVpeak that represent about 42.72% of BIL. Extra voltage reduction is achieved 
when both TR HV side and line SA are installed compared to case‐2. 

CASE‐4: Line circuit breaker contacts are opened and all surge arresters are disconnected. 

observed over voltage on enterance of GIS


Phase A
22.5k
3006.441
20.0k 19648.816
16642.375
17.5k
Min 3006.396
15.0k Max 21600.4...

12.5k
KV

10.0k

7.5k

5.0k

2.5k

0.0
x 0.00000 0.00010 0.00020 0.00030 0.00040 0.00050 0.00060 0.00070 0.00080 0.00090 0.00100 0.00000
0.00042
f 2376.769...  

Figure 66: Case‐4 observed voltage at GIS incomer 

    Page 58/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
3.5k
0.0623k
3.0k 3.3621k
3.2998k
2.5k Min 0.0623k
Max 3.3621k
2.0k

1.5k

1.0k

0.5k

0.0
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.0000
0.0010
f 1015.2178  

Figure 67: Case‐4 observed voltage at TR HV side 

As noted in previous figures 66 and 67, overvoltage at GIS entry will be 21600KVpeak and at TR 
HV side is 3362.1KVpeak while withstand value (LIWL) of GIS not more than 1368KVpeak as 
per specs.  

CASE‐5: Line circuit breaker contacts are opened and line surge arresters installed. 

observed over voltage on enterance of GIS


Phase A
1.2k
0.6329k
1.0k 0.0015k
-0.6314k
0.8k
Min -0.5258k
0.6k Max 1.0476k

0.4k
KV

0.2k

0.0

-0.2k

-0.4k

-0.6k
x 0.00000 0.00010 0.00020 0.00030 0.00040 0.00050 0.00060 0.00070 0.00080 0.00090 0.00100 0.00000
0.00042
f 2376.769...  

Figure 68: Case‐5 observed voltage at GIS incomer 

    Page 59/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
35.0
21.339
30.0 5.098
25.0 -16.241
20.0 Min -11.041
15.0 Max 32.686

10.0
5.0
0.0
-5.0
-10.0
-15.0
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.0000
0.0010
f 1015.2178  

Figure 69: Case‐5 observed voltage at TR HV side 

As shown in previous figures 68 and 69, peak value of overvoltage that will be observed on 
phase A during the back flash over stroke not more than 1047.6KVpeak that represent about 
76.57% of BIL at GIS entrance and TR HV side 32.68KVpeak.  

CASE‐6:  Line  circuit  breaker  contacts  are  opened  and  line  and  TR  HV  side  surge  arresters 
installed. 

observed over voltage on enterance of GIS


Phase A
1.2k
0.6329k
1.0k 0.0015k
-0.6314k
0.8k
Min -0.5258k
0.6k Max 1.0476k

0.4k
KV

0.2k

0.0

-0.2k

-0.4k

-0.6k
x 0.00000 0.00010 0.00020 0.00030 0.00040 0.00050 0.00060 0.00070 0.00080 0.00090 0.00100 0.00000
0.00042
f 2376.769...  

Figure 70: Case‐6 observed voltage at GIS incomer 

    Page 60/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

Transformer voltage
Phase A
30
18.587
0.001
20
-18.587
Min -25.729
10
Max 21.132

-10

-20

-30
x 0.0000 0.0002 0.0004 0.0006 0.0008 0.0010 0.0012 0.0000
0.0010
f 1015.2178  

Figure 71: Case‐6 observed voltage at TR HV side 

As shown in previous figures 70 and 71, peak value of overvoltage that will be observed on 
phase A during the back flash over stroke not more than 1047.6KVpeak that represent about 
76.57% of BIL at GIS entrance and TR HV side 25.73KVpeak.  

    Page 61/62 
INSULATION COORDINATION STUDY FOR MARASSI – SIDI ABDUL RAHMAN 220/22KV SS  02/02/2019 

7 Attachments: 

o Attachment‐1:  Single  Line  Diagram  of  Marassi  ‐  Sidi  Abdul  Rahman  220/22  KV  GIS 
Substation. 
o Attachment‐2: Tower Layout. 
o Attachment‐3: 220kv Transmission Line parameter. 
o Attachment‐4 SA SPECS and TOV documents. 
o Attachment‐5: Surge Arrester Grantee Schedule. 
o Attachment‐6: Capacitor Bank Base Design. 
o Attachment‐7: Temporary Overvoltage study Single Line View from PSCAD Software. 
o Attachment‐8: Switching Study Single Line View from PSCAD Software. 
o Attachment‐9: lightening Study Single Line View from PSCAD Software. 

    Page 62/62 

You might also like